Exhibit 10.24
*Portions omitted pursuant to a
request for confidential treatment and filed separately with the
SEC.
AGREEMENT
BETWEEN OWNER AND
DESIGN/BUILDER
ON THE BASIS OF A STIPULATED
PRICE
THIS AGREEMENT is made and entered
into this 14th day of July, 2006 by and between Heartland Grain
Fuels, LP, a South Dakota limited partner company (hereinafter
called OWNER) and ICM, Inc., a Kansas corporation (hereinafter
called DESIGN/BUILDER).
OWNER and DESIGN/BUILDER, in
consideration of the mutual covenants hereinafter set forth, agree
as follows:
Article
1. THE PROJECT AND
WORK.
1.01.
DESIGN/BUILDER shall complete all Work for the Project as specified
or indicated in the Contract Documents. The Project is generally
described as the design and construction of a dry mill fuel-grade
ethanol plant to be located in or near Aberdeen, South Dakota, as
described in more detail in Exhibit B to this Agreement. The
Work includes such engineering, labor, materials, and equipment to
design, construct, startup and achieve guaranteed performance
criteria of a dry mill ethanol plant capable of producing no less
than forty (40) million gallons per year of denatured fuel-grade
ethanol and no less than two hundred two thousand (202,000) tons
per year of wet distillers’ grains, as set forth in the
Contract Documents. A more detailed described of the Work is
set forth in the attached Exhibits (other than OWNER’s
responsibilities set forth therein).
Article
2. CONTRACT
TIMES.
2.01.
Days to Achieve Substantial Completion and Final Payment.
The Work will be Substantially Completed within [*] days
after the date when the Contract Times commence to run as provided
in paragraph 2.01.A of the General Conditions, and completed and
ready for final payment in accordance with paragraph 13.08 of the
General Conditions within one hundred eighty (180) days after
Substantial Completion , unless otherwise provided in the Contract
Documents.
Article
3. CONTRACT
PRICE.
3.01.
OWNER shall pay DESIGN/BUILDER the Contract Price for completion of
the Work in accordance with the Contract Documents. The
Contract Price may be adjusted as provided by the General
Conditions. For all Work, OWNER shall pay to DESIGN/BUILDER a
price of [*] (the “Contract Price”).
3.02.
The Work to be performed by DESIGN/BUILDER shall not include those
items designated as OWNER’s responsibilities in the Contract
Documents. Those items designated as OWNER’s
responsibilities in the Contract Documents shall include all
design, procurement, fabrication, installation and start-up
associated with such items.
3.03
DESIGN/BUILDER shall provide to OWNER the training described in
Exhibit G.
3.04
In accordance with paragraph 5.02 of the General Conditions,
DESIGN/BUILDER agrees to maintain the insurance coverages, limits,
and deductibles set forth in Exhibit H.
1
Article
4. PAYMENT
PROCEDURES
4.01
DESIGN/BUILDER shall submit and OWNER will process Applications for
Payment in accordance with Article 13 of the General Conditions and
Sections 5.01.A. through C. below.
A. Down Payment
. OWNER shall make a down payment of 10% of CONTRACT PRICE to
DESIGN/BUILDER, which shall be applied toward and credited to 10%
of each progress payment. At the time of execution of the
Agreement, OWNER shall pay [*]of such down payment to
DESIGN/BUILDER less any portion of such down payment previously
paid by OWNER to DESIGN/BUILDER under the letter of intent between
the parties, if any. Upon delivery of the Notice to Proceed,
OWNER shall pay the remaining balance of such down payment to
DESIGN/BUILDER.
B.
Progress Payments; Retainage. OWNER shall make
progress payments on account of the Contract Price on the basis of
DESIGN/BUILDER’s Applications for Payment, as provided in
this Section 4.01.B. Progress payments shall be due and
payable in accordance with 13.04 of the General Conditions.
All such payments will be measured by the acceptable Schedule of
Values established under paragraph 2.03.A of the General
Conditions.
1. Prior to
Substantial Completion, such progress payments will be made in an
amount equal to the percentage indicated below, but, in each case,
less the aggregate of payments previously made and less such
amounts as OWNER may withhold in accordance with paragraph 13.04.B
of the General Conditions.
a. Ninety-five percent
(95%) of Work completed (with the balance being
retainage).
b. Ninety-five percent (95%)
(with the balance being retainage) of the cost of materials and
equipment not incorporated in the Work (but delivered, suitably
stored and accompanied by documentation satisfactory to OWNER as
provided in paragraph 13.02.A of the General
Conditions).
2. Upon
Substantial Completion, payment will be made in an amount
sufficient to increase total payments to DESIGN/BUILDER to One
Hundred percent (100%) of the Contract Price, less (i) such amounts
as OWNER may withhold in accordance with paragraph 13.04.B of the
General Conditions, (ii) amounts mutually agreed by the parties for
completion of Punch List Items, and (iii) [*]. Amounts
withheld for Punch List Items shall be paid by OWNER to
DESIGN/BUILDER as such Work is completed.
3. Upon
successful completion of the seven-day performance test described
in Exhibit A, OWNER shall pay DESIGN/BUILDER the [*] retained
pursuant to Section 4.01.B.2.(iii) above.
C.
Final Payment. OWNER shall pay the remainder of the
Contract Price, if any, to DESIGN/BUILDER in accordance with
paragraph 13.08 of the General Conditions.
Article
5. INTEREST.
5.01.
All monies not paid when due as provided in Article 13 of the
General Conditions shall bear interest at the rate of Eighteen
percent (18%) per annum. If it is determined that OWNER
incorrectly withheld payment of any disputed payment, then such
payment shall bear interest from the date such payment would have
otherwise been due until the date actually paid to
DESIGN/BUILDER.
2
Article
6. DESIGN/BUILDER’S
REPRESENTATIONS.
6.01.
DESIGN/BUILDER makes the following representations:
A.
DESIGN/BUILDER has examined and carefully studied the Contract
Documents listed in Sections 7.01.A through C, and, to the extent
prepared (but not yet approved by OWNER) prior to the Effective
Date, the documents described in Section 7.01.D.3 and
.4.
B.
DESIGN/BUILDER is familiar with and is satisfied as to all federal,
state and local Laws and Regulations in existence on the Effective
Date that may affect cost, progress, performance, furnishing, and
completion of the Work in accordance with the Contract
Documents.
C.
DESIGN/BUILDER is familiar with the work to be performed by OWNER
and others at the Site that relates to the Work as indicated in the
Contract Documents.
D.
DESIGN/BUILDER has correlated the information known to
DESIGN/BUILDER, reports and drawings identified in the Contract
Documents, and all additional examinations, investigations, tests,
studies and data with the Contract Documents.
E.
DESIGN/BUILDER has given OWNER written notice of all conflicts,
errors, ambiguities or discrepancies that DESIGN/BUILDER has
discovered in the Contract Documents and the written resolution
thereof by OWNER is acceptable to DESIGN/BUILDER, and the Contract
Documents are sufficient to indicate and convey understanding of
all terms and conditions for performance and furnishing of the
Work.
Article
7. CONTRACT
DOCUMENTS.
7.01.
The Contract Documents which comprise the entire agreement between
OWNER and DESIGN/BUILDER concerning the Work consist of the
following:
A.
This Agreement (pages 1 to 5, inclusive).
B.
Exhibits to this Agreement (A to M, inclusive).
C.
General Conditions of the Contract Between Owner and Design/Builder
(pages 1 to 35, inclusive).
D.
The following which may be delivered, prepared, or issued after the
Effective Date of this Agreement and are not attached
hereto.
1.
Written Notice to Proceed, in
the form substantially similar to Exhibit M attached
hereto.
2.
All Written Amendments and other documents amending, modifying or
supplementing the Contract Documents pursuant to paragraph 3.03.A
of the General Conditions.
3.
Specifications as defined in paragraph 1.01.A.31 of the General
Conditions.
4.
Drawings as defined in paragraph 1.01.A.15 of the General
Conditions.
3
7.02.
There are no Contract Documents other than those listed above in
this Article 7. The Contract Documents may only be amended,
modified or supplemented as provided in paragraph 3.03.A of the
General Conditions.
Article
8.
MISCELLANEOUS.
8.01.
The attached General Conditions of the Contract between Owner and
Design/Builder are referred to herein as the General
Conditions.
8.02.
Terms used in this Agreement which are defined in Article 1 of the
General Conditions will have the meanings indicated
therein.
8.03.
No assignment by a party hereto of any rights under or interests in
the Contract Documents will be binding on another party hereto
without the written consent of the party sought to be bound, which
consent shall not be unreasonably withheld; and, specifically but
without limitation, moneys that may become due and moneys that are
due may not be assigned without such consent (except to the extent
that the effect of this restriction may be limited by law), and,
unless specifically stated to the contrary in any written consent
to an assignment, no assignment will release or discharge the
assignor from any duty or responsibility under the Contract
Documents.
8.04.
OWNER and DESIGN/BUILDER each binds itself, its successors, assigns
and legal representatives to the other party hereto, its
successors, permitted assigns and legal representatives in respect
to all covenants, agreements and obligations contained in the
Contract Documents.
8.05.
Any provision or part of the Contract Documents held to be void or
unenforceable under any Law or Regulation shall be deemed stricken,
and all remaining provisions shall continue to be valid and binding
upon OWNER and DESIGN/BUILDER, who agree that the Contract
Documents shall be reformed to replace such stricken provision or
part thereof with a valid and enforceable provision that comes as
close as possible to expressing the intention of the stricken
provision.
8.06.
This Agreement may be executed in any number of counterparts, each
of which shall be deemed to be an original and all of which shall
constitute one agreement that is binding upon all of the parties
hereto, notwithstanding that all parties are not signatories to the
same counterpart. Facsimile signatures of the parties hereto
shall be binding.
8.07.
This Agreement will be effective on date first written above.
Within ninety (90) days after such effective date, OWNER shall
provide to DESIGN/BUILDER the Notice to Proceed and evidence,
acceptable to DESIGN/BUILDER, of funding for the
Project.
4
IN WITNESS WHEREOF, OWNER and
DESIGN/BUILDER have signed this Agreement on the date first written
above.
|
OWNER: Heartland Grain Fuels,
LP
|
DESIGN/BUILDER: ICM, Inc.
|
|
|
|
|
By:_____ /s/ Bill Paulson
_____________
|
By:/s/ Dave VanderGriend
|
|
Title:______ General Manager
_________
|
Title:_President______________________
|
|
|
|
|
Addresses for giving notices and
representatives:
|
|
|
|
|
|
Name:______________________________
|
Name:_Dave VanderGriend_____________
|
|
Title:_______________________________
|
Title:_President_______________________
|
|
Address:____________________________
|
Address:310 N. First Street, Colwich,
KS
|
|
Phone:______________________________
|
Phone: 316-796-0900
|
|
Facsimile:___________________________
|
Facsimile: 316-796-0570
|
|
|
|
5
Exhibit A
to
Agreement Between Owner and
Design/Builder
On the Basis of a Stipulated
Price
Performance
Criteria:
DESIGN/BUILDER represents and
warrants to OWNER that the completed Project will achieve each of
the following performance criteria. After DESIGN/BUILDER
determines the Plant is ready for start-up, DESIGN/BUILDER, with
OWNER’s labor forces, will start-up the Plant and conduct a
seven-day performance test to establish compliance with each of the
performance criteria except the atmospheric emissions.
Compliance shall be measured simultaneously for all criteria, and
computed on the average over the seven-day performance test.
If the Project fails to reach any performance criterion, then
DESIGN/BUILDER shall (at no additional cost to OWNER) make such
changes in design, construction, or equipment as required to meet
the criteria, and conduct another seven day performance test.
Upon successful completion of a seven-day performance test, the
Plant shall be considered to have achieved the performance criteria
listed below (other than the atmospheric emissions criteria) for
purposes of the foregoing representation and warranty of
DESIGN/BUILDER.
Table 1 ethanol plant
criteria 40 MGY capacity
|
Criteria
|
|
Specification
|
|
Testing Statement
|
|
Documentation
|
|
Plant Capacity — fuel-grade
ethanol
|
|
Operate at a rate of 40 million gallons per year
of denatured fuel grade ethanol meeting the specifications of ASTM
4806
|
|
Seven-day performance test
|
|
Concurrence of production records and a written
report from DESIGN/BUILDER.
|
|
|
|
|
|
|
|
|
|
Wet Distillers Grains OR Dry Distillers
Grains
|
|
Operate at rate of 202,000 tons per year of
approximately 67% moisture WDGS OR 128,000 tons per year of approx.
11% moisture DDG.
|
|
Determined by calculation of mass flow from
centrifuge (s) in a seven- day performance test
|
|
Concurrence of production records and a written
analysis from DESIGN/BUILDER.
|
|
|
|
|
|
|
|
|
|
Carbon Dioxide
|
|
Approximately 115,000 tons per year of raw CO2
gas.
|
|
Determined as a function of fermented gallons in
a seven-day performance test.
|
|
Mass flow calculation by
DESIGN/BUILDER.
|
|
|
|
|
|
|
|
|
|
Grain to Ethanol Conversion ratio; Corn/Sorghum
56#/bu., 16% or less moisture, zero aflatoxin tolerance
|
|
Not be less than 2.8 denatured gallons (2.67
gallons undenatured) of ethanol per bushel of ground
corn.
|
|
As determined by meter readings during a
seven-day performance test.
|
|
Concurrence of production records and written
analysis by DESIGN/BUILDER.
|
|
|
|
|
|
|
|
|
|
Electrical Energy
|
|
.75 kWh per denatured gallon of fuel grade
ethanol. Does not include kWh used to operate CO2plant, CO2 gas
system, grain handling system or Chiller.
|
|
As determined by meter readings during a
seven-day performance test.
|
|
Concurrence of production records and written
analysis by DESIGN/BUILDER.
|
|
Natural Gas
|
|
Consumption shall not exceed 34,000 Btu per
denatured gallon of fuel-grade ethanol.
|
|
As determined by meter readings during a
seven-day performance test.
|
|
Concurrence of production records and written
analysis by DESIGN/BUILDER.
|
|
|
|
|
|
|
|
|
|
Process Water Discharge
|
|
zero gallons under normal operations
|
|
Process discharge meter readings during seven
day performance test
|
|
Plant control system reports from
DESIGN/BUILDER
|
|
|
|
|
|
|
|
|
|
Atmospheric Emissions
|
|
As prescribed and approved by the applicable
Department of Environmental Quality or similar agency for the State
in which the Plant is located as of the Effective Date of the
Agreement.
|
|
As determined by written emissions compliance
report from a third party mutually selected by the parties
confirming regulatory compliance of the air emissions performance
tests prescribed by the applicable Department of Environmental
Quality or similar agency for the State in which the Plant is
located as of the Effective Date of the Agreement.
|
|
As determined by written emissions compliance
report from a third party mutually selected by the parties
confirming regulatory compliance of the air emissions performance
tests prescribed by the applicable Department of Environmental
Quality or similar agency for the State in which the Plant is
located as of the Effective Date of the Agreement.
|
OWNER’s failure to materially
comply with the operating procedures issued by DESIGN/BUILDER shall
void the foregoing performance criteria and all other guarantees
and warranties set forth in the Contract Documents.
OWNER understands that the startup
of the plant requires resources and cooperation of OWNER, vendors
and other suppliers to the Project. DESIGN/BUILDER disclaims
any liability and OWNER indemnifies DESIGN/BUILDER for
non-attainment of the foregoing performance criteria directly or
indirectly caused by the material non-performance or negligence of
third parties not retained by DESIGN/BUILDER.
Exhibit B
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
General Project Scope:
Construct a no less than forty (40)
million gallon per year (MGY) dry mill fuel-grade ethanol plant
located in or near Aberdeen, South Dakota. The plant will
grind approximately 14.3 million bushels per year to produce
approximately forty (40) MGY of fuel-grade ethanol denatured with
five percent gasoline (or a similar product). The plant will
also produce not less than 202,000 tons per year of 67% moisture
Wet Distillers Grains with Solubles (WDGS), and approximately
115,000 tons per year of raw carbon dioxide (CO 2 )
gas.
OWNER to provide DESIGN/BUILDER a
level site and which shall have a soil load bearing capacity
as specified in the attached table.
Ground grain will be mixed in a
slurry tank and routed through a working system consisting of a
hydroheater, cook tube, and flash tank. The mash will
continue through liquefaction and associated heat exchangers to
fermentation. Simultaneously, propagated yeast will be added
to the mash as the fermenter is filling. After batch
fermentation is complete, the beer will be pumped to the beer well
and then to the beer column to vaporize the alcohol from the
mash.
Alcohol streams are dehydrated in
the distillation column, the side stripper and the molecular sieve
system. Two hundred proof alcohol is pumped to the tank farm
shift tanks and blended with five percent denaturant as the product
is being pumped into a final storage tank.
Corn mash from the beer stripper is
dewatered by decanter type centrifuge. Wet cake from the
centrifuge is conveyed to the wetcake pad or drying system.
Water in the thin stillage can be evaporated and recycled by the
Bio-Methanation system.
Fresh water for the boilers, cooking
and other processes will be obtained from area process wells or
city water system that supply the needs of the plant. Boiler
water may be conditioned in regenerative softeners will be pumped
through a deaerator scrubber and into a deaerator tank.
Appropriate boiler chemicals will be added as preheated water is
sent to the boiler.
DESIGN/BUILDER will provide its
standard design for the fire pump house and water treatment
space. Procurement and construction of fire protection
package will be provided by owner.
The design includes a compressed air
system consisting of compressors, a receiver tank, pre-filter,
coalescing filter and air dryer.
The design also incorporates the use
of a clean-in-place (CIP) system for cleaning cook, fermentation,
distillation, evaporation, centrifuges and other systems.
Fifty percent caustic soda is received by truck and stored in a
tank. The CIP system uses tanks for receiving, make-up, CIP
return and CIP waste which is fed to the methanator. The CIP
system includes a CIP Tank, a 50% Caustic tank, and a Waste CIP
tank. A screen is used to remove the solids.
Under normal operating
circumstances, the Plant will not have any wastewater discharges
that have been in contact with corn and sorghum mash, cleaning
system or contact process water. A bio-methanator
manufactured by DESIGN/BUILDER/Phoenix will reduce the organic
acids in process water allowing complete reuse within the Plant and
is included in the Contract Price. The
Plant will have blowdown discharges
from the cooling tower, water softeners, and Reverse Osmosis
system. OWNER is responsible for all permits, purchase and
installation of pumps, waterline construction, sanitary sewer
construction, necessary to discharge the blowdown from the cooling
tower, water softeners, and Reverse Osmosis system.
Carbon Dioxide (CO2) is a co-product
of the fermentation process. CO2 is allowed under current
Laws and Regulations to be vented to the atmosphere.
Installation of a plant or system to capture, clean and compress
the CO2 is not included in the Work. OWNER, at its cost, may
add a blower, certain associated equipment and a small amount of
piping to move the CO2 from the fermenter to a collection point for
sale or further processing.
Most of the processes within the
Plant will be computer controlled by a Siemens/Moore APACS
distributed control system with graphical user interface and three
workstations all located in the plant control room, which is
included in the Contract Price. No workstation is provided
for the administrative building or any other location. It is
estimated that the system will consist of 200 discrete inputs, 200
discreet outputs, 175 analog inputs and 120 analog outputs.
Programmable logic controllers (PLCs) will control certain process
equipment.
*[Optional: A description of
the scope of work relating to the grain handling system is attached
to the Agreement as Exhibit B-1 and incorporated
herein.]
The Work provided by DESIGN/BUILDER
will meet specifications, criteria, and allowances as provided in
the Construction Permit and all other applicable Laws and
Regulations enacted as of the Effective Date.
[OPTIONAL]
Exhibit B-1
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
SCOPE OF WORK FOR HEARTLAND GRAIN
FUELS, LP GRAIN HANDLING SYSTEM
Whole Grain Transfer —
(Heartland Grain Scope)
·
OWNER is responsible for all items
required to transfer the whole grain from the OWNER’S
existing grain facilities to the inlet of the proposed grinding bin
above the hammermills. OWNER shall be responsible for all
design, procurement, and installation of any required equipment,
structural, electrical, and all other required items associated
with the whole grain transfer system. Transfer rate of whole
grain to be mutually agreed by OWNER and DESIGN/BUILDER prior to
design.
Dust Control System — Whole
Grain Transfer system (Heartland Grain Scope)
·
The dust control system will pick-up
dust laden air at the grinder bin, or as required.
·
One dust filter with fan, sized to
meet the air permit requirements, will receive dust laden air from
the ducting at the grain handling system and will discharge the
collected dust into the receiving transfer drag
conveyor.
Grinding System (ICM
scope)
·
One steel structure will support the
grinder bin and related equipment.
·
One rotary scalper/screener rated at
3000 BPH will receive grain from the receiving and reclaim legs and
discharge to the grinding bin
·
One 5000 BU steel grinding bin will
feed the hammer mills.
·
Two 1,200 BPH hammer mills will
grind the grain.
·
One dust filter with fan, sized to
meet the air permit requirements, will collect dust from the hammer
mills and discharge to the ground grain conveyor.
Ground Grain Transfer to Plant (ICM
scope)
·
The ground grain will be transferred
from the hammer mills to the ethanol plant at 3,000 BPH, using belt
or drag conveyors.
DDG Transfer - Dryer to Flat Storage
(ICM scope)
·
DESIGN/BUILDER to provide and
install the ductwork and supports required for the transfer of DDG
from the dryer to the existing flat storage cooling cyclone inlet
flange. If any additional equipment is required to transfer
the DDG to the existing flat storage, OWNER will enter into a
Change Order with DESIGN/BUILDER to provide and install the
required equipment.
DESIGN/BUILDER reserves the right to
change, modify, or otherwise re-design any part of the proposed
grain handling system at the sole discretion of DESIGN/BUILDER on
the basis of safety, performance, or any other consideration deemed
necessary by DESIGN/BUILDER.
Exhibit C
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
Buildings and Structures by
DESIGN/BUILDER:
Construction of buildings and
structures, as listed in Table 2 and Table 3, is included in the
Contract Price.
Table 2 Ancillary Buildings and
Structures by DESIGN/BUILDER
|
Building
|
|
Type
|
|
Preliminary
Dimensions
|
|
Addition Info
|
|
MCC Buildings
|
|
CMU block wall, insulated, climate
controlled
|
|
20’ x 10’
|
|
Located near cooling tower and grain storage
silos or milling building.
|
|
Cooling Tower
|
|
Douglas Fir Structure Induced Draft Counter
Flow
|
|
34’ x 90’
|
|
Includes three (3) cooling tower
cells
|
|
Admin Building Scale
|
|
Above ground, Grain supply trucks
|
|
Owners Responsibility
|
|
Located near Admin. Bldg.
|
|
Wetcake Pad
|
|
Cast-in-Place Concrete Structure
|
|
100’ x 100’
|
|
|
Table 3 Buildings and Structures by
DESIGN/BUILDER
|
Building
|
|
Type
|
|
Preliminary
Dimensions
|
|
Addition Info
|
|
Process
|
|
Structural steel, steel siding -
Insulated
|
|
60’ x 140’ x 35’
|
|
Includes laboratory, control room & offices,
MCC room
|
|
Energy Center
|
|
Structural steel, steel siding -
Insulated
|
|
90’ x 100’ x30’
|
|
Includes centrifuge area, office, MCC
room
|
|
Evaporation
|
|
Structural steel, steel siding -
Insulated
|
|
50’ x 45’ x 35’
|
|
|
|
Grain Receiving
|
|
Structural Steel, steel siding, roof insulation
only
|
|
Owners Responsibility
|
|
|
Exhibit D
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
Administration Building by
OWNER:
The Contract Price does not include
the cost of the following additional items:
Table 4 Administration
Building
|
Description
|
|
Additional Description
|
|
Est. Amount
|
|
|
Administration Building
|
|
Free standing (37’ x 70’
x 10’)
|
|
$
|
300,000
|
|
|
Office Computer System
|
|
Microsoft Windows 2000 network
server and five personal computers, one laser printer. Includes
setup, software and labor.
|
|
$
|
40,000
|
|
|
Telephone System
|
|
Digital phone system with voice mail
for office and plant.
|
|
$
|
15,000
|
|
|
Office Copier & fax
machine
|
|
Black & white with sheet feeder
and collator. Plain paper fax machine.
|
|
$
|
10,000
|
|
|
Office Furniture
|
|
Office desks, chair & side
chairs, conference room table & chairs, three four-drawer
filing cabinets, and 10 two-drawer filing cabinets.
|
|
$
|
25,000
|
|
Exhibit E
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
OWNER’S Required Permits and
Services List:
OWNER shall provide all of the
permits, authorizations and services, including but not limited
to:
1)
Land and Grading — Land and
Grading — OWNER shall provide the Site near or in Aberdeen,
South Dakota. OWNER shall obtain all legal authority to use
the Site for its intended purpose and perform technical due
diligence for DESIGN/BUILDER to perform including but not limited
to proper zoning approvals, elevation restrictions, soil tests, and
water tests. The Site shall be rough graded per DESIGN/BUILDER
specifications and be within six inches of final grade including
the rough grading for Site roadways. The Site soils shall be
modified as required to provide a minimum allowable soil bearing
pressure as specified in the attached table for all foundation
elements. The site soils shall be modified as required to
provide a minimum allowable soil bearing pressure of 4,500 pounds
per square foot in the fermenter area, 6,500 pounds per square foot
in the grain storage concrete silos area and 3,000 pounds per
square foot for all other foundation elements. The soils
beneath the foundation elements shall not exceed the total or
differential settlements such that the Plant is unable to perform
its intended purpose. If the existing soil conditions are
such that over-excavation and re-compaction or pilings are
required, OWNER will be responsible for this work. OWNER is
also responsible for any dewatering required at the site during
construction.
Other items to be provided by the
OWNER include, but are not limited to, the following: initial site
survey (boundary and topographic) as required by the design
engineers, layout of the property corners including two
construction benchmarks, soil borings and subsequent geotechnical
report (the results of which are acceptable to DESIGN/BUILDER and
consistent with the specifications set forth herein) describing
recommendation for roads, foundations and if required, soil
stabilization/remediation, site engineering and detailed drawings
(to the extent not provided by DESIGN/BUILDER), land disturbance
permit, erosion control permit, site grading as described above
with minimum soil standards, placement and maintenance of erosion
control measures, access road from a city, county, state or federal
road designed to meet city or local county road standards (provided
that such road must contain a minimum of twelve (12) inches of
crushed rock with geo-fabric and compacted base), storm and
sanitary sewers, water main branches, to be within five (5) feet of
the designated building locations, roads as specified and designed
for the permanent elevations and effective depth, paving,
“construction” grading plan as drawn (including site
retention pond), all site seeding, landscaping, rock, plant water
well and associated permit(s), environmental monitoring,
environmental monitoring equipment, environmental testing for both
air and water, chemicals, corn or other feedstock, enzymes, a risk
management plan, laboratory equipment specified by DESIGN/BUILDER,
and all start-up supplies, including, but not limited to hoses,
equipment labels, and other items specified by
DESIGN/BUILDER,
2)
Roads — OWNER shall provide or
have provided an access road of sufficient quality to withstand
semi-truck traffic of 25,000+ annual loads with weight of 80,000
lbs each.
3)
Air Quality Permit
— A permit for construction shall be obtained from the proper
authorities prior to the issuance of the Notice to Proceed.
OWNER shall obtain an Operating Permit in timely manner to allow
startup of the Plant as scheduled by DESIGN/BUILDER.
4)
Storm Water Runoff Permit —
OWNER shall obtain the permanent industrial storm water runoff
permit. DESIGN/BUILDER shall obtain the construction storm
water runoff permit.
5)
Natural Gas Supply and Service
Agreement — Continuous supply of natural gas of at least 1.2
billion cubic feet per year, at a rate of 135 MMBtu per hour and at
a minimum pressure of 60 psig at a location specified by
DESIGN/BUILDER. OWNER shall provide supply meter and regulators to
provide burner tip pressures as specified by DESIGN/BUILDER. OWNER
will be responsible for the design, procurement, fabrication and
installation of any and all equipment necessary to deliver the gas
to all locations specified by DESIGN/BUILDER.
6)
Electrical Service —
Continuous supply of 12,000 kVA, 12,400-volt electrical energy or
more to a point immediately adjacent to the site. OWNER shall
supply a high voltage switch and, if required, a substation.
OWNER shall supply metering as specified by the power
company. This electrical capacity will be sufficient to
support the operations of the Plant as specified by DESIGN/BUILDER.
OWNER will be responsible to design, provide, and install
electricity connections to all locations specified by
DESIGN/BUILDER (including the high-voltage permanent power loop,
transformers and pads).
7)
Water Supply and Service Agreement
— For process (contact and non-contact) and sanitary
purposes, OWNER shall design, procure, fabricate and install all
equipment for the supply of fresh water, and supply such water to
all locations specified by DESIGN/BUILDER. The water
augmentation plan and all associated fees, forms, permits and
incidental requirements is the responsibility of OWNER. OWNER shall
make such water supply available at the Site, and shall provide
DESIGN/BUILDER with a water sample from such supply, at least two
(2) months prior to the commencement of Construction.
8)
Wastewater Discharge Permit - For
discharges of cooling tower blowdown, water softening, and RO
system blowdown under normal operating procedures. Process
wastewater discharges during emergency failure of wastewater
treatment plant to treat all process wastewater.
9)
Railroad — OWNER shall
design, procure, fabricate and install any railroad track siding to
the Site, at grades specified by DESIGN/BUILDER, including all
necessary earth work to properly locate the track, preparation of
the railroad track bed, and track, ties and ballast to railroad
company specifications and all required permits.
10)
Regulatory Contingency — Until
satisfactory atmospheric emissions compliance, OWNER shall maintain
a fund of no less than Two Hundred Fifty Thousand Dollars
($250,000) to cover any unforeseen governmental regulation changes
implemented after the Effective Date of the Agreement. This
contingency is not part of the Contract Price, and its use may be
authorized only by agreement of OWNER and
DESIGN/BUILDER.
11)
Water treatment — OWNER shall
design, procure, fabricate and install all water treatment
equipment as deemed necessary by DESIGN/BUILDER. This might include
reverse osmosis, softening equipment, iron removal, sulfate
removal, or other items specified by DESIGN/BUILDER. OWNER to
contract with DESIGN/BUILDER to complete water treatment
work. All costs to complete work on water treatment are not
included in base contract price, and will be billed to the Owner at
cost plus 15%.
12)
Road Paving — After
Substantial Completion, OWNER will be responsible for paving of all
roads.
13)
BATF Application/Misc Permits
— OWNER will be responsible for completing, submitting and
obtaining Bureau of Alcohol Tobacco and Firearms permitting to
produce fuel grade alcohol, tank farm permits, discharge permits
required by hydro testing the Plant, and an SPCC Plan.
14)
Office Equipment — With the
exception of the DCS control systems, OWNER will be responsible for
office furnishings, computers and software to run the day-to-day
operations of the Plant.
15)
Construction Power — OWNER
will provide and pay for all electricity needed during the
Construction, including the permanent power loop required by
DESIGN/BUILDER, by contracting with DESIGN/BUILDER for the
installation of the same and which will be billed to OWNER as an
additional cost, and not part of, the Contract Price.
16)
Fire water system — OWNER
shall be responsible for the design, procurement, fabrication and
installation of the fire water system including, without
limitation: fire water pump station, fire water loop with hydrants,
deluge systems, fire alarm panels, smoke and heat detection in any
building or MCC room, as required by Laws and Regulations and the
insurance company(ies) which provide insurance pursuant to the
Contract Documents. OWNER to contract with DESIGN/BUILDER to
complete fire water system. All costs to complete work on
fire water system are not included in base contract price, and will
be billed to the Owner at cost plus 15%.
17)
Prior to start-up of the Plant,
OWNER shall furnish to DESIGN/BUILDER the
following:
a)
Fully executed copies of all permits required to operate the
Plant;
b)
Fully executed Certificate of Substantial Completion;
and
c)
Preliminary Punchlist pursuant to paragraph 13.05 of the General
Conditions.
In the event OWNER desires that
DESIGN/BUILDER perform all or any part of the foregoing obligations
of OWNER, and DESIGN/BUILDER agrees to perform such obligations,
the Contract Price shall be increased by the amount determined
pursuant to paragraph 10.02 of the General Conditions unless
otherwise agreed by the parties.
Exhibit F
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
LICENSE AGREEMENT
THIS LICENSE AGREEMENT (this
“License Agreement”) is entered into and made effective
as of the _____ day of _____________________, 200____
(“Effective Date”) by and between Heartland Grain
Fuels, LP a South Dakota limited partner company
(“OWNER”), and ICM, Inc., a Kansas corporation
(“ICM”).
WHEREAS, OWNER and ICM have entered
into that certain AGREEMENT BETWEEN OWNER AND DESIGN/BUILDER ON THE
BASIS OF A STIPULATED PRICE dated ____________________, 200_____
(the “Contract”), under which ICM is to design and
construct forty (40) million gallons per year ethanol plant for
OWNER to be located in or near Aberdeen, South Dakota (the
“Plant”);
WHEREAS, ICM will use proprietary
technology and information of ICM in the design and construction of
the Plant; and
WHEREAS, OWNER desires from ICM, and
ICM desires to grant to OWNER, a license to use such proprietary
technology and information in connection with OWNER’s
ownership and operation of the Plant, all upon the terms and
conditions set forth herein;
NOW, THEREFORE, the parties, in
consideration of the foregoing premises and the mutual promises
contained herein and for other good and valuable consideration,
receipt of which is hereby acknowledged, agree as
follows:
1.
Upon substantial completion of the Plant by ICM pursuant to the
terms of the Contract or, if later, payment by OWNER of all amounts
due and owing to ICM under the Contract, ICM agrees to grant to
OWNER a limited license to use the Proprietary Property
(hereinafter defined) solely in connection with the ownership,
operation, maintenance and repair of the Plant, subject to the
limitations provided herein (the “Purpose”).
2.
The “Proprietary Property” means, without limitation,
documents, Operating Procedures (hereinafter defined), materials
and other information that are furnished by ICM to OWNER in
connection with the Purpose whether orally, visually, in writing,
or by any other means, whether tangible or intangible, directly or
indirectly and in whatever form or medium including, without
limitation, the design, arrangement, configuration, and
specifications of (i) the combinations of distillation,
evaporation, and alcohol dehydration equipment (including, but not
limited to, pumps, vessels, tanks, heat exchangers, piping, valves
and associated electronic control equipment) and all documents
supporting those combinations; (ii) the combination of the
distillers grain drying (DGD), and heat recovery steam generation
(HRSG) equipment (including, but not limited to, pumps, vessels,
tanks, heat exchangers, piping and associated electronic control
equipment) and all documents supporting those combinations; and
(iii) the computer system, known as the distributed control system
(DCS and/or PLC) (including, but not limited to, the software
configuration, programming, parameters, set points, alarm points,
ranges, graphical interface, and system hardware connections) and
all documents supporting that system. The “Operating
Procedures” means, without limitation, the process equipment
and specifications manuals, standards of quality,
1
service protocols, data collection
methods, construction specifications, training methods, engineering
standards and any other information prescribed by ICM from time to
time concerning the Purpose. Proprietary Property shall not
include any information or materials that OWNER can demonstrate by
written documentation: (i) was lawfully in the possession of
OWNER prior to disclosure by ICM; (ii) was in the public domain
prior to disclosure by ICM; (iii) was disclosed to OWNER by a third
party having the legal right to possess and disclose such
information or materials; or (iv) after disclosure by ICM comes
into the public domain through no fault of OWNER or its members,
directors, officers, employees, agents, contractors, consultants or
other representatives (hereinafter collectively referred to as
“Representatives”). Information and materials
shall not be deemed to be in the public domain merely because such
information is embraced by more general disclosures in the public
domain, and any combination of features shall not be deemed to be
within the foregoing exceptions merely because individual features
are in the public domain if the combination itself and its
principles of operation are not in the public domain.
3.
OWNER shall not use the Proprietary Property for any purpose other
than the Purpose. OWNER shall not use the Proprietary
Property in connection with any expansion or enlargement of the
Plant. ICM and its Representatives shall have the express
right at any time to enter upon the premises of the Plant to
inspect the Plant and its operation to ensure that OWNER is
complying with the terms of this License Agreement.
4.
OWNER’s failure to materially comply with the Operating
Procedures shall void all guarantees, representations and
warranties, whether expressed or implied, if any, that were given
by ICM to OWNER in the Contract concerning the performance of the
Plant. OWNER agrees to indemnify, defend and hold harmless
ICM and ICM’s Representatives from any and all losses,
damages and expenses including, without limitation, reasonable
attorneys’ fees resulting from, relating to or arising out of
OWNER’s or its Representatives’ (i) failure to
materially comply with the Operating Procedures or, (ii) negligent
use of the Proprietary Property.
5.
Any and all modifications to the Proprietary Property by OWNER or
its Representatives shall be the property of ICM. OWNER shall
promptly notify ICM of any such modification and OWNER agrees to
assign all of its right, title and interest in such modification to
ICM; provided, however, OWNER shall retain the right, at no cost,
to use such modification in connection with the Purpose.
6.
ICM has the exclusive right and interest in and to the Proprietary
Property and the goodwill associated therewith. OWNER will
not, directly or indirectly, contest ICM’s ownership of the
Proprietary Property. OWNER’s use of the Proprietary
Property does not give OWNER any ownership interest or other
interest in or to the Proprietary Property except for the limited
license granted to OWNER herein.
7.
OWNER shall pay no license fee or royalty to ICM for OWNER’s
use of the Proprietary Property pursuant to the limited license
granted to OWNER, the consideration for this limited license is
included in the amounts payable by OWNER to ICM for the
construction of the Plant under the Contract.
8.
OWNER may not assign the limited license granted herein, in whole
or in part, without the prior written consent of ICM, which will
not be unreasonably withheld or delayed. Prior to any
assignment, OWNER shall obtain from such assignee a written
instrument, in form and substance reasonably acceptable to ICM,
agreeing to be bound by all the terms and
2
provisions of this License
Agreement. Any assignment of this License Agreement shall not
release OWNER from (i) its duties and obligations hereunder
concerning the disclosure and use of the Proprietary Property, or
(ii) damages to ICM resulting from, or arising out of, a breach of
such duties or obligations by OWNER or its Representatives.
ICM may assign its right, title and interest in the Proprietary
Property, in whole or part, subject to the limited license granted
herein.
9.
The Proprietary Property is confidential and proprietary.
OWNER shall keep the Proprietary Property confidential and shall
use all reasonable efforts to maintain the Proprietary Property as
secret and confidential for the sole use of OWNER and its
Representatives for the Purpose. OWNER shall retain all
Proprietary Property at its principal place of business and/or the
Plant. OWNER shall not at any time without ICM’s prior
written consent, copy, duplicate, record, or otherwise reproduce
the Proprietary Property, in whole or in part, or otherwise make
the same available to any unauthorized person. OWNER shall
not disclose the Proprietary Property except to its Representatives
who are directly involved with the Purpose, and even then only to
such extent as is necessary and essential for such
Representative’s involvement. OWNER shall inform such
Representatives of the confidential and proprietary nature of such
information and, if requested by ICM, OWNER shall obtain from such
Representative a written instrument, in form and substance
reasonably acceptable to ICM, agreeing to be bound by all of the
terms and provisions of this License Agreement. OWNER shall
make all reasonable efforts to safeguard the Proprietary Property
from disclosure by its Representatives to anyone other than
permitted hereby. OWNER shall notify ICM immediately upon
discovery of any unauthorized use or disclosure of the Proprietary
Property, or any other breach of this License Agreement by OWNER or
its Representatives, and shall cooperate with ICM in every
reasonable way to help ICM regain possession of the Proprietary
Property and prevent its further unauthorized use or
disclosure. In the event that OWNER or its Representatives
are required by law to disclose the Proprietary Property, OWNER
shall provide ICM with prompt written notice of same so that ICM
may seek a protective order or other appropriate remedy. In
the event that such protective order or other appropriate remedy is
not obtained, OWNER or its Representatives will furnish only that
portion of the Proprietary Property which in the reasonable opinion
of its or their legal counsel is legally required and will exercise
its reasonable efforts to obtain reliable assurance that the
Proprietary Property so disclosed will be accorded confidential
treatment.
10.
OWNER agrees to indemnify ICM for any and all damages (including,
without limitation, reasonable attorneys’ fees) arising out
of or resulting from any unauthorized disclosure or use of the
Proprietary Property by OWNER or its Representatives. OWNER
agrees that ICM would be irreparably damaged by reason of a
violation of the provisions contained herein and that any remedy at
law for a breach of such provisions would be inadequate.
OWNER agrees that ICM shall be entitled to seek injunctive or other
equitable relief in a court of competent jurisdiction against OWNER
or its Representatives for any unauthorized disclosure or use of
the Proprietary Property without the necessity of proving actual
monetary loss or posting any bond. It is expressly understood
that the remedy described herein shall not be the exclusive remedy
of ICM for any breach of such covenants, and ICM shall be entitled
to seek such other relief or remedy, at law or in equity, to which
it may be entitled as a consequence of any breach of such duties or
obligations.
11.
The duties and obligations of OWNER under this License Agreement,
and all provisions relating to the enforcement of such duties and
obligations shall survive and remain in full
3
force and effect notwithstanding any
termination or expiration of the Contract or this License
Agreement.
12.
ICM may terminate the limited license granted to OWNER herein upon
written notice to OWNER if OWNER willfully or wantonly uses the
Proprietary Property for any purpose, or discloses the Proprietary
Property to anyone, other than permitted herein. Upon
termination of the license, OWNER shall cease using the Proprietary
Property for any purpose (including the Purpose) and, upon request
by ICM, shall promptly return to ICM all documents or other
materials in OWNER’s or its Representatives’ possession
that contain Proprietary Property in whatever format, whether
written or electronic, including any and all copies or
reproductions of the Proprietary Property. OWNER shall
permanently delete all such Proprietary Property from its computer
hard drives and any other electronic storage medium (including any
backup or archive system). OWNER shall deliver to ICM a
written certificate which certifies that all electronic copies or
reproductions of the Proprietary Property have been permanently
deleted.
13.
The laws of the State of Kansas, United States of America, shall
govern the validity of the provisions contained herein, the
construction of such provisions, and the interpretation of the
rights and duties of the parties. Any legal action brought to
enforce or construe the provisions of this License Agreement shall
be brought in the federal or state courts located in Kansas, and
the parties agree to and hereby submit to the exclusive
jurisdiction of such courts and agree that they will not invoke the
doctrine of forum non conveniens or other similar defenses in any
such action brought in such courts. Notwithstanding the
foregoing, nothing in this License Agreement will affect any right
ICM may otherwise have to bring any action or proceeding relating
to this Agreement against OWNER or its properties in the courts of
any jurisdiction.
14.
OWNER hereby agrees to waive all claims against ICM and ICM’s
Representatives for any consequential damages that may arise out of
or relate to this License Agreement, the Contract or the
Proprietary Property whether arising in contract, warranty, tort
(including negligence), strict liability or otherwise, including
but not limited to losses of use, profits, business, reputation or
financing. OWNER agrees that the aggregate amount OWNER (and
anyone claiming by or through OWNER) may collectively recover from
ICM (and its Representatives), for the Plant as a whole under the
Contract and this License Agreement shall be limited to One Million
Dollars ($1,000,000.00)
15.
The terms and conditions of this License Agreement constitute the
entire agreement between the parties with respect to the subject
matter hereof and supersede any prior understandings, agreements or
representations by or between the parties, written or oral.
Any rule of construction to the effect that any ambiguity is to be
resolved against the drafting party shall not be applicable in the
interpretation of this License Agreement. This License
Agreement may not be modified or amended at any time without the
written consent of the parties.
16.
All notices, requests, demands, reports, statements or other
communications (herein referred to collectively as
“Notices”) required to be given hereunder or relating
to this License Agreement shall be in writing and shall be deemed
to have been duly given if transmitted by personal delivery or
mailed by certified mail, return receipt requested, postage
prepaid, to the address of the party as set forth below. Any
such Notice shall be deemed to be delivered and received as of the
date so delivered, if delivered personally, or as of the third
business day following the day sent, if sent by certified
mail. Any party may, at any time, designate a different
address to which Notices shall be directed by providing written
notice in the manner
4
set forth in this
paragraph.
17.
In the event that any of the terms, conditions, covenants or
agreements contained in this License Agreement, or the application
of any thereof, shall be held by a court of competent jurisdiction
to be invalid, illegal or unenforceable, such term, condition,
covenant or agreement shall be deemed void ab initio and shall be
deemed severed from this License Agreement. In such event,
and except if such determination by a court of competent
jurisdiction materially changes the rights, benefits and
obligations of the parties under this License Agreement, the
remaining provisions of this License Agreement shall remain
unchanged unaffected and unimpaired thereby and, to the extent
possible, such remaining provisions shall be construed such that
the purpose of this License Agreement and the intent of the parties
can be achieved in a lawful manner.
18.
The duties and obligations herein contained shall bind, and the
benefits and advantages shall inure to, the respective successors
and permitted assigns of the parties hereto.
19.
The waiver by any party hereto of the breach of any term, covenant,
agreement or condition herein contained shall not be deemed a
waiver of any subsequent breach of the same or any other term,
covenant, agreement or condition herein, nor shall any custom,
practice or course of dealings arising among the parties hereto in
the administration hereof be construed as a waiver or diminution of
the right of any party hereto to insist upon the strict performance
by any other party of the terms, covenants, agreement and
conditions herein contained.
20.
In this License Agreement, where applicable, (i) references to the
singular shall include the plural and references to the plural
shall include the singular, and (ii) references to the male,
female, or neuter gender shall include references to all other such
genders where the context so requires.
IN WITNESS WHEREOF, the parties
hereto have executed this License Agreement, the Effective Date of
which is indicated on page 1 of this License Agreement.
|
OWNER:
|
|
ICM:
|
|
|
|
|
|
Heartland Grain Fuels, LP
|
|
ICM, Inc.
|
|
By:
|
|
Dave VanderGriend By:
|
|
|
|
|
|
Title:
|
|
Title: President
|
|
|
|
|
|
Date Signed:
|
|
Date Signed:
|
|
|
|
|
|
Address for giving notices:
|
|
Address for giving notices:
|
|
|
|
|
|
|
|
301 N First Street
Colwich, KS 67030
|
5
Exhibit G
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
ICM
Training:
The Contract Price includes a
commitment by DESIGN/BUILDER to perform certain training for
certain personnel of OWNER at OWNER’s ethanol plant, which is
located in Aberdeen, South Dakota.
Employee training will be
coordinated by operational personnel of DESIGN/BUILDER with the
support of personnel of OWNER on location at OWNER’s ethanol
plant. Vendor training will also occur in conjunction with this
training. The specific schedule, attendees and training detail will
be provided as Plant start up date is determined.
Such personnel of OWNER will have
the opportunity to operate the ethanol plant under the supervision
of operators of DESIGN/BUILDER. It is anticipated that personnel
participating in such training will include the plant manager,
laboratory manager and shift supervisors who will work at the Plant
for a period of 1-3 weeks. DESIGN/BUILDER will not charge any fee
to OWNER for this startup training and DESIGN/BUILDER will provide
all training materials. Expenses for OWNER’s employees
such as travel, salaries, rooms and meals of the participants will
be the responsibility of OWNER.
Exhibit H
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
INSURANCE
DESIGN/BUILDER’S
Employers’ Liability, Business Automobile Liability, and
Commercial General Liability policies, as required in General
Conditions paragraph 5.02 shall be written with at least the
following limits of liability:
1.
Employers’ Liability Insurance
a. $
1,000,000
Bodily Injury by Accident
Each Accident
b.
$1,000,000
Bodily Injury by Disease
Policy Limit
c.
$1,000,000
Bodily Injury by Disease
Each Employee
2.
Business Automobile Liability Insurance
a.
$1,000,000
Each Accident
3.
Commercial General Liability Insurance
a. $1,000,000
Each Occurrence
b.
$2,000,000
General Aggregate
c.
$2,000,000
Products/Completed
Operations
Aggregate
d. $1,000,000
Personal and Advertising
Injury
Limit
4.
Liability Umbrella policy: $10,000,000 (in addition to the
underlying limits).
5.
Professional Errors & Omissions policy. $1,000,000 per
policy year.
*Portions omitted pursuant to a
request for confidential treatment and filed separately with the
SEC.
Exhibit I
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
Equipment Warranty:
The warranty for Plant production
rates, product quality, efficiencies and emissions standards is
covered in Exhibit A. This Exhibit I specifically defines
DESIGN/BUILDER’s operating warranty for Plant equipment
inside the battery limit .
DESIGN/BUILDER reserves the right at
its own discretion, to void any and all warranty if the operation
of the Plant and/or its subsystems, exceeds nameplate capacity by
[*] or more.
DESIGN/BUILDER is OWNER’s
first point of contact for any claim of warranty by OWNER against
DESIGN/BUILDER concerning Plant equipment, during the warranty
period.
The cost of labor performed by
vendors other than DESIGN/BUILDER to settle a warranty claim
situation, without written permission from DESIGN/BUILDER, will not
be covered under any warranty expressed or implied by
DESIGN/BUILDER.
What is furnished under the
warranty:
The warranty will furnish
replacement consumables and parts covered under the warranty.
Labor will only be furnished by DESIGN/BUILDER to repair items
warranted for workmanship and originally designed and built by
DESIGN/BUILDER.
What is covered by the
warranty:
Workmanship and materials on all
plant equipment including pumps, instruments, controls, DCS,
switchgear, wiring, conveyors, gearboxes, auger flighting, valves
2” size and above, valve actuators, tanks, vessels, air
compressors, boilers, cooling towers, motors, couplers, belts,
sheaves, chains, sprockets, heat exchangers, agitators,
centrifuges, fans, blowers, Hvac units, and other related
equipment.
Warranty will cover failures of
seals for lack of coolant flush during the seven (7) day
performance test described in Exhibit A.
Warranty will cover failure of seals
and couplers caused by misalignment during the seven (7) day
performance test described in Exhibit A.
Warranty will cover failure of pump
seals caused by product misapplication.
Warranty will cover labor and parts
to repair all leakage from pipes, exchangers and valves during the
seven (7) day performance test described in Exhibit A.
1
What is not covered by the
warranty:
Warranty does not cover damage to
process equipment of any kind, from, improper maintenance, improper
operation, operator negligence or abuse.
Warranty does not cover catastrophic
failures of the critical path equipment by chain reaction, from
improper operation, abuse or neglect of other equipment or
procedures in the process equipment critical path and/or acts of
God, whether upstream or downstream.
Warranty does not cover damage
caused by customer modification of equipment included in the
warranty list during the warranty period, without the written
consent of DESIGN/BUILDER.
Warranty does not cover pipe
gaskets, sight glasses, valves under 2” in size, door knobs,
walk in doors and closers, pipe and border painting, man-way
gaskets, countertops and window glasses after the seven (7) day
performance test described in Exhibit A.
Warranty does not cover pump seals,
pump motors and bearings that fail for lack of coolant flush after
the seven (7) day performance test described in Exhibit
A.
Warranty does not cover pump seals
or couplers after the seven (7) day performance test described in
Exhibit A that fail from misalignment.
Warranty will not cover failure of
any size valve when failure is determined to be a result of owner
welding on or near the valve.
Warranty will not cover failure of
any equipment due to improper grounding of welding
equipment.
Warranty will not cover any
equipment damaged by lightning strikes, power surges, power outages
or poor quality power from the electricity supplier.
Warranty will not cover leaking
plate and frame exchangers after the seven (7) day performance test
described in Exhibit A.
Procedure for warranty
claim:
DESIGN/BUILDER does not expect OWNER
to remain out of service with equipment that has failed during the
warranty period while trying to settle the warranty claim.
Whether covered by warranty or not the plant must
operate.
Consumable items such as motors,
gearboxes, seals, switchgear and similar equipment should be
replaced and the damaged unit returned to DESIGN/BUILDER or made
available for inspection by DESIGN/BUILDER. DESIGN/BUILDER reserves
the right to return the item to the manufacturer for evaluation
before settling a warranty issue.
Failure to return or produce for
inspection the damaged parts or equipment will void any warranty
expressed or implied.
2
1.
The first step by OWNER to satisfy a
warranty question is to call DESIGN/BUILDER’s project manager
(or the delegated alternate) and notify that person of the
claim. Provide the following information:
A.
Item nomenclature
B.
Equipment or part number
C.
Description of failure
D.
Corrective action taken
E.
Location and disposition of failed
item
2.
Fill out the electronic form
provided by DESIGN/BUILDER and send the form by mail or email to
the Project manager or his designate.
3.
Project manager or delegate will
respond within one (1) working day to acknowledge the claim and
documentation, by phone and follow up with email.
4.
Determination of settlement will be
made in forty-five (45) days or less by DESIGN/BUILDER. If
conflict arises from the determination between OWNER and
DESIGN/BUILDER, such conflict will be resolved under the dispute
resolution procedure set forth in Article 15 of the General
Conditions.
Warranty Period:
The warranty period is the twelve
(12) month period commencing on the date of Substantial Completion
and ending on the date that is 12 months immediately
thereafter. In order for OWNER to make a warranty claim the
deficiency must be discovered, and OWNER must notify DESIGN/BUILDER
in writing of such deficiency within this warranty
period.
3
*Portions omitted pursuant to a
request for confidential treatment and filed separately with the
SEC.
Exhibit J
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
[*]
*Portions omitted pursuant to a
request for confidential treatment and filed separately with the
SEC.
Exhibit K
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
[*]
*Portions omitted pursuant to a
request for confidential treatment and filed separately with the
SEC.
Exhibit L
to
Agreement Between Owner and Design/Builder
On the Basis of a Stipulated Price
[*]
GENERAL CONDITIONS OF THE
CONTRACT BETWEEN
OWNER AND DESIGN/BUILDER
ARTICLE
1—DEFINITIONS
1.01 Defined
Terms
A. Wherever used in these
General Conditions or in the other Contract Documents the following
terms have the meanings indicated which are applicable to both the
singular and plural thereof:
1.
Agreement— The Agreement Between Owner and Design/Builder
on the Basis of a Stipulated Price covering the Work. Other
Contract Documents are incorporated into the Agreement and made a
part thereof as provided therein.
2.
Application for Payment— The form that is substantially
similar to Exhibit J which is to be used by DESIGN/BUILDER in
requesting progress or final payments and which is to be
accompanied by such supporting documentation as is required by the
Contract Documents.
3.
Asbestos— Any material that contains more than one
percent (1%) asbestos and is friable or is releasing asbestos
fibers into the air above current action levels established by the
United States Occupational Safety and Health
Administration.
4.
Bond— Performance or payment bond or other instrument of
security.
5.
Change Order— A written order which is signed by
DESIGN/BUILDER and OWNER which authorizes an addition, deletion or
revision in the Work, or an adjustment in the Contract Price or the
Contract Times, issued on or after the Effective Date of the
Agreement.
6.
Construction —The performing or furnishing of labor,
the furnishing and incorporating of materials and equipment into
the Work and the furnishing of services (other than Design
Professional Services) and documents, all as required by the
Contract Documents. Construction includes the materials and
equipment incorporated into the Project.
7.
Construction Subagreement —A written agreement between
DESIGN/BUILDER and a construction contractor for provision of
Construction.
8.
Contract Documents —The Agreement and related
exhibits, the Notice to Proceed, these General Conditions, the
Specifications and the Drawings together with all Change Orders,
and Written Amendments, issued on or after the Effective Date of
the Agreement.
9. Contract
Price— The moneys payable by OWNER to DESIGN/BUILDER for
completion of the Work in accordance with the Contract
Documents.
10. Contract
Times —The number of days or the dates stated in the
Agreement (i) to achieve Substantial Completion, and (ii) to
complete the Work so that it is ready for final payment in
accordance with paragraph 13.08.
11.
defective —An adjective which when modifying the term
Construction refers to Construction that is unsatisfactory, faulty
or deficient, in that it does not conform to the
1
Contract Documents, or does not meet
the requirements of any inspection, reference standard, test or
approval referred to in the Contract Documents, or has been damaged
prior to OWNER’s final payment.
12.
DESIGN/BUILDER— ICM, Inc., a Kansas
corporation.
13. Design
Subagreement— A written agreement between DESIGN/BUILDER
and a design professional for provision of Design Professional
Services.
14. Design
Professional Services— Services provided by or for
licensed design professionals during Construction, or operational
phases of the Project, including the development of drawings,
Specifications, and other design submittals specified by the
Contract Documents and required to be performed by licensed design
professionals.
15.
Drawings— Those portions of the Contract Documents
prepared by or for DESIGN/BUILDER and approved by OWNER consisting
of drawings, diagrams, illustrations, schedules and other data
which show the scope, extent, and character of the Work.
16. Effective
Date of the Agreement— The date indicated in the
Agreement on which it becomes effective, but if no such date is
indicated it means the date on which the Agreement is signed and
delivered by the last of the two parties to sign and
deliver.
17.
Engineer— A duly licensed individual or entity designated
by DESIGN/BUILDER to perform or furnish specified Design
Professional Services in connection with the Work.
18. Hazardous
Condition —The presence at the Site of Asbestos,
Hazardous Waste, PCB’s, Petroleum Products or Radioactive
Materials in such quantities or circumstances that there is a
danger to persons or property.
19. Hazardous
Waste —The term Hazardous Waste shall have the meaning
provided in Section 1004 of the Solid Waste Disposal Act (42 USC
Section 6903).
20. Laws and
Regulations; Laws or Regulations —Any and all applicable
laws, rules, regulations, ordinances, codes, permits, and orders of
any and all governmental bodies, agencies, authorities and courts
having jurisdiction.
21. Liens
—Charges, security in