Exhibit 10.10
TURNKEY ENGINEERING, PROCUREMENT
AND CONSTRUCTION
AGREEMENT FOR
ETHANOL PRODUCTION
FACILITY
BETWEEN
PANDA HEREFORD ETHANOL,
LP
A Delaware Limited
Partnership
AND
LURGI PSI, INC.
A Tennessee
Corporation
Dated as of October 15,
2005
CONFIDENTIAL TREATMENT HAS BEEN REQUESTED BY
PANDA ETHANOL, INC. FOR CERTAIN PORTIONS OF THIS DOCUMENT.
CONFIDENTIAL PORTIONS HAVE BEEN FILED SEPARATELY WITH THE
SECURITIES AND EXCHANGE COMMISSION. OMITTED PORTIONS ARE INDICATED
IN THIS AGREEMENT WITH “*****”.
TABLE OF
CONTENTS
|
|
|
|
|
|
|
Article I General Matters
|
|
|
|
Section 1.01
|
|
Defined Terms
|
|
1
|
|
Section 1.02
|
|
Interpretation
|
|
14
|
|
Section 1.03
|
|
Exhibits
|
|
15
|
|
|
|
|
Article II Retention of
Contractor
|
|
|
|
Section 2.01
|
|
Retention of Contractor
|
|
16
|
|
Section 2.02
|
|
Status of Contractor; No Partnership
|
|
16
|
|
Section 2.03
|
|
Subcontractors and Vendors
|
|
16
|
|
|
|
|
Article III Certain Obligations and
Responsibilities of Contractor
|
|
|
|
Section 3.01
|
|
Scope of Work; Applicable Standards
|
|
17
|
|
Section 3.02
|
|
Control and Method of the Work
|
|
18
|
|
Section 3.03
|
|
Compliance with Law
|
|
18
|
|
Section 3.04
|
|
Certain Matters Pertaining to Job
Site
|
|
19
|
|
Section 3.05
|
|
Access to Job Site
|
|
19
|
|
Section 3.06
|
|
Inspection and Testing of Work in
Progress
|
|
19
|
|
Section 3.07
|
|
No Waiver of Responsibility
|
|
20
|
|
Section 3.08
|
|
Intentionally left blank
|
|
20
|
|
Section 3.09
|
|
Clean-Up
|
|
20
|
|
Section 3.10
|
|
Obtaining, Maintaining and Identifying
Permits
|
|
20
|
|
Section 3.11
|
|
Labor
|
|
21
|
|
Section 3.12
|
|
Project Management
|
|
22
|
|
Section 3.13
|
|
Temporary Office Quarters
|
|
23
|
|
Section 3.14
|
|
Cooperation with Other Contractors
|
|
23
|
|
Section 3.15
|
|
Protection and Safety
|
|
23
|
|
Section 3.16
|
|
Environmental Matters
|
|
24
|
|
Section 3.17
|
|
Fire Prevention
|
|
27
|
|
Section 3.18
|
|
Religious and Archaeological
Resources
|
|
27
|
|
Section 3.19
|
|
Reports, Plans and Manuals
|
|
27
|
|
Section 3.20
|
|
Drawings, Engineering Data and Other
Materials
|
|
28
|
|
Section 3.21
|
|
Operating and Maintenance Manuals
|
|
29
|
|
Section 3.22
|
|
Training of O&M Personnel
|
|
30
|
|
Section 3.23
|
|
Accounting Information
|
|
30
|
|
Section 3.24
|
|
Contractor Taxes
|
|
30
|
|
Section 3.25
|
|
Claims and Liens for Labor and
Materials
|
|
31
|
|
Section 3.26
|
|
Spare Parts Availability
|
|
31
|
|
Section 3.27
|
|
Contractor’s Obligation to
Notify
|
|
32
|
|
Section 3.28
|
|
Construction Utilities
|
|
32
|
|
Section 3.29
|
|
Lines and Grades
|
|
32
|
-i-
|
|
|
|
|
|
|
Section 3.30
|
|
Temporary Structures
|
|
33
|
|
Section 3.31
|
|
Weatherproof Coverings
|
|
33
|
|
Section 3.32
|
|
Milestone Payment Schedule
|
|
33
|
|
Section 3.33
|
|
Emergencies
|
|
33
|
|
Section 3.34
|
|
Contractor’s Representative
|
|
33
|
|
Section 3.35
|
|
Contractor’s Insurances
|
|
33
|
|
Section 3.36
|
|
Raw Water, Sewage and PotableWater Line
Sizing
|
|
33
|
|
|
|
|
Article IV Certain Obligations of
Owner
|
|
|
|
Section 4.01
|
|
Permits
|
|
34
|
|
Section 4.02
|
|
Gas, Electric, and Water Facilities
|
|
34
|
|
Section 4.03
|
|
Fuel Supply
|
|
34
|
|
Section 4.04
|
|
Raw Water Supply
|
|
35
|
|
Section 4.05
|
|
Access to Property Site
|
|
35
|
|
Section 4.06
|
|
Right of Ways
|
|
35
|
|
Section 4.07
|
|
Survey of Property Site
|
|
35
|
|
Section 4.08
|
|
Notice of Financial Closing
|
|
35
|
|
Section 4.09
|
|
Owner Taxes
|
|
36
|
|
Section 4.10
|
|
Owner’s Cooperation
|
|
36
|
|
Section 4.11
|
|
Owner’s Representative
|
|
36
|
|
Section 4.12
|
|
Supplies
|
|
36
|
|
Section 4.13
|
|
Operation and Maintenance
|
|
36
|
|
Section 4.14
|
|
Owner’s Insurances
|
|
36
|
|
|
|
|
Article V Project Schedule
|
|
|
|
Section 5.01
|
|
Commencement of Work
|
|
37
|
|
Section 5.02
|
|
Project Schedule
|
|
37
|
|
Section 5.03
|
|
Certain Prefunding Work
|
|
38
|
|
|
|
|
Article VI Separated Contract Price; Payments
to Contractor
|
|
|
|
Section 6.01
|
|
Separated Contract Price
|
|
39
|
|
Section 6.02
|
|
Prefunding Costs
|
|
40
|
|
Section 6.03
|
|
Financial Closing Payment
|
|
41
|
|
Section 6.04
|
|
Post-Financial Closing
|
|
41
|
|
Section 6.05
|
|
General Provisions Payments
|
|
41
|
|
Section 6.06
|
|
Financing Parties’ Requirements and Lien
Waivers
|
|
42
|
|
|
|
|
Article VII Change Orders
|
|
|
|
Section 7.01
|
|
Change Order at Owner’s
Request
|
|
44
|
|
Section 7.02
|
|
Change Orders Requested by
Contractor
|
|
45
|
-ii-
|
|
|
|
|
|
|
Section 7.03
|
|
Changes to Separated Contract Price;
Disputes
|
|
47
|
|
Section 7.04
|
|
Information Requests
|
|
47
|
|
|
|
|
Article VIII Title, Risk of Loss and
Possession
|
|
|
|
Section 8.01
|
|
Clear Title
|
|
47
|
|
Section 8.02
|
|
Risk of Loss
|
|
48
|
|
Section 8.03
|
|
Possession Following Substantial
Completion
|
|
48
|
|
|
|
|
Article IX Insurance
|
|
|
|
Section 9.01
|
|
Contractor Insurance Policies
|
|
48
|
|
Section 9.02
|
|
Form of Contractor Insurance
Policies
|
|
49
|
|
Section 9.03
|
|
Qualified Insurers
|
|
50
|
|
Section 9.04
|
|
Certificates of Insurance
|
|
50
|
|
Section 9.05
|
|
Inspection of Contractor’s Insurance
Policies
|
|
51
|
|
Section 9.06
|
|
Subcontractors’ Insurance
|
|
51
|
|
Section 9.07
|
|
Remedy on Failure to Insure
|
|
51
|
|
Section 9.08
|
|
Management of Insurance Policies
|
|
51
|
|
Section 9.09
|
|
Owner Insurance Policies
|
|
51
|
|
Section 9.10
|
|
Contractor’s Assistance
|
|
52
|
|
Section 9.11
|
|
Liability not Limited to Insurance
Coverage
|
|
52
|
|
|
|
|
Article X Tests, Interim Completion,
Substantial Completion and Final Acceptance
|
|
|
|
Section 10.01
|
|
General
|
|
53
|
|
Section 10.02
|
|
Interim Completion
|
|
54
|
|
Section 10.03
|
|
Guaranteed Performance Tests
|
|
55
|
|
Section 10.04
|
|
Substantial Completion
|
|
56
|
|
Section 10.05
|
|
Punch List
|
|
57
|
|
Section 10.06
|
|
Final Acceptance
|
|
57
|
|
|
|
|
Article XI Contractor Guarantees
|
|
|
|
Section 11.01
|
|
Completion Guarantee
|
|
58
|
|
Section 11.02
|
|
Schedule Liquidated Damages for Interim
Completion
|
|
59
|
|
Section 11.03
|
|
Schedule Liquidated Damages for Substantial
Completion
|
|
59
|
|
Section 11.04
|
|
Performance Guarantees
|
|
60
|
|
Section 11.05
|
|
Liquidated Damages for Certain Performance
Guarantees
|
|
61
|
|
Section 11.06
|
|
Liquidated Damages for FBG Mechanical
Completion
|
|
63
|
|
Section 11.07
|
|
Payment of Liquidated Damages
|
|
64
|
|
Section 11.08
|
|
Contractor Bonus
|
|
65
|
|
Section 11.09
|
|
Determination of Performance
|
|
66
|
-iii-
|
|
|
|
|
|
|
Section 11.10
|
|
Retainage
|
|
66
|
|
Section 11.11
|
|
Corporate Guaranty
|
|
67
|
|
|
|
|
Article XII Contractor’s
Warranties
|
|
|
|
Section 12.01
|
|
Warranties
|
|
68
|
|
Section 12.02
|
|
Repair of Nonconforming Work
|
|
68
|
|
Section 12.03
|
|
Intentionally Left Blank
|
|
69
|
|
Section 12.04
|
|
Repairs and Testing by Owner
|
|
69
|
|
Section 12.05
|
|
Vendors and Subcontractors
|
|
70
|
|
Section 12.06
|
|
Assignment of Warranties
|
|
70
|
|
|
|
|
Article XIII Contractor’s
Representations
|
|
|
|
Section 13.01
|
|
Representations and Warranties
|
|
70
|
|
Section 13.02
|
|
Survival of Representations and
Warranties
|
|
72
|
|
|
|
|
Article XIV Force Majeure and Owner Caused
Delay
|
|
|
|
Section 14.01
|
|
Definition of Force Majeure Event
|
|
72
|
|
Section 14.02
|
|
Notice of Force Majeure Event
|
|
73
|
|
Section 14.03
|
|
Delay from Force Majeure Event
|
|
73
|
|
Section 14.04
|
|
Definition of Owner Caused Delay
|
|
74
|
|
Section 14.05
|
|
Notice of Owner Caused Delay
|
|
74
|
|
Section 14.06
|
|
Delay from Owner Caused Delay
|
|
74
|
|
Section 14.07
|
|
Performance Not Excused
|
|
75
|
|
Section 14.08
|
|
Hurricane Rescontruction
|
|
75
|
|
|
|
|
Article XV Termination
|
|
|
|
Section 15.01
|
|
Contractor Events of Default
|
|
75
|
|
Section 15.02
|
|
Termination by Owner due to Contractor
Default
|
|
77
|
|
Section 15.03
|
|
Termination by Owner for Convenience
|
|
79
|
|
Section 15.04
|
|
Suspension by Owner or Contractor for
Convenience
|
|
79
|
|
Section 15.05
|
|
Termination Due to Force Majeure
Event
|
|
81
|
|
Section 15.06
|
|
Termination by Contractor
|
|
81
|
|
Section 15.07
|
|
Continuing Obligations and Remedies During
Event of Default
|
|
82
|
|
Section 15.08
|
|
Obligations Upon Termination
|
|
82
|
|
Section 15.09
|
|
Termination and Survival of Terms
|
|
82
|
|
|
|
|
Article XVI Indemnification
|
|
|
|
Section 16.01
|
|
Contractor Indemnification
|
|
83
|
|
Section 16.02
|
|
Owner Indemnification
|
|
83
|
|
Section 16.03
|
|
Conditions of Indemnification
|
|
84
|
-iv-
|
|
|
|
|
|
|
Section 16.04
|
|
Contributory Negligence
|
|
85
|
|
Section 16.05
|
|
Remedies Not Exclusive; Joint
Responsibility
|
|
85
|
|
Section 16.06
|
|
Tax Effect of Indemnification
|
|
86
|
|
Section 16.07
|
|
Survival of Indemnification
|
|
86
|
|
|
|
|
Article XVII Dispute Resolution
|
|
|
|
Section 17.01
|
|
Friendly Consultation
|
|
86
|
|
Section 17.02
|
|
Arbitration
|
|
87
|
|
Section 17.03
|
|
Continuing Obligations and Rights
|
|
88
|
|
Section 17.04
|
|
Interim Remedies
|
|
88
|
|
Section 17.05
|
|
Joint Resolution of FBG/FBG Work
Disputes
|
|
88
|
|
|
|
|
Article XVIII Miscellaneous
|
|
|
|
Section 18.01
|
|
Assignment
|
|
89
|
|
Section 18.02
|
|
Financing Parties
|
|
89
|
|
Section 18.03
|
|
Good Faith Dealings
|
|
90
|
|
Section 18.04
|
|
Confidentiality
|
|
90
|
|
Section 18.05
|
|
Notice
|
|
90
|
|
Section 18.06
|
|
Waiver
|
|
91
|
|
Section 18.07
|
|
Severability
|
|
92
|
|
Section 18.08
|
|
Governing Law
|
|
92
|
|
Section 18.09
|
|
Entire Agreement; Amendments
|
|
92
|
|
Section 18.10
|
|
Expenses and Further Assurances
|
|
92
|
|
Section 18.11
|
|
No Third Party Beneficiary
|
|
93
|
|
Section 18.12
|
|
Offset
|
|
93
|
|
Section 18.13
|
|
Terms Sheet
|
|
93
|
|
Section 18.14
|
|
Counterparts
|
|
93
|
|
Section 18.15
|
|
Waiver of Consequential Damages; Maximum
Liability
|
|
93
|
-v-
EXHIBITS
|
|
|
|
|
EXHIBIT A
|
|
SCOPE OF
WORK
|
|
EXHIBIT
B
|
|
PROJECT
SCHEDULE
|
|
EXHIBIT
C
|
|
INTENTIONALLY
LEFT BLANK
|
|
EXHIBIT
D
|
|
MILESTONE
PAYMENT TABLE
|
|
EXHIBIT
E
|
|
FORM OF
MILESTONE ACHIEVEMENT CERTIFICATE AND FIELD MILESTONE
CERTIFICATION
|
|
EXHIBIT
F
|
|
FORM OF REQUEST
FOR PAYMENT
|
|
EXHIBIT
G
|
|
FORM OF FINAL
ACCEPTANCE CERTIFICATE
|
|
EXHIBIT
H
|
|
FORM OF
CONTRACTOR CERTIFICATE FOR PARTIAL WAIVER OF LIENS
|
|
EXHIBIT H-1
|
|
FORM OF
SUBCONTRACTOR CERTIFICATE FOR PARTIAL WAIVER OF LIENS
|
|
EXHIBIT
I
|
|
FORM OF
CORPORATE GUARANTY
|
|
EXHIBIT
J
|
|
SEPARATED
CONTRACT PRICE
|
|
EXHIBIT
K
|
|
CONTRACTOR RATE
SCHEDULE
|
|
EXHIBIT
L
|
|
CONTRACTOR
PERMITS
|
|
EXHIBIT
M
|
|
OWNER
PERMITS
|
|
EXHIBIT
N
|
|
MAJOR
EQUIPMENT
|
|
EXHIBIT
O
|
|
PROJECT
MANAGEMENT TEAM
|
|
EXHIBIT
P
|
|
INTENTIONALLY
LEFT BLANK
|
|
EXHIBIT
Q
|
|
APPROVED
SUBSTANTIAL SUBCONTRACTORS AND SUBSTANTIAL VENDORS
|
|
EXHIBIT
R
|
|
CONTRACTOR
FINAL LIEN WAIVER AND RELEASE
|
|
EXHIBIT
R-1
|
|
SUBCONTRACTOR
FINAL LIEN WAIVER AND RELEASE
|
|
EXHIBIT
S
|
|
SOIL BORING AND
SUBSURFACE DATA
|
|
EXHIBIT
T
|
|
FORM OF LETTER
OF CREDIT
|
-vi-
TURNKEY ENGINEERING, PROCUREMENT
AND CONSTRUCTION
AGREEMENT FOR
ETHANOL PRODUCTION
FACILITY
THIS TURNKEY ENGINEERING,
PROCUREMENT AND CONSTRUCTION AGREEMENT FOR ETHANOL PRODUCTION
FACILITY (this “Agreement”), dated as of
October 15, 2005 is by and between Panda Hereford Ethanol, LP,
a Delaware Limited Partnership (hereinafter called
“Owner”), and Lurgi PSI, Inc., a Tennessee Corporation
(hereinafter called “Contractor”).
W I T N E S S E T
H:
NOW, THEREFORE, in consideration of
the mutual promises and covenants herein contained, and other good
and valuable consideration, the receipt and sufficiency of which
are hereby acknowledged, Owner and Contractor hereby agree as
follows:
ARTICLE I
GENERAL MATTERS
Section 1.01 . Defined Terms . As used in this Agreement, including the
exhibits and other attachments hereto, each of the following terms
shall have the meaning assigned to such term as set forth
below:
“Acceptance Certificate”
means a certificate relating to Final Acceptance pursuant to
Section 10.06 .
“Affiliate” means, in
relation to any Person, any Person: (i) which directly or
indirectly controls, or is controlled by, or is under common
control with, such other Person; or (ii) which directly or
indirectly beneficially owns or holds fifty percent (50%) or
more of any class of voting stock of such other Person; or
(iii) which has fifty percent (50%) or more of any class
of voting stock that is directly or indirectly beneficially owned
or held by such other Person, or (iv) who either holds a
general partnership interest in such other Person or such other
Person holds a general partnership interest in the
Person.
“Allocated Contract
Price” means (a) for the time period between the
Effective Date and the later of the Financial Closing Date and the
date the Notice to Proceed is given to Contractor following the
Financial Closing Date (the “Full Release Date”), the
Ethanol Plant Price paid to Contractor; (b) for the time
period after Full Release Date and until the time when *****% of
the Ethanol Plant Price has been paid to Contractor, *****% of the
Ethanol Plant Price plus the Ethanol Plant Price paid to Contractor
to date; or (c) for the time period after *****% of the
Ethanol Plant Price has been paid to Contractor, the Ethanol Plant
Price paid to Contractor to date, as the case may be.
CONFIDENTIAL TREATMENT HAS BEEN REQUESTED BY
PANDA ETHANOL, INC. FOR CERTAIN PORTIONS OF THIS DOCUMENT.
CONFIDENTIAL PORTIONS HAVE BEEN FILED SEPARATELY WITH THE
SECURITIES AND EXCHANGE COMMISSION. OMITTED PORTIONS ARE INDICATED
IN THIS AGREEMENT WITH “*****”.
-1-
“Applicable Laws” means
any act, statute, law, regulation, permit, license, ordinance,
rule, judgment, order, decree, directive, guideline or policy (to
the extent mandatory) or any similar form of decision or
determination by, or any interpretation or administration of, any
of the foregoing by any Government Authority with jurisdiction over
the Facility, the Job Site, the performance of the Work or other
services to be performed under this Agreement.
“Applicable Permits”
means any and all permits, clearances, licenses, authorizations,
consents, filings, exemptions or approvals from or required by any
Government Authority that are necessary for the performance of the
Work.
“Builder’s Risk
Policy” has the meaning set forth in Section 9.09
.
“Business Day” means any
day other than a Saturday, Sunday or a legal holiday in Dallas,
Texas.
“Change in Law” means
any of the following events or circumstances occurring after the
date of execution of this Agreement: (i) an amendment,
modification, supplement or other change in or repeal of an
existing Applicable Law or Applicable Permit; or (ii) an
enactment or making of a new Applicable Law or Applicable
Permit.
“Change Order” has the
meaning set forth in Section 7.01(a) .
“Changes” has the
meaning set forth in Section 7.01(a) .
“Contract Amendment”
shall mean a written agreement executed by both Parties and, if
required, consented to by the Financing Parties, as set forth in
Section 18.09 .
“Contractor Bonus” means
a Schedule Bonus or Performance Bonus.
“Contractor Equipment”
means all of the equipment, materials, apparatus, structures,
tools, supplies and other goods provided by Contractor and its
Subcontractors and Vendors for performance of the Work other than
the Equipment.
“Contractor Event of
Default” was the meaning set forth in
Section 15.01 .
“Contractor Insurance
Policies” means the insurance policies maintained by
Contractor as required pursuant to Article IX .
“Contractor Internal
Costs” means the internal costs of Contractor in performing
the Prefunding Work, including general and administrative costs,
labor costs, overhead and out-of-pocket expenses such as travel,
telephone and photocopies.
“Contractor Permits”
means the Applicable Permits listed on Exhibit L
.
-2-
“Contractor Project
Engineering Manager” means the person designated by
Contractor as having the responsibility, authority and supervisory
power of Contractor for the Work.
“Contractor Project
Manager” means the person designated by Contractor as having
the centralized responsibility, authority and supervisory power of
Contractor for design, construction, testing and start-up of the
Ethanol Plant and the performance of the FBG Work, as well as all
matters relating to the administration of the provisions of this
Agreement.
“Contractor Site
Manager” means an employee of Contractor, working under the
supervision of the Contractor Project Manager, located at the Job
Site on a daily basis.
“Contractor Taxes” has
the meaning set forth in Section 3.24 .
“Contractor’s
Guarantor” has the meaning set forth in
Section 11.11 .
“Corporate Guaranty” has
the meaning set forth in Section 11.11 .
“Cost Plus Formula” has
the meaning as set forth in Section 7.02(e)
.
“Damages” has the
meaning set forth in Section 16.01 .
“Defect” means, any
designs, engineering, software, drawings, components, tools,
Equipment, installation, construction, or workmanship
furnished or performed by or on behalf of Contractor or Work,
(i) that does not materially conform to the terms of this
Agreement, (ii) that is not of uniform good quality, free from
material defects or deficiencies in design, application,
manufacture or workmanship, or that contains materially improper or
inferior workmanship or (iii) that either would materially and
adversely affect (A) the performance of the Ethanol Plant and
FBG Work under operating conditions as stated in Exhibit A, the
Scope of Work (unless, in the alternative, Performance Liquidated
Damages for such defect or deficiencies has been paid) or
(B) the continuous safe operation of the Facility, all as
determined by reference to Good Engineering Practices. The term
“Defect” shall neither be construed to include material
damage caused by Owner’s acts or omissions to the extent
arising out of abuse, misuse or negligence in operations,
maintenance and repair (unless such act or omission was taken or
made at the direction of Contractor) or failure to follow
Contractor’s or manufacturers’ recommendations and
directions and Good Engineering Practices, nor shall the term
“Defects” be construed to include ordinary wear and
tear, erosion, corrosion, and deterioration (unless as a result of
a Defect) or any other defect or deficiency that has no material
impact on the Facility’s appearance, operation or useful life
as specified in the Scope of Work.
“Denatured Ethanol”
means fuel grade ethanol in accordance with and meets the
requirements of ASTM D4806-01a dated August 10,
2001.
-3-
“Dispute” has the
meaning set forth in Section 17.01 .
“Drawings” means
(i) all specifications, designs, plans, drawings, engineering
and analyses, and other documents which determine, establish,
define or otherwise describe the scope, quantity, and relationship
of the components of the Ethanol Plant and the FBG Work, including
the structure and foundation thereof, prepared by Contractor or any
of its Subcontractors or Vendors and (ii) all technical
drawings, operating drawings, specifications, shop drawings,
diagrams, illustrations, schedules and performance charts, samples,
patterns, models, operation and maintenance manuals, piping and
instrumentation diagrams, underground structure drawings, conduit
and grounding drawings, lighting drawings, conduit and cable
drawings, electric one-lines, electric schematics, connection
diagrams and technical information of a like nature required to be
submitted by Contractor, or any Subcontractor or Vendor, from time
to time under this Agreement which illustrates any of the Equipment
or any other portion of the Work, either in components or as
completed.
“Effective Date” means
the date on which all of the following have occurred: (a) this
Agreement has been executed and delivered by both Owner and
Contractor as set forth on Page 1 hereof, (b) Owner has paid
to Contractor all amounts, if any, due under the terms of that
certain Term Sheet between the Parties, and (c) Owner has
issued to Contractor a Notice to Proceed under
Section 5.01 and in the event any such Notice to
Proceed requires the payment of any amount due pursuant to Exhibit
D, such payments are made. The Parties shall confirm the Effective
Date in writing.
“Electric Power
Consumption” means the overall electric power consumed by the
Ethanol Plant in kWh as measured at the meter for equipment
specifically and directly involved in the production of ethanol and
wet distiller’s grain in accordance with the Scope of Work.
This does not include any CO 2 processing, grain handling, or FBG
or natural gas boiler electrical power consumption.
“Electric Power Consumption
Guarantee” has the meaning set forth in
Section 11.04(a) .
“Emissions Guarantee”
has the meaning set forth in Section 11.04(e)
.
“Equipment” means all of
the equipment, materials, apparatus, structures, tools, supplies,
goods and other items provided by Contractor and its Subcontractors
and Vendors that are installed or incorporated into the Ethanol
Plant or otherwise form or are intended to form part of the Work
(other than Contractor Equipment). For avoidance of doubt, the FBG
shall not constitute a part of the Equipment.
“Ethanol Plant” means
the Facility, excluding both the Fluidized Bed Gasifier Equipment
and the FBG Work.
-4-
“Ethanol Plant Price”
means the Separated Contract Price less the FBG Work
Price.
“Ethanol Plant Reliability
Guarantee” has the meaning set forth in Section
11.04(i) .
“Ethanol Production
Rate” means the production of Denatured Ethanol measured in
gallons per hour.
“Ethanol Production Rate
Guarantee” means the production rate of Denatured Ethanol as
guaranteed by Contractor pursuant to Section 11.04(c)
.
“Ethanol Yield” means
the ratio in weight (pounds) of un-denatured ethanol per weight
(pounds) of starch, based on Un-denatured Ethanol density of 6.60
pounds per US gallon at 60F, containing a maximum of 0.5% water per
weight. The yield is based on a feedstock specification of 56 lb
per bushel test weight #2 yellow corn containing a maximum of
15.0%moisture (by weight), a maximum of 1% foreign material (by
weight), a minimum of 70% of dry fermentable starch (by weight) and
zero aflatoxin tolerance.
“Ethanol Yield
Guarantee” has the meaning set forth in
Section 11.04(d) .
“Facility” means the
nominal 105 million gallon per year design capacity of
Denatured Ethanol production facility consisting of all necessary
and fully functional systems and equipment, apparatus, accessories,
auxiliaries and controls capable of fuel grade ethanol production,
and wet distillers grain production, which Facility includes the
Ethanol Plant and an auxiliary natural gas boiler to be supplied by
Contractor and the FBG to be supplied by the Fluidized Bed Gasifier
Supplier, to be located on the Property Site as more particularly
described in the Scope of Work.
“FBG Mechanical
Completion” means that with respect to the FBG Work
(i) the FBG and all Equipment has been installed with the
required connections and controls to deliver steam to the Ethanol
Plant; (ii) the FBG and all Equipment has been installed in
accordance with construction drawings, the Scope of Work and
manufacturers recommendations, checked for alignment, lubrication
and rotation; (iii) all systems have been checked out, and are
ready for safe and proper operation; (iv) all instrumentation
(including Continuous Emissions Monitoring Systems) is operational
and has been calibrated in accordance with manufacturers’
standards and guidelines and loop checked; and (v) all systems
have been tested, flushed and cleaned out as necessary and restored
in accordance with the Scope of Work.
“FBG Mechanical Completion
Date” means the date when FBG Mechanical Completion is
achieved.
“FBG Purchase Agreement”
means that separate agreement between Owner and the Fluidized Bed
Gasifier Supplier in Appendix A of Exhibit A governing the supply
of
-5-
the FBG for the Facility, including the design,
engineering, procurement, training, commissioning, start-up and
testing activities to be performed by the Fluidized Bed Gasifier
Supplier directly for Owner.
“FBG Schedule Liquidated
Damages” has the meaning set forth in Section 11.06
(a) .
“FBG Work” means
Contractor’s design, engineering, procurement and
construction for the installation of the FBG and the tie-in of the
FBG to the Ethanol Plant in accordance with the Scope of
Work.
“FBG Work Price” shall
mean the price for the FBG Work, as stated in Exhibit J, as amended
from time to time pursuant to the terms hereof.
“Field Milestone
Certification” means a duly executed certificate in
substantially the form of the Field Milestone Certification in
Exhibit E attached hereto, which is submitted by Contractor to
Owner with a Request for Payment.
“Final Acceptance” shall
mean that all of the following have occurred: (i) Substantial
Completion of the Ethanol Plant has been achieved; (ii) the
Guaranteed Performance Tests applicable to the Ethanol Plant,
mechanical calibrations, have been successfully completed and any
Defects found have been corrected; (iii) either (A) the
Guaranteed Performance Levels applicable to the Ethanol Plant
specified in Section 11.04 have been met or exceeded as
determined pursuant to Section 11.09 , or (B) the
Ethanol Plant has achieved at a minimum the Minimum Performance
Levels as determined pursuant to Section 11.09 and
Contractor has paid all Performance Liquidated Damages applicable
to the Ethanol Plant as elected or required pursuant to
Section 11.05 and Section 11.06 ;
(iv) the Ethanol Plant has satisfied the Emissions Guarantee
and the Noise Guarantee, as more fully provided herein;
(v) the Ethanol Plant has been constructed in accordance with
this Agreement and the Drawings; (vi) the Final Plans
accurately reflect the Ethanol Plant as constructed; (vii) the
Ethanol Plant is capable of being operated in a safe manner in
accordance with the terms of this Agreement; (viii) Contractor
shall have delivered to Owner all operation and maintenance manuals
and Final Plans relating to the Ethanol Plant in accordance with
the Scope of Work; (ix) no defective or incomplete portions of
the Work exist that have or could reasonably have a material
negative impact on the operation or performance of the Ethanol
Plant as required under this Agreement; (x) either
(A) all items on the Punch List applicable to the Ethanol
Plant have been completed or (B) the Parties have reached an
agreement pursuant to Section 10.05(c) and Contractor
has paid all amounts due to Owner pursuant thereto; (xi) all
of Contractor’s cleanup and related obligations have been
completed; (xii) any and all Liens in respect to this
Agreement, the Equipment, the Job Site or any fixtures, personal
property or Equipment included in the Work and related to the
Ethanol Plant or the FBG Work created by, through or under, or as a
result of any act or omission of, Contractor or any Subcontractor,
Vendor or other Person providing labor or materials in connection
with the Work shall have been released in accordance with
Section 3.25 and in a form
-6-
reasonably satisfactory to Owner in accordance
with Exhibit R and Exhibit R-1 attached hereto (provided that
Contractor’s Final Lien Waiver and Release related to the
Ethanol Plant, in substantially the form of Exhibit R attached
hereto, shall be given concurrently with Final Acceptance of the
Ethanol Plant and payment of amounts due by Owner in connection
therewith); (xiii) Contractor shall have paid all Schedule
Liquidated Damages and Performance Liquidated Damages related to
the Ethanol Plant due under this Agreement, if any; (xiv) all
other outstanding obligations of Contractor relating to the Ethanol
Plant hereunder that Owner has notified Contractor of shall have
been satisfied; (xv) spare parts required under this Agreement
with respect to the Ethanol Plant have been delivered by Contractor
to the Property Site in accordance with
Section 3.26(a); (xvi) Contractor has provided
Owner with copies of all Contractor’s Applicable Permits
relating to the Ethanol Plant; and (xvii) Owner has approved
of and signed the Final Acceptance Certificate pursuant to
Section 10.06 . If however, Owner has failed or refused
to sign such Certificate after request by Contractor, such matter
may be submitted for dispute resolution in accordance with Article
XVII.
“Final Acceptance
Certificate” means an Acceptance Certificate executed
pursuant to Section 10.06 .
“Final Acceptance Date”
means the first date on which Final Acceptance has been
achieved.
“Final Plans” means
final Drawings and final specifications, as revised to reflect the
changes during construction, and shall include as-built drawings,
piping and instrumentation diagrams, underground structure drawings
(including buried piping, all utilities, and critical hidden
items), electric one-lines, electric schematics and connection
diagrams.
“Financial Closing”
shall mean that all of the following events shall have occurred
(which events may occur over a period of time) with respect to the
Facility: (i) the Financing Documents have been fully executed
(which documents may be executed over a period of time) which
together provide for financing for the Facility in an amount and on
the terms acceptable to Owner; (ii) all conditions precedent
to the initial availability of funds under the Financing Documents
referred to in the preceding clause (i) have been fulfilled or
waived and the first draw thereunder has been made by Owner; and
(iii) Owner has received commitments for such equity as is
required by Owner and satisfies the requirements of the Financing
Parties.
“Financial Closing Date”
shall mean the actual date of Financial Closing as specified by
Owner to Contractor pursuant to Section 4.08
.
“Financing Documents”
means all the loan agreements, notes, indentures, securities, debt
instruments, bonds, security agreements, swap agreements, letters
of credit, equity purchase agreements and other documents relating
to the financing (including refinancing) of the Facility or any
part thereof.
-7-
“Financing Parties”
means the lenders, security holders, investors, export credit
agencies, multilateral institutions, equity providers and others
providing financing or refinancing to or on behalf of Owner, for
the development, construction, ownership, operation and maintenance
of the Facility or any portion thereof, or any trustee or agent
acting on behalf of any of the foregoing.
“Fluidized Bed Gasifier
Equipment” or “Gasifier Equipment” or
“FBG” means the fluidized bed gasifier with a fired
steam generation unit and all related accessory equipment,
including the biomass handling equipment, supplied by the Fluidized
Bed Gasifier Supplier pursuant to the terms of the FBG Purchase
Agreement.
“Fluidized Bed Gasifier
Supplier” means Energy Products of Idaho (EPI). For avoidance
of doubt, the Fluidized Bed Gasifier Supplier shall not (in respect
of its obligations relating to the design, engineering,
manufacture, delivery, commissioning, start-up and testing of the
FBG) constitute a Vendor or Subcontractor under this
Agreement.
“Force Majeure Event”
has the meaning set forth in Section 14.01 .
“Good Engineering
Practices” means the practices generally recognized and
accepted as guidelines defining the standard of care that documents
the engineering practices with respect to design, construction,
documentation, operation, and maintenance of industrial facilities
(including but not limited to the engineering, operating and safety
practices generally applied to ethanol facilities) such as will be
constructed in accordance with the terms of this
Agreement.
“Government Authority”
means any and all federal, state, county, city, municipal, local or
regional authorities, departments, bodies, commissions,
corporations, branches, directorates, agencies, ministries, courts,
tribunals, judicial authorities, legislative bodies, administrative
bodies, regulatory bodies, autonomous or quasi-autonomous entities
or taxing authorities of the United States of America or any
department, municipality or other political subdivision
thereof.
“Guaranteed Dates” means
Guaranteed Interim Completion Date, Guaranteed Substantial
Completion Date, Guaranteed FBG Mechanical Completion Date, and
Final Acceptance Date.
“Guarantee Design
Conditions” has the meaning assigned to such term in the
Scope of Work.
“Guaranteed FBG Mechanical
Completion Date” means the date which is 45 calendar days
after the latest of the Scheduled FBG Delivery Dates set forth in
Exhibit A , as such date may be adjusted by (i) the
total number of days more or less, if any, before or after the
Scheduled FBG Delivery Dates and the date the applicable
deliverable is actually delivered to the Job Site by the Fluidized
Bed Gasifier Supplier, (ii) Force Majeure Events under Article
XIV, and (iii) Owner Caused Delays under Section 14.04
.
-8-
“Guaranteed Interim Completion
Date” means January 1, 2007, as such date may be
extended under the terms of this Agreement.
“Guaranteed Performance
Levels” means the performance levels of the Ethanol Plant as
guaranteed by Contractor pursuant to Section 11.04
.
“Guaranteed Performance
Tests” means collectively all guaranteed performance tests as
described in the Scope of Work.
“Guaranteed Substantial
Completion Date” means February 1, 2007, as such date
may be extended under the terms of this Agreement.
“Hazardous Material”
means any substance deemed as toxic, contaminated or hazardous
under any Applicable Law or Applicable Permit.
“Initial Site
Mobilization” means the first instance when any of Contractor
or its or its Subcontractors’ or Vendors’ Labor or
other representatives is present on the Property Site after Owner
has granted to Contractor care, custody and control of the portion
of the Property Site that is part of the Job Site.
“Interim Completion”
shall mean that (i) Mechanical Completion of the Ethanol Plant
has occurred; (ii) the Ethanol Plant is Ready for Start-Up;
(iii) the Ethanol Plant has achieved, during a minimum
continuous production period of 72 hours, on average, not less than
75 percent of the Ethanol Production Rate Guarantee, as set forth
in Section 11.04, 11.09 and in the Scope of Work and
(iv) the Ethanol Plant is capable to operate continuously,
normally and safely, in accordance with the requirements
hereunder.
“Interim Completion
Date” means the actual date of achieving Interim Completion
as determined pursuant to Section 10.02 .
“Interim Completion
Test” means the test required to demonstrate Interim
Completion, as determined in accordance with the Scope of Work and
Section 11.09 .
“Job Site” means the
Property Site (identified on the survey provided by Owner pursuant
to Section 4.07 ) and any other areas where Contractor
may temporarily obtain care, custody and control, use, easement or
license for purposes directly, indirectly or incidentally related
to performance of, or as an accommodation to, the Work.
“Labor” means the
workforce of the relevant Person, including its staff and employee
and non-employee and skilled and unskilled workers.
-9-
“LC Issuing Bank” means
Deutsche Bank, New York Branch, or such other financial institution
reasonably acceptable to Owner and Contractor.
“Letter of Credit” has
the meaning set forth in Section 11.10 .
“License Agreement”
means that certain license agreement between Contractor and Owner,
which agreement is an integral part of the transaction evidenced by
this Agreement.
“Lien” means any lien,
security interest, mortgage, hypothecation, encumbrance or other
restriction on title or property interest.
“Major Equipment” means
the Equipment listed on Exhibit N .
“Major Manufacturers”
means the manufacturers of the Major Equipment.
“Mechanical Completion”
means that (i) all Equipment has been installed with the
required connections and controls to produce steam, ethanol and wet
distillers’ grain; (ii) all Equipment has been installed
in accordance with construction drawings, the Scope of Work and
manufacturers recommendations, checked for alignment, lubrication
and rotation; (iii) all systems for the Ethanol Plant have
been checked out, and are ready for safe and proper operation;
(iv) all instrumentation (including Continuous Emissions
Monitoring Systems) for such Ethanol Plant is operational and has
been calibrated in accordance with manufacturers’ standards
and guidelines and loop checked; and (v) all systems for the
Ethanol Plant have been tested, flushed and cleaned out as
necessary and restored in accordance with the Scope of
Work.
“Milestone Achievement
Certificate” means a duly executed certificate in
substantially the form of the Milestone Achievement Certificate in
Exhibit E attached hereto, which is submitted by Contractor
to Owner with a Request for Payment.
“Milestone Payment
Table” means that table of Milestone Payments which is set
forth in Exhibit D attached hereto.
“Milestone Payments” has
the meaning set forth in Section 6.01 .
“Milestones” means the
milestones set forth in Exhibit D attached
hereto.
“Minimum Performance
Levels” means the Ethanol Plant has achieved, during a
minimum continuous production period of 72 hours, on average, not
less than ***** percent of the Ethanol Production Rate Guarantee
and ***** percent of the Ethanol Yield Guarantee, and no more than
***** percent of the Natural Gas Consumption Guarantee and no more
than ***** percent of the Electric Power Consumption Guarantee, as
set forth in Section 11.04, 11.09 and in the Scope of
Work.
CONFIDENTIAL TREATMENT HAS BEEN REQUESTED BY
PANDA ETHANOL, INC. FOR CERTAIN PORTIONS OF THIS DOCUMENT.
CONFIDENTIAL PORTIONS HAVE BEEN FILED SEPARATELY WITH THE
SECURITIES AND EXCHANGE COMMISSION. OMITTED PORTIONS ARE INDICATED
IN THIS AGREEMENT WITH “*****”.
-10-
“Natural Gas
Consumption” means the overall natural gas consumed by the
Ethanol Plant as measured in British Thermal Units on a higher
heating value (HHV) basis at the meter in accordance with the Scope
of Work when operating the Facility solely on natural gas boiler
for steam production.
“Natural Gas Consumption
Guarantee” has the meaning set forth in
Section 11.04(b) .
“Noise Guarantee” has
the meaning set forth in Section 11.04(f) .
“Notice to Proceed”
means one or more notices given from Owner to Contractor from time
to time directing Contractor to commence performance of the Work or
a portion thereof as specified in such notice.
“O&M Contractor”
means the Person selected by Owner for the operation and
maintenance of the Facility.
“O&M Personnel” has
the meaning set forth in Section 3.22 .
“Owner Caused Delay” has
the meaning set forth in Section 14.04 .
“Owner Permits” means
the Applicable Permits listed on Exhibit M .
“Owner Taxes” has the
meaning set forth in Section 4.09 .
“Owner’s Engineer”
shall mean an engineer appointed by Owner as may be changed from
time to time, and confirmed in a notice to Contractor.
“Parties” means,
collectively, Owner and Contractor.
“Performance Bonus” has
the meaning set forth in Section 11.08 .
“Performance Liquidated
Damages” has the meaning set forth in
Section 11.05 .
“Person” means an
individual, partnership, corporation, limited liability company,
company, business trust, joint stock company, trust, unincorporated
association, joint venture, Government Authority or other entity of
whatever nature.
“Pre-Existing Hazardous
Material” means Hazardous Material that existed on or in the
Job Site and/or the Property Site prior to Initial Site
Mobilization by Contractor.
“Prefunding Cancellation
Costs” means the actual and demonstrable third party costs
and Contractor Internal Costs incurred by Contractor upon
termination of this Agreement in accordance with Article XV
; provided that notwithstanding anything contained herein to the
contrary, “Prefunding Cancellation Costs” shall not
include (A)
-11-
any cancellation charges actually incurred under
the Prefunding Purchase Orders except to the extent Owner
authorizes Contractor to cancel any of such Prefunding Purchase
Orders, and (B) any other costs expressly excluded therefrom
as provided herein.
“Prefunding Purchase
Orders” has the meaning set forth in
Section 5.03(b) .
“Prefunding Third Party
Costs” means the actual and demonstrable third party costs
incurred by Contractor in performing the Prefunding Work (less all
amounts refunded, whether through cancellation of Prefunding
Purchase Orders or otherwise); provided that notwithstanding
anything contained herein to the contrary, “Prefunding Third
Party Costs” shall not include (A) any Contractor
Internal Costs except as provided for in
Section 5.03(a) and (B) any other costs expressly
excluded therefrom as provided herein.
“Prefunding Work” has
the meaning set forth in Section 5.01 .
“Procedures Manual” has
the meaning set forth in Section 3.19(c) .
“Project Schedule” means
the schedule for the completion of the Work attached hereto as
Exhibit B, as may be amended under the terms of this
Agreement.
“Property Site” means
that certain piece of property located on Owner’s Property
near Hereford, Texas as more particularly described in Exhibit
P .
“Punch List” has the
meaning set forth in Section 10.05 (b) .
“Qualified Insurer” has
the meaning set forth in Section 9.03 .
“Ready for Start-up”
means when the activities listed for Mechanical Completion have
occurred and the Ethanol Plant has been commissioned and the
Ethanol Plant is ready to mill corn at the hammer mills, produce
steam, ethanol and wet distiller’s grain.
“Reference Rate” means
the lesser of (i) the prime rate of interest for United States
of America financial institutions as reported from time to time by
The Wall Street Journal (New York Edition) plus two percent
(2%) or (ii) the maximum rate permitted by Applicable
Law.
“Request for Payment”
means the written requests from Contractor to Owner for payment
hereunder, which requests shall be in substantially the form of
Exhibit F attached hereto.
“Schedule Bonus” has the
meaning set forth in Section 11.08 .
“Schedule Liquidated
Damages” has the meaning set forth in Section 11.02
and Section 11.03 .
-12-
“Scheduled FBG Delivery
Dates” mean the dates specified for the Fluidized Bed
Gasifier Supplier’s delivery to the Job Site of the
components of the FBG and all drawings and documentation supplied
in accordance with Appendix A of Exhibit A .
“Scope of Work” means
the Scope of Work attached hereto as Exhibit A , as the same
may be amended from time to time in accordance with the terms
hereof.
“Separated Contract
Price” means the price payable by the Owner under this
Agreement for the Work (including all labor, all materials, and all
equipment comprising the Ethanol Plant and the FBG Work), as stated
in Exhibit J, as may be amended from time to time pursuant to the
terms hereof
“Steam Output” means the
steam output at 125 pounds per square inch gauge saturated as
measured in pounds per hour from the natural gas boiler as measured
downstream of the first steam shut-off valve in accordance with the
methods specified in ASME PTC 46.
“Subcontractor” means
any contractor, constructor or materialman who performs any portion
of the Work other than Contractor.
“Substantial Completion”
shall mean that all of the following have occurred:
(i) Interim Completion has been achieved; (ii) the
Ethanol Plant is capable of being operated safely, normally and
continuously in accordance with the requirements of this Agreement;
(iii) the Ethanol Plant has achieved the Minimum Performance
Levels as determined pursuant to successfully completing all the
requirements of the Guaranteed Performance Tests in accordance with
the Scope of Work; (iv) the Ethanol Plant has achieved the
Emissions Guarantee; (v) the Ethanol Plant is capable of being
operated in a safe manner in accordance with Applicable Laws and
Applicable Permits; (vi) the training of O&M Personnel has
been completed; and (vii) all Schedule Liquidated Damages then
due, if any, under this Agreement have been paid.
“Substantial Completion
Date” means the actual date the Guaranteed Performance Tests
had successfully been started for achieving Substantial Completion,
as determined pursuant to Section 10.04(a) or
Section 10.04(b) , as applicable.
“Substantial
Subcontractor” means a Subcontractor whose contract or
contracts (in the aggregate) with Contractor require payments by
Contractor totaling at least $500,000.
“Substantial Vendor”
means a Vendor whose contract or purchase orders (in the aggregate)
with Contractor require payments by Contractor of at least
$250,000.
“Terms Sheet” has the
meaning set forth in Section 18.13 .
-13-
“Termination Payment”
has the meaning set forth in Section 15.03 .
“Test Fuels” means
certain fuels, as specified in Appendix H and Appendix J of the
Scope of Work, used to complete certain performance
testing.
“Test Notice” has the
meaning set forth in Section 10.01(b) .
“Tests” means
collectively, the Guaranteed Performance Tests and the Interim
Completion Test.
“Total Prefunding Costs”
means the aggregate of, without duplication, Contractor Internal
Costs, Prefunding Third Party Costs and Prefunding Cancellation
Costs.
“Un-denatured Ethanol”
means anhydrous ethanol containing a maximum of 0.5% water by
weight.
“Vendor” means any
supplier, manufacturer or vendor of Equipment to Contractor or any
Subcontractor.
“Warranty Period” has
the meaning set forth in Section 12.01(d) .
“Work” has the meaning
set forth in Section 3.01 . The term “Work”
shall include all Work performed prior to the date hereof,
including the work performed pursuant to the Terms Sheet (as
described in Section 18.13 ).
Section 1.02 . Interpretation . Unless the
context of this Agreement otherwise requires:
(a) the headings contained in this
Agreement are used solely for convenience and do not constitute a
part of this Agreement between the Parties, nor should they be used
to aid in any manner to construe or interpret this
Agreement;
(b) the gender of all words used
herein shall include the masculine, feminine and neuter and the
number of all words shall include the singular and plural
words;
(c) the terms “hereof”,
“herein” “hereto” and similar words refer
to this entire Agreement and not to any particular Article,
Section, Exhibit or any other subdivision of this
Agreement;
(d) references to
“Article,” “Section” or
“Exhibit” are to this Agreement unless specified
otherwise;
(e) reference to “this
Agreement” (including any Exhibit hereto) or any other
agreement, Exhibit, permit or document shall be construed as a
reference to such agreement or document as the same may be amended,
modified, supplemented or
-14-
restated, and shall include a reference to any
document which amends, modifies, supplements or restates, or is
entered into, made or given pursuant to or in accordance with its
terms;
(f) references to any law, statute,
rule, regulation, notification or statutory provision (including
Applicable Laws and Applicable Permits) shall be construed as a
reference to the same as it may have been, or may from time to time
be, amended, modified or re-enacted;
(g) references to any Person shall
be construed as a reference to such Person’s successors and
permitted assigns;
(h) references to
“includes,” “including” and similar phrases
shall mean “including, without limitation”,
and
(i) in the event of a conflict or
inconsistency between this Agreement and any of the Exhibits, this
Agreement shall control.
Section 1.03 . Exhibits . The following
exhibits are attached to and incorporated into and made a part of
this Agreement:
|
|
|
|
|
(a)
|
|
Exhibit A -
Scope of Work
|
|
(b)
|
|
Exhibit B
– Project Schedule
|
|
(c)
|
|
Exhibit C
– Intentionally Left Blank
|
|
(d)
|
|
Exhibit D
– Milestone Payment Table.
|
|
(e)
|
|
Exhibit E
– Form of Milestone Achievement Certificate
|
|
(f)
|
|
Exhibit F
– Form of Request For Payment
|
|
(g)
|
|
Exhibit G
– Form of Final Acceptance Certificate
|
|
(h)
|
|
Exhibit H -
Form of Contractor Certificate for Partial Waiver of
Liens
|
|
(h-1)
|
|
Exhibit H-1 -
Form of Subcontractor Certificate for Partial Waiver of
Liens
|
|
(i)
|
|
Exhibit I
– Form of Corporate Guaranty
|
|
(j)
|
|
Exhibit J
– Separated Contract Price
|
|
(k)
|
|
Exhibit K
– Contractor Rate Schedule
|
|
(l)
|
|
Exhibit L
– Contractor Permits
|
|
(m)
|
|
Exhibit M
– Owner Permits
|
|
(n)
|
|
Exhibit N
– Major Equipment
|
|
(o)
|
|
Exhibit O
– Project Management Team
|
|
(p)
|
|
Exhibit P
– Legal Description of Property Site
|
|
(q)
|
|
Exhibit Q
– Approved Substantial Subcontractors and Substantial
Vendors
|
|
(r)
|
|
Exhibit R
– Contractor Final Lien Waiver and Release
|
|
(r-1)
|
|
Exhibit R-1
– Subcontractor Final Lien Waiver and Release
|
|
(s)
|
|
Exhibit S
– Soil Boring and Subsurface Data
|
|
(t)
|
|
Exhibit T
– Form of Letter of Credit
|
-15-
ARTICLE II
RETENTION OF
CONTRACTOR
Section 2.01 . Retention of Contractor . Owner
hereby engages Contractor, and Contractor hereby agrees to be
engaged by Owner, to perform the Work in accordance with the terms
and conditions set forth herein.
Section 2.02 . Status of Contractor; No
Partnership . Contractor shall be an independent contractor
with respect to any and all Work performed and to be performed
under this Agreement. This Agreement shall not be interpreted or
construed to create an association, joint venture or partnership
relationship among or between the Parties or any similar
relationship, obligations or liabilities. Neither Party shall have
any right, power or authority to enter into any agreement or
undertaking for, act on behalf of, or to act as or be an agent or
representative of, or to otherwise bind or obligate the other
Party.
Section 2.03 . Subcontractors and Vendors
.
(a) Subject to the terms hereof,
Contractor shall have the right to have any of the Work performed
by a Subcontractor or Vendor, including, as applicable, any
Substantial Subcontractors and/or Substantial Vendors, subject to
paragraph (b) below, qualified to perform such Work pursuant
to written subcontracts or written purchase orders; provided that
Contractor shall not be relieved from any liability or obligation
under this Agreement. Except as otherwise indicated in this
Agreement, Contractor shall be solely responsible for engaging,
managing, supervising and paying all such Subcontractors and
Vendors. Contractor shall require that all Work performed, and all
Equipment provided by Subcontractors and Vendors are received,
inspected and otherwise furnished in accordance with this
Agreement, and Contractor shall be solely liable for all acts,
omissions, liabilities and Work (including Defects therein) of such
Subcontractors and Vendors. Owner shall not have any obligation or
liability to any Subcontractor or Vendor. Nothing in any contracts,
subcontracts and purchase orders with Subcontractors and Vendors
shall in any way diminish or relieve Contractor from any duties and
obligations under this Agreement; and all such contracts,
subcontracts and purchase orders must provide that the rights
thereunder are assignable to Owner and the Financing Parties or
their designees. Except as otherwise specified herein, no
Subcontractor or Vendor is intended to be or shall be deemed a
third-party beneficiary of this Agreement.
(b) A list of approved Substantial
Subcontractors and Substantial Vendors as of the date hereof,
including a brief description of the Work to be performed by such
Persons, is attached hereto as Exhibit Q . Contractor may
retain those Substantial Subcontractors or Substantial Vendors
which are set forth on Exhibit Q without further notice to
or approval of Owner. In the event no Substantial Subcontractor or
no Substantial Vendor listed on Exhibit Q is available to perform
the requested duties, Contractor shall be entitled to request that
Owner approve additional Substantial
-16-
Subcontractors or Substantial Vendors to be
included on a revised Exhibit Q. Upon such request, Contractor
shall notify Owner and provide it with such information as
necessary to enable Owner to evaluate each such proposed
Substantial Subcontractor or Substantial Vendor for the portion of
the Work proposed to be performed by it together with all cost
information on a comparative basis required for Owner to fully
evaluate the proposed additional Substantial Subcontractor or
Substantial Vendor. Within five (5) Business Days after
receipt of such information, Owner shall advise Contractor if any
proposed Substantial Subcontractor and Substantial Vendor is
unacceptable. If Owner fails to object to any proposed Substantial
Subcontractor or Substantial Vendor within such five
(5) Business Day period, Contractor may retain such
Substantial Subcontractor or Substantial Vendor for the portion of
the Work proposed. If Owner timely objects to such proposed
Substantial Subcontractor or Substantial Vendor and states the
basis for its objection, Contractor shall not retain such proposed
Substantial Subcontractor or Substantial Vendor. Approval of any
such additional Substantial Subcontractor or Substantial Vendor
under this paragraph shall only be for the portion of the Work so
approved and shall not be deemed an amendment or modification to
Exhibit Q .
(c) The Contractor shall submit to
Owner a copy of each unpriced purchase order or agreement entered
into with a Substantial Subcontractor or Substantial Vendor for
Equipment. Each purchase order or agreement shall show, where
applicable, the Vendor’s or Subcontractor’s name,
manufacturer’s name, materials type, model number, size,
quantity and lists of the Equipment ordered, and shall be submitted
to Owner when issued for purchase.
ARTICLE III
CERTAIN OBLIGATIONS AND
RESPONSIBILITIES OF CONTRACTOR
Section 3.01 . Scope of Work; Applicable
Standards .
(a) Contractor shall, at its own
expense, directly or through its Subcontractors and Vendors,
(i) design, engineer, procure, construct, start up, and carry
out Tests on the Ethanol Plant, and perform its other obligations
hereunder, (ii) perform and provide the FBG Work, and
(iii) manage, supervise, inspect and furnish all Labor,
Equipment, Contractor Equipment, temporary structures, temporary
utilities, products and services for the foregoing, all on a
turnkey basis, in accordance with this Agreement, including,
without limitation, the Project Schedule and the Scope of Work, as
the same may be modified from time to time in accordance with the
terms hereof by a Change Order or Contract Amendment (all of the
foregoing obligations of Contractor being collectively referred to
in this Agreement as the “Work”). Subject to the
remedies provided for herein, Contractor shall perform the Work and
turn the Ethanol Plant and the FBG Work over to Owner in a manner
that is (i) sufficient, complete and adequate in all material
respects necessary to successfully achieve Substantial Completion
by the applicable Guaranteed Substantial Completion Date, as more
fully provided in this Agreement; (ii) in conformance with
Good Engineering Practices; and (iii) in compliance with the
terms of this Agreement and all Applicable Laws and Applicable
Permits.
-17-
(b) As more fully provided in
Article XII, (i) the Ethanol Plant and the Work shall, at a
minimum, comply with Good Engineering Practices (ii) the
Ethanol Plant shall be designed, constructed and manufactured to
operate, and shall be capable of being operated at all levels and
operating modes in accordance with all Applicable Laws and
Applicable Permits, and (iii) the Ethanol Plant and all items
of Equipment and improvements comprising the Ethanol Plant shall be
designed, manufactured, installed, calibrated and tested where
applicable in accordance with the published standards of the
organizations listed in the Scope of Work.
Section 3.02 . Control and Method of the Work
.
(a) Subject to the terms hereof,
Contractor shall be solely responsible for performing or causing to
be performed the Work in accordance with the terms of this
Agreement, and for all means, methods, techniques, sequences,
procedures, and safety and security programs in connection with
such performance. Contractor shall inform Owner in advance
concerning its plans for carrying out the Work.
(b) Whenever the words “as
ordered,” “as directed,” “as
required,” “as permitted,” “as
allowed,” “approved,” “reasonable,”
“suitable,” “acceptable,”
“properly,” “satisfactory,” or words or
phrases of similar effect and import are used, it shall be
understood that none of such terms shall imply that Owner has any
authority over, right to control or responsibility for supervision
of Contractor or its Subcontractors or Vendors, such supervision
(including sole control over and responsibility therefor) being
strictly reserved for Contractor. Any method of Work suggested by
Owner that is used by Contractor will be used at the risk and
responsibility of Contractor, and Owner will assume no
responsibility therefor. Contractor shall have no obligation to use
any method of Work suggested by Owner.
Section 3.03 . Compliance with Law . Contractor
shall, and shall cause all of its Subcontractors, Vendors and
Persons that it has a right to direct who are engaged in the
performance of any of the Work to comply with all Applicable Laws
and Applicable Permits. Using commercially reasonable efforts,
Contractor shall perform the Work in a manner designed to avoid
damage or nuisance to Persons and property of the public or others,
including causes arising as a consequence of methods of
construction of the Ethanol Plant and FBG Work or operation of the
Ethanol Plant. The foregoing shall not be construed as to limit
Contractor’s obligations and liabilities under
Section 3.15 . Notwithstanding anything stated or
implied herein to the contrary, if a Change in Law has a material
effect on the cost of the Work or time or performance hereunder,
such Change in Law shall entitle Contractor or Owner, as the case
may be, to a Change Order to address such effect(s). For the
avoidance of doubt, a Change in Law that does not have a material
effect on the cost of the Work or time or performance hereunder
shall not entitle either Party to a Change Order.
-18-
Section 3.04 . Certain Matters Pertaining to Job Site
. Contractor shall
inspect the Job Site, verify the working conditions and undertake
investigations as Contractor deems reasonably necessary before
commencing any Work. Except for below ground conditions not
reflected in a geotechnical report furnished by Owner to Contractor
as Exhibit S, Contractor shall be solely responsible for performing
any preliminary Work on the Job Site necessary for the commencement
of construction to occur, including removal of all physical
impediments to performing Work on the Job Site, above and below
ground. Contractor shall cause its, and its Subcontractors’
and Vendors’ vehicles and self-propelled equipment entering
on the Job Site to be clearly marked to identify the Contractor,
Subcontractor or Vendor which owns the same. Contractor is entitled
to rely on the accuracy of Exhibit S.
Section 3.05 . Access to Job Site . Owner shall
have the right to have representatives on the Job Site full time.
In addition, Contractor shall provide reasonable access at all
times, upon request by Owner, to the Job Site and the Work to
Owner, Owner’s other contractors, Owner’s Engineer,
Financing Parties’ engineer and the Financing Parties and
their respective employees, representatives, agents and
consultants; provided, however, that in the absence of an emergency
or a default by Contractor hereunder, (i) Owner shall give
reasonable prior notice to Contractor, and (ii) Contractor may
provide, and each such person shall accept, an escort or any safety
equipment or measures that Contractor, in its reasonable
discretion, deems necessary or advisable.
Section 3.06 . Inspection and Testing of Work in
Progress .
(a) Each item of Major Equipment to
be supplied by Contractor shall be subject to inspection and
testing during and upon completion of its fabrication and
installation in accordance with the provisions of the Scope of
Work. Without limiting the foregoing, Contractor shall be
responsible for inspection and testing of the Equipment in
accordance with standard inspection practices and as required by
applicable specifications before their shipment.
(b) Prior to any shipment or at the
time of fabrication and assembly of the Equipment, Owner may (or
require Contractor to) arrange for inspection of such Equipment at
the manufacturer’s premises by Owner, and/or its designated
agent. Contractor shall give notice of readiness to Owner,
Financing Parties’ engineer and the Owner’s Engineer at
least seven (7) days prior to the date when the Equipment will
be available for inspection. Contractor shall arrange for access to
the manufacturer’s facilities to permit any such inspection
to be conducted smoothly.
(c) Contractor shall permit Owner
and, as authorized by Owner, any party designated by Owner and the
Financing Parties to inspect, test and observe the Work from time
to time; provided, however, that none of such Person’s shall
have any authority or responsibility for such Work. Contractor
shall provide Owner each month during performance of the Work with
a schedule of all testing proposed for the following three
(3) month period in compliance with the requirements of the
Scope of Work.
-19-
Section 3.07 . No Waiver of Responsibility . No
inspection made, acceptance of Work, payment of money or approval
given by Owner, the Financing Parties, Financing Parties’
engineer or the Owner’s Engineer shall relieve Contractor of
its obligations for the proper performance of the Work in
accordance with the terms hereof. Owner may, upon notice to
Contractor, reject any Work with Defects, regardless of whether
Owner previously accepted any or all of such Work through oversight
or otherwise. No approval given by Owner, in and of itself, shall
be considered as an assumption of risk or liability by any such
Person. Any such approval shall mean that the Person giving the
approval has no objection to the adoption or use by Contractor of
the matter approved at Contractor’s own risk and
responsibility. Contractor shall have no claim relating to any such
matter approved, including any claims relating to the failure or
inefficiency of any method approved.
Section 3.08 . Intentionally left blank
.
Section 3.09 . Clean-Up .
(a) Without limiting the provisions
of Section 3.16 , Contractor shall at all times keep
the Job Site reasonably free from waste, rubbish and Hazardous
Material, other than Pre-Existing Hazardous Material, relating to
its Work. Contractor shall maintain the Job Site in a neat and
orderly condition throughout the performance of the Work.
Contractor shall employ sufficient personnel to clean its site
office and work areas each working day and shall cooperate with the
other Persons working at the Job Site to keep the Job Site
clean.
(b) Prior to the Final Acceptance
Date, or as soon as practicable after the termination of this
Agreement by Owner in accordance with the provisions of Article
XV , Contractor shall (i) remove all Contractor Equipment
from the Job Site (other than equipment, supplies and materials
necessary or useful to the operation or maintenance of the Facility
and Equipment and equipment, supplies and materials directed by
Owner to remain at the Job Site until completion of the Ethanol
Plant and FBG Work), (ii) have cleaned out all pits, pipes,
chambers and conduits, (iii) tear down and remove all
temporary structures on the Job Site built by it or its
Subcontractors and restore such areas substantially to their
original condition, and (iv) remove all waste, rubbish and
Hazardous Material from and around the Job Site brought onto,
caused or created by Contractor.
Section 3.10 . Obtaining, Maintaining and Identifying
Permits . Contractor shall timely obtain and maintain all
Contractor Permits. In addition, Contractor shall provide all
assistance reasonably requested by Owner in connection with
Owner’s efforts to obtain and maintain the Owner Permits,
including, without limitation, witnesses testimony, depositions,
preparation of exhibits, technical calculations and attending
meetings. In the event that any Applicable Permit is required for
the Ethanol Plant or to perform the Work that is not identified in
this Agreement, at Owner’s request, Contractor
-20-
shall obtain and maintain such Applicable Permit
at Owner’s expense. All Applicable Permits shall be issued in
the name of Owner unless otherwise required by Applicable Law or
such Applicable Permit. If any Contractor Permit (or application
therefor) is in the name of Owner or otherwise requires action by
Owner, Owner shall upon the request of Contractor sign such
application or take such action as reasonably appropriate. Owner
reserves the right to review any such application of Contractor;
provided; however, that Owner’s exercise of such right shall
not under any circumstances, be considered an approval of the
necessity, effect or contents of such application or related
permit. Contractor shall deliver to Owner true and complete copies
of all Applicable Permits obtained by Contractor upon its receipt
thereof. Contractor shall use best efforts to identify in writing
to Owner all requirements for performance of the Work of any
Government Authority not identified in this Agreement, or shall
confirm in writing prior to Financial Closing that, to the best of
Contractor’s knowledge, there are no such requirements of any
Government Authority other than as identified in this
Agreement.
Section 3.11 . Labor . Contractor shall be
responsible for retaining all Labor necessary for it to perform its
obligations hereunder and comply with the provisions hereof, all in
accordance with Applicable Laws. Contractor shall be responsible
for all costs incurred in complying with this
Section 3.11 or otherwise associated with its Labor,
including, without limitation, costs incurred by any member of its
Labor, whether by direct contract or subcontract, for medical
treatment, transport and accommodation as a result of injuries or
illness arising from engagement or employment in the execution of
the Work.
(a) Engagement of Labor.
Contractor shall make its own arrangements for the engagement of
all Labor in connection with this Agreement and the performance of
the Work. Contractor shall employ in the performance of the Work
only Labor, whether supervisors, skilled workers or laborers, who
are competent to perform their assigned duties and shall cause its
Subcontractors and Vendors to adhere to the same standard with
respect to their Labor. Contractor agrees, where required by
Applicable Law, to employ only licensed personnel in good standing
with their respective trades and licensing authorities to perform
engineering, design, architectural and other professional services
in the performance of the Work. All such professional services
shall be performed with the degree of care, skill and
responsibility customary among such licensed personnel.
(b) Identification .
Contractor shall identify each member of its and its
Subcontractor’s and Vendor’s Labor in accordance with
the standards and procedures that are mutually acceptable to the
Parties.
(c) Supply of Services for
Labor . Contractor shall provide and maintain at the Job Site,
in accordance with Applicable Laws and Applicable Permits, such
accommodations, services and amenities as necessary for all Labor
employed for the purpose of or in connection with this Agreement,
including all water supply (both for drinking and other purposes),
electricity supply, sanitation, fire prevention and fire-fighting
equipment, refuse disposal systems and other requirements in
connection with such accommodations or amenities.
-21-
(d) Alcohol and Drugs .
Contractor shall not possess, consume, import, sell, give, barter
or otherwise dispose of any alcoholic beverages or drugs (excluding
drugs for proper medical purposes and then only in accordance with
Applicable Law) at the Job Site, or permit or suffer any such
possession, consumption, importation, sale, gift, barter or
disposal by its Subcontractors, agents or Labor and shall at all
times assure that the Job Site is kept free of all such substances.
Contractor shall immediately identify and remove from its or its
Subcontractors’ employment at the Job Site any person
(whether in the charge of Contractor or any Subcontractor) who is
found to be in the possession of, under the influence, or who is a
user of any dangerous or controlled drug, alcohol or other such
substance or any other person who does or whose actions may create
any unsafe condition or other situation that may cause damage or
harm to any person or property.
(e) Arms and Ammunition .
Except as required for Job Site security, Contractor shall not
possess, give, barter or otherwise dispose of, to any person or
persons, any arms or ammunition of any kind at the Job Site, or
permit or suffer the same as aforesaid and shall at all times
assure that the Job Site is kept free from arms and
ammunition.
(f) Disorderly Conduct .
Contractor shall be responsible for the conduct and deeds of its
Labor and its Subcontractors’ Labor relating to this
Agreement and the consequences thereof. Contractor shall at all
times take all reasonable precautions to prevent any unlawful,
riotous or disorderly conduct by or among such Labor and for the
preservation of peace and protection of Persons and property in the
area of the Job Site against the same. Contractor shall not
interfere with any members of any authorized police, military or
security force in the execution of their duties.
Section 3.12 . Project Management . Contractor
has designated a management team as set forth on Exhibit O ,
and any future members of the management team must be approved by
Owner in writing prior to his/her designation, such approval not to
be unreasonably withheld or delayed. During the performance of the
Work from the Initial Site Mobilization and thereafter, Contractor
shall maintain continuously at the Job Site adequate management,
supervisory, administrative, security and technical personnel,
including the Contractor Site Manager, to ensure expeditious and
competent handling of all matters related to the Work, according to
its determination of the staffing required for this purpose.
Contractor will not re-assign, remove or replace the Contractor
Project Manager, Contractor Project Engineering Manager or
Contractor Site Manager without Owner’s prior written
consent, which consent shall not be unreasonably withheld or
delayed. Contractor shall promptly replace its Contractor Project
Manager, Contractor Project Engineering Manager or Contractor Site
Manager, upon written request and explanation of Owner, if such
individual is disorderly or if such individual is otherwise
incompetent for his position and responsibilities.
-22-
Section 3.13 . Temporary Office Quarters
.
(a) During the performance of the
Work from the Initial Site Mobilization and thereafter, Contractor
shall maintain a suitable office at the Job Site at or near the
site of the Work, which shall be the headquarters of
Contractor’s representative designated pursuant to
Section 3.34 .
(b) Contractor shall provide
Owner’s representatives and the Owner’s Engineer with
reasonably adequate office space, including all utilities, heating,
ventilation and air conditioning, contemporaneously with the
existence of Contractor’s site office specified in paragraph
(a) above, which office space shall be subject to the approval
of Owner. For purposes of this Section, “reasonably
adequate” includes at a minimum the following facilities:
(i) adequate offices to accommodate at least six (6) full
time personnel and visitors; (ii) a conference room adequate
to accommodate twelve (12) people; (iii) a secretary and
reception area; (iv) a kitchen with hot and cold running
water; (v) restroom facilities with indoor plumbing; and
(vi) a minimum of six (6) telephone jacks, including one
in each office, the conference room and the reception area.
Contractor shall properly maintain such offices and shall employ
sufficient personnel to clean such office each working day that
such offices are used. Contractor shall be responsible for paying
all utility deposits and charges, other than long distance
telephone charges related to calls made by Owner and its
representatives, related to such offices for Owner.
Section 3.14 . Cooperation with Other
Contractors . Contractor shall reasonably cooperate and
cause its Subcontractors and Vendors to cooperate with Owner and
with other unrelated contractors (including the Fluidized Bed
Gasifier Supplier) who may be working at or near the Job Site in
order to assure that neither Contractor, nor any of its
Subcontractors or Vendors , unreasonably hinders or
increases, or makes more difficult than necessary the work being
done by Owner and other unrelated contractors.
Section 3.15 . Protection and Safety
.
(a) Contractor shall be responsible
for the security, protection and safety of all Persons (including
members of the public and the employees, agents, contractors,
consultants and representatives of Owner, Financing Parties,
Contractor and its Subcontractors and Vendors, and other
contractors and subcontractors) and all public and private property
(including structures, sewers and service facilities above and
below ground, along, beneath, above, across or near the Job Site)
that are at or near the Job Site or that are in any manner affected
by the performance of the Work. Subject to and without limiting
Contractor’s obligations with respect to security, protection
and safety of the overall Job Site, as of Substantial Completion
Date, Owner shall be responsible for the security, protection and
safety of all Persons and all public and private property that are
within Owner’s operational control; provided, however,
Contractor shall remain responsible for the safety of its and its
Subcontractors’ and Vendors’ Labor and
agents.
-23-
(b) Contractor shall initiate and
maintain reasonable safety precautions and accident prevention
programs for the Job Site and in the performance of the Work, which
shall be in compliance with all Applicable Laws and Applicable
Permits, to prevent injury to persons or damage to property on,
about or adjacent to the Job Site and in the performance of the
Work. Without limiting the generality of the foregoing, Contractor
shall furnish and maintain all necessary safety equipment such as
barriers, signs, warning lights and guards as required to provide
adequate protection to persons and property. In addition,
Contractor shall give reasonable notice to owners of public and
private property and utilities when such property is susceptible to
injury or damage through the performance of the Work and shall make
all necessary arrangement with such owners relative to the removal
and replacement of protection of such property or
utilities.
Section 3.16 . Environmental Matters
.
(a) Hazardous Material .
Contractor shall, and shall cause its Subcontractors and Vendors
to, comply with all Applicable Laws relating to Hazardous Material,
all Applicable Permits, and all requirements of any Government
Authority with respect to Hazardous Material; provided however that
neither Contractor nor its Subcontractors or Vendors shall be
obligated to perform any remediation measures relating to
Pre-Existing Hazardous Material. Without limiting the generality of
the foregoing:
(i) Contractor shall, and shall
cause its Subcontractors and Vendors to, apply for, obtain, comply
with, maintain and renew all Applicable Permits required of
Contractor by Applicable Laws regarding Hazardous Material that are
necessary, customary or advisable for the performance of the Work.
Contractor shall, and shall cause its Subcontractors and Vendors to
have an independent Environmental Protection Agency identification
number for disposal of Hazardous Material under this Agreement if
and as required under Applicable Laws or Applicable
Permits.
(ii) Contractor shall conduct its
activities under this Agreement, and shall cause each of its
Subcontractors and Vendors to conduct its activities, in a manner
designed to prevent pollution of the environment or any other
release of any Hazardous Material by Contractor and its
Subcontractors and Vendors in a manner or at a level requiring
remediation pursuant to any Applicable Law.
(iii) Contractor shall not cause or
allow the release or disposal of Hazardous Material at the Job Site
relating to the Work or the Ethanol Plant, bring Hazardous Material
to the Job Site, or transport Hazardous Material from the Job Site,
except in accordance with Applicable Law and Applicable Permits.
Contractor shall be responsible for the management of and proper
disposal of all Hazardous Material brought onto or generated at the
Job Site by it or its Subcontractors or Vendors, if any. Contractor
shall cause all such Hazardous Material brought onto or generated
at the Job Site by it or its Subcontractors or Vendors, if any,
(A) to be transported only by carriers maintaining valid
permits
-24-
and operating in compliance with
such permits and laws regarding Hazardous Material pursuant to
manifest and shipping documents identifying only Contractor as the
generator of waste or person who arranged for waste disposal, and
(B) to be treated and disposed of only at treatment, storage
and disposal facilities maintaining valid permits operating in
compliance with such permits and laws regarding Hazardous Material,
from which, to the best of Contractor’s knowledge, there has
been and will be no release of Hazardous Material. Contractor shall
submit to Owner a list of all Hazardous Material to be brought onto
or generated at the Job Site prior to bringing or generating such
Hazardous Material onto or at the Job Site. Contractor shall keep
Owner informed as to the status of all Hazardous Material on the
Job Site and disposal of all Hazardous Material from the Job
Site.
(iv) If Contractor or any of its
Subcontractors or Vendors releases any Hazardous Material on, at,
or from the Job Site, or becomes aware of any Person who has
stored, released or disposed of Hazardous Material on, at, or from
the Job Site during the Work, Contractor shall immediately notify
Owner in writing. If Contractor’s work involved the area
where such release occurred, Contractor shall immediately stop any
Work affecting the area. Contractor shall, at its sole expense,
diligently proceed to take all necessary or desirable remedial
action to clean up fully the contamination caused by (A) any
knowing or negligent release by Contractor or any of its
Subcontractors or Vendors of any Pre-Existing Hazardous Material,
and (B) any Hazardous Material that was brought onto or
generated at the Job Site by Contractor or any of its
Subcontractors or Vendors, whether on or off the Job Site.
Notwithstanding anything to the contrary, Contractor shall not be
responsible for determining the existence of Pre-Existing Hazardous
Material on the Job Site.
(v) If Contractor discovers any
Pre-Existing Hazardous Material that has been stored, released or
disposed of at the Property Site, Contractor shall immediately
notify Owner in writing. If Contractor’s Work involves the
area where such a discovery was made, Contractor shall immediately
stop any Work affecting the area and Owner shall determine a
reasonable course of action. Contractor shall not, and shall cause
its Subcontractors and Vendors to not take any action that may
exacerbate any such contamination. If Owner desires Contractor to
perform all or part of any remediation or evacuation that may
become necessary as a result of the discovery of any such
Pre-Existing Hazardous Material, it shall request a Change pursuant
to Section 7.01(b) . If requested by Owner, Contractor
shall cooperate with and assist Owner in making the Property Site
available for taking necessary remedial steps to clean up any such
contamination at Owner’s expense. Notwithstanding anything
contained herein to the contrary, nothing contained herein shall be
construed as to obligate Owner or Contractor to take any remedial
action to clean up any Pre-Existing Hazardous Material, unless a
mutually acceptable Change Order is executed by both Parties or
other written agreement is reached by the Parties.
-25-
(b) Waste Treatment and
Disposal . Without limiting the foregoing:
(i) Toxic Waste and Industrial
Hazards : Contractor shall be responsible for the proper
management and disposal of all toxic waste and industrial hazards
brought onto or generated at the Job Site by it or its
Subcontractors or Vendors, if any. Contractor shall, and shall
cause its Subcontractors and Vendors to, comply with all Applicable
Laws, Applicable Permits and applicable safety standards related to
the treatment, storage, disposal, transportation and handling of
toxic wastes and industrial hazards. Contractor shall not store or
dispose of toxic wastes and industrial hazards near groundwater,
surface water or drainage systems. Liquid wastes shall not be
dumped onto the ground or in any groundwater, surface water or
drainage systems. All waste oil and grease resulting from
construction activities shall be collected and disposed of in a
manner that prevents contamination to soil, ground water, and
surface water, and incinerated if possible. Vehicle maintenance
shall be conducted in safe areas away from watercourses and oil or
fluid runoff shall be collected in grease traps. Toxic waste and
industrial hazard storage containers shall be
well-labeled.
(ii) Sanitary and Solid Waste
: Contractor shall take appropriate measures in accordance with the
Applicable Law and Applicable Permits for the treatment and
disposal of sanitary and solid waste, and in particular, Contractor
shall give due regard to protecting environmentally sensitive areas
and water supplies. Run-off from disposal sites shall be
curtailed.
(c) Fuel Storage . The
location, facilities, safety measures and environmental and
pollution control in connection with storage of fuel or like
substances brought on site by Contractor shall comply with all
Applicable Laws and Applicable Permits.
(d) Wetland Areas .
Contractor acknowledges that portions of the Property Site may be
designated as wetlands as indicated on the survey provided by Owner
pursuant to Section 4.07 . Certain of these wetland
areas, as designated on such survey, do not constitute a part of
the Job Site. Contractor shall erect a temporary wall or other
blockade to isolate this wetland area from the Job Site and
construction area, and shall not, and shall not allow, any Work to
be conducted in or other interference with such wetland areas.
Except for such wetland areas that do not constitute a part of the
Job Site, Owner anticipates obtaining a permit from U.S. Army
Corps. of Engineers, allowing construction and other Work
activities on the remaining wetland areas on the Property Site.
Contractor shall, and shall cause its Subcontractors and Vendors,
to comply with all rules, regulations and permits issued by the
U.S. Army Corps. of Engineers, and all other Applicable Laws and
Applicable Permits in connection with the wetland areas on the
Property Site.
-26-
Section 3.17 . Fire Prevention .
(a) Contractor shall be responsible
for providing adequate fire prevention and protection at the Job
Site and shall take all reasonable precautions to minimize the risk
of fire at the Job Site. Contractor shall provide instruction to
the Labor in fire prevention control and shall provide appropriate
fire-fighting and fire protection equipment and systems at the Job
Site.
(b) Contractor shall promptly
collect and remove combustible debris and waste material from the
Job Site in accordance with Applicable Laws and Applicable Permits,
and shall not permit such debris and material to accumulate.
Contractor shall control the usage of fires for any purpose in the
vicinity of the Work and shall agree upon the appropriateness of
any such fires with Owner. Any areas of vegetation damaged by fire
which are considered by Owner to have been initiated by
Contractor’s or its Subcontractors’ or Vendors’
Labor shall be recultivated and otherwise rehabilitated by
Contractor, at Contractor’s expense.
(c) Contractor will complete all
systems, procedures and Equipment constituting the Facility fire
protection system as necessary during construction to protect Work
in progress, in particular with regard to fuel and other flammable
materials.
Section 3.18 . Religious and Archaeological
Resources . In the event any archaeological or religious
sites, places, monuments or areas are discovered or identified by
Contractor during the performance of this Agreement, Contractor
shall leave such sites untouched and protected by fencing and shall
immediately stop any Work affecting the area. Contractor shall
notify the Owner of any such discovery as soon as practicable, and
Contractor shall carry out Owner’s instructions for dealing
with the same. All fossils, coins, articles of value or antiquity
and structures and other remains or things of geological,
archaeological, historical, religious, cultural or similar interest
discovered on the Job Site shall, as between Owner and Contractor,
be deemed to be the absolute property of Owner. Contractor shall
prevent its and its Subcontractors’ and Vendors’ Labor
and any other Persons from removing or damaging any such article or
thing.
Section 3.19 . Reports, Plans and Manuals
.
(a) Status Reports . Within
ten (10) days after the beginning of each month, commencing
with the second month following execution of this Agreement,
Contractor shall prepare and submit to Owner, Financing
Parties’ engineer and the Owner’s Engineer written
progress reports, in a form reasonably acceptable to Owner, which
include a description of the progress and status of the Work, the
status of Equipment and other scheduled deliveries, the
Subcontractors’ activities, and engineering and construction
progress. Photographs shall also be included documenting the
construction progress. Each photograph shall show the date,
Contractor’s name and description of the view
taken.
-27-
(b) Reporting of Accidents .
Contractor shall report in writing to Owner (and, to the extent
required by any Applicable Law or Applicable Permit, the
appropriate Government Authority) details of any accident that is
on or about the Job Site as soon as possible after its occurrence,
but in any event not later than twenty-four (24) hours after
such accident occurs. In the case of any fatality or serious injury
or accident, Contractor shall, in addition, notify Owner (and, to
the extent required by any Applicable Law or Applicable Permit, the
appropriate Government Authority) immediately.
(c) Procedures Manual . No
later than forty-five (45) days following the date hereof,
Contractor shall prepare and submit to Owner a Procedures Manual
that describes the administrative procedures to be used by
Contractor and Owner for interfacing during the performance of the
Work. Contractor shall either promptly make changes to the
Procedures Manual suggested by Owner or negotiate and resolve in
good faith with Owner such changes. Upon approval of the Procedures
Manual by the Parties, the Parties shall comply with the provisions
thereof. The Procedures Manual may be changed from time to time
with the approval of the Parties.
(d) Health, Safety and
Environmental Plan . No later than thirty (30) days from
the earlier of the Notice to Proceed or the Financial Closing Date,
Contractor shall prepare and submit to Owner a Health, Safety and
Environmental Plan that includes: (i) health, first aid and
emergency procedures; (ii) a Hazardous Material, waste and
industrial hazards management and disposal plan which details the
controlled usage and treatment of all Hazardous Material, toxic
wastes, industrial hazards, sanitary waste, solid waste and other
waste brought onto, used or produced at the Job Site or in relation
to the Work and outlines a management structure for carrying out
the specific provisions of such plan; (iii) an environmental
protection and management plan, including, without limitation, a
sediment and erosion control plan; (iv) a revegetation plan
and (v) the description, location and drawings of construction
facilities and temporary works. The Health, Safety and
Environmental Plan shall be consistent with all Applicable Laws and
Applicable Permits and shall be submitted to Owner for review and
approval. Contractor shall either promptly make changes to the
Health, Safety and Environmental Plan suggested by Owner or
negotiate and resolve in good faith with Owner such changes.
Contractor shall comply with the Health, Safety and Environmental
Plan as mutually agreed to by the Parties.
(e) Contractor Not Relieved of
Duties or Responsibilities . Neither the submission to or
approval by Owner of progress and other reports, plans and manuals,
nor the provision of general descriptions shall relieve Contractor
of any of its duties or responsibilities under this
Agreement.
Section 3.20 . Drawings, Engineering Data and Other
Materials .
(a) All Drawings, Final Plans,
reports and other information (except financial, accounting and
payroll records) furnished by Owner to Contractor, or prepared
by
-28-
Contractor, its Subcontractors or others in
connection with the performance of the Work, whenever provided,
shall be kept by Contractor in an orderly and catalogued fashion
for reference by Owner during the performance by Contractor of the
Work. Contractor shall maintain at the Property Site at least one
(1) copy of all Drawings, Final Plans, Change Orders and other
modifications in good order and marked to record all changes made
during performance of the Work, including, without limitation, all
field deviations from the construction drawings. At or prior to the
Final Acceptance Date, or the earlier termination of this
Agreement, Contractor shall transfer the Final Plans to Owner and
they shall become the sole property of Owner, subject to the terms
of the License Agreement; provided however that any such transfer
shall not, in and of itself, be deemed to convey any ownership
interest to Owner in any proprietary technology or information
provided as part of the Work (whether by Contractor or its
Subcontractors or Vendors). Nothing herein is intended to affect
either Party’s rights and obligations under the License
Agreement.
(b) Contractor shall furnish Owner
with documents that correctly reflect, with substantial
completeness, the Ethanol Plant and FBG Work or the portion of the
Work against which a Milestone Achievement Certificate is issued at
the time the Milestone Achievement Certificate is issued. Final
Plans (in both hard copy and magnetic media at no extra charge to
Owner), if not furnished earlier, shall be furnished to Owner upon
Contractor’s request for a Final Acceptance Certificate or
upon the earlier termination of this Agreement. Contractor and any
of its Subcontractors, as applicable, may, retain copies all such
documents for their records, subject to the confidentiality
provisions of this Agreement.
(c) Contractor shall submit Drawings
to Owner for review and comment as provided in the Scope of Work.
The Contractor shall revise such Drawings from time to time, as
required to reflect any changes or actual installation of Equipment
and the final installation of any individual Equipment or system or
the Ethanol Plant and FBG Work as a whole corrected to provide
Final Plans.
(d) The License Agreement sets forth
the rights and obligations of Owner and Contractor with respect to
proprietary technology or information provided as part of the Work
(whether by Contractor or its Subcontractors or Vendors), with the
exception of such proprietary technology or information as may be
provided by the Fluidized Bed Gasifier Supplier, which shall be
governed by the terms of a separate license agreement between the
Fluidized Bed Gasifier Supplier and Owner.
Section 3.21 . Operating and Maintenance
Manuals . Contractor shall supply Owner with manuals and/or
handbooks, which provide, either in a single manual or handbook or
collectively, complete operating and maintenance instructions
(including inventories of spare parts and tools and parts lists
with ordering instructions) for each major piece of Equipment and
system of the Ethanol Plant and FBG Work. Each such manual and
handbook shall comply with the requirements of the Scope of Work,
including with respect to matters such as to quantity, content and
the time when such
-29-
manuals are to be supplied to Owner, and shall
be substantially complete and delivered to Owner prior to Ready for
Start-Up in order to support training of personnel and start-up and
testing of the Ethanol Plant.
Section 3.22 . Training of O&M Personnel .
At least ninety (90) days prior to the scheduled Ready for
Start-Up, Contractor shall provide, at its own expense, a training
program in operations and maintenance of the Ethanol Plant for
Owner’s personnel and the O&M Contractor’s
personnel (collectively, “O&M Personnel”). The
training program provided by Contractor shall (a) include
classroom and field training, (b) include all manuals,
drawings, and other educational materials necessary or desirable
for the adequate training of O&M Personnel, and
(c) establish quality controls so that O&M Personnel are
suitably trained and capable of operating and maintaining the
Ethanol Plant after Substantial Completion. Representatives of
manufacturers of Equipment shall be utilized to provide specialized
training for such Equipment where deemed necessary by the Parties.
Contractor shall make every reasonable effort to use the O&M
Personnel during start-up and initial operation of the Ethanol
Plant; however, neither Owner nor O&M Contractor shall be
obligated to supply personnel for the construction of the Facility.
Contractor shall have complete responsibility for directing,
coordinating, monitoring and supervising O&M Personnel during
start-up and initial operations of the Ethanol Plant until
Substantial Completion, and shall have the right to reject any
O&M Personnel due to disorderly conduct or lack of competence
(with written explanation therefore furnished to Owner) during
training or until Substantial Completion. The cost of the O&M
Personnel’s travel, lodging, food and other living expenses
shall be borne by Owner.
Section 3.23 . Accounting Information . During
the term of this Agreement and continuing for three
(3) year(s) after the Final Acceptance Date, Contractor will
provide Owner with any reasonably necessary assistance, including
providing all documents, cost information and other information
that Owner believes necessary, in a form reasonably acceptable to
Owner, for Owner’s federal, state or local tax filings,
exemptions or positions advocated by Owner relating to the Work,
including, without limitation, sales, use and property taxes;
provided, however, that such access to cost information not
otherwise made available to Owner pursuant to the terms hereof
shall be disclosed to an independent auditor of Owner’s
choice that agrees to keep secret from Owner, Contractor’s
cost and other competitively sensitive information.
Section 3.24 . Contractor Taxes . Contractor
shall pay and administer all federal, state and local taxes and
duties incurred or payable in connection with the Work, including,
without limitation, taxes based on or related to Contractor’s
or its Subcontractors’ or Vendors’ Labor or income,
except for Owner Taxes (collectively, “Contractor
Taxes”); provided, however, that if Contractor is responsible
for payment of Owner Taxes under Applicable Law, unless otherwise
instructed by Owner or Owner is contesting such taxes, Contractor
shall pay such taxes and Owner shall reimburse Contractor therefor
upon submission of evidence of payment. Contractor shall promptly
provide Owner with reports or other evidence reasonably acceptable
to Owner showing
-30-
the payment of Contractor Taxes by Contractor.
Contractor shall cooperate with Owner to endeavor to minimize any
Owner Taxes. Contractor shall make available to Owner and claim all
applicable sales and/or use or excise tax exemptions, credits or
deductions relating to the Facility and the Equipment available to
itself or Owner, including any sale-for-resale exemption under
Applicable Law. To the extent Contractor is required by Applicable
Law, to collect sales tax from Owner, Contractor shall either
collect sales tax from Owner on all materials physically
incorporated in the Facility that are not subject to exemption or
Owner shall provide Contractor with a direct pay certificate issued
to Owner by the appropriate taxing authority. In the event that an
assessment for sales and/or use or excise taxes are levied against
Contractor, any Subcontractor or Vendor, Contractor shall promptly
notify Owner and furnish to Owner a copy of such assessment. In the
event that Owner determines that the assessment should be contested
and so notifies Contractor in writing, Owner may, at Owner’s
sole cost and expense, file such documents as are necessary to
contest such assessment. Owner shall exclusively control any
contest, assessment or other action regarding any such taxes or
assessments, or any penalties or interest in respect thereof.
Contractor shall cooperate with and assist Owner, at Owner’s
expense, in any contest or proceeding relating to taxes payable by
Owner hereunder.
Section 3.25 . Claims and Liens for Labor and
Materials . Provided that Owner has fulfilled its payment
obligations under this Agreement, Contractor shall, at
Contractor’s sole expense, discharge and cause to be
released, whether by payment or posting of an appropriate surety
bond in accordance with Applicable Law, within ten (10) days
after receipt of a written demand from Owner, any Lien in respect
to the Ethanol Plant or the FBG Work, this Agreement, the
Equipment, the Job Site or any fixtures or personal property
included in the Work (whether or not any such Lien is valid or
enforceable) created by, through or under, or as a result of any
act or omission (or alleged act or omission) of, Contractor or any
Subcontractor, Vendor or other Person providing labor or materials
within the scope of Contractor’s Work. Notwithstanding the
foregoing provision, as long as Owner, in its sole discretion,
determines that the Job Site and the improvements thereon will not
be subject to any liability, penalty or forfeiture, upon the
written request of Contractor, Owner may permit Contractor to
contest the validity, enforceability or applicability of any such
Lien, in which event Owner shall provide such cooperation as
Contractor may reasonably request in connection
therewith.
Section 3.26 . Spare Parts Availability
.
(a) Start-up Spare Parts .
Contractor shall obtain all spare parts required for the Ethanol
Plant and the FBG Work in accordance with Exhibit A, Scope of
Work.
(b) Operating Spare Parts .
Contractor agrees to use all commercially reasonable efforts to
obtain from each Major Manufacturer an assignable guaranty that
such Major Manufacturer will have available for purchase by Owner
for a period of five (5) years after the Final Acceptance Date
all spare parts for the Major Equipment supplied by such Major
Manufacturer required to keep the Ethanol Plant and the FBG Work
in
-31-
good operating condition, it being understood
that some of such parts are not “shelf items” and will
have to be manufactured by the Major Manufacturer after it receives
an order for them. In addition, Contractor agrees to use all
commercially reasonable efforts to make spare parts (other than
spare parts for the Major Equipment) available for purchase by
Owner for a period of five (5) years after the Final
Acceptance Date to the extent that Contractor is able to obtain
them from the manufacturer who supplied them for the Ethanol Plant
and the FBG Work as originally built. If Contractor is unable to
obtain such spare parts from such manufacturer, it further agrees
to use all commercially reasonable efforts to find another source
that can supply them. Contractor agrees to use all commercially
reasonable efforts to obtain a firm price for such spare parts
acceptable to Owner for a period of one (1) year after the
Final Acceptance Date. At least one hundred twenty (120) days
prior to the Ready for Start-Up date, Contractor shall provide
Owner with each manufacturer’s recommended spare parts list
for the Equipment.
Section 3.27 . Contractor’s Obligation to
Notify . Contractor shall keep Owner advised as to the
status of the Equipment and Work and shall promptly provide written
report to Owner upon the occurrence of any of the following:
(i) any occurrence or event that may be expected to materially
impact the schedule for delivery and/or installation of Equipment;
(ii) any technical problem not anticipated at the start of the
Work and is of significant magnitude that may materially impact the
Ethanol Plant, the FBG Work, or any component thereof or the
Project Schedule; (iii) upon discovery of any Defect; and
(iv) any material changes to previously submitted information.
The Owner shall have the right to verify the information provided
by Contractor. In connection therewith, Contractor shall identify
those items provided to Owner that would enable Owner to verify
such information in an expedient manner.
Section 3.28 . Construction Utilities .
Contractor shall be responsible for the cost, supply and
availability of electric power and distribution requirements for
the performance of the Work at the Job Site. Contractor shall
provide its own telephone, facsimile, radio, telex and other
communication facilities at the Job Site as necessary for the
performance of the Work. In addition, Contractor shall provide its
own temporary lighting, water and sewer facilities at the Job
Site.
Section 3.29 . Lines and Grades . Contractor
shall provide for the proper laying out of the construction Work,
for making measurements and for establishing temporary or permanent
reference marks in connection with the construction Work. Owner may
at its sole discretion and cost, check the reference marks, lines,
grades and measurements so established. Contractor shall carefully
preserve all monuments, bench marks and reference points. In case
of its destruction thereof, Contractor will be responsible for all
damages, costs and expenses related to their replacement and for
any mistake or loss of time that may result therefrom. Permanent
monuments or bench marks which must be removed or disturbed shall
be protected until they can be properly referenced for relocation.
Contractor shall furnish materials and assistance or the proper
replacement of such monuments or bench marks.
-32-
Section 3.30 . Temporary Structures . Temporary
structures for offices, quarters, storage and other uses for
Contractor, its Subcontractors and Vendors and Owner shall be
constructed only in locations as mutually approved by the Parties.
Contractor shall erect temporary walls, bulkheads or fences where
required to isolate the construction area from adjacent property in
order to increase safety and security and to minimize noise, dust
and dirt from contaminating the property surrounding the Job
Site.
Section 3.31 . Weatherproof Coverings .
Contractor shall provide adequate and sufficient weatherproof and
flame resistant coverings for outdoor storage at the Job Site. The
cover or sheeting shall be tied down to prevent moisture from
damaging the Equipment.
Section 3.32 . Milestone Payment Schedule .
Within 30 days of the Effective Date, Contractor shall provide a
Milestone Payment Table acceptable to the Owner. the Milestone
Payment Table shall reflect the projected monthly cash flow of
payments contained in Exhibit D (“Projected Cash
Flow”). The Milestone Payment Table shall not, on a
cumulative basis, exceed the Projected Cash Flow at any time, and
shall reflect specified performance milestones and percentages of
Work completion which are to be met as conditions to such payments
being made. Such Milestone Payment Table, as so provided and
accepted, shall replace the Projected Cash Flow in Exhibit
D.
Section 3.33 . Emergencies . In the event of
any emergency that endangers or could endanger life or property,
Contractor shall take such action as may be reasonable and
necessary to prevent, avoid or mitigate injury, damage or loss and
shall, as soon as possible, report any such incidents in writing,
including Contractor’s response and actions with respect
thereto, to Owner.
Section 3.34 . Contractor’s
Representative . Contractor shall appoint one individual,
with the prior written consent of Owner, which consent shall not be
unreasonably withheld, who shall be authorized to act on behalf of
Contractor and with whom Owner may consult at all reasonable times,
and whose instruction, request and decisions in writing will be
binding upon Contractor. Contractor shall not remove or replace
such representative without Owner’s prior written
consent.
Section 3.35 . Contractor’s Insurances .
As more fully provided in Article IX , Contractor shall
procure and maintain the insurance coverages required of it under
this Agreement.
Section 3.36 . Raw Water, Sewage and Potable Water Line
Sizing . Within
thirty (30) days after the date hereof, as necessary for
operation of the Facility in accordance with the design criteria
set forth in the Scope of Work, the Contractor shall provide line
sizing and capacity data for: (i) a pipeline sufficient to
meet daily capacity requirements for transport of raw water to the
Property Site, (ii) a pipeline sufficient to meet hourly
capacity requirements for transport of potable water to the
Property Site, and (iii) a pipeline sufficient to meet daily
capacity requirements for transport of sewage off the Property
Site, if applicable.
-33-
ARTICLE IV
CERTAIN OBLIGATIONS OF
OWNER
Section 4.01 . Permits . Owner shall timely
obtain and maintain, at its own expense, all Owner Permits, which
are attached hereto as Exhibit M. Prior to commencement of
construction at the Job Site, Owner shall deliver to Contractor
evidence that Owner Permits necessary to begin construction of the
Ethanol Plant and the FBG Work have been received by Owner or, if
any such required Owner Permit has not actually been issued, that
it has been approved for issuance, or in the opinion of Owner, will
be approved for issuance.
Section 4.02 . Gas, Electric, and Water
Facilities .
(a) Owner shall furnish or cause to
be furnished at the Property Site at the location designated by
Owner the natural gas interconnection flange, at least one hundred
twenty (120) days prior to Guaranteed Substantial Completion
Date. Contractor shall be responsible for all other Work on the
natural gas interconnection flange on the Property Site.
(b) Owner shall furnish or cause to
be furnished at the Property Site at the locations designated in
the Scope of Work, at least one hundred forty (140) days prior
to the Guaranteed Substantial Completion Date, a pipeline
sufficient to transport raw water to the Property Site up to the
daily capacity designated by Contractor.
(c) Owner shall furnish or cause to
be furnished at the Property Site at the location designated by
Owner the supply and availability of electric power at least one
hundred twenty (120) days prior to Guaranteed Substantial
Completion Date. Contractor shall be responsible for all other Work
related to electric power and distribution on the Property
Site.
Section 4.03 . Fuel Supply .
(a) At least forty-five
(45) days prior to Ready for Start-Up and including the first
Guaranteed Performance Test conducted in accordance with Article
X , Owner shall supply or cause to be supplied all natural gas
at the Job Site needed by Contractor in connection with the
installation, adjustment and testing of the Ethanol
Plant.
(b) In the event of failed
Guaranteed Performance Test attributable to Contractor, for each
subsequent Guaranteed Performance Test conducted in accordance with
Article X , Owner shall supply, at Contractor’s
expense (which costs shall be offset against Owner’s product
revenues), Test Fuels needed by Contractor in connection with the
installation, adjustment and testing of the Ethanol
Plant.
-34-
(c) All Test Fuels supplied by Owner
hereunder shall comply in all material respects with the fuel
specifications set forth in the Scope of Work.
Section 4.04 . Raw Water Supply . At least one
hundred forty (140) days prior to Substantial Completion and
through the Final Acceptance Date Owner shall supply or cause to be
supplied all raw water.
Section 4.05 . Access to Property Site . From
the earlier of the Notice to Proceed or the Financial Closing Date,
until the earlier of the termination of this Agreement or the Final
Acceptance Date, Owner shall permit the employees and agents of
Contractor and its Subcontractors and Vendors to have uninterrupted
access to the portions of the Property Site constituting the Job
Site. Thereafter, upon reasonable notice and during reasonable
times, and subject to such restrictions as may be reasonably
imposed by Owner in order to assure that only authorized persons
enter the Property Site, Owner shall permit the employees and
agents of Contractor and its Subcontractors and Vendors, including
any third-party repair personnel retained by Contractor or its
Subcontractors and Vendors, to have access to the Property Site as
necessary to repair or replace Defects or other Work that is not in
compliance with this Agreement. As used above, the references to
access contemplate that not only will the individuals referred to
be able to enter upon and leave the Property Site but that they
also will be able to bring onto and remove from the Property Site
any and all kinds of personal property required for performance of
the Work.
Section 4.06 . Right of Ways . Owner shall obtain at its own expense any
easements and rights of way over the property of others as
required, in order that the personnel and construction equipment of
Contractor and its Subcontractors and Vendors have ingress to and
egress from the Property Site, except for any transportation rights
of way, permits or easements. In addition, Owner shall provide
reasonable assistance to Contractor, upon its request, in
connection with Contractor’s procurement of any easements and
rights of way over the property of others that are necessary for
the personnel and construction equipment of Contractor and its
Subcontractors and Vendors to have ingress to and egress from
portions of the Job Site other than the Property Site, except for
any transportation rights of way, permits or easements.
Section 4.07 . Survey of Property Site . On or
before the execution of this Agreement, Owner shall deliver to
Contractor a survey of the Property Site showing, among other
things, the location of all easements and rights of way on the
Property Site, the location of all means of ingress to and egress
from the Property Site which will be available to
Contractor.
Section 4.08 . Notice of Financial Closing .
Owner shall give Contractor reasonably prompt advance written
notice of the scheduled and actual date of Financial
Closing.
-35-
Section 4.09 . Owner Taxes . Owner shall pay
all real property taxes assessed against the Property Site and any
permanent use charges or assessments such as water or sewer (but
excluding charges and taxes for construction utilities and fuel to
be supplied by Contractor as required hereunder, which shall be
Contractor’s responsibility), and Owner shall be responsible
for the payment of state and local sales and/or use or excise taxes
in connection with the purchase of any equipment, including
rentals, leases and consumables (collectively, “Owner
Taxes”) except for such Owner Taxes as Owner contests in good
faith by appropriate proceedings (provided that if Owner is
unsuccessful in any such contest Owner shall be responsible for the
payment of such Owner Tax). In the event that Owner is required to
pay additional state or local taxes because Contractor failed to
follow reasonable written instructions of Owner appropriately,
Contractor shall be responsible for the cost of such additional
taxes.
Section 4.10 . Owner’s Cooperation .
Owner shall cooperate in all material respects to permit Contractor
to perform its obligations hereunder and shall make reasonable
efforts to supply to Contractor, in a timely manner, either
directly or indirectly, requested material information and data
that is known to Owner and that is required for the performance of
the Work.
Section 4.11 . Owner’s Representative .
Owner shall designate in writing one or more representatives at the
Property Site (at least one of whom shall be at the site during
normal business hours) who shall have authority to administer this
Agreement on behalf of Owner, approve Contractor’s
submissions hereunder and inspect the Work, as reasonably necessary
for Contractor’s performance of the Work. Notwithstanding the
foregoing, Owner’s Representative shall not have authority to
approve Change Orders. Upon execution of this Agreement, and from
time to time thereafter, Owner shall give Contractor notice in
writing of the individual who does have authority to bind Owner
with respect to administration of this Agreement (including Change
Orders).
Section 4.12 . Supplies . At least ten
(10) days prior to Ready for Start-Up and through Final
Acceptance Date, Owner shall supply or cause to be supplied all raw
materials, including corn or other feedstocks, chemicals and other
supplies necessary to operate the Ethanol Plant in
accordance with Exhibit A.
Section 4.13 . Operation and Maintenance .
Owner shall timely provide operators having reasonable experience
and qualifications for training and for the operation of the
Ethanol Plant to support start-up and testing of the Ethanol Plant
and to participate in the training of O&M Personnel by
Contractor. From and after the Substantial Completion Date, Owner
shall provide, or cause to be provided, operation and maintenance
of the Ethanol Plant. Owner shall operate and maintain the Facility
in accordance with this Agreement.
Section 4.14 . Owner’s Insurances . As
more fully provided in Section 9.09 , Owner shall
procure and maintain the insurance coverages required of it under
this Agreement.
-36-
ARTICLE V
PROJECT SCHEDULE
Section 5.01 . Commencement of Work . After the
Effective Date, Contractor will commence performance of the Work so
as to ensure completion of the Work in accordance with the terms
hereof. The Parties agree that any and all Work performed prior to
the Financial Closing Date (the “Prefunding Work”),
except to the extent Contractor is entitled to payment pursuant to
Section 6.02(c) and/or Section 6.02(d) shall be
solely at Contractor’s expense and risk, without further
right of payment until Financial Closing. At Financial Closing,
Contractor shall be entitled to payment pursuant to
Section 6.03 . If Financial Closing has not occurred on
or before December 15, 2005, Owner shall have the right
thereafter to require Contractor to continue performing all or a
portion of the Work (as specified by Owner) by giving Contractor a
Notice to Proceed. If Owner gives Contractor such a Notice to
Proceed, Contractor shall be entitled to payment pursuant to
Section 6.02(c) . If Owner gives Contractor such a
Notice to Proceed and Financial Closing occurs on or before
April 1, 2006, Contractor shall not be entitled to additional
compensation, an extension of time for completion of all or any
part of the Work or any other amendment to the terms of this
Agreement, whether pursuant to a Change Order or otherwise, based
on the occurrence of Financial Closing by such date. Unless the
Parties agree on the terms under which Contractor will continue
performance of the Work, including any equitable adjustment (if
appropriate) to the Project Schedule, Contractor may suspend
performance of the Work (and the provisions of
Section 15.04(b) shall apply) by giving written notice
thereof to Owner upon the occurrence and during the continuation of
either of the following: (a) if Financial Closing has not
occurred on or before December 15, 2005 and Owner has not
given Contractor a Notice to Proceed on or before such date which
allows for the Work to be performed at the levels and dollar
amounts specified in the payment schedule attached as Exhibit D, or
(b) Financial Closing has not occurred on or before
April 1, 2006. Contractor shall commence full performance of
the Work upon receipt from Owner of either (i) a notice under
Section 4.08 specifying the actual date that Financial
Closing occurred or (ii) a Notice to Proceed issued under this
Section 5.01 . Following receipt of a Notice to Proceed
given by Owner under this Section 5.01 prior to
Financial Closing, Owner shall, at the request of Contractor,
furnish to the Contractor reasonable evidence that adequate
financial arrangements have been made to fulfill Owner’s
obligations hereunder for Work performed after the receipt of such
Notice to Proceed and prior to Financial Closing. If Financial
Closing has not occurred by December 31, 2006, Contractor
shall be entitled to terminate this Agreement upon ten
(10) days’ notice to Owner in accordance with
Section 15.06(c) .
Section 5.02
. Project Schedule
.
(a) Subject to the terms of Article
XI, Contractor shall perform the Work in compliance with the
Project Schedule, including completing the Work required by
the
-37-
Guaranteed Dates. Contractor shall provide the
reports as required herein, and provide any further information
required by Owner as Owner may reasonably request to verify actual
progress and forecast future progress of the Work. Contractor shall
promptly notify Owner in writing of any occurrence that Contractor
has reason to believe will adversely affect the completion of the
Work by the Guaranteed Dates or materially adversely affect
completion of the Work in accordance with the Project Schedule.
Contractor will specify in said notice the corrective action
planned by Contractor with respect thereto.
(b) Without limiting the obligations
of Contractor under Section 5.02(a) , Contractor shall
provide together with its monthly status reports required hereunder
any revisions to the Project Schedule that provide for the orderly,
practicable and expeditious completion of the Work in accordance
with the requirements of this Agreement. Each revised Project
Schedule shall be presented in such reasonable detail as Owner may
require and shall address all material elements of the Work.
Contractor shall consult with Owner in connection with each
revision to the Project Schedule provided under this paragraph.
Notwithstanding anything contained herein to the contrary, in the
absence of a Change Order, no revision to the Project Schedule
shall in any way amend, alter or otherwise change the Guaranteed
Dates.
(c) If, in the reasonable opinion of
the Owner, Contractor will not achieve Ready for Start-Up on or
before December 1, 2006, as that date may be extended pursuant
to Article VII , Contractor shall, within ten (10) days
after notice from Owner, submit a recovery plan, which shall
reasonably demonstrate the steps Contractor will take to achieve
Ready for Start-Up at the earliest date and otherwise achieve the
Guaranteed Dates.
(d) In no event will the
Contractor’s failure to complete one or more Milestones by
the date required for such Milestone change, delay or otherwise
affect the required completion date for any other Milestone.
Nothing contained in this Article V shall relieve Contractor
from its obligation to pay Schedule Liquidated Damages in the event
that Interim Completion is not achieved by the applicable
Guaranteed Interim Completion Date and/ or if Substantial
Completion is not achieved by the applicable Guaranteed Substantial
Completion Date. Specifically, but not by way of limitation, the
approval of a recovery plan (even though such recovery plan may
include a projected date for Interim Completion that is later than
the Guaranteed Interim Completion Date and/or Substantial
Completion that is later than the Guaranteed Substantial Completion
Date)