EXHIBIT 10.52-01
FIRST AMENDED AND RESTATED
INTERCONNECTION AGREEMENT
DATED OCTOBER 9,
2003
BETWEEN
EL PASO ELECTRIC
COMPANY
AND
PUBLIC SERVICE COMPANY OF NEW
MEXICO
FIRST REVISED SERVICE AGREEMENT
NO. 47
SUPERSEDING ORIGINAL SERVICE
AGREEMENT NO. 47
UNDER EL PASO ELECTRIC
COMPANY
FERC ELECTRIC TARIFF ORIGINAL
VOLUME NO. 1
EFFECTIVE DATE: OCTOBER
, 2003
Table of Contents
|
|
|
|
|
|
|
|
|
Article I
|
|
DEFINITIONS
|
|
1
|
|
|
|
1.1
|
|
“Abnormal Condition”
|
|
2
|
|
|
|
1.2
|
|
“Affiliate”
|
|
2
|
|
|
|
1.3
|
|
“Afton Switching
Station”
|
|
2
|
|
|
|
1.4
|
|
“Agents”
|
|
2
|
|
|
|
1.5
|
|
“Agreement”
|
|
2
|
|
|
|
1.6
|
|
“Applicable Laws and
Regulations”
|
|
2
|
|
|
|
1.7
|
|
“Bankruptcy Laws”
|
|
2
|
|
|
|
1.8
|
|
“Breaching Party”
|
|
2
|
|
|
|
1.9
|
|
“Business Day”
|
|
2
|
|
|
|
1.10
|
|
“Commercial Operation
Date”
|
|
2
|
|
|
|
1.11
|
|
“Commercially Reasonable
Efforts”
|
|
2
|
|
|
|
1.12
|
|
“Confidential
Information”
|
|
3
|
|
|
|
1.13
|
|
“Custodian”
|
|
3
|
|
|
|
1.14
|
|
“Due Diligence”
|
|
3
|
|
|
|
1.15
|
|
“Effective Date”
|
|
3
|
|
|
|
1.16
|
|
“Emergency”
|
|
3
|
|
|
|
1.17
|
|
“Environmental Laws”
|
|
3
|
|
|
|
1.18
|
|
“EPE”
|
|
3
|
|
|
|
1.19
|
|
“EPE Control Area”
|
|
3
|
|
|
|
1.20
|
|
“EPE Interconnection
Facilities”
|
|
4
|
|
|
|
1.21
|
|
“EPE OATT”
|
|
4
|
|
|
|
1.22
|
|
“EPE’s Palo Verde
Facilities
|
|
4
|
|
|
|
1.23
|
|
“EPE Transmission
System”
|
|
4
|
|
|
|
1.24
|
|
“Facility”
|
|
4
|
|
|
|
1.25
|
|
“Federal Power Act”
|
|
4
|
|
|
|
1.26
|
|
“FERC”
|
|
4
|
|
|
|
1.27
|
|
“General Orders”
|
|
4
|
|
|
|
1.28
|
|
“Generator”
|
|
4
|
|
|
|
1.29
|
|
“Generator’s Interconnection
Facilities”
|
|
4
|
|
|
|
1.30
|
|
“Good Utility Practice”
|
|
5
|
|
|
|
1.31
|
|
“Governmental Authority”
|
|
5
|
|
|
|
1.32
|
|
“Governor Droop”
|
|
5
|
|
|
|
1.33
|
|
“Hazardous Substances”
|
|
5
|
|
|
|
1.34
|
|
“Interconnected
Facilities”
|
|
5
|
|
|
|
1.35
|
|
“Interconnection Point”
|
|
5
|
|
|
|
1.36
|
|
“Interconnection
Service”
|
|
5
|
|
|
|
1.37
|
|
“Interconnection
Studies”
|
|
5
|
|
|
|
1.38
|
|
“Interconnection System
Upgrades”
|
|
6
|
|
|
|
1.39
|
|
“Interest Rate”
|
|
6
|
|
|
|
1.40
|
|
“Metering Equipment”
|
|
6
|
|
|
|
1.41
|
|
“NERC”
|
|
6
|
|
|
|
1.42
|
|
“Non-Breaching Party”
|
|
6
|
|
|
|
1.43
|
|
“Operating Agent”
|
|
6
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
i
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.44
|
|
“Operating Committee”
|
|
6
|
|
|
|
1.45
|
|
“Operation Date”
|
|
6
|
|
|
|
1.46
|
|
“Participant”
|
|
6
|
|
|
|
1.47
|
|
“Parties”
|
|
6
|
|
|
|
1.48
|
|
“Party”
|
|
6
|
|
|
|
1.49
|
|
“Person”
|
|
6
|
|
|
|
1.50
|
|
“Power System Stabilizer
(PSS)”
|
|
6
|
|
|
|
1.51
|
|
“Protective Equipment”
|
|
7
|
|
|
|
1.52
|
|
“Regional Transmission
Organization” or “RTO”
|
|
7
|
|
|
|
1.53
|
|
“Release”
|
|
7
|
|
|
|
1.54
|
|
“Reliability Management System” or
“RMS”
|
|
7
|
|
|
|
1.55
|
|
“Security Coordinator”
|
|
7
|
|
|
|
1.56
|
|
“SOCC”
|
|
7
|
|
|
|
1.57
|
|
“Termination Costs”
|
|
7
|
|
|
|
1.58
|
|
“Transmission Service
Agreement”
|
|
7
|
|
|
|
1.59
|
|
“WSCC”
|
|
7
|
|
|
|
1.60
|
|
“WSCC Agreement”
|
|
7
|
|
|
|
1.61
|
|
“WSCC Reliability Criteria
Agreement”
|
|
7
|
|
Article II
|
|
TERM
|
|
8
|
|
|
|
2.1
|
|
Effectiveness of this Agreement
|
|
8
|
|
|
|
2.2
|
|
FERC Filing
|
|
8
|
|
|
|
2.3
|
|
Term
|
|
8
|
|
|
|
2.4
|
|
Material Adverse Change
|
|
9
|
|
|
|
2.5
|
|
Survival
|
|
9
|
|
Article III
|
|
CONTINUING OBLIGATIONS AND
RESPONSIBILITIES
|
|
9
|
|
|
|
3.1
|
|
Interconnection Service Provided
|
|
9
|
|
|
|
3.2
|
|
Scope of Interconnection Service
|
|
9
|
|
|
|
3.3
|
|
Services Outside Scope of Agreement
|
|
10
|
|
|
|
3.4
|
|
No Guarantees; Release
|
|
10
|
|
|
|
3.5
|
|
Reporting Requirements
|
|
11
|
|
|
|
3.6
|
|
Third Party Activity
|
|
11
|
|
|
|
3.7
|
|
Compliance with EPE OATT and FERC Orders No.
888 and No. 889
|
|
11
|
|
Article IV
|
|
OPERATING COMMITTEE
|
|
11
|
|
|
|
4.1
|
|
Operating Committee
|
|
11
|
|
|
|
4.2
|
|
Responsibilities of the Operating
Committee
|
|
12
|
|
|
|
4.3
|
|
Effectiveness of Operating Committee
Determinations
|
|
12
|
|
Article V
|
|
FACILITY INTERCONNECTION
|
|
12
|
|
|
|
5.1
|
|
Establishment of Interconnection
|
|
12
|
|
|
|
5.2
|
|
Necessary Easements, Permits, Licenses,
Etc
|
|
12
|
|
|
|
5.3
|
|
Design and Construction of Generator’s
Interconnection Facilities
|
|
13
|
|
|
|
5.4
|
|
Design and
Construction of EPE Interconnection Facilities and Interconnection
System Upgrades and Transmission Credits
|
|
13
|
|
|
|
5.5
|
|
Subcontractors
|
|
15
|
|
|
|
5.6
|
|
Rights of Access
|
|
15
|
|
|
|
5.7
|
|
Course and Completion of
Construction
|
|
16
|
|
|
|
5.8
|
|
Timely Completion
|
|
17
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
ii
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.9
|
|
Environmental Compliance and
Procedures
|
|
17
|
|
|
|
5.10
|
|
Generator Modeling Data
|
|
18
|
|
|
|
5.11
|
|
Equipment Requirements
|
|
18
|
|
|
|
5.12
|
|
Required Diagrams
|
|
18
|
|
|
|
5.13
|
|
Required Personnel Information
|
|
18
|
|
|
|
5.14
|
|
Use of Afton Switching Station by Third
Parties
|
|
18
|
|
|
|
5.15
|
|
Interconnected Facilities and Facility
Additions, Modifications or Replacements
|
|
19
|
|
Article VI
|
|
ACCEPTANCE AND PERFORMANCE TESTING AND
COMPLIANCE MONITORING
|
|
20
|
|
|
|
6.1
|
|
Responsibility for Testing
|
|
20
|
|
|
|
6.2
|
|
Responsibility for Modifications Following
Testing
|
|
21
|
|
|
|
6.3
|
|
Documentation of Results to EPE or the
Operating Agent
|
|
21
|
|
|
|
6.4
|
|
Facility Certification
|
|
21
|
|
|
|
6.5
|
|
Transmission Service During Testing
|
|
21
|
|
|
|
6.6
|
|
EPE Inspection Rights
|
|
22
|
|
|
|
6.7
|
|
Generator Inspection Rights
|
|
22
|
|
|
|
6.8
|
|
EPE’s Reviews, Inspections, and
Approvals
|
|
22
|
|
Article VIII
|
|
INTERCONNECTION FACILITY COSTS AND
BILLING
|
|
22
|
|
|
|
7.1
|
|
Interconnection Construction Completion and
Cost
|
|
22
|
|
|
|
7.2
|
|
Invoices and Payments
|
|
23
|
|
|
|
7.3
|
|
Adjustments
|
|
26
|
|
|
|
7.4
|
|
Payment Not a Waiver
|
|
26
|
|
|
|
7.5
|
|
Income Taxes
|
|
26
|
|
Article VIII
|
|
OPERATIONS
|
|
27
|
|
|
|
8.1
|
|
General
|
|
27
|
|
|
|
8.2
|
|
Obligations of Operating Agent
|
|
27
|
|
|
|
8.3
|
|
Obligations of Generator
|
|
27
|
|
|
|
8.4
|
|
Reliability Criteria
|
|
28
|
|
|
|
8.5
|
|
Quality of Power
|
|
28
|
|
|
|
8.6
|
|
Protection and System Quality
|
|
29
|
|
|
|
8.7
|
|
Adjustments
|
|
29
|
|
|
|
8.8
|
|
Switching and Tagging Procedures
|
|
29
|
|
|
|
8.9
|
|
General Orders
|
|
30
|
|
|
|
8.10
|
|
Generation Alert
|
|
30
|
|
Article IX
|
|
RELIABILITY MANAGEMENT SYSTEM
|
|
30
|
|
|
|
9.1
|
|
Purpose
|
|
30
|
|
|
|
9.2
|
|
Compliance
|
|
31
|
|
|
|
9.3
|
|
Participant Status
|
|
31
|
|
|
|
9.4
|
|
Payment of Sanctions
|
|
31
|
|
|
|
9.5
|
|
Transfer of Control or Sale of
Facility
|
|
31
|
|
|
|
9.6
|
|
Failure to Comply with RMS
|
|
31
|
|
|
|
9.7
|
|
Publication
|
|
31
|
|
|
|
9.8
|
|
Third Parties
|
|
31
|
|
|
|
9.9
|
|
Reserved Rights
|
|
32
|
|
|
|
9.10
|
|
Termination
|
|
32
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
iii
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.11
|
|
Mutual Agreement
|
|
32
|
|
|
|
9.12
|
|
Severability
|
|
32
|
|
Article X
|
|
REACTIVE POWER
|
|
32
|
|
|
|
10.1
|
|
Obligation to Supply Reactive Power
|
|
32
|
|
|
|
10.2
|
|
Compensation
|
|
33
|
|
|
|
10.3
|
|
Reactive Power Standards
|
|
33
|
|
|
|
10.4
|
|
Failure to Supply Reactive Power
|
|
33
|
|
Article XI
|
|
OUTAGES, INTERRUPTIONS, AND
DISCONNECTIONS
|
|
34
|
|
|
|
11.1
|
|
Outage Scheduling
|
|
34
|
|
|
|
11.2
|
|
Scheduled Maintenance and
Coordination
|
|
34
|
|
|
|
11.3
|
|
Other Maintenance and Coordination
|
|
34
|
|
|
|
11.4
|
|
Unplanned Outages
|
|
34
|
|
|
|
11.5
|
|
Disconnection
|
|
34
|
|
|
|
11.6
|
|
Continuity of Service
|
|
35
|
|
Article XII
|
|
EMERGENCY AND ABNORMAL CONDITION
PROCEDURES
|
|
35
|
|
|
|
12.1
|
|
Emergency
|
|
35
|
|
|
|
12.2
|
|
Notice of Emergency
|
|
36
|
|
|
|
12.3
|
|
Immediate Action
|
|
36
|
|
|
|
12.4
|
|
Disconnection of Facility in Event of Potential
Emergency
|
|
36
|
|
|
|
12.5
|
|
Audit Rights
|
|
37
|
|
|
|
12.6
|
|
Abnormal Conditions
|
|
37
|
|
Article XIII
|
|
MAINTENANCE
|
|
38
|
|
|
|
13.1
|
|
The Operating Agent Obligations
|
|
38
|
|
|
|
13.2
|
|
Generator Obligations
|
|
38
|
|
|
|
13.3
|
|
Maintenance Expenses
|
|
38
|
|
|
|
13.4
|
|
Coordination
|
|
38
|
|
|
|
13.5
|
|
Observation of Deficiencies
|
|
38
|
|
|
|
13.6
|
|
Review of Maintenance Records
|
|
39
|
|
Article XIV
|
|
METERING
|
|
39
|
|
|
|
14.1
|
|
General
|
|
39
|
|
|
|
14.2
|
|
Testing
|
|
39
|
|
|
|
14.3
|
|
Data Metered
|
|
39
|
|
|
|
14.4
|
|
Data Available Upon Request
|
|
40
|
|
|
|
14.5
|
|
Costs
|
|
40
|
|
Article XV
|
|
SAFETY
|
|
40
|
|
|
|
15.1
|
|
General
|
|
40
|
|
|
|
15.2
|
|
Environmental Releases
|
|
40
|
|
|
|
15.3
|
|
Other Environmental Impact
|
|
40
|
|
Article XVI
|
|
COMMUNICATIONS
|
|
40
|
|
|
|
16.1
|
|
Equipment
|
|
40
|
|
|
|
16.2
|
|
Remote Terminal Unit
|
|
41
|
|
Article XVII
|
|
INFORMATION REPORTING
|
|
41
|
|
|
|
17.1
|
|
General
|
|
41
|
|
|
|
17.2
|
|
Compliance Monitoring Reporting
|
|
41
|
|
|
|
17.3
|
|
Regulatory Agency Reporting
|
|
41
|
|
|
|
17.4
|
|
Penalties
|
|
41
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
iv
|
|
|
|
|
|
|
|
|
|
|
|
Article XVIII
|
|
DOCUMENTATION
|
|
42
|
|
|
|
18.1
|
|
General
|
|
42
|
|
|
|
18.2
|
|
Drawings
|
|
42
|
|
Article XIX
|
|
FORCE MAJEURE
|
|
42
|
|
|
|
19.1
|
|
Definition
|
|
42
|
|
|
|
19.2
|
|
Performance Excused
|
|
43
|
|
|
|
19.3
|
|
Labor Issues
|
|
43
|
|
|
|
19.4
|
|
Payment Not Excused
|
|
43
|
|
Article XX
|
|
INDEMNIFICATION
|
|
43
|
|
|
|
20.1
|
|
INTERCONNECTION INDEMNITY
|
|
43
|
|
|
|
20.2
|
|
RECIPROCAL INDEMNITY
|
|
43
|
|
|
|
20.3
|
|
DAMAGE DISCLAIMER
|
|
44
|
|
|
|
20.4
|
|
Indemnities Reformed
|
|
44
|
|
|
|
20.5
|
|
Indemnification Procedures
|
|
44
|
|
|
|
20.6
|
|
Additional Indemnification
Provisions
|
|
45
|
|
|
|
20.7
|
|
Survival
|
|
45
|
|
Article XXI
|
|
INSURANCE
|
|
45
|
|
|
|
21.1
|
|
Generator
|
|
45
|
|
|
|
21.2
|
|
EPE or Operating Agent
|
|
45
|
|
|
|
21.3
|
|
Notice of Cancellation
|
|
46
|
|
|
|
21.4
|
|
Self-Insurance
|
|
46
|
|
Article XXII
|
|
DEFAULT
|
|
46
|
|
|
|
22.1
|
|
General
|
|
46
|
|
|
|
22.2
|
|
Events Constituting Breach
|
|
46
|
|
|
|
22.3
|
|
Notice by Breaching Party
|
|
47
|
|
|
|
22.4
|
|
Cure and Default
|
|
47
|
|
|
|
22.5
|
|
Continued Operations
|
|
47
|
|
|
|
22.6
|
|
Upon Default
|
|
48
|
|
|
|
22.7
|
|
Generator’s Default in Payment for
Equipment
|
|
48
|
|
Article XXIII
|
|
TERMINATION
|
|
48
|
|
|
|
23.1
|
|
Expiration of Term
|
|
48
|
|
|
|
23.2
|
|
Termination in the Event of Default
|
|
48
|
|
|
|
23.3
|
|
Survival
|
|
48
|
|
|
|
23.4
|
|
Disconnection and Disposition of Facilities
Upon Termination
|
|
49
|
|
Article XXIV
|
|
CREDITWORTHINESS
|
|
49
|
|
Article XXV
|
|
RELATIONSHIP OF THE PARTIES
|
|
49
|
|
Article XXVI
|
|
REPRESENTATIONS AND WARRANTIES
|
|
49
|
|
|
|
26.1
|
|
Representations of EPE
|
|
49
|
|
|
|
26.2
|
|
Representations of Generator
|
|
50
|
|
|
|
26.3
|
|
Representations of Each Party
|
|
51
|
|
Article XXVII
|
|
ASSIGNMENT
|
|
51
|
|
|
|
27.1
|
|
General
|
|
51
|
|
|
|
27.2
|
|
EPE
|
|
51
|
|
|
|
27.3
|
|
Generator
|
|
51
|
|
|
|
27.4
|
|
No Relief in Event of Assignment
|
|
51
|
|
Article XXVII
|
|
CONFIDENTIALITY
|
|
51
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
v
|
|
|
|
|
|
|
|
|
|
|
|
|
|
28.1
|
|
General
|
|
51
|
|
|
|
28.2
|
|
Scope
|
|
52
|
|
|
|
28.3
|
|
Rights in Confidential Information
|
|
52
|
|
|
|
28.4
|
|
Standard of Care
|
|
52
|
|
|
|
28.5
|
|
Required Disclosures
|
|
52
|
|
|
|
28.6
|
|
Possession of Confidential Information at
Termination of Agreement
|
|
52
|
|
|
|
28.7
|
|
Remedies Regarding Confidentiality
|
|
52
|
|
Article XXIX
|
|
DISPUTE RESOLUTION
|
|
53
|
|
|
|
29.1
|
|
Dispute Resolution by Operating
Committee
|
|
53
|
|
|
|
29.2
|
|
Dispute Resolution by Senior
Management
|
|
53
|
|
|
|
29.3
|
|
Arbitration
|
|
53
|
|
|
|
29.4
|
|
FERC Jurisdiction Over Certain
Disputes
|
|
54
|
|
|
|
29.5
|
|
Continued Performance
|
|
55
|
|
Article XXX
|
|
MISCELLANEOUS
|
|
55
|
|
|
|
30.1
|
|
Partial Invalidity
|
|
55
|
|
|
|
30.2
|
|
Successors Included
|
|
55
|
|
|
|
30.3
|
|
Applicable Laws and Regulations
|
|
55
|
|
|
|
30.4
|
|
Choice of Law and Jurisdiction
|
|
55
|
|
|
|
30.5
|
|
Entire Agreement
|
|
55
|
|
|
|
30.6
|
|
Counterparts to this Agreement
|
|
56
|
|
|
|
30.7
|
|
Amendments
|
|
56
|
|
|
|
30.8
|
|
Amendments Included
|
|
56
|
|
|
|
30.9
|
|
Notices
|
|
56
|
|
|
|
30.10
|
|
Waivers
|
|
57
|
|
|
|
30.11
|
|
No Third Party Beneficiaries
|
|
57
|
|
|
|
30.12
|
|
Further Assurances
|
|
57
|
|
|
|
30.13
|
|
Headings
|
|
57
|
|
|
|
30.14
|
|
Articles
|
|
57
|
|
|
|
30.15
|
|
Number, Gender, and Inclusion
|
|
58
|
|
|
|
30.16
|
|
Good Utility Practice
|
|
58
|
|
|
|
30.17
|
|
Succession Upon Membership in an RTO
|
|
58
|
|
|
|
30.18
|
|
Notification of Change of Operating
Agent
|
|
58
|
|
|
|
30.19
|
|
Amended and Restated
|
|
58
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
vi
|
|
|
FIRST AMENDED AND RESTATED
INTERCONNECTION AGREEMENT
This First Amended and Restated
Interconnection Agreement (as defined below,
“Agreement”) is made and entered into as of this
9 th day of OCTOBER, 2003, by and between
El Paso Electric Company (“EPE”), a corporation
organized under the laws of the State of Texas, and Public Service
Company of New Mexico (“Generator”), a corporation
organized under the laws of the State of New Mexico.
W I T N E S S E T H
WHEREAS, EPE is engaged in the
transmission and distribution of electric energy in the States of
New Mexico and Texas;
WHEREAS, EPE owns and operates the
new Afton Switching Station near Afton, New Mexico and 345 kV
transmission lines from the existing EPE Transmission System to
Afton Switching Station;
WHEREAS, EPE and Generator have
entered into an Interconnection Agreement on May 23, 2002
(“Interconnection Agreement”);
WHEREAS, Generator has constructed,
owns and operates an electric generating facility (as defined
below, “Facility”) located near Afton, New
Mexico;
WHEREAS, in accordance with the
Interconnection Agreement, Generator has constructed the new Afton
Switching Station and 345 kV transmission lines from Afton
Switching Station to EPE’s existing transmission
system;
WHEREAS, in accordance with the
Interconnection Agreement, Generator has interconnected the
Facility with the EPE Transmission System at the Afton Switching
Station;
WHEREAS, this Agreement does not
provide for transmission, distribution or ancillary services and
separate arrangements are required for such services;
and
WHEREAS, EPE and Generator desire to
amend and restate the Interconnection Agreement by allocating the
costs of interconnection facilities in accordance with FERC policy
as set forth herein.
NOW, THEREFORE, in consideration of the premises
and mutual covenants set forth herein, the Parties agree as
follows:
Article I
DEFINITIONS
For purposes of this Agreement, the
following terms shall have the following meanings.
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
1
|
|
|
|
1.1
|
“Abnormal Condition”
means any condition at the Facility,
on the Interconnected Facilities, on the EPE Transmission System,
or on the transmission system of other utilities which is outside
normal operating parameters such that facilities are operating
outside their normal ratings or reasonable operating limits have
been exceeded and would result in an Emergency if these conditions
continue. Any condition or situation that results from lack of
sufficient planned generating capacity to meet load requirements or
that results solely from economic conditions shall not, standing
alone, constitute an Abnormal Condition.
|
|
1.2
|
“Affiliate” means, with respect to any Person, any other
Person (other than an individual) that, directly or indirectly,
through one or more intermediaries, controls, or is controlled by,
or is under common control with, such Person. For this purpose,
“control” means the direct or indirect ownership of
fifty percent (50%) or more of the outstanding capital stock or
other equity interests having ordinary voting power.
|
|
1.3
|
“Afton
Switching Station” means the 345 kV substation constructed by
Generator, and owned and operated by EPE near Afton, New Mexico as
depicted in Appendices B and E.
|
|
1.4
|
“Agents” means the officers, directors, shareholders,
employees or agents acting on behalf of a Party or group of
Parties.
|
|
1.5
|
“Agreement” means this First Amended and Restated
Interconnection Agreement between EPE and Generator, including
attachments, exhibits, and appendices.
|
|
1.6
|
“Applicable Laws and
Regulations” means
all applicable federal, state and local laws, codes, ordinances,
rules and regulations, and all duly promulgated orders and other
duly authorized actions, as amended from time to time, and whether
now existing or hereafter enacted, promulgated, entered or
otherwise arising, of any Governmental Authority having
jurisdiction over the Parties and/or their respective
facilities.
|
|
1.7
|
“Bankruptcy Laws”
shall have the meaning set forth in
Article 22.2(c).
|
|
1.8
|
“Breaching Party”
shall have the meaning set forth in
Article 22.2.
|
|
1.9
|
“Business Day”
means any day on which the Federal
Reserve member banks are open for business. A Business Day shall
commence at 8:00 a.m. and close at 5:00 p.m., local time, at the
location of the relevant Party’s principal place of business,
or at such other location as the context may require. The relevant
Party, in each instance unless otherwise specified, shall be the
Party to which the notice, payment, or delivery is being sent and
by which the notice, payment, or delivery is being
received.
|
|
1.10
|
“Commercial Operation
Date” means the
first day on which the Facility generates electric energy, other
than test energy, for sale.
|
|
1.11
|
“Commercially Reasonable
Efforts” means
efforts by a Party to perform the particular obligation under this
Agreement using skills, time and funds which are customary and
reasonable in transactions of the kind and nature contemplated by
this Agreement in order for such Party to satisfy such obligation
under this Agreement.
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
2
|
|
|
|
1.12
|
“Confidential
Information” means
any confidential, proprietary, or trade secret information
associated with a plan, specification, pattern, procedure, design,
device, list, concept, policy, or compilation relating to the
present or planned business of a Party (including all information
relating to a Party’s technology, research and development,
business affairs and pricing), which is designated as
“Confidential” by the Party supplying the information,
whether conveyed orally, in writing, electronically, through
inspection, or otherwise prior to or after the Effective Date. Any
Confidential Information designated as such by a Party that is
conveyed in writing or electronically must clearly be designated or
marked as confidential on the face of the document or electronic
transmission. To the extent that the Confidential Information is
designated as such by a Party orally or through inspection, the
Party providing such information must inform the Party receiving
such information that it is Confidential Information.
|
|
1.13
|
“Custodian” shall have the meaning set forth in Article
22.2(c).
|
|
1.14
|
“Due
Diligence” means
the exercise of good faith efforts to perform a required act on a
timely basis and in accordance with Good Utility Practice using the
necessary technical resources and personnel.
|
|
1.15
|
“Effective Date”
means the date set forth in Article
2.1 of this Agreement.
|
|
1.16
|
“Emergency” means (a) a condition or situation which, in the
judgment of the Operating Agent, requires immediate manual or
automatic action to prevent (i) endangerment of life or property,
or (ii) loss of firm load, equipment damage, or tripping of system
elements that could adversely affect the reliability of the EPE
Transmission System or the electrical transmission systems of
others to which the EPE Transmission System is directly or
indirectly connected, and which requires that the output of the
Facility be adjusted to help avoid or mitigate such condition or
situation, and (b) a condition or situation which Generator deems
imminently likely to (i) endanger life or property, or (ii)
adversely affect or impair the reliability of the Facility. The
conditions or situations described in Articles 1.16(a)(ii) and
1.16(b)(ii) include equipment damage, danger of instability,
voltage collapse or uncontrollable cascading outages. Any condition
or situation that results from lack of sufficient planned
generating capacity to meet load requirements or that results
solely from economic conditions shall not, standing alone,
constitute an Emergency.
|
|
1.17
|
“Environmental Laws”
means federal, state, and local
laws, regulations, rules, ordinances, codes, decrees, judgments,
directives, or judicial or administrative orders (and any
amendments thereto) relating to pollution or protection of the
environment, archaeological or natural resources, or human health
and safety, including laws relating to exposures, Releases or
threatened Releases of Hazardous Substances (including Releases or
threatened Releases to ambient air, surface water, groundwater,
land, surface and subsurface strata) or otherwise relating to the
manufacture, processing, distribution, use, treatment, storage,
Release, transport, or handling of Hazardous Substances.
|
|
1.18
|
“EPE” shall have the meaning set forth in the first
paragraph of this Agreement.
|
|
1.19
|
“EPE Control
Area” means the
power system where EPE is responsible for matching generation
within the control area and net transactions with other control
areas with the prevailing real-time
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
3
|
|
|
|
|
electrical load in the control
area, for maintaining within limits generally accepted as Good
Utility Practice scheduled interchange with neighboring control
areas, and for maintaining frequency within reasonable limits in
accordance with Good Utility Practice.
|
|
1.20
|
“EPE
Interconnection Facilities” means all equipment and other facilities,
including Protective Equipment and Metering Equipment owned,
operated and maintained by EPE from the Generator’s side of
air switch 32485 to the Interconnection Point. The EPE
Interconnection Facilities are listed in Appendix B.
|
|
1.21
|
“EPE
OATT” means
EPE’s Open Access Transmission Tariff filed with FERC in
accordance with FERC’s Order No. 888, and any successor
transmission service tariff thereto, including any such successor
tariff of a Regional Transmission Organization to which EPE
transfers operating authority over the EPE Transmission
System.
|
|
1.22
|
“EPE’s Palo Verde
Facilities” means
three 500 kv lines and related facilities, that extend 165 miles in
total from the Palo Verde Nuclear Generating Station near Phoenix,
Arizona, with two of the lines extending to the Westwing substation
and one extending to the Kyrene substation, all facilities entirely
in Arizona.
|
|
1.23
|
“EPE
Transmission System” means all of the facilities owned by EPE,
including the Interconnection System Upgrades that are made
available for the purpose of providing transmission service under
the EPE OATT.
|
|
1.24
|
“Facility” means Generator’s electric generating
facility with an output of 142 MW (Summer) and 149 MW (Winter)
located near Afton, New Mexico, together with the other property,
facilities, and equipment owned and/or operated by Generator up to
and including the output terminals of the generator as indicated in
Appendix A.
|
|
1.25
|
“Federal Power Act”
means the Federal Power Act, 16
U.S.C. § 791a et seq., as amended from time to
time.
|
|
1.26
|
“FERC” means the Federal Energy Regulatory Commission,
or any successor federal agency.
|
|
1.27
|
“General Orders”
means the set of standard operating
procedures, as modified from time to time, by which the Operating
Agent operates the EPE Transmission System and which are applicable
to generating facilities connected to that transmission system,
including, at the Effective Date, the Facility.
|
|
1.28
|
“Generator” shall have the meaning set forth in the first
paragraph of this Agreement.
|
|
1.29
|
“Generator’s Interconnection
Facilities” means
all equipment and other facilities, including certain Protective
Equipment, owned, operated and maintained by Generator, from the
generator output terminals up to the Generator’s side of air
switch 32485 as indicated in Appendices B (Attachment 1) and E,
including any modifications, additions, or upgrades made to such
facilities, which, in conjunction with the EPE Interconnection
Facilities, are necessary to connect the Facility to the EPE
Transmission System at the Afton Switching Station.
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
4
|
|
|
|
1.30
|
“Good
Utility Practice” means any of the practices, methods, and acts
required, approved, or engaged in by the WSCC, NERC, RTO (if
applicable) or a significant portion of the electric utility
industry during the relevant time period, or any of the practices,
methods, and acts which, in the exercise of reasonable judgment in
light of the facts known at the time the decision was made, could
have been expected to accomplish the desired result at a reasonable
cost consistent with good business practices, reliability, safety,
and expedition. Good Utility Practice is not intended to be limited
to the optimum practice, method, or act; rather, it is intended to
be a spectrum of practices, methods, and acts generally accepted by
the electric utility industry in the WSCC region. Good Utility
Practice shall include compliance with Applicable Laws and
Regulations.
|
|
1.31
|
“Governmental Authority”
means any entity with proper
jurisdiction or authority over the Parties and/or their respective
facilities, including (i) a federal, tribal, state, local or
municipal governmental body; (ii) a governmental, regulatory or
administrative agency, commission, body or other authority
exercising or entitled to exercise administrative, executive,
judicial, legislative, policy, regulatory or taxing authority or
power; and (iii) a court or governmental tribunal.
|
|
1.32
|
“Governor Droop”
means the governor response
characteristic (speed versus output characteristic) defining the
decrease in frequency needed to cause generator output to go from
no load to full load.
|
|
1.33
|
“Hazardous Substances”
means (a) any petrochemical or
petroleum products, oil, coal ash, radioactive materials, radon
gas, asbestos in any form that is or could be friable, urea
formaldehyde foam insulation and transformers or other equipment
that contains dielectric fluid that may contain polychlorinated
biphenyls; (b) any chemicals, materials, or substances defined as
or included in the definition of “hazardous
substances,” “hazardous wastes,” “hazardous
materials,” “hazardous constituents,”
“restricted hazardous materials,” “extremely
hazardous substances,” “toxic substances,”
“contaminants,” “pollutants,” “toxic
pollutants,” or words of similar meaning and regulatory
effect under any applicable Environmental Law; or (c) any other
chemical, material, or substance, exposure to which is prohibited,
limited, or regulated by any applicable Environmental
Law.
|
|
1.34
|
“Interconnected
Facilities” means
the EPE Interconnection Facilities and the Generator’s
Interconnection Facilities.
|
|
1.35
|
“Interconnection Point”
means the point where the EPE
Interconnection Facilities attach to the bus bar within the Afton
Switching Station as delineated in Appendices B and E.
|
|
1.36
|
“Interconnection Service”
means the service provided by EPE to
interconnect the Facility, via Generator’s Interconnection
Facilities, with the EPE Transmission System.
|
|
1.37
|
“Interconnection Studies”
means the studies performed by or on
behalf of EPE pursuant to an interconnection request by Generator
which have determined the design, specifications and cost estimate
for the Interconnected Facilities and the Interconnection System
Upgrades required to accommodate the interconnection of the
Facility.
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
5
|
|
|
|
1.38
|
“Interconnection System
Upgrades” means the
additions, modifications, and upgrades to the EPE Transmission
System, including Protective Equipment and Metering Equipment,
required beyond the Interconnection Point to accommodate the
interconnection of the Facility to the EPE Transmission System
through the EPE Interconnection Facilities as identified in
Appendix B, including any modifications, additions, or upgrades
made to such facilities.
|
|
1.39
|
“Interest Rate”
means the prime interest rate for
currency as published from time to time under “Money
Rates” by The Wall Street Journal, or its successor (or, if
no longer so published, any substitute mutually agreeable to the
Parties), as of the payment due date and/or default date, plus two
(2) percent; provided, however, that in no event shall the Interest
Rate exceed the maximum interest rate permitted by Applicable Laws
and Regulations.
|
|
1.40
|
“Metering Equipment”
means all metering equipment to be
installed at the Facility and at or near the Interconnection Point
and Afton Switching Station. Metering Equipment is identified in
Appendices A, B, and D.
|
|
1.41
|
“NERC” means the North American Electric Reliability
Council, or any successor organization.
|
|
1.42
|
“Non-Breaching Party”
shall have the meaning set forth in
Article 22.2(g).
|
|
1.43
|
“Operating Agent”
shall mean the entity that operates
the EPE Transmission System. On the Effective Date of this
Agreement, EPE is the Operating Agent for the EPE Transmission
System.
|
|
1.44
|
“Operating Committee”
shall have the meaning set forth in
Article 4.1.
|
|
1.45
|
“Operation Date”
means the day upon which the
Interconnected Facilities, Interconnection System Upgrades and
Facility have been completed to EPE’s and Generator’s
mutual satisfaction and energized in parallel operation as
confirmed in a written notice provided by EPE to Generator, which
occurred January 1, 2003.
|
|
1.46
|
“Participant”
has the meaning as stated in Article
9.3.
|
|
1.47
|
“Parties” means EPE (including in its capacity as
Operating Agent) and Generator or the successor or permitted
assignee of the rights and obligations of any of the foregoing
under this Agreement.
|
|
1.48
|
“Party” means one of the Parties.
|
|
1.49
|
“Person” means an individual, partnership, corporation
(including a business trust), limited liability company, joint
stock company, trust, unincorporated association, joint venture or
other entity or a government or any political subdivision or agency
thereof.
|
|
1.50
|
“Power
System Stabilizer (PSS)” means a control system applied at a generator
that monitors variables such as current, voltage and shaft speed
and sends the appropriate control signals to the voltage regulator
to damp system oscillations.
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
6
|
|
|
|
1.51
|
“Protective Equipment”
means such protective relay systems,
locks and seals, breakers, automatic synchronizers, associated
communication equipment and other control schemes and protective
apparatus as is reasonably necessary under Good Utility Practice
and standards of EPE for the operation of the Facility in parallel
with the EPE Transmission System and to permit the facilities of
EPE and the Facility to operate reliably and safely.
|
|
1.52
|
“Regional Transmission
Organization” or
“RTO” means an entity approved by FERC to assume
responsibility for providing electric transmission services and
certain operational functions in a specific region in accordance
with FERC Order No. 2000 or any other Applicable Laws and
Regulations (including, but not limited to, other FERC
orders).
|
|
1.53
|
“Release” means any release, spill, leak, discharge,
disposal, pumping, pouring, emission, emptying, injection,
leaching, dumping, escape into or through the environment of any
Hazardous Substance.
|
|
1.54
|
“Reliability Management
System” or
“RMS” means the contractual reliability management
program implemented through the WSCC Reliability Criteria
Agreement, Article IX of this Agreement, and any similar
contractual arrangement(s).
|
|
1.55
|
“Security Coordinator”
means the entity authorized by the
WSCC to have the final authority to direct electric system
operations to prevent or remedy problems or disturbances that have
regional impacts.
|
|
1.56
|
“SOCC” means System Operations Control
Center.
|
|
1.57
|
“Termination Costs”
means the costs incurred by or on
behalf of EPE upon termination of this Agreement in accordance with
Article XXIII in taking one or more of the following actions: (a)
returning or canceling pending orders made by EPE for equipment or
facilities required for the interconnection contemplated by this
Agreement; (b) removing any portion of the EPE Interconnection
Facilities or Interconnection System Upgrades; and (c) performing
such work as may be necessary to ensure the safety of persons and
property and to preserve the integrity of the EPE Transmission
System.
|
|
1.58
|
“Transmission Service
Agreement” means
any transmission service agreements between Generator and EPE,
excluding any agreement for transmission service that is provided
over EPE’s Palo Verde Facilities.
|
|
1.59
|
“WSCC” means the Western Systems Coordinating Council,
or any successor organization.
|
|
1.60
|
“WSCC
Agreement” means
the Western Systems Coordinating Council Agreement dated March 20,
1967.
|
|
1.61
|
“WSCC
Reliability Criteria Agreement” means the Western Systems Coordinating Council
Reliability Criteria Agreement dated June 18, 1999, among the WSCC
and certain members of WSCC.
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
7
|
|
|
Article II
TERM
|
2.1
|
Effectiveness of this Agreement.
Article 2.2 and the fourth sentence
of this Article 2.1 of this Agreement shall become effective upon
execution by the Parties. The remaining provisions of this
Agreement shall become effective on the effective date specified by
FERC in accepting this Agreement (“Effective Date”)
under Section 205 of the Federal Power Act. This Agreement shall
supercede the Interconnection Agreement upon the Effective Date.
Notwithstanding the foregoing and with respect to this Agreement,
no Party shall take any action which is inconsistent with the terms
of this Agreement and Applicable Laws and Regulations during the
period between execution of this Agreement and acceptance by FERC
or earlier termination of this Agreement.
|
2.2.1 Within a reasonable time after
execution of this Agreement by the Parties, EPE shall file this
Agreement with FERC as an amended “Rate Schedule”
within the meaning of Part 35 of FERC’s regulations and with
any other Governmental Authority to the extent required by
Applicable Laws and Regulations. Each of the Parties shall support
this Agreement in its current form at FERC when filed. Generator
shall reasonably cooperate with EPE with respect to obtaining FERC
approval of such FERC filing and provide any information, including
testimony, reasonably required by EPE to comply with the applicable
FERC filing requirements.
2.2.2 Promptly upon execution by the
Parties of any amendment to this Agreement, EPE shall, if
necessary, file such amendment with FERC and with any other
Governmental Authority, to the extent required by Applicable Laws
and Regulations. Each of the Parties shall support any such
amendment at FERC when filed. Generator shall reasonably cooperate
with EPE with respect to obtaining FERC approval of such FERC
filing and provide any information, including testimony, reasonably
required by EPE to comply with the applicable FERC filing
requirements.
2.2.3 If FERC requires conditions to
or modifications of any of the terms, conditions or provisions
agreed to herein or in an amendment hereto and: (i) neither Party
notifies the other Party in writing within fourteen (14) calendar
days following receipt of FERC’s order that the notifying
Party takes exception to FERC’s order, the FERC-ordered
modifications and/or conditions shall become part of this Agreement
as an amendment or appendix; or (ii) the Party taking exception to
FERC’s conditions or modifications gives fourteen (14)
calendar days notice (following receipt of FERC’s order) to
the other Party of such exception, then the Parties shall promptly
negotiate an amendment to this Agreement acceptable to FERC and
providing similar benefit, rights, or effect to the Parties. Any
such amendment shall be effective when accepted for filing by FERC.
For purposes of this Article 2.2.3, each Party reserves and may
exercise all of its rights under Applicable Laws and
Regulations.
|
2.3
|
Term. This Agreement shall continue in full force and
effect until a mutually agreed termination date; provided, however,
that such termination date shall be no later than the date on which
the Facility permanently ceases commercial operation; and provided
further that this
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
8
|
|
|
Agreement may be terminated earlier
(a) upon a Party’s default in accordance with the provisions
of Article 23.2 or (b) by the mutual agreement of the Parties or as
explicitly provided elsewhere in this Agreement. Unless no longer
required by FERC, any termination of this Agreement permitted
hereunder shall not take effect until the filing at FERC of a
notice of termination of this Agreement which notice is accepted
for filing by FERC.
|
2.4
|
Material
Adverse Change. In the
event of a change in law or regulation after the Effective Date
that has a material adverse effect, or may reasonably be expected
to have a material adverse effect, on a Party’s ability to
perform under this Agreement, the Parties shall negotiate in good
faith any amendment or amendments to this Agreement necessary to
adapt the terms of this Agreement to such change in law or
regulation. If the Parties are unable to reach agreement on any
such amendments within sixty (60) days of the commencement of their
negotiations, each Party reserves and may exercise all its rights
under Applicable Laws and Regulations.
|
|
2.5
|
Survival. The applicable provisions of this Agreement
shall continue in effect after cancellation, expiration, or
termination of this Agreement to provide for final billings,
billing adjustments, and the determination and enforcement of
liability and indemnification obligations arising from acts or
events that occurred while this Agreement was in effect. In
addition, upon termination of this Agreement subject to the terms
of Article 23, Generator shall be responsible for any Termination
Costs incurred by or on behalf of EPE.
|
Article III
CONTINUING OBLIGATIONS AND
RESPONSIBILITIES
|
3.1
|
Interconnection Service Provided.
EPE shall provide Generator with
Interconnection Service for the Facility, as such service is
defined in Article 1.36 and described in this Article III. EPE
shall not provide Interconnection Service under this Agreement for
any other generating units, wherever located. Any other generating
units shall be covered by a separate interconnection agreement or
an amendment of this Agreement as provided for in Article
3.2.3.
|
|
3.2
|
Scope of
Interconnection Service.
|
3.2.1 Interconnection Service shall
consist of the services necessary to allow the physical
interconnection of the Facility pursuant to the terms of this
Agreement. Interconnection Service does not mean and shall not
include transmission service, ancillary services, losses, or any
other service available under the EPE OATT. Specifically,
Interconnection Service shall not include the purchase or sale of
energy or ancillary services to or from the Facility beyond the
Interconnection Point, or the delivery of energy or ancillary
services from the Facility beyond the Interconnection Point, which
services shall be provided separately under the EPE OATT or by
others under separate agreements, as applicable.
3.2.2 Generator shall be responsible
for (a) making arrangements under the EPE OATT for transmission and
ancillary services on the EPE Transmission System, and under other
applicable tariffs for such services on other transmission
system(s), associated with the injection or delivery of the
capacity and/or energy produced by the Facility beyond the
Interconnection Point, which services shall not be provided under
the terms of this Agreement, (b) obtaining capacity and/or energy
to satisfy its Facility service or other requirements, and (c)
making
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
9
|
|
|
arrangements under applicable
tariffs for transmission services, losses, and ancillary services
associated with the use of the EPE Transmission System for the
injection or delivery of capacity and/or energy to other generating
facilities owned by Generator for the purpose of supplying facility
service or for any other use. EPE makes no representations to
Generator regarding the availability of transmission service on the
EPE Transmission System, and Generator agrees that the availability
of such transmission service may not be inferred or implied from
this Agreement. Generator must request such transmission service in
accordance with the EPE OATT.
3.2.3 In the event of an increase in
the output of the Facility or other material change or modification
to the configuration and/or operation of the Facility, the Parties
shall negotiate appropriate revisions to this Agreement, including,
as necessary, the performance by EPE of studies to determine the
effects of such increase or change, and changes to the
specifications or requirements set forth in the Appendices to this
Agreement, as necessary to permit EPE to provide Interconnection
Service to the Facility under this Agreement in a safe, secure and
reliable manner.
|
3.3
|
Services
Outside Scope of Agreement.
|
3.3.1 This Agreement provides only
for interconnection of the Facility with the EPE Transmission
System at the Afton Switching Station. Nothing in this Agreement
shall be read as a request by Generator, or a commitment by EPE, to
install any facilities other than those necessary to interconnect
the Facility with the EPE Transmission System at the Afton
Switching Station.
3.3.2 This Agreement does not
obligate any Party to purchase, sell, transmit or otherwise provide
any rights other than Interconnection Service. This Agreement does
not obligate any Party to provide, or entitle any Party to receive,
any transmission or other service not expressly provided for
herein. This Agreement does not provide a right to inject or
transmit energy which right shall be realized through the necessary
arrangements for transmission rights and service, including
mitigation related to transmission service, if any. Each Party is
responsible for making any arrangements necessary for it to receive
any transmission or other service not expressly provided for herein
that it may desire from the other Party or any other Person.
Notwithstanding any other provision of this Agreement, nothing
herein shall be construed as a relinquishment or foreclosure of any
rights to transmission credits to which Generator may be entitled,
now or in the future, as a result of, or otherwise, associated
with, the transmission capacity, if any, created by the
Interconnection System Upgrades, if any.
3.3.3 This Agreement does not
provide for the injection, sale or purchase of power or energy from
or to the Facility. Upon Generator’s request, construction,
back-up, start-up, auxiliary, station, and maintenance power
required for the Facility at the Facility site shall be provided
under a separate agreement or any applicable tariff.
|
3.4
|
No Guarantees;
Release. EPE (which, for
the purposes of this Article 3.4, shall be deemed to include the
Operating Agent) does not warrant against the occurrence of, and
Generator releases EPE from any and all claims or damages
associated with: (a) damage to Generator’s Interconnection
Facilities or the Facility resulting from electrical transients, or
(b) any
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
10
|
|
|
interruption in the availability of
the EPE Interconnection Facilities, or any Interconnection System
Upgrades, except, in the case of subpart (a) or (b), to the extent
determined to be attributable to the negligence of, willful
misconduct of, or default under Article XXII by EPE. Generator does
not warrant against the occurrence of, and EPE releases Generator
from any and all claims or damages associated with: (y) damage to
the EPE Interconnection Facilities, any Interconnection System
Upgrades, or the EPE Transmission System resulting from electrical
transients, or (z) any interruption in the availability of
Generator’s Facility, except, in the case of subpart (y) or
(z), to the extent determined to be attributable to
Generator’s negligence, willful misconduct or default under
Article XXII.
3.5 Reporting
Requirements. Each Party
shall notify the other Party promptly when it becomes aware of its
inability to comply with the terms and conditions of this
Agreement, and provide a sufficient explanation of its inability to
comply, including the date, duration, and reasons for its inability
to comply, and corrective actions taken; provided that such
notification shall not release such Party from its obligation to
comply with this Agreement, except as provided under Article
XIX.
3.6 Third Party Activity.
During the term of this Agreement, other Persons may develop,
construct or acquire, and operate generating facilities in
EPE’s service territory, and reservations of transmission
service by such Persons under the EPE OATT may adversely affect the
availability of transmission service for the Facility’s
electric output. EPE has no obligation to disclose to Generator any
information regarding such third party activity, except as may be
required under the EPE OATT or under this Agreement subject to the
provisions of Article 3.7. To the extent that such third party
activity has, or EPE reasonably expects the third party activity to
have, a material adverse impact on the operation of the Facility or
the Interconnected Facilities, EPE shall, subject to Article 3.7,
disclose to Generator such material information as is necessary for
Generator to understand the nature and extent of such adverse
impact and the viable remedies.
3.7 Compliance with EPE OATT and
FERC Orders No. 888 and No. 889. Nothing in this Agreement
shall be deemed or construed to obligate EPE to provide or make
available to Generator any information in violation of the EPE
OATT, FERC Orders No. 888 and No. 889 or any other Applicable Laws
and Regulations.
Article IV
OPERATING COMMITTEE
4.1 Operating Committee.
Within fifteen (15) days after the Effective Date, each Party shall
designate a primary and alternate representative to serve on an
operating committee (“Operating Committee”), which
shall meet periodically to ensure effective cooperation in system
planning, to deal promptly with the various operating and technical
issues that may arise during the term of this Agreement, and to
attempt to resolve any disputes that may arise under this
Agreement, as more specifically described in Article 4.2. Each
primary and alternate representative shall be authorized, on behalf
of the designating Party, to act with respect to all matters
delegated to the Operating Committee. Each Party shall promptly
notify the other Party of the designation of its primary and
alternate representatives and of any subsequent changes in such
designations in accordance with Article 30.9.
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
11
|
|
|
|
4.2
|
Responsibilities of the Operating
Committee. The Operating
Committee shall have the following responsibilities and functions,
each of which shall be performed consistent with the terms and
conditions of this Agreement and Good Utility Practice: (a) to
establish general policies to be followed in the coordination of
the operation and maintenance of the Interconnected Facilities; (b)
to establish procedures and standard practices, consistent with the
terms and conditions of this Agreement, for guidance for each
Party’s system controllers and other operating personnel
regarding the interconnected operations of the Afton Switching
Station and the Interconnected Facilities; (c) to establish
detailed procedures to govern in the event of an Emergency; (d) to
establish detailed procedures and standard practices for metering,
communications, and control facilities; (e) to establish the plan
for disconnection of the Facility at the termination of this
Agreement; (f) to establish other procedures and standard practices
as may be needed from time to time and to engage in other
activities consistent with the terms and conditions of this
Agreement, provided that the Operating Committee shall not have the
authority to modify or amend any term or condition of this
Agreement; and (g) to attempt to resolve any disputes that may
arise under this Agreement in accordance with Article
29.1.
|
|
4.3
|
Effectiveness of Operating Committee
Determinations. All
determinations made by the Operating Committee, including the
establishment of any procedure or standard practice, within the
scope of the Operating Committee’s responsibilities set forth
in Article 4.2, shall be effective when signed by one designated
representative of each Party and, if necessary, accepted for filing
or approved by FERC.
|
Article V
FACILITY INTERCONNECTION
|
5.1
|
Establishment of Interconnection.
The Facility constructed by
Generator shall be interconnected to the EPE Transmission System at
the Afton Switching Station, such interconnection being further
described in Appendices A, B, and E. Appendix E may be revised by
mutual written agreement of the Parties. Pursuant to this
Agreement, the Parties shall, during the term of this Agreement,
continue in service the existing transmission lines and essential
terminal equipment, to the extent required to establish and
maintain a reliable interconnection.
|
|
5.2
|
Necessary Easements, Permits,
Licenses, Etc. Subject to
Articles 5.6.1 and 5.6.2, each Party shall diligently pursue all
rights, easements, permits, licenses, certificates and properties
necessary to construct, own and maintain its portion of the
Interconnected Facilities and the Interconnection System Upgrades.
If a Party cannot reasonably acquire all the rights, easements,
permits, licenses, certificates and properties necessary to
construct, own and maintain its portion of the Interconnected
Facilities and/or Interconnection System Upgrades, the Party shall
promptly provide written notice to the other Party indicating its
inability. After such notice, Generator shall have thirty (30) days
to authorize EPE to initiate and diligently pursue the following at
Generator’s expense: (a) condemnation proceedings, (b)
alternate routes, designs, methods or procedures necessary for the
construction, ownership, or maintenance of the Interconnected
Facilities and/or Interconnection System Upgrades, or (c) any other
appropriate action mutually agreed upon by the Parties. Each Party
shall also pursue with Due Diligence and maintain all necessary
governmental approvals, permits, licenses and inspections necessary
for its performance of this Agreement. Generator shall also assign
to
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
12
|
|
|
EPE, that portion of
Generator’s rights under the Bureau of Land Management
(“BLM”) Right of Way NMNM102630 (“BLM 102630
R-O-W”) for the land underlying the Interconnection System
Upgrades and the portion of the EPE Interconnection Facilities
delineated as TRACT 3 on Appendix F. Contemporaneous with the
partial assignment of the BLM 102630 R-O-W, the grants of access
pursuant to Articles 5.6.1 and 5.6.2 shall become effective. All
expenses associated with such transfer shall be at
Generator’s cost and shall be a part of the cost of
Interconnection System Upgrades and delineated in Appendix
B.
|
5.3
|
Design and
Construction of Generator’s Interconnection
Facilities.
|
5.3.1 Unless the Parties agree
otherwise in writing, Generator shall, at its own expense, design,
procure, construct, install, operate, maintain and repair/replace
Generator’s Interconnection Facilities.
5.3.2 Protective Equipment to be
installed by Generator is set forth in Appendix A. This Protective
Equipment shall be subject to review and approval by EPE, which
approval shall not be unreasonably withheld or denied. EPE’s
review and/or approval shall not be deemed an endorsement of any
equipment nor as any warranty as to the fitness, safety, durability
or reliability of any equipment.
5.3.3 Generator shall design,
procure, construct and install Generator’s Interconnection
Facilities in accordance with applicable Interconnection Studies
and Good Utility Practice.
5.3.4 At Generator’s expense,
Generator’s Interconnection Facilities shall be constructed
by Generator or, at Generator’s option, a third party
contractor to be selected by Generator. Notwithstanding the
foregoing, Generator understands and agrees that EPE shall be
responsible for closing the connection of the EPE Interconnection
Facilities and Generator’s Interconnection
Facilities.
5.3.5 Generator shall, at its own
expense, operate, maintain and repair/replace Generator’s
Interconnection Facilities in accordance with Articles VIII and
XIII.
|
5.4
|
Design and
Construction of EPE Interconnection Facilities and Interconnection
System Upgrades, and Transmission Credits.
|
5.4.1 At Generator’s expense,
Generator shall design, procure equipment for and construct the EPE
Interconnection Facilities and the Interconnection System Upgrades
required to connect the Facility to the existing EPE Transmission
System.
5.4.2 At Generator’s expense,
EPE will review and approve all design, procurement of equipment
and construction of the EPE Interconnection Facilities and
Interconnection System Upgrades. EPE’s approval shall not be
unreasonably withheld or denied. EPE’s review and/or approval
shall not be deemed an endorsement of any design, facility or
equipment nor as any warranty as to the fitness, safety, durability
or reliability of any design, facility or equipment.
5.4.3 At Generator’s expense,
EPE shall own, operate, maintain, and repair/replace the EPE
Interconnection Facilities.
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
13
|
|
|
5.4.4 EPE shall own the
Interconnection System Upgrades, including Afton Switching Station.
After the Operation Date, EPE shall, at its own expense, operate,
maintain and repair/replace Interconnection System Upgrades in
accordance with Good Utility Practice.
5.4.5 The cost to design, engineer,
procure equipment, and construct the EPE Interconnection Facilities
and the Interconnection System Upgrades is set forth in Appendix B,
subject to audit by EPE pursuant to Article 7.1.3 below.
5.4.6 The schedule for Generator and
EPE to perform the design, procurement of equipment, construction
and testing is set forth in Appendix C .
5.4.7 The design, procurement,
construction and installation of the EPE Interconnection Facilities
and the Interconnection System Upgrades shall be in accordance with
applicable Interconnection Studies and Good Utility Practice. The
EPE Interconnection Facilities and Interconnection System Upgrades
must be sufficient, as designed and built, to deliver the full
Facility output as defined in Article 1.24 to the Interconnection
Point and to enable the Facility to receive capacity necessary to
satisfy its operational requirements (not to exceed 10 MW of
capacity).
5.4.8 As of the Effective Date, the
Parties agree that the Interconnection System Upgrades and the EPE
Interconnection Facilities have been installed. The costs of the
Interconnection System Upgrades and the EPE Interconnection
Facilities, subject to audit by EPE pursuant to Article 7.1.3
below, are delineated in Exhibit B.
5.4.9 Notwithstanding any other
provision of this Agreement, Generator shall not be responsible for
any costs or expenses associated with the design, procurement,
construction, installation, testing, operation, maintenance,
repair/replacement, or any modifications or upgrades to the EPE
Transmission System that are undertaken in order to prevent,
mitigate, or otherwise remedy conditions that existed prior to the
establishment of the interconnection of the Facility with the EPE
Transmission System at the Afton Switching Station, and that were
required or should have been required in order to prevent,
mitigate, or remedy such conditions regardless of, or that
otherwise are unrelated to, such interconnection. To the extent
that Generator has made payment to EPE for any such costs and
expenses, EPE shall refund to Generator such sums, with interest at
the Interest Rate calculated from the date Generator made such
payment(s) to the date Generator receives the refund, within thirty
(30) days of any determination as to the appropriate allocation of
the costs for such modifications or upgrades.
5.4.10 Subject to the provisions of
this section, EPE shall credit Generator against charges for
transmission service under any Transmission Service Agreement in an
amount equal to the cost paid by Generator, including tax gross-up
payments made by Generator to EPE in accordance with Article 7.5,
for the Interconnection System Upgrades, plus interest calculated
at the FERC approved interest rate from the date Generator incurred
costs associated with the construction, engineering and
installation of the Interconnection System Upgrades
(“Transmission Service Credits”); provided, however,
that such credits shall not apply to service under any Transmission
Service Agreement under which transmission service credits or
payments are due for transmission service upgrades until the cost
of such upgrades has been fully amortized through payments by the
Generator. If the amount of any remaining unapplied
Transmission
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
14
|
|
|
Service Credits (including those
held by Generator’s assignee) that exist five (5) years from
the Effective Date is equal to or less than three (3) million
dollars, EPE shall refund such remaining unapplied Transmission
Service Credits to Generator within thirty (30) days after reaching
such five (5) year period, and no further Transmission Service
Credits will be due to Generator or any other Person. If the amount
of any remaining unapplied Transmission Service Credits (including
those held by Generator’s assignee) that exists five (5)
years after the Effective Date is greater than three (3) million
dollars, EPE shall continue to credit Generator against charges for
transmission service under any Transmission Service Agreement until
the date the remaining balance of such unapplied Transmission
Service Credits is equal to three (3) million dollars. Within
thirty (30) days of such date, EPE shall refund three (3) million
dollars to Generator (not to exceed the remaining balance of the
unapplied Transmission Service Credits), and no further
Transmission Service Credits shall be due to Generator or any other
Person. Generator may assign any portion of the Transmission
Service Credits to any Person that purchases the Facility or that
purchases power from the Facility. In the event of such assignment,
EPE will credit the assignee against charges for transmission
services provided to the assignee with respect to power purchased
from the Facility, subject to the limitations set forth above. Such
assigned Transmission Service Credits shall reduce the amount of
Transmission Service Credits available to the Generator on a dollar
for dollar basis. Without limiting the foregoing, Generator will
receive Transmission Service Credits against the charges for
transmission service that EPE has invoiced Generator for service
with respect to the Facility under the existing Transmission
Service Agreement (filed with the FERC on October 29, 2002 in FERC
Docket No. ER03-93-000) from the date such transmission service
commenced thereunder until the Effective Date; provided that within
thirty (30) days after the Effective Date, the Parties shall
reconcile the amount of Transmission Service Credits to be applied
against the charges for transmission service with respect to the
Facility during such period.
|
5.5
|
Subcontractors. Nothing in this Agreement shall prevent any
Party from using the services of subcontractors as it deems
appropriate; provided, however, each Party shall require such
subcontractors to comply with the relevant terms and conditions of
this Agreement. The creation of any subcontractor relationship
shall not relieve the retaining Party of any of its obligations
under this Agreement.
|
5.6.1 Prior to the assignment of a
portion of the BLM 102630 R-O-W, by Generator to EPE in accordance
with Article 5.2, Generator shall provide EPE access to the
Interconnection System Upgrades and the portion of the EPE
Interconnection Facilities located within the Facility property
boundary to enable EPE to perform required operation and
maintenance activities of these facilities in accordance with Good
Utility Practice. Contemporaneous with the assignment of a portion
of the BLM 102630 R-O-W, Generator grants EPE at no cost to EPE and
the Operating Agent, as applicable, access, easements, or licenses
upon, over, under, and across TRACTS 1 and 2 as delineated on
Appendix F that are necessary for EPE and the Operating Agent, as
applicable, and their Agents and subcontractors to design, procure,
construct, install, test, operate, maintain and repair/replace the
EPE Interconnection Facilities and the Interconnection System
Upgrades in accordance with the terms of this Agreement. With
respect to TRACT 2 both before and after the assignment of a
portion of BLM 102630 R-O-W, EPE or Operating Agent shall exercise
such access rights without notification of or supervision
by
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
15
|
|
|
Generator. With respect to TRACT 3
before the assignment of a portion of BLM 102630 R-O-W, EPE shall
exercise such access rights without notification of or supervision
by Generator, except for the area inside the Afton Switching
Station, which area will be subject to the notification
requirements in the Afton Generating Plant Operating Procedures.
With respect to TRACT 1 both before and after the assignment of a
portion of the BLM 102630 R-O-W EPE or Operating Agent shall
exercise such access rights only with supervision by Generator. EPE
or Operating Agent shall provide Generator reasonable notice under
the circumstances of any request for such supervised access, and
Generator and EPE shall mutually agree upon a date and time of such
supervised access and such agreement shall not be unreasonably
withheld or delayed. In addition to the aforementioned requirement,
in exercising such supervised access rights, EPE and the Operating
Agent, as applicable, shall (a) not unreasonably disrupt or
interfere with normal operations of Generator’s business, (b)
act in a manner consistent with Good Utility Practice, and (c)
adhere to the safety rules and procedures established by Generator.
Generator shall execute such documents as EPE and the Operating
Agent, as applicable, may reasonably require to enable EPE or the
Operating Agent, as applicable, to establish record evidence of
such access rights. Such access rights shall remain in effect for
so long as this Agreement is in effect.
5.6.2 Contemporaneous with the
assignment of a portion of the BLM 102630 R-O-W by Generator to EPE
in accordance with Article 5.2, EPE grants, at no cost to
Generator, all access, easements or licenses upon, over, under and
across TRACT 3 as delineated on Appendix F that are necessary for
Generator and its Agents and subcontractors to design, procure,
construct, install, test, operate, maintain and repair/replace
Generator’s Interconnection Facilities, EPE Interconnection
Facilities, and Facility, as applicable, in accordance with the
terms of this Agreement. Such access rights for Generator’s
facilities located inside the Afton Switching Station shall be
exercised by Generator only with supervision by EPE or the
Operating Agent, as applicable. Generator shall provide EPE or the
Operating Agent, as applicable, reasonable notice under the
circumstances of any request for such supervised access to the
Afton Switching Station, and EPE or Operating Agent, as applicable,
and Generator shall mutually agree upon the date and time of such
supervised access, such agreement not to be unreasonably withheld
or delayed. In addition to the aforementioned requirement, in
exercising such access rights, Generator shall (a) not unreasonably
disrupt or interfere with normal operations of EPE or the Operating
Agent, (b) act in a manner consistent with Good Utility Practice,
and (c) adhere to the safety rules and procedures established by
the Operating Agent and EPE. EPE or the Operating Agent, as
applicable, shall execute such documents as Generator may
reasonably require to enable it to establish record evidence of
such access rights. Such access rights shall remain in effect for
so long as this Agreement is in effect.
5.6.3 Any Party or its
subcontractors performing construction, or other work, on the
property of the other Party shall be responsible for proper
housekeeping during the period the work is being performed and
proper clean-up of the property in a timely fashion after the work
is completed.
|
5.7
|
Course and
Completion of Construction.
|
5.7.1 Generator shall promptly
notify EPE in writing when the construction of Generator’s
Interconnection Facilities and the EPE Interconnection Facilities
is complete. Likewise, each
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
16
|
|
|
Party shall promptly notify the
other Party in writing when the construction of the Interconnection
System Upgrades is complete.
5.7.2 Generator shall keep the
Generator’s Interconnection Facilities, the EPE
Interconnection Facilities, Interconnection System Upgrades, and
any real or personal property of EPE related to this
interconnection project free and clear of all Generator,
contractor, subcontractor, supplier or materialmen’s liens,
claims and encumbrances arising out of the construction of the
Generator’s Interconnection Facilities, the EPE
Interconnection Facilities and Interconnection System Upgrades.
Generator shall provide to EPE lien waivers from Generator and all
such contractors, subcontractors, suppliers or materialmen before
or upon completion of the Generator’s Interconnection
Facilities, the EPE Interconnection Facilities and Interconnection
System Upgrades. In the event that any such lien arising out of the
construction of the Generator’s Interconnection Facilities,
the EPE Interconnection Facilities and Interconnection System
Upgrades shall nevertheless be filed or asserted against the real
or personal property of EPE, Generator agrees to take all steps
necessary and proper for the release and discharge of such liens in
the manner allowed under New Mexico law. Generator shall indemnify
and hold EPE harmless against any and all loss, claims, or suits
(including costs and attorneys’ fees), for any lien claims
asserted or filed by any party on or against EPE’s real or
personal property relating to the construction of Generator’s
Interconnection Facilities, the EPE Interconnection Facilities and
the Interconnection System Upgrades.
5.8.1 Generator shall use
Commercially Reasonable Efforts to design, procure, construct,
install, and test Generator’s Interconnection Facilities and
EPE Interconnection Facilities in accordance with the schedule set
forth in Appendix C, which schedule may be revised from time to
time by mutual agreement of the Parties.
5.8.2 Each Party shall use
Commercially Reasonable Efforts to design, procure, construct,
install, and test the Interconnection System Upgrades, in
accordance with the schedule set forth in Appendix C, which
schedule may be revised from time to time by mutual agreement of
the Parties. EPE shall, at Generator’s request and expense,
take all appropriate actions to accelerate its work under this
Agreement in order to meet the schedule set forth in Appendix C,
provided that Generator authorizes such actions and the costs
associated therewith in advance and pays such costs in accordance
with the payment schedule mutually agreed upon by the
Parties.
5.8.3 If any of the Interconnection
System Upgrades is not reasonably expected to be completed prior to
the Commercial Operation Date of the Facility, Generator may, at
its option, have operating studies performed at its expense to
determine the maximum allowable output of the Facility, based upon
the portion of the Interconnection System Upgrades that is expected
to be completed prior to such Commercial Operation Date and,
subject to EPE’s standards and Good Utility Practice,
Generator will be permitted to operate the Facility, provided such
limited operation of the Facility does not adversely affect the
safety and reliability of the EPE Transmission System.
|
5.9
|
Environmental Compliance and
Procedures. The Parties
shall comply with (a) all applicable Environmental Laws in meeting
all their obligations under this Agreement; and (b) all
local
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
17
|
|
|
|
|
notification and response
procedures required for all applicable environmental and safety
matters which affect the ability of the Parties to meet their
respective obligations under this Agreement.
|
|
5.10
|
Generator
Modeling Data. Generator
shall provide the Operating Agent and EPE with such final modeling
data of the Facility and Interconnected Facilities that reflect
final Facility unit data and settings of the generation protection
and control equipment as is reasonably requested by the Operating
Agent and EPE and is necessary for reliable operation of the EPE
Transmission System, including (a) the turbine speed/load controls
including the governor; and (b) the excitation system including the
automatic voltage regulator, power system stabilizer,
over-excitation controls and limits, and other controls and limits.
Such modeling data is to be provided in the format of the computer
programs utilized by the Operating Agent and EPE. On the Operation
Date, such programs are: Powerflow-General Electric PSLF; Transient
Stability-General Electric PSLF; Short Circuit-Aspen One
Liner.
|
|
5.11
|
Equipment
Requirements. All
equipment shall be of utility grade that meets or exceeds the
quality of the equipment as required by EPE. The trip energy source
for the interconnection breaker shall be of a stored energy type
(i.e., battery) that will be available under circumstances when the
alternating current source is unavailable. Generator shall ensure
that Generator’s Interconnection Facilities comply with all
applicable requirements of the National Electrical Safety Code, as
amended from time to time, and/or any Applicable Laws and
Regulations.
|
|
5.12
|
Required
Diagrams. Generator shall
maintain the following equipment at locations approved by the
Operating Agent, which approval shall not be unreasonably withheld
or denied: (a) a permanent and weatherproof one-line electrical
diagram of the Facility located at the Facility site; and (b) a
permanent and weatherproof map of the Facility showing the location
of all major equipment. EPE shall maintain, at locations approved
by Generator, which approval shall not be unreasonably withheld or
denied, a permanent and weatherproof one-line diagram of the EPE
Interconnection Facilities.
|
|
5.13
|
Required
Personnel Information. No
later than fifteen (15) Business Days after the Effective Date,
Generator shall provide the Operating Agent the names and current
telephone numbers of at least two (2) persons who are authorized to
provide access to the Facility and who have authority to make
decisions regarding the Facility, Generator’s Interconnection
Facilities, and Generator’s operations. Generator shall keep
the names and telephone listings current at all times during the
term of this Agreement.
|
|
5.14
|
Use of Afton
Switching Station by Third Parties.
|
5.14.1 If required by Applicable
Laws and Regulations, or if EPE in its sole discretion allows one
or more third parties to use Afton Switching Station, or any part
thereof, and such use decreases the capacity of Afton Switching
Station available to the Facility, or otherwise causes any
detriment to the Facility or to Generator, or benefits any party
(including EPE) other than Generator, then Generator and such third
party (parties) shall negotiate in good faith to determine the
appropriate compensation due to Generator as a result of such third
party use and to determine the appropriate allocation of the annual
carrying charges. EPE shall include a provision comparable to this
Article 5.14.1 in its agreements with third party users providing
for
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
18
|
|
|
such third party users to
participate in such negotiations. In any case, the Generator shall
only be entitled to receive a reduction in charges under this
Agreement equal to the amount of charges allocated to the third
party user(s) (with a corresponding reduction in credits against
the cost of transmission service in accordance with Article
5.4.10). If the issue of such compensation or allocation cannot be
resolved through such negotiations, it shall be submitted to the
FERC for resolution.
5.14.2 If one or more third parties
are to use Afton Switching Station in accordance with this Article
5.14 and the Operating Agent determines that, as a result, Good
Utility Practice requires that modifications be made to the
Interconnected Facilities, the Operating Agent must comply with
notification and scheduling provisions of Article 5.15. In no event
shall Generator be responsible for the costs of any such
modifications.
5.14.3 If it is determined by the
FERC or any Governmental Authority that any costs associated with
the design, engineering, construction, procurement, or installation
of any of the EPE Interconnection Facilities or Interconnection
System Upgrades paid for by Generator pursuant to this Agreement
are not Generator’s responsibility, EPE shall refund to
Generator, no later than sixty (60) days after the determination by
FERC or any Governmental Authority, that portion of the costs paid
by Generator that are included in the transmission revenue
requirement or were paid by Generator and that have not been
reflected in credits, if any, against the cost of transmission
service from the Facility, with interest at the Interest
Rate.
|
5.15
|
Interconnected Facilities and Facility
Additions, Modifications or Replacements.
|
5.15.1 EPE Interconnection
Facilities and EPE Transmission System.
|
|
(a)
|
Any additions
to, modifications to, or replacements of the EPE Interconnection
Facilities must be constructed and operated in accordance with Good
Utility Practice. If such additions, modifications, or replacements
made after the Operation Date will likely cause a material adverse
effect on Generator’s operation of the Facility, the
Operating Agent will, except in cases of Emergency, provide a
minimum of thirty (30) days’ advance written notice to
Generator prior to undertaking such additions, modifications, or
replacements. In the written notice, the Operating Agent must
advise Generator when such additions, modifications or replacements
are expected to be made; the time period expected to be required to
complete such additions, modifications or replacements; and
whether, if known, such additions, modifications or replacements
are expected to interrupt or curtail the flow of electricity from
the Facility. The Parties shall mutually agree in advance upon a
schedule for such additions, modifications or replacements, such
agreement not to be unreasonably withheld or delayed.
|
|
|
(b)
|
Unless required by Applicable
Laws and Regulations, Generator shall not be responsible for the
costs of any additions, modifications, or replacements made to the
EPE Transmission System by EPE, in its sole
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
19
|
|
|
|
|
discretion, after the Operation
Date in order to facilitate (a) the interconnection of a third
party or (b) the provision of transmission service to or for a
third party. Generator shall, however, be responsible for all costs
of any additions, modifications, or replacements made to the EPE
Transmission System as a result of any additions, modifications, or
replacements made by Generator to the Facility.
|
|
|
(c)
|
If any
additions, modifications, or replacements to the EPE
Interconnection Facilities (other than those caused by additions,
modifications, or replacements made by the Generator to the
Facility) cause a material adverse effect on the Generator’s
Interconnection Facilities or the interconnection of the Facility
(via Generator’s Interconnection Facilities) to the EPE
Transmission System at the Afton Switching Station, EPE shall be
responsible, at its sole cost and expense, for all actions
necessary to mitigate such effect on the interconnection
(“Mitigation Actions”) and, if necessary, to promptly
and expeditiously re-establish the connection of the Facility (via
Generator’s Interconnection Facilities) with the EPE
Transmission System at the Afton Switching Station, in accordance
with Good Utility Practice and/or secure such services as are
necessary to deliver the capacity and energy to the Interconnection
Point in accordance with Good Utility Practice (“Reconnection
Activities”); provided, however, that, if EPE is required by
Applicable Laws and Regulations or the RTO (if applicable) to
undertake such additions, modifications, or replacements, EPE shall
not be required to undertake any Mitigation Action or Reconnection
Activity.
|
5.15.2 Generator’s
Interconnection Facilities and Facility. Except for changes deemed
by the Operating Agent to be necessary to ensure the protection and
safety of a Party’s personnel and the safety and reliability
of a Party’s property, Generator shall not be required to
make any modifications to the Facility or Generator’s
Interconnection Facilities unless such change is consistent with
Good Utility Practice and required (i) as a result of a change in
the Facility or (ii) as a result of a change on the EPE
Transmission System which is required by Good Utility Practice.
Generator shall not be responsible for the cost of any such
modifications and the cost of operating and maintaining such
modifications unless required by Applicable Laws and Regulations or
such modifications are required as a result of a change in the
Facility made by Generator.
Article VI
ACCEPTANCE AND PERFORMANCE TESTING
AND COMPLIANCE MONITORING
|
6.1
|
Responsibility for Testing.
|
6.1.1 Prior to the Operation Date,
Generator shall perform all testing of the Facility and
Generator’s Interconnection Facilities required by the RTO
(if applicable), NERC and WSCC. EPE or the Operating Agent, as
applicable, may require Generator to perform additional
testing
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
20
|
|
|
whenever EPE or the Operating Agent
reasonably determines that such additional testing is required for
reliability reasons. All testing shall be successfully completed
before the Operation Date. Testing subsequent to the Operation Date
shall be performed in compliance with the frequency requirements of
NERC, WSCC, and the RTO (if applicable) and any other reliability
requirements of any other organization/entity with responsibility
for electricity and whose requirements Generator is obligated to
follow. All such tests shall be performed to the specifications of
NERC, WSCC, the RTO (if applicable), or any other specifications
required by new or other reliability organizations with
responsibility for electricity and whose requirements Generator is
obligated to follow. Generator shall inform EPE or the Operating
Agent, as applicable, in advance (whenever possible, a minimum of
five (5) Business Days) when such tests are scheduled to occur, and
EPE shall have the right to have representatives observe and
monitor such tests. The cost of all such testing shall be borne by
Generator.
6.1.2 Prior to the Operation Date,
EPE or the Operating Agent, as applicable, shall perform all
testing of the EPE Interconnection Facilities and the
Interconnection System Upgrades required by NERC, WSCC and the RTO
(if applicable). All testing shall be successfully completed before
the Operation Date. After the Operation Date, the Operating Agent
and EPE shall test their facilities at their own expense (or, in
the case of the Operating Agent, the EPE Interconnection Facilities
at the expense of EPE) in accordance with Good Utility Practice.
Generator shall have the right, upon five (5) Business Days’
advance written notice to the Operating Agent or EPE to require
additional testing of such entity’s facilities, at
Generator’s expense, if Generator reasonably believes that
such entity’s facilities are causing a material adverse
effect on the operation of the Facility or Generator’s
Interconnection Facilities, or as may be otherwise prudent in
accordance with Good Utility Practice, and shall have the right to
be present during such tests.
|
6.2
|
Responsibility for Modifications Following
Testing. Based upon the
pre-operational testing, Generator is responsible for making any
modifications necessary to ensure the safe and reliable operation
of Generator’s Interconnection Facilities and the EPE
Interconnection Facilities in accordance with Good Utility
Practice; EPE is responsible for making any modifications necessary
to ensure the safe and reliable operation of the Interconnection
System Upgrades in accordance with Good Utility Practice. The costs
of all such modifications are to be borne by Generator, except to
the extent the modifications are required as a result of the sole
negligence or willful misconduct of EPE, or any Agent of
EPE.
|
|
6.3
|
Documentation of Results to EPE or the Operating
Agent. Generator shall
provide EPE or the Operating Agent, as applicable, with necessary
documentation of all test results for all tests performed pursuant
to Article 6.1.1. The documentation shall be, at a minimum, that
required to conform with any RTO, NERC or WSCC
requirements.
|
|
6.4
|
Facility
Certification. Generator
shall comply with any facility certification requirements of NERC,
WSCC, and the RTO (if applicable).
|
|
6.5
|
Transmission
Service During Testing. Generator has sole responsibility to make
necessary arrangements under the EPE OATT to procure any
transmission service over the EPE Transmission System that may be
required to accommodate the testing procedures of the
Facility.
|
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
21
|
|
|
|
6.6
|
EPE
Inspection Rights. EPE
(which, for the purposes of this Article 6.6, shall be deemed to
include the Operating Agent) shall have the right, but shall have
no obligation or responsibility, to: (a) observe Generator’s
tests and/or inspection of any of Generator’s Protective
Equipment; (b) review the settings of Generator’s Protective
Equipment; and (c) review Generator’s maintenance records
relative to the Generator’s Protective Equipment. EPE may
exercise the foregoing rights from time to time as it deems
necessary upon five (5) Business Days’ written notice to
Generator. However, the exercise or non-exercise by EPE of any of
the foregoing rights of observation, review or inspection shall be
construed neither as an endorsement or confirmation of any aspect,
feature, element, or condition of the Facility or Generator’s
Protective Equipment or the operation thereof, nor as a warranty as
to the fitness, safety, durability, or reliability of
same.
|
|
6.7
|
Generator
Inspection Rights. Generator, upon five (5) Business Days’
advance written notice to the Operating Agent has the right, but
not the obligation, to inspect or observe the operation and
maintenance activities, equipment tests, installation,
construction, or other modifications to the EPE Interconnection
Facilities which could cause a material adverse effect on
Generator’s operations. However, the exercise or non-exercise
by Generator of any of the foregoing rights of observation, review
or inspection shall be construed neither as an endorsement or
confirmation of any aspect, feature, element, or condition of the
EPE Interconnection Facilities or the operation thereof, nor as a
warranty as to the fitness, safety, durability, or reliability of
same.
|
|
6.8
|
EPE’s
Reviews, Inspections, and Approvals. EPE’s or Operating Agent’s review,
inspection, and approval, related to the Generator’s
Interconnection Facilities and EPE’s Interconnection
Facilities required under this Agreement shall not be unreasonably
withheld or delayed, and will be limited to the purpose of ensuring
the safety, reliability, protection and control of the EPE
Transmission System.
|
Article VII
INTERCONNECTION FACILITY COSTS AND
BILLING
|
7.1
|
Interconnection Construction Completion and
Cost.
|
7.1.1 Notification of Delay. If any
event occurs that will materially affect the time for completion of
the Interconnection System Upgrades, or the ability to complete
them, the Party responsible for the construction of the affected
portion of the Interconnection System Upgrades shall, within five
(5) Business Days of its knowledge of any such event, notify the
other Party . In such circumstances, the responsible Party shall,
within ten (10) Business Days of notifying the other Party of such
an event and corresponding delay, convene a technical meeting with
the other Party to evaluate the alternatives available to the other
Party. The responsible Party also shall make available to the other
Party all studies and work papers related to the event and
corresponding delay, including all information that is in the
responsible Party’s possession that is reasonably needed by
the other Party to evaluate alternatives.
7.1.2 Cost Estimate. Pursuant to
Article 5.4.5 and delineated in Exhibit B and subject to audit by
EPE pursuant to Article 7.1.3 below, the Parties have established
the cost to design,
|
|
|
|
|
|
|
First Amended and
Restated
Interconnection Agreement
between
El Paso Electric Company
and
Public Service Company of New
Mexico
|
|
22
|
|
|
engineer, procure equipment, and
construct the Interconnection System Upgrades and the EPE
Interconnection Facilities.
7.1.3 Audit of Cost. Each Party
shall have the right to receive such cost information as is
reasonably necessary to verify the cost of the Interconnection
System Upgrades and the EPE Interconnection Facilities constructed
by the other Party and that such cost was incurred in accordance
with Good Utility Practice. EPE shall have the right to receive
such cost information as is reasonably necessary to verify the cost
of Generator’s activities associated with the Interconnection
System Upgrades and the EPE Interconnection Facilities and that
such costs were incurred in accordance with Good Utility Practice.
Each Party shall have the right to audit (a) the othe |