BC HYDRO AND ZELLSTOFF CELGAR LIMITED PARTNERSHIP ELECTRICITY PURCHASE AGREEMENT

Power Purchase Agreement

BC HYDRO 

AND 

ZELLSTOFF CELGAR LIMITED PARTNERSHIP 

ELECTRICITY PURCHASE AGREEMENT | Document Parties: MERCER INTERNATIONAL INC. | ZELLSTOFF CELGAR LIMITED PARTNERSHIP You are currently viewing:
This Power Purchase Agreement involves

MERCER INTERNATIONAL INC. | ZELLSTOFF CELGAR LIMITED PARTNERSHIP

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: BC HYDRO AND ZELLSTOFF CELGAR LIMITED PARTNERSHIP ELECTRICITY PURCHASE AGREEMENT
Date: 3/2/2009
Industry: Paper and Paper Products     Sector: Basic Materials

BC HYDRO 

AND 

ZELLSTOFF CELGAR LIMITED PARTNERSHIP 

ELECTRICITY PURCHASE AGREEMENT, Parties: mercer international inc. , zellstoff celgar limited partnership
50 of the Top 250 law firms use our Products every day

Exhibit 10.17

BC Hydro Bioenergy Call for Power (Phase I) EPA

*

 

CERTAIN NON-PUBLIC INFORMATION HAS BEEN OMITTED FROM THIS AGREEMENT PURSUANT TO A REQUEST FOR CONFIDENTIAL TREATMENT FILED WITH THE SECURITIES AND EXCHANGE COMMISSION ON MARCH 2, 2009. SUCH NON-PUBLIC INFORMATION HAS BEEN FILED WITH THE SEC ON A CONFIDENTIAL BASIS. THE LOCATION OF THESE OMISSIONS HAS BEEN NOTED BY [*]

BC HYDRO

AND

ZELLSTOFF CELGAR LIMITED PARTNERSHIP

ELECTRICITY PURCHASE AGREEMENT

BIOENERGY CALL FOR POWER – PHASE I

Effective Date: January 27, 2009

- 1 - 


 

BC Hydro Bioenergy Call for Power (Phase I) EPA

TABLE OF CONTENTS

 

 

 

 

 

 

 

Page No.

 

1. INTERPRETATION

 

 

1

 

1.1 Definitions

 

 

1

 

1.2 Appendices

 

 

1

 

1.3 Headings

 

 

2

 

1.4 Plurality and Gender

 

 

2

 

1.5 Governing Law

 

 

2

 

1.6 Industry Terms

 

 

2

 

1.7 Statutory References

 

 

2

 

1.8 Currency

 

 

2

 

1.9 Reference Indices

 

 

2

 

1.10 Conversions

 

 

2

 

1.11 Acknowledgement

 

 

3

 

1.12 Additional Interpretive Rules

 

 

3

 

1.13 General Partner

 

 

3

 

 

 

 

 

 

2. TERM

 

 

3

 

2.1 Term

 

 

3

 

 

 

 

 

 

3. REGULATORY REVIEW

 

 

4

 

3.1 Regulatory Review Termination

 

 

4

 

3.2 Regulatory Filing

 

 

4

 

3.3 EPA Support

 

 

4

 

3.4 Termination

 

 

4

 

3.5 Effect of Termination

 

 

4

 

3.6 Exemption

 

 

4

 

 

 

 

 

 

4. DEVELOPMENT

 

 

5

 

4.1 Development and Construction of the Incremental Seller’s Plant

 

 

5

 

4.2 Permits

 

 

5

 

4.3 Development Reports

 

 

5

 

4.4 Buyer Cost Responsibilities

 

 

5

 

4.5 Changes to Seller’s Plant before COD

 

 

5

 

 

 

 

 

 

5. COMMERCIAL OPERATION DATE

 

 

6

 

5.1 Guaranteed COD

 

 

6

 

5.2 Requirements for COD

 

 

6

 

5.3 Buyer Right to Observe

 

 

7

 

5.4 COD Disputes

 

 

7

 

5.5 Early COD

 

 

8

 

5.6 No Liability for Delay

 

 

8

 

5.7 Early Network Upgrades

 

 

8

 

5.8 Postponement of Guaranteed COD

 

 

8

 

 

 

 

 

 

6. OPERATION OF SELLER’S PLANT

 

 

8

 

6.1 Owner and Operator

 

 

8

 

6.2 Standard of Operation

 

 

8

 

Celgar Green Energy


 

BC Hydro Bioenergy Call for Power (Phase I) EPA

 

 

 

 

 

 

 

Page No.

 

6.3 Planned Outages

 

 

9

 

6.4 Records

 

 

9

 

6.5 Reports to the Buyer

 

 

10

 

6.6 Changes to Seller’s Plant

 

 

12

 

6.7 Exemption from Utility Regulation

 

 

12

 

6.8 Disclosure of Information by FortisBC and Transmission Authority

 

 

12

 

 

 

 

 

 

7. PURCHASE AND SALE OBLIGATIONS

 

 

13

 

7.1 Pre-COD Energy

 

 

13

 

7.2 Post-COD Sale of Energy

 

 

13

 

7.3 Post-COD Purchase of Energy

 

 

13

 

7.4 Exclusivity

 

 

13

 

7.5 Custody, Control and Risk of, and Title to, Energy

 

 

14

 

7.6 Price and Payment Obligation

 

 

14

 

7.7 Limitations on Delivery and Acceptance Obligations

 

 

14

 

7.8 Deemed Deliveries

 

 

15

 

7.9 Modification to Seasonally Firm Energy Amount

 

 

15

 

7.10 Modification to Seasonal GBL

 

 

16

 

7.11 Buyer Capacity Right

 

 

16

 

 

 

 

 

 

8. ENVIRONMENTAL ATTRIBUTES

 

 

17

 

8.1 Transfer of Environmental Attributes

 

 

17

 

8.2 Exclusivity

 

 

17

 

8.3 Representations and Warranties

 

 

18

 

8.4 EcoLogo M Certification

 

 

18

 

8.5 Alternate Certification

 

 

18

 

 

 

 

 

 

9. METERING

 

 

18

 

9.1 Installation of Metering Equipment

 

 

18

 

9.2 Operation of Metering Equipment

 

 

19

 

9.3 Duplicate Metering Equipment

 

 

19

 

9.4 Delivery Verification

 

 

19

 

 

 

 

 

 

10. STATEMENTS AND PAYMENT

 

 

20

 

10.1 Statements

 

 

20

 

10.2 Payment

 

 

20

 

10.3 Taxes

 

 

20

 

10.4 Billing Guideline

 

 

20

 

10.5 Set-off

 

 

21

 

 

 

 

 

 

11. INSURANCE/DAMAGE AND DESTRUCTION

 

 

21

 

11.1 Insurance

 

 

21

 

11.2 Damage or Destruction of the Seller’s Plant

 

 

22

 

 

 

 

 

 

12. FORCE MAJEURE

 

 

22

 

12.1 Invoking Force Majeure and Notice

 

 

22

 

12.2 Exclusions

 

 

23

 

 

 

 

 

 

13. LIQUIDATED DAMAGES

 

 

24

 

13.1 COD Delay

 

 

24

 

13.2 Delivery Shortfalls (Seasonal)

 

 

24

 

Celgar Green Energy

ii 


 

BC Hydro Bioenergy Call for Power (Phase I) EPA

 

 

 

 

 

 

 

Page No.

 

13.3 Capacity Call Delivery Shortfalls (Hourly)

 

 

25

 

13.4 Hourly Firm Credit Table

 

 

26

 

13.5 Exclusive Remedies for Buyer

 

 

27

 

13.6 Exclusive Remedies for Seller

 

 

27

 

13.7 Limits of Liability

 

 

27

 

13.8 Consequential Damages

 

 

27

 

 

 

 

 

 

14. PERFORMANCE AND INTERCONNECTION SECURITY

 

 

28

 

14.1 Delivery

 

 

28

 

14.2 Return

 

 

28

 

14.3 Enforcement

 

 

29

 

14.4 Form

 

 

29

 

14.5 Replenishment

 

 

29

 

14.6 Right to Withhold Payment

 

 

30

 

14.7 Letter of Credit Failure

 

 

30

 

 

 

 

 

 

15. SUSPENSION

 

 

30

 

15.1 Buyer Suspension

 

 

30

 

15.2 Seller Suspension

 

 

30

 

15.3 Resuming Deliveries

 

 

30

 

 

 

 

 

 

16. TERMINATION

 

 

30

 

16.1 Termination by the Buyer

 

 

30

 

16.2 Termination by the Seller

 

 

31

 

16.3 Effect of Termination

 

 

32

 

16.4 Payment on Termination by the Buyer

 

 

33

 

16.5 Payment on Termination by the Seller

 

 

33

 

16.6 Calculation of Gains, Economic Losses and Costs

 

 

34

 

16.7 Interconnection Costs Payable on Termination

 

 

35

 

16.8 Termination Payment Date

 

 

35

 

16.9 Exclusive Remedies

 

 

35

 

 

 

 

 

 

17. ASSIGNMENT

 

 

36

 

17.1 Assignment

 

 

36

 

17.2 Preconditions to Assignment

 

 

36

 

17.3 Assignment to Facility Lender

 

 

37

 

17.4 No Implied Consent to Exercise of Rights

 

 

37

 

17.5 Costs

 

 

37

 

17.6 No Assignment Before COD

 

 

37

 

 

 

 

 

 

18. INSPECTION AND AUDIT

 

 

37

 

18.1 General Inspection and Audit Rights

 

 

37

 

18.2 Inspection and Audit Rights Regarding Environmental Attributes

 

 

38

 

18.3 Consents Regarding Clean or Renewable Electricity

 

 

38

 

 

 

 

 

 

19. REPRESENTATIONS AND WARRANTIES

 

 

38

 

19.1 By Seller

 

 

38

 

19.2 By Buyer

 

 

39

 

 

 

 

 

 

20. INDEMNITIES

 

 

40

 

20.1 Seller Indemnity

 

 

40

 

Celgar Green Energy

iii 


 

BC Hydro Bioenergy Call for Power (Phase I) EPA

 

 

 

 

 

 

 

Page No.

 

20.2 Buyer Indemnity

 

 

40

 

20.3 Indemnification Conditions

 

 

41

 

20.4 Third Party Beneficiary Conditions

 

 

41

 

 

 

 

 

 

21. CONFIDENTIALITY

 

 

41

 

21.1 RFP Confidentiality Agreement

 

 

41

 

21.2 Additional Confidentiality Obligation

 

 

41

 

21.3 Freedom of Information and Protection of Privacy Act

 

 

42

 

21.4 Exemption from Disclosure

 

 

42

 

 

 

 

 

 

22. GENERAL PROVISIONS

 

 

43

 

22.1 Independence

 

 

43

 

22.2 Enurement

 

 

43

 

22.3 Notices

 

 

43

 

22.4 Entire Agreement and Amendment

 

 

43

 

22.5 No Waiver

 

 

44

 

22.6 Dispute Resolution

 

 

44

 

22.7 Eligible Financial Contract/Forward Contract

 

 

44

 

22.8 Further Assurances

 

 

45

 

22.9 Severability

 

 

45

 

22.10 Counterparts

 

 

45

 

 

 

APPENDIX 1 DEFINITIONS

 

APPENDIX 2 ENERGY PROFILE

 

APPENDIX 3 ENERGY PRICE – SEASONALLY FIRM

 

APPENDIX 4 SELLER’S PLANT DESCRIPTION

 

APPENDIX 5 FUEL PLAN

 

APPENDIX 6 COD CERTIFICATE

 

APPENDIX 7 SAMPLE FORM PERFORMANCE SECURITY / INTERCONNECTION SECURITY LETTER OF CREDIT

 

APPENDIX 8 SAMPLE FORM LENDER CONSENT AGREEMENT

 

APPENDIX 9 SAMPLE FORM DEVELOPMENT PROGRESS REPORT

 

APPENDIX 10 ADDRESSES FOR DELIVERY OF NOTICES

 

APPENDIX 11 RFP CONFIDENTIALITY AGREEMENT

Celgar Green Energy

iv 


 

BC HYDRO

ELECTRICITY PURCHASE AGREEMENT

THIS ELECTRICITY PURCHASE AGREEMENT (“ EPA ”) is made as of                      , 2008 (the “ Effective Date ”)

BETWEEN:

ZELLSTOFF CELGAR LIMITED PARTNERSHIP , a limited partnership formed under the laws of British Columbia represented by its general partner, Zellstoff Celgar Limited, a corporation incorporated under the laws of British Columbia (the “ General Partner ”), with its head office at Suite 2840, PO Box 11576, 650 West Georgia Street, Vancouver, BC V6B 4N8

(“ Seller ”)

AND:

BRITISH COLUMBIA HYDRO AND POWER AUTHORITY , a corporation continued under the Hydro and Power Authority Act , R.S.B.C. 1996, c. 212, with its head office at 333 Dunsmuir Street, Vancouver, BC V6B 5R3

(“ Buyer ”).

WHEREAS:

A. The Buyer issued a Bioenergy Call for Power (Phase I) — Request for Proposals on February 6, 2008 for the supply of electrical energy to the Buyer generated from Forest-based Biomass by projects located in British Columbia.

B. A Proposal in respect of the Project was submitted in response to the RFP.

C. The Seller desires to sell to the Buyer, and the Buyer desires to purchase from the Seller, Eligible Energy from the Seller’s Plant on the terms and conditions set forth in this EPA.

1. INTERPRETATION

1.1 Definitions — Appendix 1 sets out or references the definitions applicable to certain words and phrases used in this EPA.

1.2 Appendices — Attached to and forming part of this EPA are the following Appendices:

 

SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more