Statement of Work #
SBSS Integration
Support
This Statement of Work #
(“SOW”) is made this 22 day of
October 2008 by and between Elektrobit Inc .
(“Elektrobit” or “EB”) and TerreStar
Networks Inc . (“TerreStar” or “TSN”)
for the on-site support of Hughes SBSS Integration activities, and
is governed by the Master Development and Licensing Agreement
between Elektrobit and TerreStar dated August 10, 2007, as
amended (“Agreement”).
This SOW defines the scope of
technical work to be performed by EB for the on-site support of
Hughes Network Systems, LLC (“Hughes”) Satellite Base
Station Subsystem (“SBSS”) Integration
activities.
The main objectives of this SOW
are:
1 - For EB to provide support to
Hughes’ SBSS integration activities at [***] development
laboratory. [***]
[***]
2 - For EB to provide support for
and implementation of the [***]
Additionally, the following
secondary objectives are planned:
[***]
It is expected that this work will
extend for a period of approximately [***] months, starting on or
around October 27, 2008 and ending on or around
[***].
|
|
|
|
SBSS Integration Support SOW
10 September 2008
|
|
Page 1 of 5
|
|
|
|
|
|
Milestones
|
|
Target
Date
|
|
|
[***]
|
|
[***
|
]
|
|
[***]
|
|
[***
|
]
|
|
[***]
|
|
[***
|
]
|
|
[***]
|
|
[***
|
]
|
|
5
|
TerreStar
Furnished Items
|
[***]
[***]
|
|
|
|
SBSS Integration Support SOW
10 September 2008
|
|
Page 2 of 5
|
|
7
|
Project
dependencies and assumptions
|
The following table lists some but
not all of the project dependencies and assumptions. These inputs
will work as enablers for EB work and have an effect on the
schedule, cost and quality of EB Support. Dependencies are
indicated with a D and Assumptions with an A.
|
|
|
|
|
|
|
|
Category
|
|
Description
|
|
1.
|
|
[***]
|
|
[***]
|
|
2.
|
|
[***]
|
|
[***]
|
|
8
|
Place of
Performance and Delivery Terms
|
EB will perform the support work
primarily on [***]. Travel to other domestic locations will be
considered additional expenses and must be pre-approved by
TerreStar.
|
9
|
Acceptance
of Deliverables
|
As set forth in Section 5.1 of
the Agreement, TSN will notify EB of its acceptance or rejection of
the Deliverables within the thirty (30) day Acceptance Period.
See the schedule in Section 4 in this SOW.
Additionally, TerreStar reserves the
right to terminate the SOW at Milestone M1.
This services under this SOW will be
performed on a fixed rate basis including materials, travel and
other expe