AGREEMENT BETWEEN OWNER AND DESIGN/BUILDER ON THE BASIS OF A STIPULATED PRICEFee Agreement |
|
|
|
You are currently viewing: This Fee Agreement involves
ADVANCED BIOENERGY, LLC | Heartland Grain Fuels, LP | ICM, Inc. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here. |
|
|
|
Search Fee Agreement by:
Exhibit 10.24
*Portions omitted pursuant to a request for confidential treatment and filed separately with the SEC.
AGREEMENT
BETWEEN OWNER AND DESIGN/BUILDER
ON THE BASIS OF A STIPULATED PRICE
THIS AGREEMENT is made and entered into this 14th day of July, 2006 by and between Heartland Grain Fuels, LP, a South Dakota limited partner company (hereinafter called OWNER) and ICM, Inc., a Kansas corporation (hereinafter called DESIGN/BUILDER).
OWNER and DESIGN/BUILDER, in consideration of the mutual covenants hereinafter set forth, agree as follows:
Article 1. THE PROJECT AND WORK.
1.01. DESIGN/BUILDER shall complete all Work for the Project as specified or indicated in the Contract Documents. The Project is generally described as the design and construction of a dry mill fuel-grade ethanol plant to be located in or near Aberdeen, South Dakota, as described in more detail in Exhibit B to this Agreement. The Work includes such engineering, labor, materials, and equipment to design, construct, startup and achieve guaranteed performance criteria of a dry mill ethanol plant capable of producing no less than forty (40) million gallons per year of denatured fuel-grade ethanol and no less than two hundred two thousand (202,000) tons per year of wet distillers’ grains, as set forth in the Contract Documents. A more detailed described of the Work is set forth in the attached Exhibits (other than OWNER’s responsibilities set forth therein).
Article 2. CONTRACT TIMES.
2.01. Days to Achieve Substantial Completion and Final Payment. The Work will be Substantially Completed within [*] days after the date when the Contract Times commence to run as provided in paragraph 2.01.A of the General Conditions, and completed and ready for final payment in accordance with paragraph 13.08 of the General Conditions within one hundred eighty (180) days after Substantial Completion , unless otherwise provided in the Contract Documents.
Article 3. CONTRACT PRICE.
3.01. OWNER shall pay DESIGN/BUILDER the Contract Price for completion of the Work in accordance with the Contract Documents. The Contract Price may be adjusted as provided by the General Conditions. For all Work, OWNER shall pay to DESIGN/BUILDER a price of [*] (the “Contract Price”).
3.02. The Work to be performed by DESIGN/BUILDER shall not include those items designated as OWNER’s responsibilities in the Contract Documents. Those items designated as OWNER’s responsibilities in the Contract Documents shall include all design, procurement, fabrication, installation and start-up associated with such items.
3.03 DESIGN/BUILDER shall provide to OWNER the training described in Exhibit G.
3.04 In accordance with paragraph 5.02 of the General Conditions, DESIGN/BUILDER agrees to maintain the insurance coverages, limits, and deductibles set forth in Exhibit H.
1
Article 4. PAYMENT PROCEDURES
4.01 DESIGN/BUILDER shall submit and OWNER will process Applications for Payment in accordance with Article 13 of the General Conditions and Sections 5.01.A. through C. below.
A. Down Payment. OWNER shall make a down payment of 10% of CONTRACT PRICE to DESIGN/BUILDER, which shall be applied toward and credited to 10% of each progress payment. At the time of execution of the Agreement, OWNER shall pay [*]of such down payment to DESIGN/BUILDER less any portion of such down payment previously paid by OWNER to DESIGN/BUILDER under the letter of intent between the parties, if any. Upon delivery of the Notice to Proceed, OWNER shall pay the remaining balance of such down payment to DESIGN/BUILDER.
B. Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER’s Applications for Payment, as provided in this Section 4.01.B. Progress payments shall be due and payable in accordance with 13.04 of the General Conditions. All such payments will be measured by the acceptable Schedule of Values established under paragraph 2.03.A of the General Conditions.
1. Prior to Substantial Completion, such progress payments will be made in an amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as OWNER may withhold in accordance with paragraph 13.04.B of the General Conditions.
a. Ninety-five percent (95%) of Work completed (with the balance being retainage).
b. Ninety-five percent (95%) (with the balance being retainage) of the cost of materials and equipment not incorporated in the Work (but delivered, suitably stored and accompanied by documentation satisfactory to OWNER as provided in paragraph 13.02.A of the General Conditions).
2. Upon Substantial Completion, payment will be made in an amount sufficient to increase total payments to DESIGN/BUILDER to One Hundred percent (100%) of the Contract Price, less (i) such amounts as OWNER may withhold in accordance with paragraph 13.04.B of the General Conditions, (ii) amounts mutually agreed by the parties for completion of Punch List Items, and (iii) [*]. Amounts withheld for Punch List Items shall be paid by OWNER to DESIGN/BUILDER as such Work is completed.
3. Upon successful completion of the seven-day performance test described in Exhibit A, OWNER shall pay DESIGN/BUILDER the [*] retained pursuant to Section 4.01.B.2.(iii) above.
C. Final Payment. OWNER shall pay the remainder of the Contract Price, if any, to DESIGN/BUILDER in accordance with paragraph 13.08 of the General Conditions.
Article 5. INTEREST.
5.01. All monies not paid when due as provided in Article 13 of the General Conditions shall bear interest at the rate of Eighteen percent (18%) per annum. If it is determined that OWNER incorrectly withheld payment of any disputed payment, then such payment shall bear interest from the date such payment would have otherwise been due until the date actually paid to DESIGN/BUILDER.
2
Article 6. DESIGN/BUILDER’S REPRESENTATIONS.
6.01. DESIGN/BUILDER makes the following representations:
A. DESIGN/BUILDER has examined and carefully studied the Contract Documents listed in Sections 7.01.A through C, and, to the extent prepared (but not yet approved by OWNER) prior to the Effective Date, the documents described in Section 7.01.D.3 and .4.
B. DESIGN/BUILDER is familiar with and is satisfied as to all federal, state and local Laws and Regulations in existence on the Effective Date that may affect cost, progress, performance, furnishing, and completion of the Work in accordance with the Contract Documents.
C. DESIGN/BUILDER is familiar with the work to be performed by OWNER and others at the Site that relates to the Work as indicated in the Contract Documents.
D. DESIGN/BUILDER has correlated the information known to DESIGN/BUILDER, reports and drawings identified in the Contract Documents, and all additional examinations, investigations, tests, studies and data with the Contract Documents.
E. DESIGN/BUILDER has given OWNER written notice of all conflicts, errors, ambiguities or discrepancies that DESIGN/BUILDER has discovered in the Contract Documents and the written resolution thereof by OWNER is acceptable to DESIGN/BUILDER, and the Contract Documents are sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
Article 7. CONTRACT DOCUMENTS.
7.01. The Contract Documents which comprise the entire agreement between OWNER and DESIGN/BUILDER concerning the Work consist of the following:
A. This Agreement (pages 1 to 5, inclusive).
B. Exhibits to this Agreement (A to M, inclusive).
C. General Conditions of the Contract Between Owner and Design/Builder (pages 1 to 35, inclusive).
D. The following which may be delivered, prepared, or issued after the Effective Date of this Agreement and are not attached hereto.
1. Written Notice to Proceed, in the form substantially similar to Exhibit M attached hereto.
2. All Written Amendments and other documents amending, modifying or supplementing the Contract Documents pursuant to paragraph 3.03.A of the General Conditions.
3. Specifications as defined in paragraph 1.01.A.31 of the General Conditions.
4. Drawings as defined in paragraph 1.01.A.15 of the General Conditions.
3
7.02. There are no Contract Documents other than those listed above in this Article 7. The Contract Documents may only be amended, modified or supplemented as provided in paragraph 3.03.A of the General Conditions.
Article 8. MISCELLANEOUS.
8.01. The attached General Conditions of the Contract between Owner and Design/Builder are referred to herein as the General Conditions.
8.02. Terms used in this Agreement which are defined in Article 1 of the General Conditions will have the meanings indicated therein.
8.03. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound, which consent shall not be unreasonably withheld; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and, unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.
8.04. OWNER and DESIGN/BUILDER each binds itself, its successors, assigns and legal representatives to the other party hereto, its successors, permitted assigns and legal representatives in respect to all covenants, agreements and obligations contained in the Contract Documents.
8.05. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon OWNER and DESIGN/BUILDER, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.
8.06. This Agreement may be executed in any number of counterparts, each of which shall be deemed to be an original and all of which shall constitute one agreement that is binding upon all of the parties hereto, notwithstanding that all parties are not signatories to the same counterpart. Facsimile signatures of the parties hereto shall be binding.
8.07. This Agreement will be effective on date first written above. Within ninety (90) days after such effective date, OWNER shall provide to DESIGN/BUILDER the Notice to Proceed and evidence, acceptable to DESIGN/BUILDER, of funding for the Project.
4
IN WITNESS WHEREOF, OWNER and DESIGN/BUILDER have signed this Agreement on the date first written above.
|
OWNER:
Heartland Grain Fuels, LP |
DESIGN/BUILDER: ICM, Inc. |
|
|
|
|
By:_____/s/ Bill Paulson_____________ |
By:/s/ Dave VanderGriend |
|
Title:______General Manager_________ |
Title:_President______________________ |
|
|
|
|
Addresses for giving notices and representatives: |
|
|
|
|
|
Name:______________________________ |
Name:_Dave VanderGriend_____________ |
|
Title:_______________________________ |
Title:_President_______________________ |
|
Address:____________________________ |
Address:310 N. First Street, Colwich, KS |
|
Phone:______________________________ |
Phone: 316-796-0900 |
|
Facsimile:___________________________ |
Facsimile: 316-796-0570 |
|
|
|
5
Exhibit A
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
Performance
Criteria:
DESIGN/BUILDER represents and warrants to OWNER that the completed Project will achieve each of the following performance criteria. After DESIGN/BUILDER determines the Plant is ready for start-up, DESIGN/BUILDER, with OWNER’s labor forces, will start-up the Plant and conduct a seven-day performance test to establish compliance with each of the performance criteria except the atmospheric emissions. Compliance shall be measured simultaneously for all criteria, and computed on the average over the seven-day performance test. If the Project fails to reach any performance criterion, then DESIGN/BUILDER shall (at no additional cost to OWNER) make such changes in design, construction, or equipment as required to meet the criteria, and conduct another seven day performance test. Upon successful completion of a seven-day performance test, the Plant shall be considered to have achieved the performance criteria listed below (other than the atmospheric emissions criteria) for purposes of the foregoing representation and warranty of DESIGN/BUILDER.
Table 1 ethanol plant criteria 40 MGY capacity
|
Criteria |
|
Specification |
|
Testing Statement |
|
Documentation |
|
Plant Capacity — fuel-grade ethanol |
|
Operate at a rate of 40 million gallons per year of denatured fuel grade ethanol meeting the specifications of ASTM 4806 |
|
Seven-day performance test |
|
Concurrence of production records and a written report from DESIGN/BUILDER. |
|
|
|
|
|
|
|
|
|
Wet Distillers Grains OR Dry Distillers Grains |
|
Operate at rate of 202,000 tons per year of approximately 67% moisture WDGS OR 128,000 tons per year of approx. 11% moisture DDG. |
|
Determined by calculation of mass flow from centrifuge (s) in a seven- day performance test |
|
Concurrence of production records and a written analysis from DESIGN/BUILDER. |
|
|
|
|
|
|
|
|
|
Carbon Dioxide |
|
Approximately 115,000 tons per year of raw CO2 gas. |
|
Determined as a function of fermented gallons in a seven-day performance test. |
|
Mass flow calculation by DESIGN/BUILDER. |
|
|
|
|
|
|
|
|
|
Grain to Ethanol Conversion ratio; Corn/Sorghum 56#/bu., 16% or less moisture, zero aflatoxin tolerance |
|
Not be less than 2.8 denatured gallons (2.67 gallons undenatured) of ethanol per bushel of ground corn. |
|
As determined by meter readings during a seven-day performance test. |
|
Concurrence of production records and written analysis by DESIGN/BUILDER. |
|
|
|
|
|
|
|
|
|
Electrical Energy |
|
.75 kWh per denatured gallon of fuel grade ethanol. Does not include kWh used to operate CO2plant, CO2 gas system, grain handling system or Chiller. |
|
As determined by meter readings during a seven-day performance test. |
|
Concurrence of production records and written analysis by DESIGN/BUILDER. |
|
Natural
Gas |
|
Consumption shall not exceed 34,000 Btu per denatured gallon of fuel-grade ethanol. |
|
As determined by meter readings during a seven-day performance test. |
|
Concurrence of production records and written analysis by DESIGN/BUILDER. |
|
|
|
|
|
|
|
|
|
Process Water Discharge |
|
zero gallons under normal operations |
|
Process discharge meter readings during seven day performance test |
|
Plant control system reports from DESIGN/BUILDER |
|
|
|
|
|
|
|
|
|
Atmospheric Emissions |
|
As prescribed and approved by the applicable Department of Environmental Quality or similar agency for the State in which the Plant is located as of the Effective Date of the Agreement. |
|
As determined by written emissions compliance report from a third party mutually selected by the parties confirming regulatory compliance of the air emissions performance tests prescribed by the applicable Department of Environmental Quality or similar agency for the State in which the Plant is located as of the Effective Date of the Agreement. |
|
As determined by written emissions compliance report from a third party mutually selected by the parties confirming regulatory compliance of the air emissions performance tests prescribed by the applicable Department of Environmental Quality or similar agency for the State in which the Plant is located as of the Effective Date of the Agreement. |
OWNER’s failure to materially comply with the operating procedures issued by DESIGN/BUILDER shall void the foregoing performance criteria and all other guarantees and warranties set forth in the Contract Documents.
OWNER understands that the startup of the plant requires resources and cooperation of OWNER, vendors and other suppliers to the Project. DESIGN/BUILDER disclaims any liability and OWNER indemnifies DESIGN/BUILDER for non-attainment of the foregoing performance criteria directly or indirectly caused by the material non-performance or negligence of third parties not retained by DESIGN/BUILDER.
Exhibit B
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
General Project Scope:
Construct a no less than forty (40) million
gallon per year (MGY) dry mill fuel-grade ethanol plant located in or near
Aberdeen, South Dakota. The plant will grind approximately 14.3 million
bushels per year to produce approximately forty (40) MGY of fuel-grade ethanol
denatured with five percent gasoline (or a similar product). The plant
will also produce not less than 202,000 tons per year of 67% moisture Wet
Distillers Grains with Solubles (WDGS), and approximately 115,000 tons per year
of raw carbon dioxide (CO2) gas.
OWNER to provide DESIGN/BUILDER a level site and which shall have a soil load bearing capacity as specified in the attached table.
Ground grain will be mixed in a slurry tank and routed through a working system consisting of a hydroheater, cook tube, and flash tank. The mash will continue through liquefaction and associated heat exchangers to fermentation. Simultaneously, propagated yeast will be added to the mash as the fermenter is filling. After batch fermentation is complete, the beer will be pumped to the beer well and then to the beer column to vaporize the alcohol from the mash.
Alcohol streams are dehydrated in the distillation column, the side stripper and the molecular sieve system. Two hundred proof alcohol is pumped to the tank farm shift tanks and blended with five percent denaturant as the product is being pumped into a final storage tank.
Corn mash from the beer stripper is dewatered by decanter type centrifuge. Wet cake from the centrifuge is conveyed to the wetcake pad or drying system. Water in the thin stillage can be evaporated and recycled by the Bio-Methanation system.
Fresh water for the boilers, cooking and other processes will be obtained from area process wells or city water system that supply the needs of the plant. Boiler water may be conditioned in regenerative softeners will be pumped through a deaerator scrubber and into a deaerator tank. Appropriate boiler chemicals will be added as preheated water is sent to the boiler.
DESIGN/BUILDER will provide its standard design for the fire pump house and water treatment space. Procurement and construction of fire protection package will be provided by owner.
The design includes a compressed air system consisting of compressors, a receiver tank, pre-filter, coalescing filter and air dryer.
The design also incorporates the use of a clean-in-place (CIP) system for cleaning cook, fermentation, distillation, evaporation, centrifuges and other systems. Fifty percent caustic soda is received by truck and stored in a tank. The CIP system uses tanks for receiving, make-up, CIP return and CIP waste which is fed to the methanator. The CIP system includes a CIP Tank, a 50% Caustic tank, and a Waste CIP tank. A screen is used to remove the solids.
Under normal operating circumstances, the Plant will not have any wastewater discharges that have been in contact with corn and sorghum mash, cleaning system or contact process water. A bio-methanator manufactured by DESIGN/BUILDER/Phoenix will reduce the organic acids in process water allowing complete reuse within the Plant and is included in the Contract Price. The
Plant will have blowdown discharges from the cooling tower, water softeners, and Reverse Osmosis system. OWNER is responsible for all permits, purchase and installation of pumps, waterline construction, sanitary sewer construction, necessary to discharge the blowdown from the cooling tower, water softeners, and Reverse Osmosis system.
Carbon Dioxide (CO2) is a co-product of the fermentation process. CO2 is allowed under current Laws and Regulations to be vented to the atmosphere. Installation of a plant or system to capture, clean and compress the CO2 is not included in the Work. OWNER, at its cost, may add a blower, certain associated equipment and a small amount of piping to move the CO2 from the fermenter to a collection point for sale or further processing.
Most of the processes within the Plant will be computer controlled by a Siemens/Moore APACS distributed control system with graphical user interface and three workstations all located in the plant control room, which is included in the Contract Price. No workstation is provided for the administrative building or any other location. It is estimated that the system will consist of 200 discrete inputs, 200 discreet outputs, 175 analog inputs and 120 analog outputs. Programmable logic controllers (PLCs) will control certain process equipment.
*[Optional: A description of the scope of work relating to the grain handling system is attached to the Agreement as Exhibit B-1 and incorporated herein.]
The Work provided by DESIGN/BUILDER will meet specifications, criteria, and allowances as provided in the Construction Permit and all other applicable Laws and Regulations enacted as of the Effective Date.
[OPTIONAL]
Exhibit B-1
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
SCOPE OF WORK FOR HEARTLAND GRAIN FUELS, LP GRAIN HANDLING SYSTEM
Whole Grain Transfer — (Heartland Grain Scope)
·
OWNER is responsible for all items
required to transfer the whole grain from the OWNER’S existing grain
facilities to the inlet of the proposed grinding bin above the
hammermills. OWNER shall be responsible for all design, procurement, and
installation of any required equipment, structural, electrical, and all other
required items associated with the whole grain transfer system. Transfer
rate of whole grain to be mutually agreed by OWNER and DESIGN/BUILDER prior to
design.
Dust Control System — Whole Grain Transfer system (Heartland Grain Scope)
·
The dust control system will pick-up dust
laden air at the grinder bin, or as required.
·
One dust filter with fan, sized to meet
the air permit requirements, will receive dust laden air from the ducting at
the grain handling system and will discharge the collected dust into the
receiving transfer drag conveyor.
Grinding System (ICM scope)
·
One steel structure will support the
grinder bin and related equipment.
·
One rotary scalper/screener rated at 3000
BPH will receive grain from the receiving and reclaim legs and discharge to the
grinding bin
·
One 5000 BU steel grinding bin will feed
the hammer mills.
·
Two 1,200 BPH hammer mills will grind the
grain.
·
One dust filter with fan, sized to meet
the air permit requirements, will collect dust from the hammer mills and
discharge to the ground grain conveyor.
Ground Grain Transfer to Plant (ICM scope)
·
The ground grain will be transferred from
the hammer mills to the ethanol plant at 3,000 BPH, using belt or drag
conveyors.
DDG Transfer - Dryer to Flat Storage (ICM scope)
·
DESIGN/BUILDER to provide and install the
ductwork and supports required for the transfer of DDG from the dryer to the
existing flat storage cooling cyclone inlet flange. If any additional
equipment is required to transfer the DDG to the existing flat storage, OWNER
will enter into a Change Order with DESIGN/BUILDER to provide and install the
required equipment.
DESIGN/BUILDER reserves the right to change, modify, or otherwise re-design any part of the proposed grain handling system at the sole discretion of DESIGN/BUILDER on the basis of safety, performance, or any other consideration deemed necessary by DESIGN/BUILDER.
Exhibit C
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
Buildings and Structures by DESIGN/BUILDER:
Construction of buildings and structures,
as listed in Table 2 and Table 3, is included in the Contract Price.
Table 2 Ancillary Buildings and Structures
by DESIGN/BUILDER
|
Building |
|
Type |
|
Preliminary |
|
Addition Info |
|
MCC Buildings |
|
CMU block wall, insulated, climate controlled |
|
20’ x 10’ |
|
Located near cooling tower and grain storage silos or milling building. |
|
Cooling Tower |
|
Douglas Fir Structure Induced Draft Counter Flow |
|
34’ x 90’ |
|
Includes three (3) cooling tower cells |
|
Admin Building Scale |
|
Above ground, Grain supply trucks |
|
Owners Responsibility |
|
Located near Admin. Bldg. |
|
Wetcake Pad |
|
Cast-in-Place Concrete Structure |
|
100’ x 100’ |
|
|
Table 3 Buildings and Structures by
DESIGN/BUILDER
|
Building |
|
Type |
|
Preliminary Dimensions |
|
Addition Info |
|
Process |
|
Structural steel, steel siding - Insulated |
|
60’ x 140’ x 35’ |
|
Includes laboratory, control room & offices, MCC room |
|
Energy Center |
|
Structural steel, steel siding - Insulated |
|
90’ x 100’ x30’ |
|
Includes centrifuge area, office, MCC room |
|
Evaporation |
|
Structural steel, steel siding - Insulated |
|
50’ x 45’ x 35’ |
|
|
|
Grain Receiving |
|
Structural Steel, steel siding, roof insulation only |
|
Owners Responsibility |
|
|
Exhibit D
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
Administration Building by OWNER:
The Contract Price does not include the cost of the following additional items:
Table 4 Administration Building
|
Description |
|
Additional Description |
|
Est. Amount |
|
|
|
Administration Building |
|
Free standing (37’ x 70’ x 10’) |
|
$ |
300,000 |
|
|
Office Computer System |
|
Microsoft Windows 2000 network server and five personal computers, one laser printer. Includes setup, software and labor. |
|
$ |
40,000 |
|
|
Telephone System |
|
Digital phone system with voice mail for office and plant. |
|
$ |
15,000 |
|
|
Office Copier & fax machine |
|
Black & white with sheet feeder and collator. Plain paper fax machine. |
|
$ |
10,000 |
|
|
Office Furniture |
|
Office desks, chair & side chairs, conference room table & chairs, three four-drawer filing cabinets, and 10 two-drawer filing cabinets. |
|
$ |
25,000 |
|
Exhibit E
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
OWNER’S Required Permits and Services List:
OWNER shall provide all of the permits,
authorizations and services, including but not limited to:
1)
Land and Grading — Land and Grading
— OWNER shall provide the Site near or in Aberdeen, South Dakota.
OWNER shall obtain all legal authority to use the Site for its intended purpose
and perform technical due diligence for DESIGN/BUILDER to perform including but
not limited to proper zoning approvals, elevation restrictions, soil tests, and
water tests. The Site shall be rough graded per DESIGN/BUILDER specifications
and be within six inches of final grade including the rough grading for Site roadways.
The Site soils shall be modified as required to provide a minimum allowable
soil bearing pressure as specified in the attached table for all foundation
elements. The site soils shall be modified as required to provide a
minimum allowable soil bearing pressure of 4,500 pounds per square foot in the
fermenter area, 6,500 pounds per square foot in the grain storage concrete
silos area and 3,000 pounds per square foot for all other foundation
elements. The soils beneath the foundation elements shall not exceed the
total or differential settlements such that the Plant is unable to perform its
intended purpose. If the existing soil conditions are such that
over-excavation and re-compaction or pilings are required, OWNER will be
responsible for this work. OWNER is also responsible for any dewatering
required at the site during construction.
Other items to be provided by the OWNER include, but are not limited to, the following: initial site survey (boundary and topographic) as required by the design engineers, layout of the property corners including two construction benchmarks, soil borings and subsequent geotechnical report (the results of which are acceptable to DESIGN/BUILDER and consistent with the specifications set forth herein) describing recommendation for roads, foundations and if required, soil stabilization/remediation, site engineering and detailed drawings (to the extent not provided by DESIGN/BUILDER), land disturbance permit, erosion control permit, site grading as described abo






