Exhibit 10.9.3
AMENDED AND RESTATED
ADDITIONAL POWER
CONTRACT
AMENDED AND RESTATED ADDITIONAL POWER
CONTRACT, dated as of April 30, 1984, as amended and restated
as of the 1st day of July, 2004, between CONNECTICUT YANKEE ATOMIC
POWER COMPANY ("Connecticut Yankee"), a Connecticut corporation,
and (the names of the Purchasers appear in the attached Appendix A)
(the "Purchaser").
In consideration of the following
understandings and the respective undertakings of the parties, it
is agreed as follows:
1.
Basic
Understandings
Connecticut Yankee was organized in
1962 to provide for the supply of power to its sponsoring utility
companies (including the Purchaser). Connecticut Yankee constructed
a nuclear electric generating unit of the pressurized water type,
having a maximum net capability of approximately 582 megawatts
electric, at a site adjacent to the Connecticut River at Haddam,
Connecticut (said unit, together with the site and all related
facilities owned or to be owned by Connecticut Yankee, being
referred to herein as the "Unit"). On June 30, 1967, Connecticut
Yankee was issued a full-term, operating license for the Unit from
the Atomic Energy Commission (now the Nuclear Regulatory
Commission, which, together with any successor agency or agencies,
is hereafter called the "NRC"), which license expires on May 26,
2004, and the Unit commenced commercial operation on January 1,
1968.
The Unit is operated to supply power
to the purchasers from Connecticut Yankee (collectively the
"Purchasers"), each of which by a Power Contract dated as of July
1, 1964, as supplemented by Supplementary Power Contracts
dated as of March 1, 1978, such Supplementary Power Contracts
amended on August 22, 1980 and October 15, 1982 (collectively the
"Power Contracts"), has undertaken to purchase a fixed percentage
of the capacity and output of the Unit for a term extending through
December 31, 1997. The names of the Purchasers and their respective
percentages ("entitlement percentages") of the capacity and output
of the Unit are as follows:
|
|
Entitlement
Percentage
|
|
The
Connecticut Light and Power Company
New England Power Company (for itself and
as Successor to Montaup Electric Company
|
34.5%
19.5%
|
|
The
Connecticut Light and Power Company
|
34.5%
|
|
New
England Power Company (for itself and as Western Massachusetts
Electric Company
|
9.5%
|
|
The
United Illuminating Company
|
9.5%
|
|
Boston Edison Company
|
9.5%
|
|
Central Maine Power Company
|
6.0%
|
|
Public Service Company of New Hampshire
|
5.0%
|
|
Cambridge Electric Light Company
|
4.5%
|
|
Central Vermont Public Service Corporation
|
2.0%
|
The Power Contracts have been
supplemented most recently by Second Supplementary Power Contracts,
dated as of 1984, between Connecticut Yankee and each of the
Purchasers (the "Second Supplementary Power Contracts"). The
Second Supplementary Power Contracts provide for the
collection of funds to defray the ultimate cost of decommissioning
the Unit and to provide an allowance for potential taxes payable by
Connecticut Yankee with respect to the decommissioning fund.
Connecticut Yankee and the Purchasers
desire to provide for the orderly continuation of the sale and
purchase of the capacity and output of the Unit during the useful
life of the Unit to the extent that such useful life continues
beyond the termination date of the Power Contracts and the Second
Supplementary Power Contracts and to provide appropriate provisions
for the collection of funds for, and the payment of,
decommissioning costs and any other costs, including potential
taxes, with respect to the Unit during and after the useful life of
the Unit.
2.
Effective Date,
Term and Waiver
This contract shall become effective
upon receipt by the Purchaser of notice that Connecticut Yankee has
entered into Additional Power Contracts, as contemplated by Section
1 above, with each of the other Purchasers. The operative
term of this contract shall commence on such date as may be
authorized by the FERC and shall terminate on the date (the "End of
Term Date") which is the later to occur of (i) 30 days after the
date on which the last of the financial obligations of Connecticut
Yankee which constitute elements of the payment calculated pursuant
to Section 7 of this contract has been extinguished by Connecticut
Yankee, or (ii) 30 days after the date on which Connecticut Yankee
is finally relieved of all obligations under the last of any
licenses (operating and/or possessory) which it now holds from, or
which may hereafter be issued to it by, the NRC with respect to the
Unit under applicable provisions of the Atomic Energy Act of 1954,
as amended from time to time (the "Act'').
The Purchaser hereby irrevocably
waives its right to extend the contract term of its Power Contract
pursuant to subsections (a) or (b) of Section 8
thereof.
3.
Operation
and Maintenance of the Unit
Connecticut
Yankee will operate and maintain the Unit in accordance with good
utility practice under the circumstances and all applicable law,
including the applicable provisions of the Act and of any licenses
issued thereunder to Connecticut Yankee. Within the limits
imposed by good utility practice under the circumstances and
applicable law, the Unit will be operated at its maximum capability
and on a long hour use basis.
Outages for inspection, maintenance,
refueling and repairs and replacements will be scheduled in
accordance with good utility practice and insofar as practicable
shall be mutually agreed upon by Connecticut Yankee and the
Purchaser. In the event of an outage, Connecticut Yankee will
use its best efforts to restore the Unit to service as promptly as
practicable.
4.
Decommissioning
After commercial operation of the Unit
permanently ceases, Connecticut Yankee will decommission the Unit
in a manner authorized by Connecticut Yankee's board of directors
and approved by the NRC in accordance with the Act and the rules
and regulations thereunder then in effect and by any agency having
jurisdiction over decommissioning of the Unit.
It is understood that, pursuant to the
1987 Supplementary Power Contracts, the Purchasers are currently
being billed for Total Decommissioning Costs which, as of the date
of this contract, are being accumulated in a separate fund which
was established for the purpose of reimbursing Connecticut Yankee
for Decommissioning Expenses incurred in the process of
decommissioning the Unit and that such billings ate subject to
change in accordance with the provisions of the 1987 Supplementary
Power Contracts, subject to the jurisdiction of the Federal Energy
Regulatory Commission or any successor agency thereto (the "FERC").
It is contemplated that sufficient funds will be accumulated
pursuant to those contracts and paragraph 7 hereof to make payment
to reimburse Connecticut Yankee for the full cost of
decommissioning the Unit.
5.
Purchaser's
Entitlement
The Purchaser will, throughout the
term of this contract, be entitled and obligated to take its
entitlement percentage of the capacity and net electrical output of
the Unit, at whatever level the Unit is operated or operable,
whether more or less than 582 megawatts electric.
6.
Deliveries and Metering
The Purchaser's entitlement percentage
of the output of the Unit will be delivered to and accepted by the
Purchaser at the step-up substation at the site. All deliveries
will be made in the form of 3-phase, 60 cycle, alternating
current at a nominal voltage of 345,000 volts. The Purchaser
will make its own arrangements for the transmission of its
entitlement percentage of the output of the Unit.
Connecticut Yankee will supply and
maintain all necessary metering equipment for determining the
quantity and conditions of supply of deliveries under this
contract, will make appropriate tests of such equipment in
accordance with good utility practice and as reasonably requested
by the Purchaser, and will maintain the accuracy of such equipment
within reasonable limits. Connecticut Yankee will furnish the
Purchaser with such summaries of meter readings as the Purchaser
may reasonably request.
7.
Payment
With respect to each month commencing
on or after the commencement of the operative term of this
contract, whether or not this contract continues fully or partially
in effect, the Purchaser will pay Connecticut Yankee as deferred
payment for the capacity and output of the Unit provided to the
Purchaser by Connecticut Yankee prior to the permanent shutdown of
the Unit on December 4, 1996, to the extent not otherwise paid in
accordance with the Power Contract, but without duplication: an
amount equal to the Purchaser's entitlement percentage of the sum
of (a) the Total Decommissioning Costs for the month with respect
to the Unit, plus (b) Connecticut Yankee's total operating expenses
for the month with respect to the Unit, plus (c) an amount for
operating income as determined in accordance with Section
7.
"Equity investment" as of any date
shall consist of the sum of(i) all amounts theretofore paid to
Connecticut Yankee for all common capital stock theretofore issued,
plus all amounts paid to Connecticut Yankee by any of its common
stockholders as capital contributions or advances, less the sum of
any amounts paid by Connecticut Yankee to its common stockholders
in the form of stock retirements, repurchases or redemptions,
return of capital or repayments of such contributions or advances;
plus (ii) any credit balance in the capital surplus account not
included under (i) and in the retained earnings account on the
books of Connecticut Yankee as of such date.
"Uniform System" shall mean the
Uniform System of Accounts prescribed by the FERC for Class A and
Class B Public Utilities and Licensees, as from time to time in
effect.
Connecticut Yankee's "operating
expanses" shall include all amounts properly chargeable to
operating expense accounts, less any applicable credits thereto, in
accordance with the Uniform System; however, excluding for purposes
of this contract Total Decommissioning Costs, but including for
purposes of this contract:
(i)
with respect to each month until the
commencement of decommissioning of the Unit, the Purchaser's
entitlement percentage of all expenses related to the storage or
disposal of nuclear fuel or other radioactive materials, and all
expenses related to protection and maintenance of the Unit during
such period, including to the extent applicable all of the various
sorts of expenses included in the definition of "Decommissioning
Expenses," to the extent incurred during the period prior to the
commencement of decommissioning.
(ii)
with respect to each month until
expenses associated with disposal of pre-April 7, 1983 spent
nuclear fuel have been fully covered by amounts which have been
collected from Purchasers and paid to a segregated fund as
contemplated by Section 8 of the 1987 Supplementary Power Contract,
dated as of April 1, 1987, between Connecticut Yankee and the
Purchaser, as amended (the "1987 Contract"), the Purchaser’s
entitlement percentage of previously uncollected
expenses associated with disposal of such prior spent nuclear fuel,
as determined in accordance with Section 10 of the 1987 Contract;
and
(iii)
with respect to each month until End
of License Term, the Purchaser's entitlement percentage of monthly
amortization of (a) the amount of any unamortized deferred
expenses, as permitted from time to time by the Federal Energy
Regulatory Commission or its successor agency, plus (b) the
remaining unamortized amount of Connecticut Yankee's investment in
plant, nuclear fuel and materials and supplies and other assets.
Such amortization shall be accrued at a rate sufficient to amortize
fully such unamortized deferred expenses and Connecticut Yankee's
investments in plant, nuclear fuel and materials and supplies or
other assets over a period exte