Land Consolidation and Development Agreement of the Galaxy Bay ProjectDevelopment Agreement |
|
|
|
You are currently viewing: This Development Agreement involves
GREAT CHINA INTERNATIONAL HOLDINGS, INC. | Shenyang Jitian Property Company Limited | Shengyang Maryland International Industry Company Limited. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here. |
|
|
|
Search Development Agreement by:
Land
Consolidation and Development Agreement of the Galaxy Bay Project
This
agreement is signed among the undersigned on November 16, 2006 in Beijing, the
People’s Republic of China (hereafter called “China”):
Party A: Shenyang Jitian Property Company Limited Registered
Address: No301-8 Shuangyuan Road Dongling District Shenyang Authorized
Representative: Duan Jingshi
Party B: Shengyang Maryland International Industry Company
Limited Registered Address: No.69 Heping North Street, Heping District Shenyang
Authorized Representative: Jiang Fang
Whereas:
|
1. |
Party A is a
legally established operating as a Wholly Owned Foreign Enterprise formed
under the laws of the People’s Republic of China in Shenyang, Liaoning,
PRC. Silverstrand International Holdings Company Limited (hereafter called
“Silverstrand International”) holds 100% of Party A’s
equity interest when this agreement is concluded. In addition, Party B is a
Foreign Funded Enterprises established in China by Silverstrand International. |
|
2. |
On March 20,
2006, the Chessboard Mountain Tourism Development Board of the Shenyang City
Planning and Land Resources Bureau signed a “National Land Use Right
Transfer Contract” (No. 20060003) with Party A. The Bureau approved
Party A to develop a residential project (including commercial development)
with an area of 420,317 m(2) on a piece of land numbered QPS06-001 in the
Chessboard Mountain Development Zone Qianling Community Xiaohenan. The
project is hereinafter referred to the Galaxy Bay Project. |
|
3. |
Upon signing
this agreement, Silverstrand International will sign an Equity Transfer
Agreement – Jitian Property Company Limited (hereafter called the
“Equity Transfer Agreement”) with Beijing Capital Land Limited (
hereafter called “Bj Capital”) and Reco Ziyang Pte Ltd (hereafter
called “ Reco Ziyang”) in which Bj Capital and Reco Ziyang will
purchase respectively 50% of Party A’s equity interest held by
Silverstrand International. Party A will then be changed to a Sino-Foreign
Joint-venture Company(hereafter called the “Joint-venture
Company”). Upon completion of the aforesaid equity transfer, Party A
will be called “Joint-venture Company” in this agreement. Upon
signing the equity transfer agreement, Bj Capital and Reco Ziyang will
increase Party A’s total investment capital from $29,000,000.00 to
$79,000,000.00, and the registered capital from $20,000,000.00 to $ 40,
000,000.00, which Bj Capital and Reco Ziyang shall pay Party A’s
registered capital of $20,000,000.00 respectively. While Silverstrand International
has invested a registered capital of $1,399,970.00 for Party A, Bj Capital
and Reco Ziyang shall invest $19,300,015.00 respectively as the registered
capital to Party A upon the completion of the equity transfer. |
|
4. |
Party B will be
responsible for the land consolidation and development of the Galaxy Bay
Project such as “Three Supplies One Level” and formal
“Seven Supplies One Level” as of the start of the project. As the
principal party for development and construction of the project, the
Joint-venture Company shall pay Party B the corresponding land consolidation
fee. |
|
|
Hereby,
concerning the land consolidation and development of the Galaxy Bay
Project’s construction land use, through negotiation, Party A and Party
B have unanimously come to an agreement with following terms: |
Chapter 1 Outline of
Construction Land Use of the Galaxy Bay Project
|
|
|
|
|
|
|
|
|
|
Location |
Xiaohenan Qianling
Community Chessboard Mountain Tourism Development Zone Shenyang Liaoning |
|
|
Land Purpose |
Residence and commerce |
|
|
Size of Transferred Land |
420,317m2 |
|
|
Years of Land Use Right
Transfer |
Residential land use of 70
years, commercial land use of 40years, counted upon the date of the
conclusion of the national land use right transfer contract about this land |
|
|
Project Name to be
Constructed on the Land |
the Galaxy Bay Project |
|
|
Construction scale of
Project |
Total Size of Floor Area:
893,943.50 m2 |
|
|
|
|
Chapter 2 Obligations of Party
B in the Land Consolidation and Development
|
2.1 |
Party B accepts
the responsibility of urging the Chessboard Mountain Tourism Development
Board of the Shenyang City Planning and Land Resources Bureau to sign the
Supplement Agreement to the National Land Use Right Transfer Contract (No.
20060003, hereinafter called the “Transfer Contract”) with Party
A as of November 30, 2006, in which the following contents should be covered;
that the size of the transferred land of the Galaxy Bay Project is
471,350.21m(2), that the plot ratio is a minimum of 1.7, and that no
additional amount of money will be paid by Party A after its payment in the
sum of RMB 456,043,945.00¥ as the land price for the entire project as
specified in the Confirmation Letter of Auction of the Galaxy Bay Project
land use(document Shen Qi Jiao Zi20061). |
|
2.2 |
Party B
guarantees to be responsible to complete the necessary applications for a new
National Land Use Permit following the increase of land use size for the
Galaxy Bay Project as of December 15, 2006, upon conclusion of the Supplement
Agreement to the Transfer Contract as specified in Clause 2.1 of the
agreement. Party A should pay the remaining unpaid balance of RMB
26,043,945.00¥of the total land price of RMB |
2
|
|
456,043,945.00¥
of the Galaxy Bay Project; Party Party B will be responsible to obtain the
new National Land Use Permit within 3 working days upon the completion of
Party A’s payment in the aforesaid mentioned amount of the unpaid land
price. |
|
2.3 |
Party B accepts
the responsibility for the completion of the planning adjustment procedures
of the Galaxy Bay Project and obtaining the necessary Planning Permit for
Land Use for construction purposes as of November 30, 2006. The specific
adjustment index is as follows: |
|
|
2.3.1 |
The plot ratio
of the Galaxy Bay Project is increased from 1.6 to a 1.7 minimum. |
|
|
2.3.2 |
The floor area
of the Galaxy Bay Project is increased to minimum 801,295.357m2. |
|
2.4 |
Party B accepts
responsibility to insure the construction area of the Galaxy Bay meets the
standard of “Three Supplies One Level” as of November 30, 2006,
pay any corresponding expenses accrued and all necessary equipment, material,
construction and closing fees, etc., to the standard of the aforementioned
“Three Supplies One Level”. Construction refers to: |
|
|
2.4.1 |
Road
Supply:Party B accepts the responsibility to construct and complete a two-way
motorway, accessible within the building line of the Galaxy Bay Project. |
|
|
2.4.2 |
Water
Supply:Party B accepts the responsibility to meet the requirement of a
temporary water supply for the Galaxy Bay Project (with piping a minimum of
50mm in diameter) connecting to the well and water meter within the building
line of the construction area, with complete installment of the water meter,
construction and inspection of the well and all related valves. |
|
|
2.4.3 |
Electricity Supply:
Party B accepts the responsibility to meet the requirement of temporary
electricity supply for the purpose of construction with installment of the
transformer, a low-voltage brake box at the exit port and the necessary outer
lines, as of November 30, 2006. |
|
|
2.4.4 |
Land Level:Party
B accepts the responsibility to demolish the necessary buildings, remove
and/or dismantle the aerial circuitries, remove or cut down the necessary
trees needed to complete the construction area of the Galaxy Bay. The clearing
the construction site of all above and below ground debris, waste materials,
toxins etc. Party A will not be held responsible for the theft of sand from
the construction site.M |
|
2.5 |
Party B accepts
responsibility to insure that the construction area of the Galaxy Bay Project
meet the standards set forth in the “Seven Supplies One Level” as
of November 30, 2007, and pay any of the necessary, corresponding fees
(except Party C’s proportion specified in Clause 2.5 of the agreement)
accrued, such as; finance fees, equipment and material fees, construction
fees and closing fees, etc.. The standard of the aforementioned “Seven
Supplies One Level” refers to: |
3
|
|
2.5.1 |
Road Supply:
Party B accepts responsibility to pave the road outside of the building line
of the Galaxy Bay Project to meet the requirements of the Shenyang City Urban
Planning Commission. |
|
|
2.5.2 |
Communication,
CATV and ADSL Supplies: Party B accepts the responsibility to bury and pave
cables to the nearest connecting point within the building line of the Galaxy
Bay Project and complete the construction of all necessary connections. |
|
|
2.5.3 |
Water Supply:
Party B accepts the responsibility to connect the water-supply piping to the
general valve well, complete the installment of the valve, overseeing the
completion of the well thus insuring the water supply. The construction
standard and water-supply capacity of the aforementioned water-supply piping
and well should be in accordance with the design specifications and
corresponding provisions of the State as well as Shenyang City. |
|
|
2.5.4 |
Gas Supply:
Party B accepts the responsibility to connect the gas-supply piping to the
pressure-adjustment station within the building line of the Galaxy Bay
Project, and complete the construction and inspection, thus insuring that it
is safe and in working order. Party A is to prepay the gas finance fee of RMB
1,600¥ for each household. The construction standard and gas-supply
capacity of the aforementioned gas-supply piping and pressure-adjustment station
should be in accordance with the design specifications and corresponding
provisions of the State and Shenyang City. |
|
|
2.5.5 |
Sewerage
Discharge Supply: Party B accepts the responsibility to connect the
sewerage-discharge piping to the necessary facility within the building line
of the Galaxy Bay Project, complete the construction and inspection of the
facility and provide facilities for sewerage discharge in accordance with the
project scale. The construction standard and sewerage-discharge capacity of the
aforementioned sewerage-discharge pipe and checking well should be in
accordance with the design specifications and corresponding provisions of the
State and Shenynag City. Party B also guarantees to coordinate with relevant
government administration bureaus not to construct any sewage discharge
facility to the south of the Newly Developed River or to the east of the
Dongli Road. |
|
|
2.5.6 |
Heat: Supply:
Party B accepts the responsibility to connect the heat-supply pipeline to the
heat-transformer station within the building line of the Galaxy Bay Project,
complete the construction and inspection of the station and procedures
associated with heat supply. Party A will pay the related heat-supply fee of
a maximum RMB 70¥ per m2 of the floor area. The construction standard and
heat-supply capacity of the aforementioned heat-supply pipeline and
heat-transformer station should be in accordance with the design
specifications and corresponding provisions of the State and Shenyang City. |
|
|
2.5.7
|