Back to top

UNILATERAL CHANGE ORDER FORM

Independent Contractor Agreement

UNILATERAL CHANGE ORDER FORM You are currently viewing:
This Independent Contractor Agreement involves

CHENIERE ENERGY INC | Sabine Pass LNG, L.P.

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: UNILATERAL CHANGE ORDER FORM
Date: 3/13/2006
Industry: OILPRD    

Search Independent Contractor Agreement by:

Document Title:

Entire Document: (optional)

50 of the Top 250 law firms use our Products every day
Change Order 1-27

EXHIBIT 10.15

SCHEDULE D-2

UNILATERAL CHANGE ORDER FORM

 

 

 

 

PROJECT NAME: Sabine Pass LNG Receiving,

  

CHANGE ORDER NUMBER: SP/BE-001

Storage and Regasification Terminal

  

 

 

  

DATE OF CHANGE ORDER: January 18, 2005

 

 

OWNER: Sabine Pass LNG, L.P.

  

Increase Sendout Pressure to 1440 PSIG

 

 

CONTRACTOR: Bechtel Corporation

  

 

 

 

DATE OF AGREEMENT: December 18, 2004

  

 

 


You are hereby directed to make the following additions or modifications to, or deductions from, the Work: (attach additional documentation if necessary)

Increase sendout pressure of the Natural Gas as measured at the back-pressure control valve located just upstream of the Master Meter from 1250 psig to 1440 psig. Piping from outlet of the high pressure sendout pumps through to and including the last flange of the LNG terminal shall be ANSI Class 900 lb. Temperature of sendout gas and all other requirements of the Minimum Acceptance Criteria and the Performance Guarantees as specified in Attachment S and Attachment T of the Agreement shall be remain the same.

Contractor shall proceed with design solely on the basis of a 1440 psig sendout pressure and prepare the required documentation, including a completed Schedule D-3 in accordance with Article 6.1A of the Agreement.

 


Compensation for the changes specified in this Change Order is on a time and materials basis as provided in Section 6.1C and 6.2D of the Agreement.

Contractor shall commence with the performance of the change(s) described above on January 18, 2005.

This Change Order is signed by Owner’s duly authorized representative.

 

 

 

/s/    Ed Lehotsky

Owner Representative

Ed Lehotsky

 

 

 

January18, 2005

Date of signing

 


SCHEDULE D-1

CHANGE ORDER FORM

 

 

 

 

PROJECT NAME: Sabine Pass LNG Receiving,

  

CHANGE ORDER NUMBER: SP/BE-002

Storage and Regasification Terminal

  

 

 

  

DATE OF CHANGE ORDER: February 7, 2005

 

 

OWNER: Sabine Pass LNG, L.P.

  

 

 

 

CONTRACTOR: Bechtel Corporation

  

 

 

 

DATE OF AGREEMENT: December 18, 2004

  

 

 


The Agreement between the Parties listed above is changed as follows:


Adjustment to Contract Price

 

 

 

 

 

The original Contract Price was

  

$

646,936,000

Net change by previously authorized Change Orders (#                )

  

$

0

The Contract Price prior to this Change Order was

  

$

646,936,000

The Contract Price will be increased by this Change Order in the amount of

  

$

1,500,000

The new Contract Price including this Change Order will be

  

$

648,436,000

Adjustment to dates in Project Schedule

The following dates are modified (list all dates modified; insert N/A if no dates modified):

The Target Bonus Date will be unchanged.

The Target Bonus Date as of the date of this Change Order therefore is 1,095 Days following NTP

The Guaranteed Substantial Completion Date will be unchanged.

The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is 1,247 Days following NTP

Adjustment to other Changed Criteria: The Tank Subcontract will be awarded to MHI/MSI

Adjustment to Milestone Payment Schedule, Schedule C-1:

 

 

 

Milestone Number 2.02, LNG Tank Subcontract Awarded, will be increased by $1,500,000 from $3,234,680 to $4,734,680. The entire $1,500,000 increase will be provided as an increased payment to the LNG Tank Subcontractor MHI/MSI

 

 

 

Milestone Number 4.03, “LNG Tank test piling started,” will be decreased by $350,000 from $3,234,680 to $2,784,680 to offset the payment to MHI/MSI for LNTP, as described in the Adjustment to Payment Schedule, Schedule C-2 below

Adjustment to Monthly Payment Schedule, Schedule C-2:

 

 

 

Payment for Month #2, Feb-05, will be increased by $350,000 from $2,005,502 to $2,355,502. The entire $350,000 increase will be provided as a payment for Limited Notice to Proceed to the LNG Tank Subcontractor MHI/MSI

Adjustment to Minimum Acceptance Criteria: None


Adjustment to Design Basis: None

Other adjustments to liability or obligation of Contractor or Owner under the Agreement:

MHI/MSI shall be awarded the Tank Subcontract

This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change as described in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change.

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties, duly authorized representatives.

 

 

 

 

 

 

 

 

 

/s/ Charif Souki

 

 

 

/s/ C. Asok Kumar

* Charif Souki

Chairman

 

 

 

Contractor

 

 

 

 

C. Asok Kumar

 

 

 

 

Name

 

 

 

 

 

 

 

Project Director

 

 

 

 

Title

 

 

 

   

 

 

 

February 7, 2005

Date of Signing

 

 

 

Date of Signing

 

 

 

/s/ Keith Meyer

 

 

 

 

* Keith Meyer

President

 

 

 

 

 

 

 

February 7, 2005

 

 

 

 

Date of Signing

 

 

 

 

 

 

 

/s/ Ed Lehotsky

 

 

 

 

* Ed Lehotsky

Owner Representative

 

 

 

 

 

 

 

February 7, 2005

 

 

 

 

Date of Signing

 

 

 

 

 

*

Required Owner signature


SCHEDULE D-2

UNILATERAL CHANGE ORDER FORM

 

 

 

 

PROJECT NAME: Sabine Pass LNG Receiving,

  

CHANGE ORDER NUMBER: SP/BE-003

Storage and Regasification Terminal

  

 

 

  

DATE OF CHANGE ORDER: January 25, 2005

 

 

OWNER: Sabine Pass LNG, L.P.

  

 

 

 

CONTRACTOR: Bechtel Corporation

  

 

 

 

DATE OF AGREEMENT: December 18, 2004

  

 

 


You are hereby directed to make the following additions or modifications to, or deductions from, the Work

Contractor shall delete the High Pressure Compressor from its scope (included in the reimbursable scope) and instead install only the tie-ins and space necessary for a “Future” diesel driven compressor. All other requirements of the Agreement shall remain the same.

Discussions with FERC indicate that they feel a High Pressure Sendout Compressor is required in case the LNG Tanks are de-inventoried in order to “mothball” the LNG Terminal. Since this is a very remote possibility, and since venting of this gas is neither a safety nor environmental concern, Owner will present formal arguments to FERC to delete this requirement. Failing this, Owner will propose to FERC that only connections and space are provided for this compressor. If the Terminal is mothballed, Owner will purchase or rent a portable compressor(s), heater, and other equipment, install it, and accomplish the required transfer to the pipeline.

Contractor shall proceed with design as described above and prepare the required documentation, including a completed Schedule D-3 in accordance with Article 6.1A of the Agreement.

Contractor shall commence with the performance of the change(s) described above on January 25, 2005.

This Change Order is signed by Owner’s duly authorized representatives.

 

 

 

 

 

 

 

 

 

/s/ Charif Souki

 

 

 

/s/ Keith Meyer

* Charif Souki

Chairman

 

 

 

* Keith Meyer

President

 

 

 

 

 

 

 

 

February 11, 2005

 

 

 

February 9, 2005

Date of Signing

 

 

 

Date of Signing

 

 

 

 

 

 

 

 

 

 

 

/s/ Ed Lehotsky

 

 

 

 

* Ed Lehotsky

Owner Representative

 

 

 

 

 

 

 

 

 

 

 

 

January 25, 2005

 

 

 

 

Date of Signing

 

 

 

 

 

*

Required Owner signature


SCHEDULE E-1

CHANGE ORDER FORM

 

 

 

 

PROJECT NAME: Sabine Pass LNG Receiving,

  

CHANGE ORDER NUMBER: SP/BE-004

Storage and Regasification Termina100l

  

 

 

  

DATE OF CHANGE ORDER: 03/22/2005

 

 

OWNER: Sabine Pass LNG, L.P.

  

 

 

 

CONTRACTOR: Bechtel Corporation

  

 

 

 

DATE OF AGREEMENT: December 18, 2004

  

 

 


The Agreement between the Parties listed above is changed as follows: Approval of Change Orders via Schedule D-1 and D-2 (Rev. 1) of the EPC Agreement will require the signatures of both Messrs. Charif Souki and Keith Meyer, in addition to the designated Owner Representative, Ed Lehotsky. This requirement will not apply to any other correspondence under the EPC Agreement.

A revised copy of Schedules D-1 and D-2 is attached reflecting the above change.

 


Adjustment to Contract Price

 

 

 

 

 

The original Contract Price was

 

$

646,936,000

Net change by previously authorized Change Orders (#SP/BE-002)

 

$

1,500,000

The Contract Price prior to this Change Order was

 

$

648,436,000

The Contract Price will be unchanged by this Change Order in the amount of

 

$

0

The new Contract Price including this Change Order will be

 

$

648,436,000

Adjustment to dates in Project Schedule

The following dates are modified (list all dates modified; insert N/A if no dates modified):

The Target Bonus Date will be unchanged.

The Target Bonus Date as of the date of this Change Order therefore is 1,095 Days following NTP.

The Guaranteed Substantial Completion Date will be unchanged.

The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is 1,247 Days following NTP.

Adjustment to other Changed Criteria: None

Adjustment to Payment Schedule: None

Adjustment to Minimum Acceptance Criteria: None

Adjustment to Performance Guarantees: None

Adjustment to Design Basis: None

Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A

 

1


This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change as described in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change.

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.

 

 

 

 

 

 

 

 

 

/s/ Charif Souki

 

 

 

/s/ C. Asok Kumar

* Charif Souki

Chairman

 

 

 

Contractor

 

 

 

 

C. Asok Kumar

 

 

 

 

Name

 

 

 

 

 

 

 

Project Director

 

 

 

 

Title

 

 

 

   

 

 

 

March 31, 2005

Date of Signing

 

 

 

Date of Signing

 

 

 

/s/ Keith Meyer

 

 

 

 

* Keith Meyer

President

 

 

 

 

 

 

 

March 29, 2005

 

 

 

 

Date of Signing

 

 

 

 

 

 

 

/s/ Ed Lehotsky

 

 

 

 

* Ed Lehotsky

Owner Representative

 

 

 

 

 

 

 

   

 

 

 

 

Date of Signing

 

 

 

 

 

*

Required Owner signature

 

2


SCHEDULE D-1

CHANGE ORDER FORM

 

<

 

 

 

PROJECT NAME: Sabine Pass LNG Receiving,

  

CHANGE ORDER NUMBER: SP/BE-005

Storage and Regasification Terminal

  

 

 

  

DATE OF CHANGE ORDER: 3/23/2005

 

 

OWNER: Sabine Pass LNG, L.P.