Cooperative Contract on Coke-oven Gas Power Generation
Project of Xi’an TCH Energy Technology Co., Ltd.
and
Shenmu County Jiujiang Trading Co., Ltd.
2009
Cooperative Contract on Coke-oven Gas Power Generation
Project
Party A:
Xi’an TCH Energy Technology Co., Ltd. (hereinafter referred
to as Party A)
Address: No.
86, Gaoxin Road, Hi-tech Zone, Xi’an, Shaanxi
Province
Legal
Representative: Ku Guohua
Party B: Shenmu
County Jiujiang Trading Co., Ltd. (hereinafter referred to as Party
B)
Address:
Shagoumao Village, Xigou Office, Shenmu County
Legal
Representative: Hao Ziwei
Through
friendly negotiation, based on the principle
of equality and voluntariness, both Party A and Party B
conclude the following clauses on the
relevant cooperation matters that Party
A invests and constructs auxiliary coke-oven gas
power generation device to the coke-oven plant of Shenmu
County Jiujiang Trading Co., Ltd. which is wholly owned and
controlled by Party B.
Article 1:
Definition of investment construction
1. By mutual
consent, Party A shall invest, construct
and manage the tail gas power generation project
for the coke-oven plant of Party B ( hereinafter referred to
as “power generation project”) and supply energy saving
and emissions reduction service for Party B.
2. The
“power generation project” belongs to Party
A, Party A shall be responsible for the design, equipment
selection, equipment procurement
and manufacture, construction work, project
installment and test/adjustment, formal
synchronization power generation of the whole project and the
project management, maintenance, operation and safety
after put into production, and Party B shall provide
active cooperation.
Article 2:
Party A's term
1. The term of
Party A supplying energy saving service to Party B is 10
years from the date of signing this contract
and the power generation project is formally built and
put into operation.
Article 3:
Rights, obligations and guarantee of the both
parties
1. Party B
shall guarantee the coke-oven plant is its wholly
owned holding company, and the coke-oven plant
is established legally and a China enterprise legal
person that continues to exist effectively and can operate and
produce normally.
2. Party B
guarantees to urge coke-oven plant to sign
written gas supply agreement with Party A with a term not
less than 10 years.
3. Party B
shall be responsible for all the procedures
including project proposal, review and approval, and
environment evaluation etc. for the project construction which are
required by state laws and regulations and bear the
expense. Party B shall be responsible
for synchronization power generation procedure of
“power generation project”, which should be done
after the signing date of this contract and before
the date of power generation project is formally built and put
into operation.
4. Party A
promises that the construction of the “power generation
project” shall be finished within 90 days after this
agreement becomes effective and both parties confirm
the commencement condition for the project is
available. However, if the project cannot proceed
successfully due to Party B's reason (including, but not
limited to its activities that affect
normal construction, installation, test/adjustment
or safety work etc.), Party A's construction period shall
be extended accordingly and Party B shall compensate
relevant losses caused to Party A hereof. If the
project cannot proceed successfully due to Party A's reason
(including, but not limited to its activities affect
normal construction, installation, testing or safety
work etc.), Party A shall compensate relevant losses
caused to Party B hereof.
5. Party A
shall be responsible for the design, equipment
order, construction, installation
and test/adjustment of the “power generation
project”, etc. Party B shall be responsible for
completing the connection of utilities and level the ground of the
land before the commencement of construction of the
project, and provide necessary utility facilities to
the project.
6. Party B
shall provide a lien with sufficient value as its guarantee
for this cooperative “power generation
project” and sign a Lien Agreement
with Party A within 10 working days after signing this
contract. Party B shall complete the lien/mortgage
registration process within 15 working days after signing this
contract. The Lien Agreement shall take effect along
with this contract on “the effective
day”.
7. Party B
shall urge its top five individual shareholders to
assume an unlimited joint liability guarantee for
Party B for the implementation of this contract
and urge the individual shareholders to sign Unlimited
and Joint Liability Guarantee Agreement with Party A
within 15 working days after signing this contract. The
Unlimited and Joint Liability Guarantee Agreement shall
become effective along with this contract on “the
effecti