Back to top

Lease Agreement

Lease Agreement

Lease Agreement | Document Parties: Dalian Befut Wire & Cable Manufacturing Co., LTD | Dalian Wanbao Industrial Co.,LTD You are currently viewing:
This Lease Agreement involves

Dalian Befut Wire & Cable Manufacturing Co., LTD | Dalian Wanbao Industrial Co.,LTD

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: Lease Agreement
Date: 10/9/2009

Lease Agreement, Parties: dalian befut wire & cable manufacturing co.  ltd , dalian wanbao industrial co. ltd
50 of the Top 250 law firms use our Products every day

Exhibit 10.6

 

Lease Agreement

 

Party A: Dalian Wanbao Industrial Co.,LTD (the “Lessor”)

 

Party B: Dalian Befut Wire & Cable Manufacturing Co., LTD (“Lessee”)

 

Under the principles of equal rights and mutual benefit, lessor and lessee enter into a lease agreement whereby lessor leases to lessee a plant site that was originally owned by Dalian Grain Drying Co., Ltd. The lease terms are as follow:

 

I

Lessor leases to lessee the plant site with properties that was originally owned by Dalian Baolihang Grain Drying Co., LTD for the purpose of lessee establishing a cable manufacturing plant. The said land with properties are located in Qipan Village with valid land use certificate. Details of the land and properties are as follows:

 

1.      An office building of 170 square meters

2.      A boiler room of 450 square meters

3.      An employee dormitory of 300 square meters

4.      Power facilities with power load of 400KW

5.      Water supply facilities

6.      A guard post

7.      A land area of 15 thousand square meters (All hardened surface)

8.      Surrounding walls

 

II.     The lease is valid for 50 years starting from October 1, 2001 through October 1, 2051.

 

III.    Lease amount and payment method: Total lease amount is RMB 2.5 million

 

Payment method: A security deposit of RMB 100 thousand will be paid within five days of the execution of the lease agreement;  another RBM 900 thousand will be paid when approvals for design and construction are secured. The remaining balance of RMB1.5 million will be paid evenly over three years starting from the third year of the lease. Payments should be made by November 30 of each year.

 

IV.    Responsibilities and Obligations of Each Party

 

1. Lessor bears the responsibility and cost for securing land use certificate and land planning and construction permits.

 

 

1


 

 

2. With lessor’s assistance, lessee bears the responsibility and cost for securing construction design and construction permit. Both lessor and lessee share the responsibility but lessee bears the cost for obtaining certificate of building.

3. With lessor’s active assistance, lessee bears the responsibility and cost for securing permits needed for operations, such as business license , environmental protection certificate and fire safety certificate.

4. Lessor bears the responsibility but lessee bears the cost for securing governmental a


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more