<PAGE>
Exhibit 4.7
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
AMENDMENT AGREEMENT NUMBER 4
(FOUR) TO THE MIXED AGREEMENT OF FINANCED PUBLIC
WORK NUMBER PIF-005/2003, FOR
THE RECOGNITION AND PAYMENT OF THE INCREASE IN THE
COST OF STEEL ENTERED INTO BY
AND BETWEEN ON THE ONE PART COMISION FEDERAL DE
ELECTRICIDAD (THE FEDERAL
COMMISSION OF ELECTRICITY), REPRESENTED BY ENG.
EUGENIO LARIS ALANIS, IN HIS
CAPACITY AS DIRECTOR OF FINANCED INVESTMENT
PROJECTS AND ON THE OTHER
PART THE COMPANY CONSTRUCTORA INTERNACIONAL DE
INFRAESTRUCTURA, S.A. DE
C.V., REPRESENTED BY ENG. LUIS HORCASITAS MANJARREZ, IN
HIS CAPACITY AS LEGAL
REPRESENTATIVE, HEREINAFTER REFERRED TO AS THE
"COMMISSION" AND THE
"CONTRACTOR", RESPECTIVELY, ACCORDING TO THE FOLLOWING
RECITALS AND
CLAUSES:
RECITALS
I. The PARTIES
represent:
I.1 That on
March 26, 2003, they executed the Mixed Agreement of
Financed
Public Work, recorded with the number PIF - 005/2003, legal
instrument
that shall hereinafter be referred to as the "Agreement", awarded
to
the CONTRACTOR by means of the International Public Bidding
Process,
established by Articles 27, paragraph I, 28 and 30, paragraph II,
32,
33 and 45 of the Law of Public Works and Services Related to the
Same,
which purpose consists of: the execution of the Civil
Works,
Electromechanical Works and Associated Works, supply,
engineering,
manufacturing, transportation, installation, testing and start up
of
two equipped turbo-generating Units, of 375 MW of nominal power
each,
for the fall and expense of specified design and that is detailed
in
Section 8 of the Bidding Rules, Works that all together are
named
Hydroelectric Project El Cajon, and which principal structures
are
located in the Municipalities of La Yesca and Santa Maria del Oro,
in
the State of Nayarit of Mexico.
The Works which consist of the Lump-sum Price Activities are
described
in detail in
Exhibits OE-3, OE-4 and OE-5 of Section 4 of the Bidding
Rules and are to be
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
conducted under the modality of lump-sum, because the portion of
the
Works that correspond to the Lump-sum Activities are depicted in
detail
in Exhibit OE - 5A of Section 4 of the Bidding Rules and shall
be
executed under the base of lump-sum.
I.2 That on
July 04, 2003, the PARTIES executed the Amendment
Agreement
Number 1 to the Agreement (hereinafter "Amendment Agreement Number
1").
I.3 That the
Price of the Agreement that the COMMISSION agreed to pay
to
the CONTRACTOR, agreed in Clause 9.1, was agreed to as total
payment
for the execution of the Works that correspond to the
Lump-Sum
Activities, the lump-sum price of US $ 682,517,584.80 Dollars
(Six
Hundred and Eighty Two Million Five Hundred and Seventeen Thousand
Five
Hundred and Eighty Four Dollars 80/100 Currency of the United
States),
and for the Unit Price Activities, the price of US $
65,773,072.59
Dollars (Sixty Five Million Seven Hundred and Seventy Three
Thousand
Seventy Two Dollars 59/100 Currency of the United States) plus
the
corresponding value added tax.
According to that established in the Third Clause of the
Amendment
Agreement Number 1 the COMMISSION and the CONTRACTOR agreed to
increase
the amount of the Unit Price Activities of the Agreement in the
amount
of US $ 5,801,271.26 Dollars (Five Million Eight Hundred and
One
Thousand Two Hundred and Seventy One Dollars 26/100 Currency of
the
United States) plus the Value Added tax, which represented an
increase
of 8.82 % (eight point eighty two per cent) relative to that
originally
contracted, thus remaining an accumulated aggregate amount of
the
Agreement based in unit prices of US $ 71,574,343.85 Dollars
(Seventy
One Million Five Hundred and Seventy Four Thousand Three Hundred
and
Forty Three Dollars 85/100 Currency of the United States) plus
the
corresponding value added tax, in accordance with the budget
of
Additional Works.
2
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
I.4 That on
September 10, 2003, the PARTIES executed the Amendment
Agreement Number 2 to the Agreement (hereinafter the
"Amendment
Agreement Number 2") in accordance with that established in
Articles 59
of the Law of Public Works and Services Related to the Same, and 69
and
79 of its Regulations, in order to: (i) under the Sixth Clause of
the
Amendment Agreement Number 1, modify the original Execution
Schedule
due to the new date for the commencement of the Works that is April
24,
2003; (ii)
agree to the disarrangement of the Critical Events Dates
1.1, 1.2, 1.3 and 1.4 established in Exhibit Number 3 of the
Agreement,
derived from the modifications to the contractual conditions that
have
ruled up to this date according to Clause 13.1 of the Agreement;
(iii)
recognize and pay, if applicable, under the modality of unit prices
the
Additional Costs related to the modifications of the original
Execution
Schedule, as a consequence of the late delivery and under
different
conditions to those established in the Bidding Rules and in
the
Agreement, of the portals of the deviation tunnels and the access
road
to the Site, for causes not imputable to the CONTRACTOR and adjust
the
Lump-sum Activities because of the modification to the length of
the
deviation tunnels and the reduction of the volume of the cofferdam
in
the upstream waters; (iv) approval in the event the COMMISSION
decides
their completion, of the payment of the Associated Additional
Costs
that derive from the Additional Works of Deviation under the
modality
of unitary prices for the building of the deviation tunnels and
the
pre-deviation tunnels by the left or right margins; (v) ratify
in
accordance with the Seventh Clause of the Amendment Agreement
Number 1
that the Critical Event 1.4 of Exhibit 3 of the Agreement ceased to
be
a Punishable Critical Event.
In
accordance with that established in the Sixth Clause of
the
Amendment Agreement Number 2 the COMMISSION and the CONTRACTOR
agreed
to increase the original amount of the Lump-sum Activities of
the
Agreement, due to the Additional Works of Deviation
hereinafter
described, subject to the condition that the COMMISSION decides
their
execution:
3
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
-
The increase of resources and extension of the crossing
tunnel
equals the amount of US $ 1,810,899.51 Dollars (One
Million
Eight Hundred and Ten Thousand Eight Hundred and Ninety
Nine
Dollars 51/100 Currency of the United States; plus VAT;
-
Pre-deviation by the left bank equals the amount of US $
2,969,437.75 Dollars (Two Million Nine Hundred and Sixty
Nine
Thousand Four Hundred and Thirty Seven Dollars 75/100
Currency
of the United States) plus VAT;
-
In the event the COMMISSION decides not to execute the
pre-deviation by the left bank, this shall pay for the
"emportalamiento" of said tunnel the amount of $
338,578.50
Dollars (Three Hundred and Thirty Eight Thousand Five
Hundred
and Seventy Eight Dollars 50/100 Currency of the United
States) plus VAT;
-
Pre-deviation by the right bank equals the amount of US
$
3,533,182.44 Dollars (Three Million Five Hundred and
Thirty
Three Thousand One Hundred and Eighty Two Dollars 44/100
Currency of the United States), plus VAT;
-
In the event the COMMISSION decides not to execute the
pre-deviation by the right bank, the COMMISSION shall pay
for
the construction of the access road, the ramp and
"emportalamiento" of said tunnel the amount of US $
1,662,411.00 Dollars (One Million Six Hundred and Sixty
Two
Thousand Four Hundred and Eleven Dollars 00/100 Currency
of
the United States) plus VAT.
I.5 That on
September 30, 2004, the PARTIES subscribed the Amendment
Agreement Number 3 to the Agreement (hereinafter referred to
as
"Amendment Agreement Number 3") according to that established
by
Articles 59 of the Law of Public Works and Services Related to
the
Same, and 69 and 79 of its Regulations, in order to: (i) Modify
the
Execution Schedule of the Amendment Agreement Number 2, according
to
that established in the Third Clause and in the last paragraph of
the
Fourth Clause of the same Amendment Agreement Number 2, as well as
that
contained in Recitals I.6 and II of this Agreement and upon
analyzing
the actual geological conditions found at the deviation tunnel No.
1 in
the intersection with the crossing tunnel the
4
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
activities conducted for the execution of the pre-deviation by
the
right bank and the effect on the construction of the baseboard
(plinth)
in the river bed, because of Calypso's default, the parties agree
to a
new Execution Schedule of the Works that is attached to the
Amendment
Agreement Number 3 as Exhibit 5. (ii) Recognize the real amount of
the
Associated Additional Costs that derived from the execution
of
Additional Works of Deviation, ordered by the commission under
the
modality of unitary prices, for the execution of the deviation
tunnels
and the pre-deviation tunnel by the right bank, as well as the
works
ordered by
the commission, for the potential pre-deviation by the
left
bank. (iii) Cancel the amounts of the Additional Deviation
Works
indicated in Clause Sixth of the amendment Agreement number 2,
which
was not necessary to build. (iv) Recognize and pay, if
applicable,
under the modality of unitary prices, the affectations in time and
cost
for the recovering of the program derived from that indicated
in
Recital I.6 and the Recitals of item II of this Agreement. (v)
Define
the new Dates of Critical Events 1.3, 1.5, 1.6, 1.12 and
1.13,
established in Exhibit Number 3 of the Agreement, derived from
the
modifications to the contractual conditions that prevailed to
this
date, according to
Clauses 13.3 and 27.3 second paragraph of the
Agreement and that are attached to Amendment Agreement Number 3
as
Exhibit 4, replacing that indicated in Exhibit 3 of the Agreement.
(iv)
Precise the average daily yields that the CONTRACTOR, in
accordance
with the Execution Schedule, shall execute for each of the
materials
that form the rock-fill dam in each of the phases of its
construction
process, to comply with the Critical Event 1.9 related to the
"final
closure of the deviation tunnels to start the filling of
the
reservoir", which date is July 1st., 2006, that are attached
to
Amendment Agreement Number 3 Exhibit 6.
According to that provided for in the Third Clause of the
Amendment
Agreement Number 3 the PARTIES agree and acknowledge to increase
the
original amount of the portion of the unitary prices of the
agreement
for the Associated Additional Works that derived from the execution
of
the following Additional Deviation Works ordered by the COMMISSION
and
that were effectively executed:
5
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
(i) Extension
of the crossing tunnel from the connection of tunnel
1 to tunnel 2 (sic) the amount of this Additional work
equals
the amount of US$ 261,145.08 (Two Hundred and Sixty One
Thousand One Hundred and Forty Five Dollars 08/100 Currency
of
the United States) plus VAT.
(ii)
The execution of the pre-deviation by the right bank,
the
amount of this Additional Deviation Work equals the amount
of
$ 1,457,047.88 US (One Million Four Hundred and Fifty
Seven
Thousand Forty Seven Dollars 88/100 Currency of the
United
States) plus VAT.
In accordance with the above, an increase is presented with respect
to
the original amount of the Price of the Agreement in the
portion
related to the Catalog of Unitary Prices, in the amount of
$
1,718,192.96 Dollars (One Million Seven Hundred and Eighteen
Thousand
One Hundred and Ninety Two Dollars 96/100 Currency of the
United
States), which represents a 2.61 % (two point sixty one per cent)
of
increase with respect to the original amount of the Price of
the
Agreement in the portion related to Unitary Prices and a 11.43
%
(eleven point forty three per cent) accumulated with respect to
the
original amount of the Price of the Agreement in the portion
related to
Unitary Prices, as a result the total amount of the portion
regarding
the Unitary Prices of the Agreement, in the amount of US
$
73,292,536.81 Dollars (Seventy Three Million Two Hundred and Ninety
Two
Thousand Five Hundred and Thirty Six Dollars 81/100 Currency of
the
United States) plus VAT.
I.6 That
Clause 11 "Adjustment of Costs" of the Agreement provides
as
follows:
The COMMISSION and the CONTRACTOR acknowledge that the portion of
the
works covered by the Agreement under the modality of payment of
unitary
prices,
6
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
this is, the Activities at Unitary Prices, shall not be subject to
the
adjustment of costs established in the Law of Public Works and
Services
Related to the Same and its Regulations because the quotation for
such
works derives from the basic elements of cost valued in Dollars,
and
therefore the CONTRACTOR expressly waives the right to adjustment
of
costs to the price of the aforementioned works. Said works shall
only
be subject
to adjustment of costs in accordance with the guidelines
issued, if applicable, by the Ministry of the Comptrollership
and
Administrative Development, in accordance with that established
in
Article 59 of the Law of Public Works and Services Related to the
Same.
The COMMISSION and the CONTRACTOR acknowledge that portion of the
works
covered by the Agreement under the modality of lump-sum price, this
is
the Lump-sum Activities, shall only be subject to costs adjustments
in
accordance with the guidelines issued, if such is the case, by
the
Ministry of the Comptroller and Administrative Development,
in
accordance with that established in Article 59 of the Law of
Public
Works and Services Related to the Same.
I.7 Article 59
of the Law of Public Works and Services Related to the
same
provides in its third, fourth, fifth and sixth paragraph, as
follows:
The lump-sum agreements or the portion of the mixed ones of this
kind
shall not be modified in their amount or term, nor shall they
be
subject to any adjustment of costs.
However, in the event that following the awarding of a
lump-sum
agreement or the portion of the mixed ones of this kind,
economic
circumstances of general nature may arise without the
responsibility of
the parties and therefore they could not have been subject matter
of
consideration in the tender that served as basis for the awarding
of
the correspondent agreement; such as, among others: fluctuations in
the
exchange rate or changes in the national or international prices
that
result in the direct increase or reduction in the costs of the
raw
materials necessary for the
7
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
works not yet executed in accordance with the originally
agreed
schedule; the agencies and entities shall recognize the increases
or
request reductions.
The provisions of the above paragraph shall be governed by
the
guidelines issued by the Comptrollership; same that shall
consider,
among other matters, the mechanisms available to the PARTIES to
face
these situations.
Once the potential modifications to the corresponding agreement
are
determined, the timely execution of the agreements shall be
the
responsibility of the corresponding agency or entity.
I.8 On May 21,
2004, the Ministry of Public Office published in the
Official Gazette of the Federation, the Order that provides
the
guidelines to conduct the review and adjustment of the price of
Steel
in the agreements and orders formalized under the Public Works Laws
and
Services Related to the Same, and the Acquisitions, Leases and
Services
of the Public Sector and its Regulations (hereinafter
the
"Guidelines"), same that became effective on the day following
its
publication and for a term of six months as of the date in which
they
became effective, to be applicable only for purposes of recognizing
the
change in the price of Steel in the relevant participation
that
corresponds to this concept regarding the total amount of
the
agreement. The adjustments shall be calculated as of the month
of
November 2003 regarding works not yet executed, according to
the
current Execution Schedule or, in the event of delay not
attributable
to the CONTRACTOR, with respect to the agreed upon
schedule.
For purposes of the Guidelines it is understood by "Steel"
the
different presentations of the aforementioned metal, among
others,
slabs, rolled-shape, extrusive angles, corrugated bar, rustles,
etc.
8
<PAGE>
FEDERAL COMMISSION OF ELECTRICITY
AGREEMENT NUM. PIF-005/2003
CONTRACT NUM. 4 (FOUR)
Said Order in its first three paragraphs of the portion of
the
considerations establishes that as of December 2003 the price of
the
Steel in its several presentations has been increasing constantly
and
unforeseeable in the market ranging such increases from 20 % to 50
%.
That such event has had an impact on the public works agreements
under
completion in which the raw material of Steel and its
different
presentations represents at least 10 % of the total amount of
related
operations and contracts not being this a limitation because
in
accordance with official communication UNAOPSPF/309/BM/1460/2004
said
10 % is only enunciatively in the consideration, thus
the
entrepreneurial chambers, suppliers and contractors, as well as
the
governmental agencies and Entities involved in the problematic
filed a
petition to the Ministry of Public Office stressing the need
of
establishing the correspondent guidelines and normative
mechani