CONFIDENTIAL PORTIONS
OMITTED
Exhibit 10-1
ENGINEERING, PROCUREMENT
AND CONSTRUCTION CONTRACT
between
PACIFICORP
and
STONE & WEBSTER, INC.
dated as of February 10, 2004
FOR
THE CURRANT CREEK POWER STATION
|
ARTICLE 1
|
|
DEFINITIONS
|
1
|
|
|
|
|
|
|
1.1
|
|
D EFINED T ERMS
|
1
|
|
|
|
|
|
|
1.2
|
|
I NTERPRETATION
|
7
|
|
|
|
|
|
|
ARTICLE 2
|
|
CONTRACTOR’S WORK AND OTHER
OBLIGATIONS
|
7
|
|
|
|
|
|
|
2.1
|
|
C OMMENCEMENT OF THE W ORK
|
7
|
|
|
|
|
|
|
2.2
|
|
T HE W
ORK
|
7
|
|
|
|
|
|
|
2.3
|
|
H AZARDOUS S UBSTANCES
AND O FF -S ITE I MPACTS
|
8
|
|
|
|
|
|
|
2.4
|
|
C OORDINATION W ITH R EGULATORS
|
9
|
|
|
|
|
|
|
2.5
|
|
B OOKS AND R ECORDS
|
9
|
|
|
|
|
|
|
2.6
|
|
S TANDARDS OF P ERFORMANCE
|
9
|
|
|
|
|
|
|
2.7
|
|
T ITLE
|
9
|
|
|
|
|
|
|
2.8
|
|
F ACILITY S ITE C ONDITIONS
|
10
|
|
|
|
|
|
|
2.9
|
|
N ATURE OF THE W ORK
|
10
|
|
|
|
|
|
|
2.10
|
|
S UBCONTRACTORS
|
10
|
|
|
|
|
|
|
2.11
|
|
C OOPERATION
|
12
|
|
|
|
|
|
|
2.12
|
|
C ONTRACTOR R ESPONSIBILITIES WITH R ESPECT
TO O WNER F URNISHED E QUIPMENT
|
12
|
|
|
|
|
|
|
2.13
|
|
P ERMITS
|
12
|
|
|
|
|
|
|
2.14
|
|
C OORDINATION OF W ORK
|
12
|
|
|
|
|
|
|
ARTICLE 3
|
|
OWNER’S
OBLIGATIONS
|
12
|
|
|
|
|
|
|
3.1
|
|
F ACILITY R EAL E STATE R IGHTS
AND A CCESS TO F ACILITY S ITE
|
12
|
|
|
|
|
|
|
3.2
|
|
O WNER F URNISHED E QUIPMENT
|
12
|
|
|
|
|
|
|
3.3
|
|
P ERMITS
|
13
|
|
|
|
|
|
|
3.4
|
|
S TART-UP P ERSONNEL
|
13
|
|
|
|
|
|
|
3.5
|
|
S TART- U P
AND T ESTING F UEL S UPPLY
|
13
|
|
|
|
|
|
|
3.6
|
|
O THER
|
13
|
|
|
|
|
|
|
ARTICLE 4
|
|
SCHEDULE
|
14
|
|
|
|
|
|
|
4.1
|
|
S CHEDULE
|
14
|
|
|
|
|
|
|
4.2
|
|
A LTERATIONS TO S CHEDULE
|
14
|
|
|
|
|
|
|
4.3
|
|
R EVISION OF S CHEDULE
|
14
|
|
|
|
|
|
|
ARTICLE 5
|
|
INSPECTION AND
APPROVAL
|
14
|
|
|
|
|
|
|
5.1
|
|
O WNER’S R IGHT
TO A TTEND C ONTRACTOR I NSPECTIONS
|
14
|
|
|
|
|
|
|
5.2
|
|
I NSPECTION AND R E-
P ERFORMANCE
|
14
|
|
|
|
|
|
|
5.3
|
|
O WNER A PPROVAL
|
15
|
|
|
|
|
|
|
ARTICLE 6
|
|
TARGET PRICE AND
PAYMENT
|
15
|
|
|
|
|
|
|
6.1
|
|
T ARGET P RICE
|
15
|
|
|
|
|
|
|
6.2
|
|
D IRECT C OSTS
|
15
|
|
|
|
|
|
|
6.3
|
|
T OTAL P AYMENTS
|
19
|
|
|
|
|
|
|
6.4
|
|
M ONTHLY D IRECT C OST P AYMENTS
|
19
|
|
|
|
|
|
|
6.5
|
|
F EE
|
22
|
|
|
|
|
|
|
6.6
|
|
P AYMENT N OT
A CCEPTANCE
|
22
|
|
|
|
|
|
|
6.7
|
|
T AXES
|
22
|
|
|
|
|
|
|
6.8
|
|
R ECONCILIATION
|
22
|
|
|
|
|
|
|
6.9
|
|
L ATE P AYMENT
/ N ON- P AYMENT
|
23
|
i
|
ARTICLE 7
|
|
COMPLETION, ACCEPTANCE AND
LIQUIDATED DAMAGES
|
23
|
|
|
|
|
|
|
7.1
|
|
G UARANTEED S UBSTANTIAL C OMPLETION D ATES
|
23
|
|
|
|
|
|
|
7.2
|
|
S UBSTANTIAL C OMPLETION
|
24
|
|
|
|
|
|
|
7.3
|
|
N OTICE AND R EPORT
OF S UBSTANTIAL C OMPLETION
|
24
|
|
|
|
|
|
|
7.4
|
|
A CHIEVEMENT OF S UBSTANTIAL C OMPLETION
|
24
|
|
|
|
|
|
|
7.5A
|
|
L ATE S UBSTANTIAL C OMPLETION L IQUIDATED D AMAGES
|
25
|
|
|
|
|
|
|
7.5B
|
|
E ARLY S UBSTANTIAL C OMPLETION B ONUS
|
25
|
|
|
|
|
|
|
7.6A
|
|
P ERFORMANCE L IQUIDATED D AMAGES
|
26
|
|
|
|
|
|
|
7.6 B
|
|
P ERFORMANCE B ONUS
|
26
|
|
|
|
|
|
|
7.6 C
|
|
E XCLUSIVE N ATURE
OF L IQUIDATED D AMAGES
|
26
|
|
|
|
|
|
|
7.7
|
|
T RANSFER OF P OSSESSION
AND C ONTROL OF THE F ACILITY
TO O WNER
|
26
|
|
|
|
|
|
|
7.8
|
|
C REATION OF P UNCH -L IST
|
26
|
|
|
|
|
|
|
7.9
|
|
F INAL C OMPLETION
|
27
|
|
|
|
|
|
|
7.10
|
|
U SE D
OES N OT
C ONSTITUTE A CCEPTANCE
|
27
|
|
|
|
|
|
|
ARTICLE 8
|
|
TESTING
|
28
|
|
|
|
|
|
|
8.1
|
|
T ESTING
|
28
|
|
|
|
|
|
|
8.2
|
|
R ESTORING OF F ACILITY
|
28
|
|
|
|
|
|
|
8.3
|
|
O UTPUT D URING T ESTING
|
28
|
|
|
|
|
|
|
ARTICLE 9
|
|
LIMITATION OF
LIABILITY
|
28
|
|
|
|
|
|
|
9.1
|
|
A GGREGATE L IABILITY
|
28
|
|
|
|
|
|
|
9.2
|
|
C ONSEQUENTIAL D AMAGES
|
28
|
|
|
|
|
|
|
9.3
|
|
P ROOF OF A CTUAL D AMAGES
IF L IQUIDATED D AMAGES G ELD U NENFORCEABLE
|
29
|
|
|
|
|
|
|
ARTICLE 10
|
|
WARRANTIES AND
GUARANTEES
|
29
|
|
|
|
|
|
|
10.1
|
|
W ARRANTIES
|
29
|
|
|
|
|
|
|
10.2
|
|
W ARRANTY P ERIOD
|
29
|
|
|
|
|
|
|
10.3
|
|
R EPAIR OF D EFECTS
|
29
|
|
|
|
|
|
|
10.4
|
|
W ARRANTY P ERIOD E XTENSION
|
30
|
|
|
|
|
|
|
10.5
|
|
N O L
IENS OR E NCUMBRANCES
|
30
|
|
|
|
|
|
|
10.6
|
|
S UBCONTRACTOR W ARRANTIES
|
30
|
|
|
|
|
|
|
10.7
|
|
L IMITATION OF W ARRANTY
|
30
|
|
|
|
|
|
|
ARTICLE 11
|
|
CHANGES
|
31
|
|
|
|
|
|
|
11.1
|
|
C HANGES
|
31
|
|
|
|
|
|
|
11.2
|
|
P ROCEDURE FOR C HANGES
|
32
|
|
|
|
|
|
|
11.3
|
|
C ONTINUED P ERFORMANCE P ENDING R ESOLUTION
OF D ISPUTES
|
34
|
|
|
|
|
|
|
11.4
|
|
P RESERVATION OF S CHEDULE
AND T ARGET C OSTS
|
34
|
|
|
|
|
|
|
ARTICLE 12
|
|
FORCE MAJEURE
|
34
|
|
|
|
|
|
|
12.1
|
|
F ORCE M AJEURE E VENT
|
34
|
|
|
|
|
|
|
12.2
|
|
E XCUSED P ERFORMANCE
|
34
|
|
|
|
|
|
|
12.3
|
|
C OSTS AND S CHEDULE
|
35
|
|
|
|
|
|
|
ARTICLE 13
|
|
INDEMNIFICATION
|
35
|
|
|
|
|
|
|
13.1
|
|
C ONTRACTOR’S I NDEMNITY
|
35
|
|
|
|
|
|
|
13.2
|
|
O WNER’S I NDEMNITY
|
36
|
ii
|
ARTICLE 14
|
|
SUSPENSION AND
TERMINATION
|
36
|
|
|
|
|
|
|
14.1
|
|
R IGHT TO S USPEND W ORK
FOR C AUSE
|
36
|
|
|
|
|
|
|
14.2
|
|
R IGHT TO S USPEND W ORK
FOR C ONVENIENCE
|
36
|
|
|
|
|
|
|
14.3
|
|
T ERMINATION FOR C ONVENIENCE
|
37
|
|
|
|
|
|
|
14.4
|
|
T ERMINATION U PON C ONTRACTOR’S M ATERIAL B REACH
|
37
|
|
|
|
|
|
|
14.5
|
|
A CTIONS U PON T ERMINATION
|
38
|
|
|
|
|
|
|
14.6
|
|
T ERMINATION FOR C ONTRACTOR E VENT
OF D EFAULT
|
38
|
|
|
|
|
|
|
14.7
|
|
C ONSEQUENCES OF T ERMINATION
|
38
|
|
|
|
|
|
|
14.8
|
|
S URVIVING O BLIGATIONS
|
38
|
|
|
|
|
|
|
14.9
|
|
C ONTRACTOR’S R IGHT
TO S USPEND OR T ERMINATE
|
38
|
|
|
|
|
|
|
ARTICLE 15
|
|
SECURITY
|
38
|
|
|
|
|
|
|
ARTICLE 16
|
|
REPRESENTATIONS AND
WARRANTIES
|
39
|
|
|
|
|
|
|
16.1
|
|
R EPRESENTATIONS AND W ARRANTIES OF C ONTRACTOR
|
39
|
|
|
|
|
|
|
16.2
|
|
R EPRESENTATION AND W ARRANTIES
OF O WNER
|
40
|
|
|
|
|
|
|
ARTICLE 17
|
|
DISPUTE RESOLUTION
|
40
|
|
|
|
|
|
|
17.1
|
|
A PPLICABILITY OF R ESOLUTION P ROCEDURES
|
40
|
|
|
|
|
|
|
17.2
|
|
M ANAGEMENT D ISCUSSIONS
|
40
|
|
|
|
|
|
|
17.3
|
|
M EDIATION
|
40
|
|
|
|
|
|
|
17.4
|
|
A RBITRATION AND F INAL R ESOLUTION
|
41
|
|
|
|
|
|
|
17.5
|
|
A DJUDICATION
|
41
|
|
|
|
|
|
|
17.5
|
|
O BLIGATIONS C ONTINUE
|
41
|
|
|
|
|
|
|
17.5
|
|
I NJUNCTIVE R ELIEF
|
41
|
|
|
|
|
|
|
17.6
|
|
S URVIVAL
|
41
|
|
|
|
|
|
|
ARTICLE 18
|
|
LABOR AND
PERSONNEL
|
41
|
|
|
|
|
|
|
18.1
|
|
L ABOR AND P ERSONNEL
|
41
|
|
|
|
|
|
|
ARTICLE 19
|
|
INSURANCE
|
41
|
|
|
|
|
|
|
ARTICLE 20
|
|
MISCELLANEOUS
|
42
|
|
|
|
|
|
|
20.1
|
|
G OVERNING D OCUMENTS
|
42
|
|
|
|
|
|
|
20.2
|
|
A UTHORIZED R EPRESENTATIVES
|
42
|
|
|
|
|
|
|
20.3
|
|
A SSIGNMENTS
|
42
|
|
|
|
|
|
|
20.4
|
|
G OVERNING L AW
|
42
|
|
|
|
|
|
|
20.5
|
|
T IME IS A M ATERIAL E LEMENT
|
42
|
|
|
|
|
|
|
20.6
|
|
S EVERABILITY
|
42
|
|
|
|
|
|
|
20.7
|
|
N OTICES
|
42
|
|
|
|
|
|
|
20.8
|
|
A RTICLE AND S ECTION H EADINGS
|
43
|
|
|
|
|
|
|
20.9
|
|
N O W
AIVER OF R IGHTS
|
43
|
|
|
|
|
|
|
20.10
|
|
D UTIES AND R EMEDIES L IMITED
|
43
|
|
|
|
|
|
|
20.11
|
|
N O D
ISCLOSURE
|
43
|
|
|
|
|
|
|
20.12
|
|
E NTIRE A GREEMENT
|
44
|
|
|
|
|
|
|
20.13
|
|
A MENDMENTS
|
44
|
|
|
|
|
|
|
20.14
|
|
N O T
HIRD P ARTY R IGHTS
|
44
|
|
|
|
|
|
|
20.16
|
|
R ELATIONSHIP OF THE P ARTIES
|
44
|
iii
|
|
|
|
|
|
20.17
|
|
C OUNTERPARTS
|
62
|
|
|
|
|
|
|
20.18
|
|
F URTHER A SSURANCES
|
62
|
|
List of Appendices
|
|
|
|
|
|
|
|
Appendix A :
|
|
Facility Site
|
|
|
|
|
|
|
|
Appendix B :
|
|
Approved Project Schedule
|
|
|
|
|
|
|
|
Appendix C :
|
|
Fuel Specifications
|
|
|
|
|
|
|
|
Appendix D :
|
|
Testing
|
|
|
|
|
|
|
|
Appendix E :
|
|
Payment, Direct Costs and
Fee
|
|
|
|
|
|
|
|
Appendix F :
|
|
Insurance Requirements
|
|
|
|
|
|
|
|
Appendix G :
|
|
Performance Guarantees
|
|
|
|
|
|
|
|
Appendix H :
|
|
Permits/Consents
|
|
|
|
|
|
|
|
Appendix I :
|
|
Invoice
|
|
|
|
|
|
|
|
Appendix J :
|
|
Form of Contractor Parent Guarantee
and Performance Security
|
|
|
|
|
|
|
|
Appendix K :
|
|
[RESERVED]
|
|
|
|
|
|
|
|
Appendix L :
|
|
Lien Release Forms
|
|
|
|
|
|
|
|
Appendix M :
|
|
Change Order Request Form
|
|
|
|
|
|
|
|
Appendix N :
|
|
Approved Bidders List
|
|
|
|
|
|
|
|
Appendix O :
|
|
Interface Points
|
|
|
|
|
|
|
|
Appendix P :
|
|
Form of Escrow Agreement
|
|
|
|
|
|
|
|
Appendix Q :
|
|
Scope of Work
|
|
|
|
|
|
|
|
Appendix R :
|
|
Owner Furnished Equipment
|
|
|
|
|
|
|
|
Appendix S :
|
|
Subcontractor standard terms and
conditions
|
|
|
|
|
|
|
|
Appendix T :
|
|
Contractor and Owner Knowledge of
claims or potential bases for Changes to Cost, Schedule and/or
Scope of Work at time of Contract Execution
|
|
|
|
|
|
|
|
Appendix U :
|
|
[RESERVED]
|
|
|
|
|
|
|
|
Appendix V :
|
|
Adjudication
|
|
iv
ENGINEERING, PROCUREMENT AND
CONSTRUCTION CONTRACT
THIS ENGINEERING, PROCUREMENT AND
CONSTRUCTION CONTRACT (this “Contract” ) is
entered into as of the 10 th day of February, 2004, by
and between PacifiCorp, a corporation organized under the laws of
the state of Oregon, with offices at 201 South Main Street, Suite
2200, Salt Lake City, Utah 84111 ( “Owner” ) and
Stone & Webster, Inc., a corporation organized under the laws
of Louisiana with offices at 9201 East Dry Creek Road, Centennial,
CO 80112 ( “Contractor” ).
W I T N E S
S E T H :
WHEREAS, Owner intends to build, own
and operate a 525 MW nominal natural gas fired combined cycle power
plant known as the Currant Creek Power Station and located in Juab
County near Mona, Utah (the “Project”); and
WHEREAS, Owner desires to engage
Contractor to perform the Work for the Project upon the terms and
subject to the conditions set forth in this Contract;
and
WHEREAS, Contractor desires to
undertake the Work for the Project upon the terms and subject to
the conditions set forth in this Contract;
NOW, THEREFORE, in consideration of
the premises and the mutual covenants and agreements contained
herein, and other good and valuable consideration, the receipt and
sufficiency of which are hereby acknowledged, the Parties covenant
and agree as follows:
ARTICLE 1
Definitions
1.1 Defined Terms . As used
in this Contract, the following terms shall have the following
meanings (such meanings as necessary to be equally applicable to
both the singular and plural forms of the terms defined unless the
context otherwise requires):
“ACC”
means the Air Cooled Steam Condenser
to be procured and erected by Owner as more fully described in
Appendix R.
“Actual
Cost” or
“AC” means the total of the Direct Costs at
Final Completion.
“Adjudication”
shall have the meaning set forth in
Section 17.5, as more fully described in Appendix V.
“Aggregated Compensatory
Damages” shall have
the meaning set forth in Section 9.1.2.
“Aggregate Liquidated
Damages” shall have
the meaning set forth in Section 9.1.1.
“Applicable
Laws” means the
laws, treaties, ordinances, judgments, decrees, injunctions, writs
and orders of any court, arbitrator or governmental agency or
authority and rules, regulations, orders, interpretations and
Permits of any federal, state, provincial, county, municipal,
regional, environmental or other governmental body,
instrumentality, agency, authority, or court having jurisdiction
over Contractor, the design and construction of the Project, the
Facility Site, performance of the Work or operation of the Facility
as may be in effect or known to the parties to be pending at the
time of the execution of the Contract and upon Final
Completion.
“Applicable
Permits” means all
Permits (including Building Permits) as may be in effect from time
to time required to be obtained or maintained in connection with
construction of the Facility on the Facility Site, performance of
the Work or operation of the Facility, as further delineated in
Appendix H.
“Application for Monthly
Payment” means
Contractor’s official monthly request for payment of Direct
Costs, as described in Section 6.4.2 and Appendix E
.
1
“Approved Bidders
List” means the
list of Subcontractors in Appendix N that have been approved by
Owner, as such list is amended from time to time by addition or
deletion of Subcontractors by agreement of Owner and
Contractor.
“Approved Project
Schedule” means
that certain approved project schedule set forth in Appendix
B , as may be amended from time to time in accordance with the
provisions of this Contract.
“Authorized
Representative” means, with respect to each Party, the
individual appointed by such Party under Section 19.2 to act on
such Party’s behalf with respect to that Party’s duties
and responsibilities under this Contract. “Balance of
Plant Equipment” means all materials, workmanship, Work
and equipment other than the Owner Furnished Equipment necessary to
perform the Work.
“BOP Aux Electrical
Load” has the
meaning set forth in Appendix G.
“Building
Permits” means
those Permits required to be obtained or maintained in order for
Contractor to perform the engineering, procurement, site clearing,
civil works, construction and testing of the Facility on the
Facility Site or the performance of the Work related to similar
activities; provided, that if any such required Permits need to be
obtained in the name of Owner and not in the Contractor’s or
Subcontractors’ name, each of Owner and Contractor shall
cooperate with the other as reasonably necessary to enable the
party with responsibility to obtain a Permit to obtain such Permit
in the Owner’s name. Building Permits shall not include
Permits pertaining to (i) environmental regulation of the
Facility Site (other than with respect to Contractor’s
activities thereon in its performance of the Work), (ii) land
use or zoning matters affecting the Facility Site,
(iii) environmental regulation of start-up, testing or
operation of the Facility, or (iv) ownership or operation of the
Facility and the Project.
“Business
Day” means any
calendar day, except Saturdays, Sundays and national holidays,
which are observed by Federal Reserve member banks in New York
City, New York and Pioneer Day as observed by the state of
Utah.
“Change”
has the meaning set forth in Section
11.1.1.
“Change
Order” has the
meaning set forth in Section 11.1.2.
“Commencement
Date” has the
meaning set forth in Section 2.1.
“Commissioning
Test” has the
meaning set forth in Appendix D.
“Completion
Tests” means all
the tests required to establish compliance with the Contract in
order to achieve Substantial Completion of Phase 1 or Phase 2, as
applicable, and for the avoidance of doubt, includes the
Performance Acceptance Tests and the Performance Tests.
“Construction
Documents” has the
meaning set forth in Section 2.2.2.4.
“Contingency”
means the amount of [
* * * ] * as such amount may be adjusted
pursuant to this Contract, which is available to cover Direct Costs
if, in the aggregate, the Direct Costs exceed the Target
Cost.
“Contract”
means this Engineering, Procurement
and Construction Contract, including the Appendices identified in
the table of contents hereto, as the same may be amended, modified
or supplemented from time to time.
“Contract
Documents” has the
meaning set forth in Section 20.1.
“Contractor” has the meaning set forth in the preamble to
this Contract.
“Contractor Event of
Default” has the
meaning set forth in Section 14.4
“Contractor’s Excess
Cost Liability” has
the meaning set forth in Section 6.3.1
“Contractor Initiated
Change” has the
meaning set forth in Section 11.2.1
______________
*
CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
2
“Contractor
Taxes” has the
meaning set forth in Section 6.7.1.
“Contractor’s
Personnel” means
Contractor, its employees, agents and Subcontractors and each
Subcontractor’s employees, agents and
subcontractors.
“Contractor Critical
Schedule Milestone” has the meaning set forth in Appendix B
.
“Contractor
Guarantor” means
The Shaw Group Inc., or such substitute guarantor as Owner may
approve in its discretion from time to time.
“Credit
Requirement” means,
in the case of Contractor, that Contractor meets the requirements
of any one or more of clause (i) and clause (ii) below: (i)
Contractor or
Contractor’s Guarantor
maintains a senior unsecured debt rating from Standard &
Poor’s of [ * * * ] * ; (ii)
if Contractor or Contractor’s Guarantor has no debt rating,
Contractor meets ALL of the following credit standards: a) tangible
net worth equal to the projected maximum exposure under the
Contract, b) no change in the condition of Contractor’s
earnings, net worth, or working capital since the effective date of
The Shaw Group, Inc.’s 10Q for the period ending November 30,
2003, which would reasonably be anticipated to impair the
Contractor’s ability to meet its obligations under this
Contract, and c) Contractor is not in default under any of its
other agreements and is current on all of its financial
obligations; and in the case of Owner, that Owner maintains a
senior unsecured debt rating from Standard & Poor’s of
[ * * * ] * or Moody’s Investor
Services of [ * * * ] * .
“Design Development
Documents” has the
meaning set forth in Section 2.2.2.2.
“Delay LD
Cap” has the
meaning set forth in Section 7.5.
“Direct
Costs” means the
actual allowable costs and charges incurred by Contractor in the
performance of the Work to be paid or reimbursed by Owner as more
particularly set forth in Section 6.2.
“Excluded
Obligations” has
the meaning set forth in Section 9.1.5
“Facility”
means all those components,
including Phase 1 and Phase 2, comprising a nominal 525 MW natural
gas fired combined cycle power plant and all systems relating
thereto (as further described in the Contract
Documents).
“Facility
Site” means that
certain parcel of land owned, leased, or to be owned or leased by
Owner on which the Facility will be located, as further described
in Appendix A .
“Fee”
means the amount of [ * * * ]
* , as such amount may be adjusted from time to
time to reflect Material Changes to the Scope of Work instituted at
Owner’s request pursuant to Section 11.2.2 of this
Contract.
“Final
Completion” has the
meaning set forth in Section7.9.1.
“Final Completion
Certificate” has
the meaning set forth in Section 7.9.3.
“Force
Majeure” has the
meaning set forth in Section 12.1.
“Fuel”
has the meaning established in
Appendix C.
“Full Notice to
Proceed” has the
meaning established in Section 2.1.2.
“Gas
Turbines” means the
two General Electric Frame 7F combustion turbine generators and
related equipment to be procured by Owner as more fully described
in Appendix R.
“GSUs”
means the three generation step up
transformers and related equipment to be procured by Owner as more
fully described in Appendix R.
______________
* CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
3
“Guaranteed BOP Aux
Electrical Load” has the meaning set forth in Section
7.6A.
“Guaranteed Substantial
Completion Dates” has the meaning set forth in
Section 7.1(ii).
“Hazardous
Substance” means
any and all chemicals, constituents, contaminants, pollutants,
materials, and wastes and any other carcinogenic, corrosive,
ignitable, radioactive, reactive, toxic or otherwise hazardous
substances or mixtures (whether solids, liquids, gases), or any
substances now or at any time subject to regulation, control,
remediation or otherwise addressed as a hazardous substance under
Applicable Laws, including those laws, regulations and policies
relating to the discharge, emission, spill, release, or threatened
release into the environment or relating to the disposal,
distribution, manufacture, processing, storage, transport,
treatment, transport, or other use of such substances.
“HRSGs”
means the two heat recovery steam
generators and related equipment (including the bypass stacks and
dampers (if elected by Owner) and FAA lighting, if required) to be
procured by Owner as more fully described in Appendix R.
“Interim Construction
Agreement” means
the Contract between PacifiCorp and Stone & Webster, Inc. for
Currant Creek Initial Site Activities dated as of December 31,
2003.
“Late Substantial
Completion LDs” has
the meaning set forth in Section 7.5.
“Limited Notice to
Proceed” has the
meaning set forth in Section 2.1.1.
“Material Adverse
Change” means that
Contractor has, in the reasonable opinion of Owner, experienced a
material adverse change in the ability to fulfill its obligations
under this Contract, including, but not limited to, any such change
that results in its failing to comply with the Credit
Requirement.
“Milestone” means any and each of the milestones specified
in the Milestone Fee Payment Schedule.
“Milestone Fee
Payment” means the
Fee payable to Contractor pursuant to the Milestone Fee Payment
Schedule.
“Milestone Fee Payment
Schedule” means the
Fee payment milestone schedule contained in Appendix E.
“Minimum Performance
Levels” means the
Facility meets the performance standards applicable to the Facility
for each of Phase 1 and Phase 2 required for Substantial
Completion, as more fully set out in Appendix G.
“Monthly Progress
Report” means a
progress report containing the information required by Section
6.4.4.5
“Notice of Final
Completion” has the
meaning set forth in Section 7.9.2.
“Notice of Substantial
Completion” has the
meaning set forth in Section 7.3.
“Operation and Maintenance
Manuals” means the
instructions for the operation and maintenance of the Facility to
be prepared by Contractor as described in Section 10.1, and as more
fully described, as to form and substance, in the Scope of
Work.
“Owner”
has the meaning set forth in the
preamble to this Contract, and shall include its successors and
assigns.
“Owner Critical Schedule
Milestones” has the
meaning set forth in Appendix B.
“Owner’s Executive
Representative” means the person to whom notices pursuant to
Section 6.9.6 are to be delivered, as identified in Section 20.7 as
the same may be amended from time to time.
“Owner Initiated
Change” has the
meaning set forth in Section 11.2.2
4
“Owner
Subcontractors” means any party with whom Owner contracts for
the provision of goods or services other than Contractor with
respect to the Project.
“Owner(’s)
Personnel” means
Owner, its employees, agents and Owner Subcontractors and each
Owner Subcontractor’s employees, agents and
subcontractors.
“Owner
Indemnitees” has
the meaning set forth in Section 13.1.1.
“Owner Furnished
Equipment” means
the Gas Turbines, HRSGs, Steam Turbine, ACC, GSUs, Unit Aux
Transformers and Switchyard, together with their related
components, materials, supplies and parts, as further described in
Appendix R .
“Owner Furnished Equipment
Documents” means
the purchase orders and other procurement documents for Owner
Furnished Equipment.
“Parties
” means Owner and Contractor;
“Party” means Owner or Contractor, as the case
may be.
“Payment Escrow
Account” shall have
the meaning as set forth in Section 6.4.4.
“Payment
Schedule” shall
have the meaning as set forth in Appendix E, as further described
in Section 6.4.1.
“Performance Acceptance
Tests” means the
tests for establishing compliance with the Minimum Performance
Levels for each of Phase 1 or Phase 2, as applicable, required for
Substantial Completion, as more fully set out in Appendix
D.
“Performance
Guaranty” shall
have the meaning set forth in Appendix G.
“Performance
LDs” shall have the
meaning as set forth in Section 7.6.
“Performance
Tests” shall mean
those tests required to establish the extent of achievement of the
Performance Guaranty.
“Permits”
means all valid and effective
waivers, franchises, variances, permits, authorizations, licenses
or orders of or from any federal, state, provincial, county,
municipal, regional, environmental or other governmental body,
instrumentality, agency, authority, or court having jurisdiction
over construction of the Facility, the Facility Site, performance
of the Work, or operation of the Facility, as may be in effect from
time to time.
“Person”
means any individual, corporation,
partnership, limited liability company, association, joint stock
company, trust, unincorporated organization, joint venture,
government or political subdivision or agency thereof, other than
Owner or Contractor.
“Phase 1”
means the two simple cycle
combustion turbines and all supporting equipment, having achieved
Substantial Completion for such phase and operating or capable of
being operated as stand-alone generating units, as described more
fully in the Contract Documents.
“Phase 2”
means the conversion of Phase 1 into
a 2x1 combined cycle operation generating facility, including the
incorporation of one steam turbine generator, the air cooled
condensing unit and all supporting equipment, having achieved
Substantial Completion for the Project, as described more fully in
the Contract Documents.
“Procurement
Documents” shall
have the meaning set forth in Section 2.2.2.3.
“Project”
means, collectively, the design,
engineering, permitting, procurement, construction, installation,
commissioning, start-up, testing and completion of the
Facility.
“Project Design
Book” means the
index of documents, drawings and information which reflects the
Facility design, including the Design Development Documents, the
Construction Documents and the other documents required to be
produced or delivered by Contractor hereunder, as further described
in the Scope of Work.
“Project
Taxes” has the
meaning set forth in Section 6.7.2.
5
“Prolonged Delay
Date” has the
meaning set forth in Section 7.5.
“Prudent Electric Power
Industry Practices” means the practices, methods, techniques and
standards that, at the particular time of performance of the Work,
are prudent and generally accepted in the electric power industry
in the United States, or if more stringent, those practices,
methods, techniques and standards that are specifically practiced
by Contractor, for use in connection with the design, procurement,
engineering, construction, testing and operation of power plants of
the same or similar size and type as the Facility. Prudent Electric
Power Industry Practices are not limited to the optimum practice or
method to the exclusion of others, but rather refer to commonly
used and reasonable practices and methods.
“Punch-List” means the list prepared in accordance with
Section 7.8, which list shall set forth all items of work that
remain to be performed in order to ensure that the Work fully
complies with all of the standards and requirements set forth
herein. The Punch List shall not include any items of work, alone
or in the aggregate, the non-completion of which prevents the
Facility from (i) reaching Substantial Completion or (ii)
being legally and safely placed in commercial operation.
“Real Estate
Rights” means all
rights in or to real estate (including title to or other rights to
use or access the Facility Site, leases, contracts, permits,
easements, licenses, private rights of way, and utility and
railroad crossing rights) required to be obtained or maintained in
connection with construction of the Facility on the Facility Site,
performance of the Work, or operation of the Facility (including
the transportation of all necessary materials, equipment and other
items to the Facility Site, access for the construction, and the
startup and testing of the Facility).
“Required
Changes” has the
meaning set forth in Section 11.3.5.
“Scope of
Work” means the
scope of work attached hereto as Appendix Q .
“Steam
Turbine” means the
steam turbine generator and related equipment to be procured by
Owner as more fully described in Appendix R.
“Subcontract”
means any contract by Contractor
with a Subcontractor with respect to performing any part of the
Work or providing any services, equipment or materials in
connection with the Work.
“Subcontractor”
means each and every vendor,
supplier, materialmen or contractor under a Subcontract to
Contractor, performing any part of the Work or providing any
services, equipment or materials in connection with the
Work.
“Substantial
Completion” has the
meaning set forth in Section 7.2.
“Substantial Completion
Certificate” means
the certificate issued by Owner upon achievement of Substantial
Completion pursuant to Section 7.4.
“Switchyard” means the switchyard and related equipment to be
procured and erected on a turnkey basis by Owner as more fully
described in Appendix R.
“Target
Cost” means the sum
of all allowable Direct Costs agreed upon by the Parties as of the
Commencement Date that will be incurred in Contractor’s
performance of the Work, (specifically including amounts paid under
the Limited Notice to Proceed and the Interim Construction
Agreement), and shall be equal to [ * * * ]
* , as such amount may be adjusted pursuant to
this Contract.
“Target
Price” or
“TP” is the sum of the Target Cost and the
Contingency.
“Terms and
Conditions” means
Articles 1 through 20 hereof.
______________
*
CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
6
“Turnover
Package” means the
documentation (including drawings, start-up procedures, log sheets,
settings, and other items) in content, form and substance
reasonably acceptable to Owner, submitted by Contractor to Owner
which demonstrates that the systems comprising the Facility have
been completed in accordance with this Contract and may be operated
safely for their intended purposes.
“Unit Aux
Transformers” means
the two unit auxiliary transformers and related equipment to be
procured by Owner as more fully described in Appendix R.
“Warranty”
has the meaning set forth in Section
10.1.
“Warranty
Period” has the
meaning set forth in Section 10.2.
“Work”
has the meaning set forth in Section
2.2.
“Work
Product” has the
meaning set forth in Section 2.7.
1.2 Interpretation . Unless
the context requires otherwise, in this Contract (a) words
singular or plural in number shall be deemed to include the other
and pronouns having a masculine or feminine gender shall be deemed
to include the other; (b) any reference contained herein to this
Contract or any other agreement or any appendix, schedule, exhibit
or attachment hereto or thereto shall mean this Contract or such
other agreement and such schedules, exhibits and attachments as
amended, supplemented or otherwise restated from time to time; (c)
any reference in this Contract to any Person shall include its
permitted successors and assigns and, in the case of any
governmental instrumentality, any Person succeeding to its
functions and capacities; (d) any reference in this Contract to any
Article, Section, Appendix, Exhibit or Schedule shall mean and
refer to the Article or Section contained in or the Appendix,
Exhibit or Schedule attached to this Contract; and (e) the words
“include” and “including” shall mean to
include, without limitation.
ARTICLE 2
Contractor’s Work and Other
Obligations
2.1 Commencement of the Work
.
2.1.1 Limited Notice to
Proceed . Owner has issued and delivered to Contractor (i) a
limited notice to proceed dated August 18, 2003 (such notice and
the subsequent extensions thereto are collectively referred to
herein as the “Limited Notice to Proceed” ), and
(ii) the Interim Construction Agreement, in anticipation of the
execution of this Contract, which authorized Contractor to perform
certain work on the Project for which Contractor has been or is
being separately reimbursed. Upon issuance of the Full Notice to
Proceed, any of the work actually performed under the Limited
Notice to Proceed or under the Interim Construction Contract shall
be deemed to have been performed as Work under and pursuant to the
terms of this Contract. The amounts paid under the Limited Notice
to Proceed and the Interim Construction Contract identified in
Appendix E constitute Direct Costs under this Contract
2.1.2 Full Notice to Proceed
. Following the receipt of approvals from the Utah Public Service
Commission and the Utah Division of Air Quality and such other
governmental or regulatory bodies as Owner in its sole discretion
deems appropriate for the construction and operation of the
Facility, Owner may issue to Contractor a written notice directing
Contractor to commence performance of the Work (the “ Full
Notice to Proceed ”), and Contractor shall commence full
performance of the Work as of the date of such notice (the “
Commencement Date ”). If Owner issues the Full Notice
to Proceed after February 23, 2004, then effects to schedule and
costs will be addressed through the Change Order process described
in Article 11.
2.2 The Work . Contractor
shall (except only to the extent otherwise defined as Owner’s
responsibility in the Contract) perform or cause to be performed
all of the work, services and obligations (including the
satisfaction of those liabilities associated with such work,
services and obligations), required in connection with the design,
engineering, permitting, procurement, civil works, construction,
installation, integration (as more particularly described in
Appendix Q) of Owner Furnished Equipment, training for operation,
commissioning, start-up, testing and Substantial Completion and
Final Completion of the Project and shall provide the materials and
equipment, machinery, tools, labor, utilities, chemicals,
transportation (including without limitation transportation of
Owner Furnished Equipment, as further described in Appendix Q, from
the rail siding to the Facility Site), administration
7
and other services and items
required for and related to the foregoing, all as further described
in Appendix Q and otherwise to be performed in accordance with the
Contract Documents, including any Change Orders (the
“Work”). Contractor shall perform the Work in the most
efficient and cost effective means available within the
requirements of this Contract.
2.2.1 Work in General . In general, the Work
shall consist of two phases, including integration of the Owner
Furnished Equipment, as follows: (1) Phase 1 to reach Substantial
Completion by [ * * * ] * ; and (2) Phase
2 to reach Substantial Completion by [ * * * ]
* . Each phase is described in more detail in
Appendix Q.
2.2.2 Engineering, Design,
Procurement and Construction . Contractor represents and
warrants that it has thoroughly familiarized itself with the
Facility Site and the Contract Documents and agrees that it will
perform the Work in a manner that meets or exceeds the requirements
set forth in the Contract Documents.
2.2.2.1 Engineering .
Contractor will perform all engineering services necessary to
perform the Work and will cooperate with Owner’s reasonable
requests to review and, to the extent Owner may require pursuant to
Article 5, approve the engineering and design efforts of
Contractor, including cooperating with any third parties acting at
the request of Owner, (including without limitation any federal,
state and local agencies or others as Owner may direct). Contractor
shall determine the extent to which engineering work to be
performed by Contractor, or any Subcontractor requires
certification under Applicable Law by professional engineers
licensed and properly qualified to perform such engineering
services in the jurisdiction in which such services are to be
performed, and to provide or cause to be provided all such required
certifications.
2.2.2.2 Design Development
Documents . As further described in the Contract Documents,
Contractor will prepare, by the date specified in the Approved
Project Schedule, those design development documents for the
Facility listed in Appendix Q consisting of drawings,
models, specifications, plans and other documents necessary to fix
and describe the Facility (collectively, the “ Design
Development Documents ”).
2.2.2.3 Procurement Documents
. As further described in the Contract Documents, Contractor will
prepare, by the date specified in the Approved Project Schedule,
those procurement policies, standards and documents, including
terms and conditions, (the “Procurement
Documents” ) necessary for Contractor to perform the
procurement services called for herein.
2.2.2.4 Construction
Documents . As further described in the Contract Documents,
based upon Design Development Documents or any further adjustments
in the scope or quality of the Project approved by Owner pursuant
to Article 11, Contractor will prepare, prior to undertaking the
related Work, those drawings and specifications specified in
Appendix Q setting forth in detail the requirements for the
construction of the Facility (collectively, the “
Construction Documents ”).
2.3 Hazardous Substances and
Off-Site Impacts .
2.3.1 Contractor shall not release
or cause the release of any Hazardous Substances brought onto the
Facility Site or adjacent areas by Contractor, any Subcontractor or
others in the course of performing the Work. Contractor will
immediately notify Owner of any known spills, emissions or other
releases of Hazardous Substances that occur in connection with the
performance of the Work. Contractor will be responsible for
removing from the Facility Site and areas adjacent thereto, and for
properly disposing of, in a manner acceptable to Owner and in
compliance with the Contract Documents, Applicable Laws and
Applicable Permits, Hazardous Substances brought onto or released,
generated or accumulated at the Facility Site by Contractor or any
Subcontractor in the course of performing the Work. As a condition
precedent to Final Completion, Contractor will provide to Owner a
certification in a form acceptable to Owner stating that
(a) no Hazardous Substances were installed or otherwise
incorporated in the Facility, other than Hazardous Substances
notified to Owner in said certification, and utilized in the
performance of the Work, and (b) Hazardous Substances brought
onto or generated at the Facility Site by Contractor or any
Subcontractor were used released, removed or disposed of in
compliance with the Contract Documents, Applicable Laws and
Applicable Permits.
______________
*
CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
8
2.3.2 In the event Contractor
encounters on the Facility Site material reasonably believed to be
a pre-existing Hazardous Substance, then Contractor will, as
necessary, immediately cease performance of any Work in the area
affected and immediately will report the condition to Owner.
Contractor will not thereafter resume performance of the Work in
the affected area except with the prior written permission of
Owner. If Owner instructs Contractor to resume performance of the
Work, and to the extent that the Parties agree in writing on
Contractor’s course of subsequent actions (consistent with
Applicable Law) in connection with such Hazardous Substance in
order to allow continued performance of the Work, then Contractor
will proceed with the Work in the affected area subject to Article
11 where applicable.
2.3.3 Contractor shall, in
performing the Work, control fugitive dust, storm water runoff and
noise and otherwise act in a manner so as to limit all impacts of
the Work off of the Facility Site in compliance with Applicable
Laws.
2.4 Coordination With
Regulators . Contractor shall cooperate with Owner’s
reasonable requests in connection with its dealings with federal,
state and local governmental agencies in regards to the Work, any
Applicable Permits as may be required to complete the Work and any
approvals from any state utility regulatory commission (including
in connection with proceedings dealing with Owner’s rate or
cost recovery applications), the Federal Energy Regulatory
Commission or others that Owner determines are
necessary.
2.5 Books and Records .
Contractor shall maintain fiscal records and books of account
pertaining to the Project in accordance with U.S. generally
accepted accounting principles consistently applied and Applicable
Laws.
2.6 Standards of Performance
. Contractor shall be responsible for construction means, methods,
techniques, standards, sequences, procedures and safety and
security programs in connection with the performance of the Work.
Contractor shall perform the Work (a) in accordance with the
Contract Documents (b) in a professional, prudent,
cost-effective, good and workmanlike manner, and (c) in
accordance with Applicable Laws, Applicable Permits,
and Prudent Electric Power Industry Practices, including
applicable engineering, environmental, construction, safety, and
electrical generation codes and standards as required under or
listed in the Scope of Work or as otherwise may apply as such codes
and standards exist on the Commencement Date In the case of issues
that may materially impact the Work, Contractor shall act with
reasonable diligence (but except as otherwise provided in the
Contract not including any obligation to engage in formal dispute
resolution processes) to achieve satisfactory resolution of such
issues.
2.7 Title .
2.7.1 Title to all materials,
supplies, equipment and machinery used in connection with the Work
and which become a permanent part of the Facility shall vest in
Owner upon the earlier of (a) the installation of such
materials, supplies, equipment or machinery into the Facility Site,
or (b) full payment therefore by Owner pursuant to Article 6.
Title to water, soil, rock, gravel, sand, minerals, timber and any
other resources developed or obtained in the excavation or the
performance by Contractor of the Work and the right to use said
items or dispose of the same is hereby expressly vested in and
reserved by Owner. Notwithstanding the foregoing, title to Owner
Furnished Equipment shall at all times remain with
Owner.
2.7.2 Contractor shall retain title
in its non-Project specific standard drawing details, designs,
specifications, databases, computer software and any other
proprietary property as identified as such and agreed to by Owner
at the time of use by Contractor; provided , however
, that Owner shall at all times (including after any termination of
this Contract), have the right to retain copies thereof and is
hereby granted a perpetual, irrevocable license to use such
drawings, designs, specifications, databases, computer software and
any other information of Contractor related to the Project and the
Facility at no additional cost, fee or royalty to Owner.
Owner’s use of any such documents or information for any
purpose other than as set forth in this Contract, or modification
to such documents by anyone other than Contractor, shall be at the
Owner’s sole risk and without liability or legal exposure to
Contractor. Title to all drawings, designs, details, models,
specifications, reports, plans, databases, computer software and
other documents produced by Contractor in connection with the Work
shall vest in Owner upon payment pursuant to Article 6. All work
product of Contractor, its agents and employees and each
Subcontractor performed pursuant to this Contract (collectively,
the “ Work Product ”) shall be deemed, to the
greatest extent possible, “works made for hire” (as
defined in the Copyright Act, as
9
amended 17 U.S.C.A. § 101
et seq.). Contractor agrees to execute and deliver and cause its
employees and agents and all Subcontractors to execute and deliver
to Owner any transfers, assignments, documents or other instrument
which Owner may deem necessary or appropriate to vest complete
title and ownership of any or all Work Product, and all rights
therein, in Owner. Notwithstanding the foregoing, Contractor shall
have the right to use the Work Product, including business methods
and technical methods and processes used and developed in the
course of the Work, in its general business practices and
operations as long as Contractor maintains such Work Product in
strict confidence and does not reveal such Work Product to any
third party without the written consent of Owner.
2.8 Facility Site Conditions
. Contractor has inspected the Facility Site prior to execution of
the Contract and Contractor has based the Target Price on such
inspection. In addition, Contractor conducted a geotechnical
investigation prior to execution of the Contract based on the
proposed layout of major equipment as of the date of this Contract,
and the Target Price takes into account the results of such
investigation.
2.9 Nature of the Work . In
setting the Target Price and performing the Work, Contractor shall
be responsible for having taken steps reasonably necessary to
understand the nature of the Work, the general local physical,
topographic and weather conditions which are anticipated to affect
the Work and the costs thereof. With respect to any known
pre-existing structures set out in Appendix Q with which the Work
may interface or within which the Work or any portion thereof may
be integrated, Contractor shall be responsible for having taken
reasonable steps to fully understand the structural limitations,
soundness and construction makeup of such structures. Failure by
Contractor to fully acquaint itself with such conditions which may
affect the Work shall not relieve Contractor of its
responsibilities under this Contract.
2.10 Subcontractors.
2.10.1 Acceptable
Subcontractors . Unless a Subcontractor is already listed on
the Approved Bidders List in Appendix N, Owner shall have the right
to approve (such approval not to be unreasonably withheld or
delayed) each Subcontractor from whom Contractor or any
Contractor’s Personnel proposes to solicit bids or otherwise
engage in connection with the Work for any aggregate value in
excess of [ * * * ]* or which is associated with a
critical plant component, as identified by Owner to Contractor from
time to time, such identification to be made in advance of
Contractor’s solicitation for bids. Once approved by Owner,
such Subcontractor shall be considered added to the Approved
Bidders List for the specific classes of goods or services for
which such Subcontractor is added to the Approved Bidders List.
Contractor shall select each Subcontractor from among those
pre-approved by Owner. Any successor or replacement of any such
Subcontractor shall be subject to Owner’s prior written
approval, unless such successor or replacement is already on the
Approved Bidders List for the specific classes of goods or services
for which such Subcontractor is added to the Approved Bidders List.
All other vendors, suppliers, materialmen, consultants or
subcontractors may be selected by Contractor following reasonable
advance written notification to Owner. Contractor shall provide to
Owner such information concerning each Subcontractor as Owner may
request. Owner shall have the right to rescind its approval of any
Subcontractor for cause by notice to Contractor with respect to
contracts with the specific Subcontractor not executed prior to the
date on which Owner provides such notice of rescission.
2.10.2 Supervise . Contractor
shall be solely responsible for and have exclusive control over
each Subcontractor, labor, construction means, material suppliers,
methods, techniques, sequences and procedures and for supervising
and directing all portions of the Work. Contractor shall be fully
responsible for any part of the Work accomplished by any
Subcontractor and for the actions or inactions of each
Subcontractor, including Persons either directly or indirectly
employed by it. Contractor shall be solely responsible for dealing
with, coordinating and handling any communications, negotiations
and dispute resolutions concerning each Subcontractor and the
Work.
______________
* CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
10
2.10.3 No Privity with Owner
. Owner shall not be deemed by virtue of this Contract or otherwise
to have any contractual obligation to or relationship with any
Subcontractor. Contractor shall include a clause to this effect in
each Subcontract with each Subcontractor. Contractor shall be
solely responsible for paying each Subcontractor for services,
equipment, material or supplies in connection with the Work and the
Facility without prejudice to Owner’s payment obligations to
Contractor pursuant to Section 6.4.
2.10.4 Purchase Orders and
Subcontracts . Consistent with the provisions of Section
2.10.5, Contractor shall use the Procurement Documents in
connection with the Work. Owner shall have the right to review and
approve the Procurement Documents and Subcontracts valued in excess
of $ [ * * * ] * or which are associated
with a critical plant component, as identified by Owner to
Contractor from time to time, such approval not to be unreasonably
withheld or delayed. Contractor and Owner shall meet and attempt to
develop a framework of material terms and conditions. If such terms
and conditions are included in any Procurement Document or
Subcontract substantially in the form attached as Appendix S, such
document shall not be subject to further approval by Owner;
provided, however, that in each event Owner shall have the right to
review and approve risk mitigation measures (including without
limitation liquidated damages schedules) in each Subcontract or
Procurement Document in excess of $ [ * * * ]* . If
Owner has not expressly approved or rejected the terms of a
specific Procurement Document or Subcontract within [ * * * ]
* Business Days after delivery of such document
by Contractor, then that Procurement Document or Subcontract shall
be deemed approved as submitted. Contractor will provide Owner with
copies of all Subcontracts and the Procurement Documents relating
to the Facility.
2.10.5 Subcontractor
Warranties . Contractor will procure from each Subcontractor
sufficient warranties consistent with Article 10 with respect to
any portion of the Work provided by such Subcontractor for a period
of no less than twelve (12) months after Substantial Completion of
Phase 1 and Phase 2, as applicable, and for a further twelve (12)
months after any warranty repair with respect to the subject of the
repair; provided that Contractor shall not be required to
procure any Subcontractor warranty with a total warranty period
longer than 24 months from Substantial Completion for Phase 1 and
Phase 2, as applicable. Contractor will obtain and maintain all
such warranties in full force and effect until assignment to Owner
upon Substantial Completion. Upon Substantial Completion of Phase 1
and Phase 2, as applicable, or upon the earlier termination of this
Contract under Article 14, Contractor will assign its rights under
all such Subcontractor warranties to Owner; provided, however, that
Contractor shall in all cases be responsible to perform all
Subcontractor warranties to the extent a Subcontractor is an
Affiliate of Contractor to the extent that such Subcontractor fails
to do so; and further provided that thereafter, Contractor’s
sole obligation shall be to assist Owner in enforcing any such
warranties. Contractor shall not waive or otherwise impair the
obligation of any Subcontractor to perform the Subcontractor
warranties to be delivered pursuant to the Contract, whether in
connection with any dispute resolution process or
otherwise.
2.10.6 Assignment of
Subcontracts . Each Subcontract shall provide that, upon
written notification to the Subcontractor by Owner that (a) this
Contract has been terminated, (b) Contractor’s right to
proceed with the Work has been terminated, or (c) Owner otherwise
is assuming Contractor’s rights under such Subcontract, then
such Subcontractor shall continue to perform its responsibilities
under such Subcontract for the benefit of Owner and shall recognize
Owner as being vested with all the rights and responsibilities of
Contractor under such Subcontract. Notwithstanding the foregoing,
it is specifically understood and agreed (and each Subcontract
shall acknowledge) that no Subcontractor shall have any right to
look to Owner for the performance of Contractor’s obligations
(including as to payment) under any Subcontract prior to the date
that Owner provides the aforementioned written notice to such
Subcontractor.
______________
* CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
11
2.10.7 Subcontractor
Insurance . In each Subcontract, Contractor shall require each
Subcontractor to obtain, maintain and keep in force throughout the
time during which it is engaged by Contractor such insurance
coverage as is set forth in Appendix F.
2.11 Cooperation . Contractor
shall fully cooperate and coordinate with Owner in all aspects of
Contractor’s performance of the Work in a manner that will
ensure that the Work is performed in accordance with the Contract
Documents.
2.12 Contractor Responsibilities
with Respect to Owner Furnished Equipment . Contractor shall
provide Owner the following services with respect to Owner
Furnished Equipment:
2.12.1 Engineering and procurement
services as Owner’s engineer;
2.12.2 Construction management
services with respect to erection and installation of the ACC and
the Switchyard;
2.12.3 Construction, installation
and commissioning of the Gas Turbines, the Steam Turbine, the
HRSGs, the GSUs, and the Unit Aux Transformers; all as more fully
described in Appendix Q, in all cases consistent with the
provisions of Section 3.2.
2.13 Permits . Contractor
will secure and maintain all Applicable Permits which are
designated in Appendix H as Contractor’s
responsibility and other Permits which are required by Applicable
Laws to be obtained by Contractor or which are typically to be
provided by contractors for the design and construction of projects
similar to the Project.
2.14 Coordination of Work .
Following Substantial Completion of Phase 1 Contractor shall
continue to perform the Work necessary to achieve Substantial
Completion of Phase 2 and Final Completion of the Project in a
manner reasonably designed to minimize disruptions with
Owner’s operation of Phase 1. Contractor shall, in addition
to its periodic reports delivered to Owner hereunder, notify Owner
by reasonable notice, and in no case less than 48 hours, in advance
of performing any portion of the Work that will require the
shutdown of all or any portion of Phase 1 or involves activities
that create a substantial risk of causing an unplanned shutdown of
all or any portion of Phase 1.
ARTICLE 3
Owner’s
Obligations
3.1 Facility Real Estate Rights
and Access to Facility Site . Owner will secure and maintain at
its own expense all Real Estate Rights. Owner will furnish to
Contractor full and unimpeded access to the Facility Site as
necessary in support of the Approved project Schedule for
Contractor to perform the Work. Contractor shall perform the Work
consistent with such Real Estate Rights to the extent Owner makes
the Real Estate Rights known to Contractor and shall cooperate with
Owner’s reasonable requests in connection with Owner’s
dealings in regards to the Real Estate Rights.
3.2 Owner Furnished Equipment
.
3.2.1 Owner will cause the Owner
Furnished Equipment to be procured (and in the case of the ACC and
the Switchyard, to be furnished and erected, subject and without
prejudice to Section 2.12) and delivered into Contractor’s
custody and control in accordance with Appendix Q and the delivery
schedule to be set forth in the Approved Project
Schedule.
3.2.2 Ownership of and
responsibility to correct or repair the Owner Furnished Equipment
shall remain with Owner except to the extent that the need for any
correction or repair is demonstrated to be due to the negligence or
breach of contract of Contractor in which case Contractor shall
correct or repair such Owner Furnished Equipment as a Direct Cost,
but only to the extent that such costs of repair or correction
would otherwise qualify as a Direct Cost pursuant to the provisions
of the Contract.
3.2.3 Owner will provide or cause to
be provided to Contractor, copies of the Owner Furnished Equipment
Documents (redacted as appropriate), together with any other
related information and documentation all
12
to the extent only that they are:
(i) reasonably necessary for the purpose of Contractor performing
the Work or (ii) reasonably required to support the Approved
Project Schedule (to the extent Contractor has given appropriate
notice to Owner of both the documents and information required and
a time schedule within which it is needed).
3.2.4 Owner shall provide at
Owner’s cost, the appropriate and adequate technical advisors
to support Contractor during the installation, storage, start-up
and testing of the Owner Furnished Equipment, as reasonably
required. Such advisors shall be responsible to verify to Owner and
to the Owner Furnished Equipment suppliers that such activities are
properly performed in accordance with the requirements of the Owner
Furnished Equipment Suppliers; provided, that such verification
does not relieve Contractor of its performance obligations under
this Contract.
3.2.5 The Target Cost specifically
excludes the purchase price and related procurement expenses of the
Owner Furnished Equipment, including expediting and off-site
inspection services related thereto, but for the avoidance of doubt
specifically includes the costs of those activities and obligations
to be performed by Contractor pursuant to
Section 2.12.
3.2.6 Notwithstanding anything to
the contrary in this Contract (but without limiting
Contractor’s obligations under Section 2.12 with respect to
the Work), Owner shall be responsible for the performance of Owner
Furnished Equipment, without Contractor incurring any liability in
connection therewith, except to the extent that any deficiencies in
performance arise from Contractor’s negligence or breach of
this Contract.
3.2.7 Without prejudice to the
obligations of Contractor with respect to the integration of Owner
Furnished Equipment, Owner shall, with respect to any issues
involving the Owner Furnished Equipment reasonably raised by
Contractor that materially impact the Work, act with respect to the
providers thereof in a manner consistent with Prudent Electric
Power Industry Practice, including using reasonably diligence, not
including any obligation to engage in formal dispute resolution
processes, to obtain a satisfactory resolution of such
issues
3.3 Permits . Owner will
secure and maintain at its own expense all Applicable Permits which
are designated in Appendix H as Owner’s responsibility
and other Permits which are not required by Applicable Laws to be
obtained by Contractor or which are typically to be provided by
owners or developers, including but not limited to permits
necessary for the ownership and operation of the
Project.
3.4 Start-up Personnel .
Owner, at its cost, will provide a sufficient number of qualified
operating and maintenance personnel and technicians, consistent
with Contractor’s reasonable requirements as specified in
writing by Contractor, to be trained by Contractor and to assist
Contractor by performing normal operating and maintenance duties in
connection with the start-up of Phase 1 and Phase 2, as applicable,
and the performance of the Commissioning Tests and the Completion
Tests. Contractor shall be responsible for the direction and
supervision of Owner’s operating and maintenance personnel
and technicians during the start-up and testing of Phase 1 and
Phase 2, as applicable, consistent with any applicable collective
bargaining agreements and Facility Site rules and this Contract.
Owner shall be responsible for the training on all Owner Furnished
Equipment; provided that Contractor shall be responsible for
training Owner’s personnel in operation of Phase 1 and Phase
2, as applicable, reflecting the integration of the Owner Furnished
Equipment into the Facility. Owner shall provide the qualified
individuals to work under the Contractor’s management
direction within its start-up organization through Substantial
Completion.
3.5 Start-Up and Testing Fuel
Supply . Owner shall provide Fuel for the Facility in the
quality as specified in Appendix C and quantity required for
construction, startup and testing in support of the Approved
Project Schedule. Such Fuel will be utilized by Contractor to
perform start-up and testing of Phase 1 and Phase 2, as applicable,
in accordance with the Contract Documents.
3.6 Other . Owner shall
provide or cause to be provided at times consistent with the
Approved Project Schedule at no cost to Contractor all raw water to
the relevant Interface Points described in Appendix O, telephone
connections up to a single delivery point at the boundary of the
Facility Site, back-feed power and other power needs for
construction (at 480 Volt and 1,000 kW minimum) start-up and
testing delivered to the Owner side of the relevant Interface Point
in Appendix O (but not including any obligation to provide mobile
or temporary generation facilities on the Contractor side of the
relevant Interface Point described in Appendix O), and Owner shall
be responsible for all gas lines, power lines and other utilities
from and beyond the Owner side of the relevant Interface Points
described in Appendix O.
13
In addition, Owner shall be
responsible for providing space for a lay-down area, temporary
facilities and a parking area within the boundaries of the Facility
Site as further identified in Appendix Q, and the preliminary
design work necessary for applying for permits for the Facility
evaporation pond, as delivered to Contractor on or about
December 19, 2003.
ARTICLE 4
Schedule
4.1 Schedule . Contractor and
Owner will perform their respective responsibilities related to the
Work in accordance with the Approved Project Schedule, as it may be
adjusted in accordance with Article 11, and Owner shall cause each
Owner Critical Schedule Milestone and Contractor shall cause each
Contractor Critical Schedule Milestone, as applicable, to be
achieved on or prior to the applicable Critical Schedule Milestone
date, as those dates may be adjusted in accordance with Article
11.
4.2 Alterations to Schedule .
Contractor shall not, without the prior written consent of Owner
pursuant to Article 11, make any alteration to the Contractor
Critical Schedule Milestones. However, Contractor shall have the
flexibility to re-sequence its construction and other activities as
it sees fit provided that it does not adversely impact the
Guaranteed Substantial Completion Dates, the Owner Critical
Schedule Milestones or the Target Price.
4.3 Revision of Schedule .
Contractor shall notify Owner as soon as possible of any
circumstances of which it becomes aware that might result in the
Contractor Critical Schedule Milestones on the Approved Project
Schedule not being met. If, as a result of Contractor’s
notice or otherwise, Owner determines that Contractor Critical
Schedule Milestones will not be achieved per the Approved Project
Schedule, then Owner may, in its sole discretion, and without
prejudice to any other rights of Owner hereunder: (i) change the
Approved Project Schedule to provide for later completion of such
Contractor Critical Schedule Milestones; or (ii) order Contractor
to provide a schedule recovery plan to show how the impact on the
Guaranteed Substantial Completion Dates can be mitigated. In the
latter case, Contractor shall proceed with diligence to implement
such recovery plan. For the avoidance of doubt, any entitlement to
changes to the Substantial Completion Date and the Target Price
shall be exclusively as set out in Article 11.
Without prejudice to the foregoing,
if the progress of the Work is not proceeding in accordance with
the Contract Documents or the Approved Project Schedule, Owner will
be entitled to make recommendations to Contractor for the purpose
of remedying such deficiencies, which recommendations shall be
incorporated within Contractor’s recovery plan. Contractor
shall use commercially reasonable efforts to maintain and, if
necessary, restore compliance with the Approved Project Schedule
and to meet the Contractor Critical Schedule Milestones, subject to
this Section 4.3.
ARTICLE 5
Inspection and
Approval
5.1 Owner’s Right to Attend
Contractor Inspections . Contractor will notify Owner of any
testing to or inspections of the Work or any portion thereof which
are specifically identified in Appendix Q , including the
Commissioning Tests and the Completion Tests (a) three (3) days in
advance of such testing or inspection, for any testing or
inspection outside the Facility Site, and (b) forty-eight (48)
hours in advance of such testing or inspection for any testing or
inspection at the Facility Site. Owner will have the option of
being present at the inspections and testing on or off the Facility
Site specifically identified in Appendix Q . Owner’s
presence or non-presence at any testing or inspection shall not be
deemed a waiver of any of Contractor’s obligations under this
Contract or be construed as an approval or acceptance of the Work
or any portion thereof.
5.2 Inspection and
Re-Performance . Owner will have the right to access and
inspect the Work wherever located and at any stage of completion.
Owner may reject any Work that does not comply with the Contract
Documents. If Owner’s inspection or any other information
reveals such non-compliance or any other defects in any portion of
Work, then Contractor will promptly correct such defective Work. If
Contractor fails to initiate correction of the defective Work
within fourteen (14) days of its discovery, Owner may, upon seven
(7) days’
14
written notice, correct such
defective Work. Owner’s correction of such defective Work
will not relieve Contractor of its obligations under this Contract.
The incremental costs and expenses related to such actions of Owner
will be deducted from any sums due to Contractor under this
Contract and shall be deducted from the Target Price.
Without prejudice to the foregoing,
if the quality of the Work is not in accordance with the Contract
Documents, Owner will be entitled to make recommendations to
Contractor for the purpose of remedying such
deficiencies.
5.2.1 Cover . Contractor
shall not cover any portion of the Work required to be inspected by
Owner without providing Owner with notice of covering at least
twenty-four (24) hours before such portion of the Work is to be
covered. If any portion of the Work should be covered without
Contractor first providing such notice, it must, if required in
writing by the Owner, at Contractor’s expense and not as a
Direct Cost, be uncovered for observation and shall be recovered.
If Owner does not perform its inspection within two (2) Business
Days after Contractor provided the notice of inspection, Owner
shall waive its right of inspection and Contractor may proceed to
cover the Work.
5.3 Owner Approval . Owner
shall have the right to review and approve those Design Development
Documents and Construction Documents identified in Appendix Q,
together with such other documents as Owner may reasonably specify
from time to time. Before any Work as required or inferred from any
Design Development Document or Construction Documents is commenced,
Contractor will submit such Design Development Document or
Construction Document to Owner for review. Owner shall review and
respond within five (5) Business Days of receipt of such Design
Development Document or Construction Document. Contractor may
proceed with the Work prior to the completion of review by Owner if
Contractor is certain that it is necessary to do so to meet the
Schedule. If Owner does not respond within the five (5) Business
Days, Contractor shall proceed as though the Owner has no comments;
provided, however, that review or failure to review any Design
Development Document or Construction Document by Owner shall not
constitute an admission or agreement by Owner that the Work to be
provided or performed in accordance with such Design Development
Document or Construction Document is approved or is in conformance
with the representations, covenants and warranties of Contractor
under this Contract. Whether or not specified in this Contract,
review, approval or acceptance by Owner or its designee, of all or
any part of the Work, including drawings shall not relieve
Contractor from any obligation under the Contract. Such review
shall not be deemed a waiver by Owner of any claim arising from a
Contractor Event of Default or nonperformance of the Work or any
other obligation of Contractor hereunder. It is the sole
responsibility of Contractor to properly complete the Work and to
provide proper drawings.
ARTICLE 6
Target Price and
Payment
6.1 Target Price . Contractor
shall use its reasonable best efforts to achieve Final Completion
of the Project for an amount at or below the Target Price. The
Target Price shall consist of the Target Cost plus the Contingency.
Except as otherwise provided herein, Owner shall pay Contractor:
(i) the Direct Costs incurred by Contractor in the performance of
the Work; (ii) the Fee; and (iii) such other payments as described
in the Contract.
6.2 Direct Costs .
6.2.1 Subject to Section 6.2.2,
Direct Costs shall mean those costs incurred by Contractor in the
performance of the Work (including such mark-ups and/or multipliers
as the parties have agreed are applicable thereto, as solely and
exclusively set out in Appendix E; but provided always (a)
that nothing in this Contract shall require nor permit the charging
or payment of a multiplier or markup upon a sum that has already
been subject to multiplication or markup, and (b) such multipliers
and markups shall be fixed for the period of the Contract and not
subject to increase or reduction by virtue of Changes, Change
Orders or otherwise) consisting of:
15
|
|
(i)
|
the cost of labor, material and
services for the design, engineering, procurement, construction and
commissioning of the Project (including engineering, fabrication,
services and erection),
|
|
|
(ii)
|
Project management,
planning/scheduling,
|
|
|
(v)
|
charges for engineering and field
non-manual personnel,
|
|
|
(vi)
|
construction supervision
personnel,
|
|
|
(ix)
|
labor attraction
premiums,
|
|
|
(xi)
|
material and equipment
costs,
|
|
|
(xii)
|
equipment rental costs (if equipment
is owned by Contractor, then fair market value),
|
|
|
(xiii)
|
vendor representatives
costs,
|
|
|
(xiv)
|
start-up spare parts, first fills,
consumables,
|
|
|
(xv)
|
start-up and testing material and
services,
|
|
|
(xvii)
|
insurance premiums and associated
deductibles for those insurances placed pursuant to this Contract
as set out in Exhibit F, except, with respect to deductibles, to
the extent that the relevant damage or loss was attributable to
[ * * * ] * or [ * * * ] * ,
including without limitation damage and losses referenced in
Section 3.2.2; provided, however, that to the extent the
relevant deductible is in excess of $ [ * * * ]
* , the amount in excess of $ [ * * * ]
* shall be allowable as a Direct Cost to the
extent that the relevant damage or loss was attributable to [
* * * ] * ,
|
|
|
(xviii)
|
legal fees (including fees of claims
consultants) reasonably and properly incurred with prior written
consent of Owner, such consent not to be unreasonably withheld or
delayed for the purpose of enforcing obligations of Subcontractors,
insurers or third parties in connection with the Project, but
specifically excluding legal fees associated with the negotiations
or any dispute resolution between Owner and Contractor; provided,
however, that if Contractor incurs any such fees without
Owner’s prior written consent, then such fees shall remain
Direct Costs to the extent that [ * * * ]
* has not been exceeded,
|
|
|
(xix)
|
acceleration costs, subject to
Section 6.2.2,
|
|
|
(xx)
|
repair costs during construction,
subject to Section 6.2.2,
|
|
|
(xxii)
|
third-party costs or fees for
incremental or extended warranties obtained at the request of or
with the written consent of Owner to the extent only that such
costs or fees were not otherwise reimbursable under another
provision of this Contract,
|
|
|
(xxiii)
|
freight and transportation
costs,
|
______________
* CONFIDENTIAL PORTION OMITTED AND FILED
SEPARATELY WITH THE SEC.
16
|
|
(xxiv)
|
import duties and fees,
|
|
|
(xxv)
|
bond and other security premiums or
issuance costs (including the Performance Security, not to exceed
[ * * * ]* % per annum), in no event to include any
reimbursement with respect to draws on the principal amounts of
such bond or Performance Security,
|
|
|
(xxvi)
|
third-party license fees,
|
|
|
(xxvii)
|
third-party technology
fees,
|
|
|
(xxviii)
|
currency fluctuation hedging costs,
and
|
|
|
(xxix)
|
quality assurance inspection and
testing costs,
|
together with any costs of the same
or a broadly similar nature; provided, in each and every case with
respect to all of the foregoing that all such costs shall be Direct
Costs only to the extent that such costs are reasonably necessarily
and properly incurred in furtherance of the Project.
6.2.2 Notwithstanding Section
6.2.1 , Direct Costs shall not include the following costs
incurred by Contractor in the performance of the Work, which shall
not be allowed for recovery by Contractor:
|
|
(i)
|
Late Substantial Completion LDs and
Performance LDs;
|
|
|
(ii)
|
costs incurred for repeating,
repairing, rectifying or remediating any part of the Work, to the
extent that the Contractor was entitled to have such repeat,
repair, rectification or remediation conducted or performed without
charge (or is reimbursed for the cost thereof) by or on behalf of a
Subcontractor, except to the extent that, having used commercially
reasonable efforts Contractor fails to recover such costs from such
Subcontractor, in which case to the extent of such non-recovery
only, that amount will, unless disallowed by virtue of another
provision of the Contract, be deemed to constitute Direct Costs
payable by Owner; provided, however, in each case that such costs
are reimbursed to Contractor by Owner as Direct Costs (a)
Contractor shall not waive or compromise in any manner any rights
that Contractor may have against such Subcontractor with regard to
the particular matter, (b) Contractor shall assign to Owner all
such rights Contractor may have against such Subcontractor, and (c)
if and to the extent that Contractor at any time recovers from such
Subcontractor any amounts in regard to such matter, Subcontractor
shall hold in trust for the benefit of Owner such sum(s), shall
promptly notify Owner of the recovery and amount of such sums, and
upon Owner’s request shall transfer to Owner’s account
such sum(s);
|
|
|
(iii)
|
costs greater than $ [ * * * ]
* incurred for repeating, repairing, rectifying
or remediating any part of the Work that has been repeated,
repaired, rectified or re-performed on a previous
occasion;
|
|
|
(iv)
|
costs incurred for repeating,
repairing, rectifying or remediating any part of the Work to the
extent and provided (a) that the cost in question is more than $
[ * * * ] * with respect to each such
instance, and (b) that no such costs will be disallowed until the
aggregate of such costs exceeds $ [ * * * ] ,
* in which event such costs up to $ [ * * * ]
* shall be Direct Costs and the excess
(including costs below $ [ * * * ] ,
* but in each case subject to clause (c))
shall be disallowed and (c) no such cost shall be disallowed with
respect to any such Work if and to the extent that the value cost
or liability thereof is less than $ [ * * * ]
* . For the avoidance of doubt, when determining
whether each or any of the thresholds in this subparagraph (iv)
have been exceeded, the cost in question shall be considered in
isolation without regard to other costs or expenses that are
otherwise reimbursable pursuant to this Contract and without
aggregation with any other unconnected cost;
|
|
|
(v)
|
any damage to or destruction of the
Facility or other real or personal property to the extent covered
by insurance (including Subcontractors’ insurance) or
recovered by Contractor or any Subcontractor from any third
party;
|
______________
*
CONFIDENTIAL PORTION OMITTED
AND FILED SEPARATELY WITH THE SEC.
17
|
|
(vi)
|
any costs that would be included as
Direct Costs, to the extent they are attributable to
Contractor’s Personnel’s gross negligence or willful
misconduct;
|
|
|
(vii)
|
costs of acceleration of the Work,
to the extent that the Contractor was entitled to have such costs
or recovery measures performe
|