LUMP SUM DESIGN-BUILD
AGREEMENT
CARDINAL ETHANOL, LLC (“
OWNER ”)
FAGEN, INC. (“
DESIGN-BUILDER ”)
*
Portions omitted pursuant to a request for confidential
treatment and filed separately with the SEC.
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
Article 1 Definitions; Rules of
Interpretation
|
|
|
1
|
|
|
|
|
|
|
|
|
|
|
|
|
Rules of
Construction
|
|
|
1
|
|
|
|
|
Defined
Terms
|
|
|
2
|
|
|
|
|
|
|
|
|
|
|
Article 2 The Project
|
|
|
6
|
|
|
|
|
|
|
|
|
|
|
|
|
Services to be
Performed
|
|
|
6
|
|
|
|
|
Extent of
Agreement
|
|
|
6
|
|
|
|
|
Conflicting
Provisions
|
|
|
7
|
|
|
|
|
|
|
|
|
|
|
Article 3 Design-Builder
Responsibilities
|
|
|
7
|
|
|
|
|
|
|
|
|
|
|
|
|
Design-Builder’s Services in
General
|
|
|
7
|
|
|
|
|
Design
Development and Services
|
|
|
8
|
|
|
|
|
Standard of
Care
|
|
|
8
|
|
|
|
|
Government
Approvals and Permits
|
|
|
9
|
|
|
|
|
Subcontractors
|
|
|
9
|
|
|
|
|
Maintenance of
Site
|
|
|
9
|
|
|
|
|
Project
Safety
|
|
|
10
|
|
|
|
|
Submission of
Reports
|
|
|
10
|
|
|
|
|
Training
|
|
|
10
|
|
|
|
|
|
|
|
|
|
|
Article 4 Owner’s
Responsibilities
|
|
|
11
|
|
|
|
|
|
|
|
|
|
|
|
|
Duty to
Cooperate
|
|
|
11
|
|
|
|
|
Furnishing of
Services and Information
|
|
|
11
|
|
|
|
|
Financial
Information; Cooperation with Lenders; Failure to Obtain Financial
Closing
|
|
|
12
|
|
|
|
|
Owner’s
Representative
|
|
|
12
|
|
|
|
|
Government
Approvals and Permits
|
|
|
12
|
|
|
|
|
Owner’s
Separate Contractors
|
|
|
13
|
|
|
|
|
Security
|
|
|
13
|
|
|
|
|
|
|
|
|
|
|
Article 5 Ownership of Work Product; Risk
of Loss
|
|
|
13
|
|
|
|
|
|
|
|
|
|
|
|
|
Work
Product
|
|
|
13
|
|
|
|
|
Owner’s
Limited License Upon Payment in Full
|
|
|
13
|
|
|
|
|
Owner’s
Limited License Upon Owner’s Termination for Convenience or
Design-Builder’s Election to Terminate
|
|
|
14
|
|
|
|
|
Owner’s
Limited License Upon Design-Builder’s Default
|
|
|
14
|
|
|
|
|
Owner’s
Indemnification for Use of Work Product
|
|
|
15
|
|
|
|
|
Risk of
Loss
|
|
|
15
|
|
|
|
|
|
|
|
|
|
|
Article 6 Commencement and Completion of
the Project
|
|
|
15
|
|
|
|
|
|
|
|
|
|
|
|
|
Phase I and
Phase II Engineering
|
|
|
15
|
|
|
|
|
Notice to
Proceed; Commencement
|
|
|
15
|
|
|
|
|
Project
Start-Up and Testing
|
|
|
16
|
|
Table of Contents
(continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
Substantial
Completion
|
|
|
17
|
|
|
|
|
Final
Completion
|
|
|
18
|
|
|
|
|
Post Completion
Support
|
|
|
19
|
|
|
|
|
|
|
|
|
|
|
Article 7 Performance Testing and
Liquidated Damages
|
|
|
19
|
|
|
|
|
|
|
|
|
|
|
|
|
Performance
Guarantee
|
|
|
19
|
|
|
|
|
Performance
Testing
|
|
|
19
|
|
|
|
|
Liquidated
Damages
|
|
|
20
|
|
|
|
|
Bonds and Other
Performance Security
|
|
|
21
|
|
|
|
|
|
|
|
|
|
|
Article 8 Warranties
|
|
|
22
|
|
|
|
|
|
|
|
|
|
|
|
|
Design-Builder
Warranty
|
|
|
22
|
|
|
|
|
Correction of
Defective Work
|
|
|
22
|
|
|
|
|
Warranty Period
Not Limitation to Owner’s Rights
|
|
|
23
|
|
|
|
|
|
|
|
|
|
|
Article 9 Contract Price
|
|
|
23
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract
Price
|
|
|
23
|
|
|
|
|
Effect of
Construction Cost Index Increase on Contract Price
|
|
|
24
|
|
|
|
|
|
|
|
|
|
|
Article 10 Payment
Procedures
|
|
|
24
|
|
|
|
|
|
|
|
|
|
|
|
|
Payment at
Financial Closing
|
|
|
24
|
|
|
|
|
Progress
Payments
|
|
|
24
|
|
|
|
|
Final
Payment
|
|
|
25
|
|
|
|
|
Failure to Pay
Amounts Due
|
|
|
26
|
|
|
|
|
Design-Builder’s Payment
Obligations
|
|
|
26
|
|
|
|
|
Record Keeping
and Finance Controls
|
|
|
26
|
|
|
|
|
|
|
|
|
|
|
Article 11 Hazardous Conditions and
Differing Site Conditions
|
|
|
26
|
|
|
|
|
|
|
|
|
|
|
|
|
Hazardous
Conditions
|
|
|
26
|
|
|
|
|
Differing Site
Conditions; Inspection
|
|
|
27
|
|
|
|
|
|
|
|
|
|
|
Article 12 Force Majeure; Change in Legal
Requirements
|
|
|
28
|
|
|
|
|
|
|
|
|
|
|
|
|
Force Majeure
Event
|
|
|
28
|
|
|
|
|
Effect of Force
Majeure Event
|
|
|
28
|
|
|
|
|
Change in Legal
Requirements
|
|
|
29
|
|
|
|
|
Time Impact And
Availability
|
|
|
29
|
|
|
|
|
Effect of
Industry-Wide Disruption on Contract Price
|
|
|
29
|
|
|
|
|
|
|
|
|
|
|
Article 13 Changes to the Contract Price
and Scheduled Completion Dates
|
|
|
30
|
|
|
|
|
|
|
|
|
|
|
|
|
Change
Orders
|
|
|
30
|
|
|
|
|
Contract Price
Adjustments
|
|
|
30
|
|
|
|
|
Emergencies
|
|
|
31
|
|
|
|
|
Failure to
Complete Owner’s Milestones
|
|
|
31
|
|
|
|
|
|
|
|
|
|
|
Article 14 Indemnity
|
|
|
31
|
|
|
|
|
|
|
|
|
|
|
|
|
Tax Claim
Indemnification
|
|
|
31
|
|
|
|
|
Payment Claim
Indemnification
|
|
|
31
|
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
Table of Contents
(continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
Design-Builder’s General
Indemnification
|
|
|
32
|
|
|
|
|
Owner’s
General Indemnification
|
|
|
32
|
|
|
|
|
Patent and
Copyright Infringement
|
|
|
33
|
|
|
|
|
|
|
|
|
|
|
Article 15 Stop Work; Termination for
Cause
|
|
|
34
|
|
|
|
|
|
|
|
|
|
|
|
|
Owner’s
Right to Stop Work
|
|
|
34
|
|
|
|
|
Owner’s
Right to Perform and Terminate for Cause
|
|
|
34
|
|
|
|
|
Owner’s
Right to Terminate for Convenience
|
|
|
35
|
|
|
|
|
Design-Builder’s Right to Stop
Work
|
|
|
36
|
|
|
|
|
Design-Builder’s Right to Terminate for
Cause
|
|
|
36
|
|
|
|
|
Bankruptcy of
Owner or Design-Builder
|
|
|
37
|
|
|
|
|
Lenders’
Right to Cure
|
|
|
37
|
|
|
|
|
|
|
|
|
|
|
Article 16 Representatives of the
Parties
|
|
|
37
|
|
|
|
|
|
|
|
|
|
|
|
|
Designation of
Owner’s Representatives
|
|
|
37
|
|
|
|
|
Designation of
Design-Builder’s Representatives
|
|
|
38
|
|
|
|
|
|
|
|
|
|
|
Article 17 Insurance
|
|
|
39
|
|
|
|
|
|
|
|
|
|
|
|
|
Insurance
|
|
|
39
|
|
|
|
|
Design-Builder’s Insurance
Requirements
|
|
|
39
|
|
|
|
|
Owner’s
Liability Insurance
|
|
|
40
|
|
|
|
|
Owner’s
Property Insurance
|
|
|
41
|
|
|
|
|
|
|
|
|
|
|
Article 18 Representations and
Warranties
|
|
|
42
|
|
|
|
|
|
|
|
|
|
|
|
|
Design-Builder
and Owner Representations and Warranties
|
|
|
42
|
|
|
|
|
Design-Builder
Representations and Warranties
|
|
|
43
|
|
|
|
|
|
|
|
|
|
|
Article 19 Dispute
Resolution
|
|
|
43
|
|
|
|
|
|
|
|
|
|
|
|
|
Dispute
Avoidance and Mediation
|
|
|
43
|
|
|
|
|
Arbitration
|
|
|
43
|
|
|
|
|
Duty to
Continue Performance
|
|
|
44
|
|
|
|
|
No
Consequential Damages
|
|
|
44
|
|
|
|
|
Limitation of
Liability
|
|
|
44
|
|
|
|
|
|
|
|
|
|
|
Article 20 Confidentiality of Shared
Information
|
|
|
45
|
|
|
|
|
|
|
|
|
|
|
|
|
Non-Disclosure
Obligation
|
|
|
45
|
|
|
|
|
Publicity and
Advertising
|
|
|
46
|
|
|
|
|
Term of
Obligation
|
|
|
46
|
|
|
|
|
|
|
|
|
|
|
Article 21 Miscellaneous
|
|
|
46
|
|
|
|
|
|
|
|
|
|
|
|
|
Assignment
|
|
|
46
|
|
|
|
|
Successors
|
|
|
47
|
|
|
|
|
Governing
Law
|
|
|
47
|
|
|
|
|
Severability
|
|
|
47
|
|
|
|
|
No
Waiver
|
|
|
47
|
|
|
|
|
Headings
|
|
|
47
|
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
Table of Contents
(continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
Notice
|
|
|
47
|
|
|
|
|
No Privity with
Design Consultant/Subcontractors
|
|
|
48
|
|
|
|
|
Amendments
|
|
|
48
|
|
|
|
|
Entire
Agreement
|
|
|
49
|
|
|
|
|
Third-Party
Beneficiaries
|
|
|
49
|
|
|
|
|
Counterparts
|
|
|
49
|
|
|
|
|
Survival
|
|
|
49
|
|
|
|
|
|
|
|
EXHIBIT A Performance Guarantee
Criteria
|
|
|
A-1
|
|
|
|
|
|
|
|
EXHIBIT B General Project Scope
|
|
|
B-1
|
|
|
|
|
|
|
|
EXHIBIT C Owner’s
Responsibilities
|
|
|
C-1
|
|
|
|
|
|
|
|
EXHIBIT D ICM License Agreement
|
|
|
D-1
|
|
|
|
|
|
|
|
EXHIBIT E Schedule of Values
|
|
|
E-1
|
|
|
|
|
|
|
|
EXHIBIT F Form of Informational
Report
|
|
|
F-1
|
|
|
|
|
|
|
|
EXHIBIT G Required Permits
|
|
|
G-1
|
|
|
|
|
|
|
|
EXHIBIT H Form of Performance
Bond
|
|
|
H-1
|
|
|
|
|
|
|
|
EXHIBIT I Form of Payment Bond
|
|
|
I-1
|
|
|
|
|
|
|
|
EXHIBIT J Draw (Payment)
Schedule
|
|
|
J-1
|
|
|
|
|
|
|
|
EXHIBIT K Air Emissions Application or
Permit
|
|
|
K-1
|
|
|
|
|
|
|
|
EXHIBIT L Phase I and Phase II Engineering
Services Agreement
|
|
|
L-1
|
|
|
|
|
|
|
|
EXHIBIT M Form of Application for
Payment
|
|
|
M-1
|
|
|
|
|
|
|
|
EXHIBIT N Form of Lien Waiver
|
|
|
N-1
|
|
|
|
|
|
|
|
EXHIBIT O Form of Consent to
Assignment
|
|
|
O-1
|
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
LUMP SUM DESIGN-BUILD
CONTRACT
This
LUMP SUM DESIGN-BUILD CONTRACT (the “ Agreement
”) is made as of December 14, 2006, (the “
Effective Date ”) by and between Cardinal Ethanol,
LLC, an Indiana limited liability company (the “ Owner
”) and Fagen, Inc., a Minnesota corporation (the “
Design-Builder ”) (each a “ Party ”
and collectively, the “ Parties ”).
A. The
Owner desires to develop, construct, own and operate a one hundred
(100) million gallons per year (“ MGY ”)
natural gas-fired dry grind ethanol production facility located at
Winchester, Indiana (the “ Plant ”);
and
B. Design-Builder
desires to provide design, engineering, procurement and
construction services for the Plant.
NOW,
THEREFORE, in consideration of the mutual covenants and obligations
contained herein and for other good and valuable consideration,
Owner and Design-Builder agree as follows.
Definitions; Rules of
Interpretation
1.1 Rules of
Construction. The capitalized terms listed in this Article
shall have the meanings set forth herein whenever the terms appear
in this Agreement, whether in the singular or the plural or in the
present or past tense. Other terms used in this Agreement but not
listed in this Article shall have meanings as commonly used in the
English language and, where applicable, in generally accepted
construction and design-build standards of the fuel ethanol
industry in the Midwest United States. Words not otherwise defined
herein that have well known and generally accepted technical or
trade meanings are used herein in accordance with such recognized
meanings. In addition, the following rules of interpretation shall
apply:
|
|
(a)
|
|
The
masculine shall include the feminine and neuter.
|
|
|
|
|
|
|
|
(b)
|
|
References to
“Articles,” “Sections,”
“Schedules,” or “Exhibits” shall be to
Articles, Sections, Schedules or Exhibits of this
Agreement.
|
|
|
|
|
|
|
|
(c)
|
|
This Agreement was negotiated and
prepared by each of the Parties with the advice and participation
of counsel. The Parties have agreed to the wording of this
Agreement and none of the provisions hereof shall be construed
against one Party on the ground that such Party is the author of
this Agreement or any part hereof.
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
1.2 Defined
Terms. In addition to definitions appearing elsewhere in this
Agreement, the following terms have the following
meanings:
AAA is
defined in Section 19.1.
Agreement is defined in the Preamble.
Air
Emissions Tester means a
third party entity engaged by Owner meeting all required state and
federal requirements for such testing entities, to conduct air
emissions testing of the Plant in accordance with
Exhibit A.
|
|
(a)
|
|
any
and all laws, legislation, statutes, codes, acts, rules,
regulations, ordinances, treaties or other similar legal
requirements enacted, issued or promulgated by a Governmental
Authority;
|
|
|
|
|
|
|
|
(b)
|
|
any
and all orders, judgments, writs, decrees, injunctions,
Governmental Approvals or other decisions of a Governmental
Authority; and
|
|
|
|
|
|
|
|
(c)
|
|
any
and all legally binding announcements, directives or published
practices or interpretations, regarding any of the foregoing in
(a) or (b) of this definition, enacted, issued or
promulgated by a Governmental Authority;
|
to the extent,
for each of the foregoing in (a), (b) and (c) of this
definition, applicable to or binding upon (i) a Party, its
affiliates, its shareholders, its members, its partners or their
respective representatives, to the extent any such person is
engaged in activities related to the Project; or (ii) the
property of a Party, its affiliates, its shareholders, its members,
its partners or their respective representatives, to the extent
such property is used in connection with the Project or an activity
related to the Project.
Application
for Payment is defined in
Section 10.2.1.
As Built
Plans is defined in
Section 5.2.
Bankrupt
Party is defined in
Section 15.6.1.
Baseline
Index is defined in
Section 9.2.1.
Change
Order is defined in
Section 13.1.1.
CCI is
defined in Section 9.2.
Certificate
of Substantial Completion is defined in Section 6.4.3.
Confidential
Information is defined in
Section 20.1.
Construction
Documents is defined in
Section 3.2.1.
Contract
Documents is defined in
Section 2.2.
Contract
Price is defined in
Section 9.1.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
2
Contract
Time(s) means scheduled
dates provided for in the Contract Documents including Scheduled
Substantial Completion Date and Final Completion Date.
Damages is defined in Section 14.3.1.
Day or
Days shall mean calendar days unless otherwise specifically
noted in the Contract Documents.
Design-Builder is defined in the Preamble.
Design-Builder’s Representative
is defined in
Section 16.2.
Design-Builder’s Senior
Representative is defined
in Section 16.2.
Design
Consultant is a
qualified, licensed design professional that is not an employee of
Design-Builder, but is retained by Design-Builder, or employed or
retained by anyone under contract with Design-Builder or
Subcontractor, to furnish design services required under the
Contract Documents.
Differing
Site Conditions is
defined in Section 11.2.1.
Early
Completion Bonus is
defined in Section 6.4.4.
Effective
Date is defined in the
Preamble.
Fagen
Engineering is defined in
Section 6.1.
Final
Application for Payment is defined in Section 10.3.
Final
Completion is defined in
Section 6.5.2.
Final
Completion Date is
defined in Section 6.5.1.
Final
Payment is defined in
Section 10.3.
Financial
Closing means the
execution of the Financing Documents by all the parties
thereto.
Financing
Documents means the final
loan documents with the Lender or Lenders providing financing for
the construction or term financing of the Plant and any and all
agreements necessary to demonstrate a binding commitment of Owner
or Lenders to fund the construction of the Plant.
Force
Majeure Event is defined
in Section 12.1.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
3
Governmental
Approvals are any
material authorizations or permissions issued or granted by any
Governmental Authority to the Project, its Owner, the
Design-Builder, Subcontractors and their affiliates in connection
with any activity related to the Project.
Governmental
Authority means any
federal, state, local or municipal governmental body; any
governmental, quasi-governmental, regulatory or administrative
agency, commission, body or other authority exercising or entitled
to exercise any administrative, executive, judicial, legislative,
policy, regulatory or taxing authority or power; or any court or
governmental tribunal; in each case having jurisdiction over the
Owner, the Design-Builder, the Project, or the Site.
Hazardous
Conditions are any
materials, wastes, substances and chemicals deemed to be hazardous
under applicable Legal Requirements, or the handling, storage,
remediation, or disposal of which are regulated by applicable Legal
Requirements.
ICM means ICM, Inc., a Kansas
corporation.
ICM License
Agreement means the
license agreement to be executed between Owner and ICM, Inc.,
substantially in the form attached hereto as
Exhibit D.
Indemnified
Parties is defined in
Section 5.2.
Independent
Engineer means
Owner’s and Lenders’ independent engineer.
Industry-Wide Disruption is defined in Section 12.4.
Informational Report is defined in Section 3.8.
Legal
Requirements or
Laws are all applicable federal, state and local statutes,
laws, codes, ordinances, rules, regulations, judicial decisions,
orders, decrees, plans, injunctions, permits, tariffs, governmental
agreements and governmental restrictions, whether now or hereafter
in effect, of any government or quasi-government entity having
jurisdiction over the Project or Site, the practices involved in
the Project or Site, or any Work, including any consensus standards
for materials, products, systems, and services established by ASTM
International, any successor organization thereto, or any
Governmental Authority.
Lenders means the lenders that are party to the
Financing Documents.
Lenders’ Agent means an agent or agents acting on behalf of the
Lenders.
Manufacturer’s Warranty
shall mean a warranty provided by
the original manufacturer or vendor of equipment used by
Design-Builder in the Plant.
MGY is
defined in the Recitals.
Notice to
Proceed is defined in
Section 6.2.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
4
Operating
Procedures means, without
limitation, the process equipment and specifications manuals,
standards of quality, service protocols, data collection methods,
construction specifications, training methods, engineering
standards and any other information prescribed by Design-Builder
and ICM from time to time concerning the ownership, operation,
maintenance and repair of the Plant, subject to the limitations
provided in the Agreement and in the ICM License
Agreement.
Owner is defined in the Preamble.
Owner
Indemnified Parties is
defined in Section 14.3.1.
Owner’s Milestones is defined in Section 13.4.
Owner’s Operator means the entity that Owner identifies, upon
written notice to Design-Builder, as operator of the Project or any
other entity that Owner chooses, upon notice to Design-Builder, to
replace such entity as operator of the Project.
Owner’s Representative
is defined in
Section 16.1.
Owner’s Senior Representative
is defined in
Section 16.1.
Party or
Parties is defined in the
Preamble.
Pass Through
Warranties mean any
warranties provided to Design-Builder by a Subcontractor which are
assigned to Owner.
Pay
Period means, with
respect to a given Application for Payment, the one (1) month
period following the last day of the previous Pay Period to which
the immediately prior Application for Payment is applied; provided
that the initial Pay Period shall commence on the date of delivery
of the Notice to Proceed and end on the twenty-fourth (24
th ) day of the calendar month during which the
Notice to Proceed is issued.
Payment
Bond is defined in
Section 7.4.2.
Performance
Bond is defined in
Section 7.4.1.
Performance
Guarantee Criteria means
the criteria listed in Exhibit A.
Performance
Tests is defined in
Section 7.2.1.
Phase
I is defined in
Exhibit L.
Phase I and
Phase II Engineering Services Agreement is defined in Section 6.1.
Phase
II is defined in
Exhibit L.
Plant is defined in the Recitals.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
5
Project is defined in Section 2.1.
Punch
List is defined in
Section 6.4.3.
Qualified
Independent Expert means
an expert retained by Owner and approved by Design-Builder pursuant
to Section 11.1.2.
Safety
Representative is defined
in Section 3.7.1.
Schedule of
Values is defined in
Section 10.2.5.
Scheduled
Substantial Completion Date is defined in Section 6.4.1.
Site is the land or premises on which the Project is
located.
Subcontractor is any person or entity retained by
Design-Builder, or by any person or entity retained directly or
indirectly by Design-Builder, in each case as an independent
contractor to perform a portion of the Work, and shall include
materialmen and suppliers.
Substantial
Completion is defined in
Section 6.4.2.
Work is defined in Section 3.1.
Work
Product is defined in
Section 5.1.
2.1 Services
to be Performed.
Pursuant to this Agreement,
Design-Builder shall perform all work and services in connection
with the engineering, design, procurement, construction startup,
testing and training for the operation and maintenance of the
Plant, and provide all material, equipment, tools and labor
necessary to complete the Plant in accordance with the terms of
this Agreement. The Plant, together with all equipment, labor,
services and materials furnished hereunder is defined as the
“ Project .”
2.2 Extent of
Agreement. This Agreement consists of the following documents,
and all exhibits, schedules, appendices and attachments hereto and
thereto (collectively, the “ Contract Documents
”):
2.2.1 All written modifications, amendments and change
orders to this Agreement.
2.2.2 This Agreement, including all exhibits and
attachments, executed by Owner and Design-Builder, including those
below:
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
6
|
|
|
|
|
|
|
Performance
Guarantee Criteria
|
|
|
|
General Project
Scope
|
|
|
|
Owner’s
Responsibilities
|
|
|
|
ICM License
Agreement
|
|
|
|
Schedule of
Values
|
|
|
|
Form of
Informational Report
|
|
|
|
Required
Permits
|
|
|
|
Form of
Performance Bond
|
|
|
|
Form of Payment
Bond
|
|
|
|
Draw (Payment)
Schedule
|
|
|
|
Air Emissions
Application or Permit
|
|
|
|
Phase I and
Phase II Engineering Services Agreement
|
|
|
|
Form of
Application for Payment
|
|
|
|
Form of Lien
Waiver
|
|
|
|
Form of Consent
to Assignment
|
2.2.3 Construction Documents to be prepared by
Design-Builder pursuant to Section 3.2.1 shall be incorporated
in this Agreement.
2.3
Conflicting Provisions. In the event of any conflict or
inconsistency between the body of this Agreement and any Exhibit or
Schedule hereto, the terms and provisions of this Agreement, as
amended from time to time, shall prevail and be given priority.
Subject to the foregoing, the several documents and instruments
forming part of this Agreement are to be taken as mutually
explanatory of one another and in the case of ambiguities or
discrepancies within or between such parts the same shall be
explained and interpreted, if possible, in a manner which gives
effect to each part and which avoids or minimizes conflicts among
such parts. No oral representations or other agreements have been
made by the Parties except as specifically stated in the Contract
Documents.
Design-Builder
Responsibilities
3.1
Design-Builder’s Services in General. Except for services
and information to be provided by Owner and specifically set forth
in Article 4 and Exhibit C, Design-Builder shall perform
or cause to be performed all design, engineering, procurement,
construction services, supervision, labor, inspection, testing,
start-up, material, equipment, machinery, temporary utilities and
other temporary facilities to complete construction of the Project
consistent with the Contract Documents (the “ Work
”). All design and engineering and construction services and
other Work of the Design-Builder shall be performed in accordance
with, and upon completion the Plant shall comply with (i) the
general project scope guidelines set forth in Exhibit B,
(ii) the Construction Documents, (iii) all Legal
Requirements, and (iv) generally accepted construction and
design-build standards of the fuel ethanol industry in the United
States during the relevant time period. Any design and engineering
or other professional service to be performed pursuant to this
Agreement, which under Applicable Law must be performed by licensed
personnel, shall be performed by licensed personnel as required by
Law. The enumeration of specific duties and
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
7
obligations to
be performed by the Design-Builder under the Contract Documents
shall not be construed to limit in any way the general undertakings
of the Design-Builder as set forth herein. Design-Builder’s
Representative shall be reasonably available to Owner and shall
have the necessary expertise and experience required to supervise
the Work. Design-Builder’s Representative shall communicate
regularly with Owner and shall be vested with the authority to act
on behalf of Design-Builder.
3.2 Design
Development and Services.
3.2.1 Where required by Law, Design-Builder shall provide
through qualified, licensed design professionals employed by
Design-Builder, or procured from qualified, independent licensed
Design Consultants, the necessary design services, including
architectural, engineering and other design professional services,
for the preparation of the required drawings, specifications and
other design submittals required to permit construction of the Work
in accordance with this Agreement (such drawings, specifications
and design submittals collectively, the “ Construction
Documents ”). To the extent not prohibited by Legal
Requirements, Design-Builder may prepare Construction Documents for
a portion of the Work to permit construction to proceed on that
portion of the Work prior to completion of the Construction
Documents for the entire Work.
3.2.2 Construction of the Plant shall be consistent with the
Construction Documents.
3.2.3 Design-Builder shall maintain a current, complete set
of drawings and specifications at the Site. Owner shall have the
right to review such drawings and specifications. Owner and
Independent Engineer may not make copies of the available drawings
and specifications without Design-Builder’s written
permission, and, granted such permission, may only do so to the
extent such drawings and specifications directly pertain to the
Plant; provided however that, pursuant to Section 5.1 of this
Agreement, Design-Builder retains ownership of and property
interests in any drawing or specifications made available and/or
copied.
3.2.4 Except as provided elsewhere in this Agreement, it is
understood and agreed that review, comment and/or approval by Owner
(or its designees) or Independent Engineer of any documents or
submittals that Design-Builder is required to submit to Owner (or
its designees) or Independent Engineer hereunder for their review,
comment and/or approval (including without limitation the
Construction Documents pursuant to Sections 3.2.1 and 3.2.3
hereof) shall not relieve or release Design-Builder from any of its
duties, obligations or liabilities provided for under the terms of
this Agreement or transfer any design liability from Design-Builder
to Owner.
3.3 Standard
of Care. All services performed by the Design-Builder and its
Subcontractors pursuant to the Construction Documents shall be
performed in accordance with the standard of care and skill
generally accepted in the fuel ethanol industry in the Midwest
United States during the relevant time period or in accordance with
any of the practices, methods and acts that in the exercise of
reasonable judgment in light of the facts known at the time the
decision was made, could have been expected to accomplish the
desired result at a reasonable cost consistent with good business
practices, safety and expedition. This standard of care is not
intended to be limited to the optimum practice, method or act to
the exclusion of all others, but
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
8
rather to be
acceptable practices, methods or acts generally accepted in the
construction and design-build standards of the fuel ethanol
industry in the Midwest United States. Design-Builder and its
Subcontractors shall perform all construction activities
efficiently and with the requisite expertise, skill, competence,
resources and care to satisfy the requirements of the Contract
Documents and all applicable Legal Requirements. Design-Builder
shall at all times exercise complete and exclusive control over the
means, methods, sequences and techniques of
construction.
3.4 Government
Approvals and Permits. Except as identified in Exhibit C
and, with respect to items identified as Owner’s
responsibility, in Exhibit G (which items shall be obtained by
Owner pursuant to Section 4.5), Design-Builder shall obtain
and pay for all necessary permits, approvals, licenses, government
charges and inspection fees required for the prosecution of the
Work by any government or quasi-government entity having
jurisdiction over the Project. Design-Builder shall provide
reasonable assistance to Owner in obtaining those permits,
approvals and licenses that are Owner’s
responsibility.
3.5.1 Design-Builder may subcontract portions of the Work in
accordance with the terms hereof. Any subcontractor employed by
Design-Builder shall be licensed and qualified to perform the Work
consistent with the Contract Documents.
3.5.2 Design-Builder assumes responsibility to Owner for the
proper performance of the Work of Subcontractors and any acts and
omissions in connection with such performance. Nothing in the
Contract Documents is intended or deemed to create any legal or
contractual relationship between Owner and any Subcontractor,
including but not limited to any third-party beneficiary
rights.
3.5.3 Design-Builder shall coordinate the activities of all
of Design-Builder’s Subcontractors. If Owner performs other
work on the Project or at the Site with separate contractors under
Owner’s control, Design-Builder agrees to reasonably
cooperate and coordinate its activities with those separate
contractors so that the Project can be completed in an orderly and
coordinated manner without unreasonable disruption.
3.5.4 Design-Builder shall ensure that each subcontract with
a Subcontractor is assignable to Owner without consent of the
Subcontractor or any other person or entity in the event that
Design-Builder shall be in an uncured default or terminated with
cause under the terms of this Agreement.
3.6
Maintenance of Site. Design-Builder shall keep the Site
reasonably free from debris, trash and construction wastes to
permit Design-Builder to perform its construction services
efficiently, safely and without interfering with the use of
adjacent land areas. Upon Substantial Completion of the Work
Design-Builder shall remove all debris, trash, construction wastes,
materials, equipment, machinery and tools arising from the Work to
permit Owner to occupy the Project for its intended use.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
9
3.7.1 Design-Builder recognizes the importance of performing
the Work in a safe manner so as to prevent damage, injury or loss
to (i) any individuals at the Site, whether working or
visiting, (ii) the Work, including materials and equipment
incorporated into the Work or stored on-Site or off-Site, and
(iii) any other property at the Site or adjacent thereto.
Design-Builder assumes responsibility for implementing and
monitoring all safety precautions and programs related to the
performance of the Work. Design-Builder shall, prior to commencing
construction, designate a representative (the “ Safety
Representative ”) with the necessary qualifications and
experience to supervise the implementation and monitoring of all
safety precautions and programs related to the Work. Unless
otherwise required by the Contract Documents,
Design-Builder’s Safety Representative shall be an individual
stationed at the Site who may have responsibilities on the Project
in addition to safety. The Safety Representative shall make routine
daily inspections of the Site and shall hold weekly safety meetings
with Design-Builder’s personnel, Subcontractors and others as
applicable.
3.7.2 Design-Builder and Subcontractors shall comply with
all Legal Requirements relating to safety, as well as any
Owner-specific safety requirements set forth in the Contract
Documents; provided, that such Owner-specific requirements do not
violate any applicable Legal Requirement. As promptly as
practicable, Design-Builder will report in writing any
safety-related injury, loss, damage or accident arising from the
Work to Owner’s Representative and, to the extent mandated by
Legal Requirements, to all government or quasi-government
authorities having jurisdiction over safety-related matters
involving the Project or the Work.
3.7.3 Design-Builder’s responsibility for safety under
this Section 3.7 is not intended in any way to relieve
Subcontractors of their own contractual and legal obligations and
responsibility for (i) complying with all Legal Requirements,
including those related to health and safety matters, and
(ii) taking all necessary measures to implement and monitor
all safety precautions and programs to guard against injury,
losses, damages or accidents resulting from their performance of
the Work.
3.8 Submission
of Reports. Design-Builder shall provide Owner with a monthly
informational report substantially in the form of Exhibit F
attached hereto (“ Informational Report
”).
3.9
Training. At a mutually agreed time prior to start-up,
Design-Builder shall provide up to two (2) weeks of training
at a facility designated by ICM for all of Owner’s employees
and Owner Operator’s employees required for the operation and
maintenance of the Plant in accordance with all design
specifications therefor contained in the Contract Documents and
necessary in order to maintain the Performance Guarantee Criteria,
including operators, laboratory personnel, general, plant and
maintenance managers. Other personnel of Owner and Owner Operator
may receive such training by separate arrangement between Owner and
Design-Builder and as time is available. All training personnel and
costs associated with such training personnel, including labor and
all training materials will be provided to Owner and Owner Operator
within the Contract Price at no additional cost. Owner and Owner
Operator will be responsible for all travel and expenses of their
employees and the Owner and Owner Operator will pay all wages and
all other expenses for their personnel during the training. The
training
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
10
services will
include training on computers, laboratory procedures, field
operating procedures, and overall plant section performance
expectations. Prior to the start-up training, Design-Builder shall
provide Owner training manuals and operating manuals and other
documents reasonably necessary for the start-up process.
4.1.1 Owner shall, throughout the performance of the Work,
cooperate with Design-Builder and perform its responsibilities,
obligations and services in a timely manner to facilitate
Design-Builder’s timely and efficient performance of the Work
and so as not to delay or interfere with Design-Builder’s
performance of its obligations under the Contract
Documents.
4.1.2 Owner shall pay all reasonable costs incurred by
Design-Builder for frost removal so that winter construction can
proceed. Such costs may include, but are not limited to, equipment
costs, equipment rental costs, sheltering costs, special material
costs, fuel costs and associated labor costs. Owner acknowledges
and agrees that such costs are in addition to, and not included in,
the Contract Price, and that the payment of such costs, which shall
be billed on a weekly basis, shall not require the issuance of a
Change Order or the obtaining of any Owner approval prior to the
issuance of invoices for such costs.
4.2 Furnishing
of Services and Information.
4.2.1 Prior to the issuance of the Notice to Proceed, at its
own cost and expense, Owner shall provide the following items to
Design-Builder for Design-Builder’s information and use and
all of which Design-Builder is entitled to rely upon in performing
the Work:
|
|
(a)
|
|
surveys describing the property,
boundaries, topography and reference points for use during
construction, including existing service and utility
lines;
|
|
|
|
|
|
|
|
(b)
|
|
geotechnical studies describing
subsurface conditions including soil borings, and other surveys
describing other latent or concealed physical conditions at the
Site;
|
|
|
|
|
|
|
|
(c)
|
|
temporary and permanent easements,
zoning and other requirements and encumbrances affecting land use,
or necessary to permit the proper design and construction of the
Project and enable Design-Builder to perform the Work;
|
|
|
|
|
|
|
|
(d)
|
|
A
legal description of the Site;
|
|
|
|
|
|
|
|
(e)
|
|
to
the extent available, as-built and record drawings of any existing
structures at the Site; and
|
|
|
|
|
|
|
|
(f)
|
|
all
environmental studies, reports and impact statements describing the
environmental conditions, including Hazardous Conditions, in
existence at the Site that have been conducted or
performed.
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
11
4.2.2 Owner shall provide to Design-Builder all
Owner’s deliverables under Exhibit C pursuant to
Owner’s Milestones. Such deliverables shall be provided, at
Owner’s own cost and expense, for Design-Builder’s
information and use. Design-Builder is entitled to rely upon such
deliverables in performing the Work.
4.2.3 Owner is responsible for securing and executing all
necessary agreements with adjacent land or property owners that are
necessary to enable Design-Builder to perform the Work and that
have been identified and notified in writing by Design-Builder to
Owner prior to the Effective Date. Owner is further responsible for
all costs, including attorneys’ fees, incurred in securing
these necessary agreements.
4.3 Financial
Information; Cooperation with Lenders; Failure to Obtain Financial
Closing. Design-Builder acknowledges that Owner is seeking
financing for the Project. Design-Builder agrees to cooperate with
Owner in good faith in order to satisfy the reasonable requirements
of Owners’ financing arrangements, including, where
appropriate and reasonable, the execution and delivery of documents
or instruments necessary to accommodate the Financial Closing.
Owner agrees to pay all documented costs incurred by Design-Builder
incurred prior to and at Financial Closing, and thereafter during
the term of this Agreement, in connection with satisfying the
requirements of Owners’ financing arrangements including all
documented attorney’s fees. Design-Builder and Owner also
acknowledge that the Lenders, as a condition to providing financing
for the Plant, shall require Owner to provide the Independent
Engineer with certain reasonable participation and review rights
with respect to Design-Builder’s performance of the Work.
Design-Builder acknowledges and agrees that such reasonable
participation and review rights shall consist of the right to
(i) enter the Site and inspect the Work upon reasonable notice
to Design-Builder; (ii) attend all start-up and testing
procedures; and (iii) review and approve such other items for
which Owner is required by Lenders to obtain the concurrence,
opinion or a certificate of the Independent Engineer or the Lenders
pursuant to the Financing Documents which items do not alter the
rights or impose additional obligations on Design-Builder. Nothing
in this Section 4.3 shall be deemed to require Design-Builder
to agree to any amendments to this Agreement that would adversely
affect Design-Builder’s risks, rights or obligations under
this Agreement. Upon Financial Closing, Owner shall promptly
provide to Design-Builder an officer’s certificate certifying
that Financial Closing has occurred and such Owner’s
officer’s certificate shall constitute evidence satisfactory
to Design-Builder that Owner has adequate funds available and
committed to fulfill its obligations under the Contract Documents
for all purposes hereunder. Owner must provide such officer’s
certificate prior to issuing the Notice to Proceed.
4.4
Owner’s Representative. Owner’s Representative, as
set forth in Section 16.1 hereof, shall be responsible for
providing Owner-supplied information and approvals in a timely
manner to permit Design-Builder to fulfill its obligations under
the Contract Documents. Owner’s Representative shall also
provide Design-Builder with prompt notice if it observes any
failure on the part of Design-Builder to fulfill its contractual
obligations, including any errors, omissions or defects in the
performance of the Work. Owner’s Representative shall be
vested with the authority to act on behalf of Owner and
Design-Builder shall be entitled to rely on written communication
from Owner’s Representative with respect to a Project
matter.
4.5 Government
Approvals and Permits. Owner shall obtain and pay for all
necessary Governmental Approvals required by Law, including
permits, approvals, licenses,
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
12
government
charges and inspection fees set forth in Exhibit C and, to the
extent identified as Owner’s responsibility, Exhibit G.
Owner shall provide reasonable assistance to Design-Builder in
obtaining those permits, approvals and licenses that are
Design-Builder’s responsibility pursuant to Exhibit G
and Section 3.4.
4.6
Owner’s Separate Contractors. Owner is responsible for
all work, including such work listed on Exhibit C, performed
on the Project or at the Site by separate contractors under
Owner’s control. Owner shall contractually require its
separate contractors to cooperate with, and coordinate their
activities so as not to interfere with, Design-Builder in order to
enable Design-Builder to timely complete the Work consistent with
the Contract Documents.
4.7
Security. Owner shall be responsible for Site security
(including fencing, alarm systems, security guarding services and
the like) at all times during the term of this Agreement to prevent
vandalism, theft and danger to the Project, the Site, and
personnel. Owner shall coordinate and supervise ingress and egress
from the Site so as to minimize disruption to the Work.
Ownership of Work Product; Risk
of Loss
5.1 Work
Product. All drawings, specifications, calculations, data,
notes and other materials and documents, including electronic data
furnished by Design-Builder to Owner under this Agreement (“
Work Product ”) shall be instruments of service and
Design-Builder shall retain the ownership and property interests
therein, including the copyrights thereto.
5.2
Owner’s Limited License Upon Payment in Full. Upon
Owner’s payment in full for all Work performed under the
Contract Documents, Design-Builder shall grant Owner a limited
license to use the Work Product in connection with Owner’s
occupancy, operation, maintenance and repair of the Plant.
Design-Builder acknowledges and agrees that the limited license to
use the Work Product granted hereby shall provide Owner sufficient
rights in and to the Work Product as shall be necessary for Owner
to operate and maintain the Plant and shall include any Pass
Through Warranties in connection therewith. Design-Builder shall
provide Owner with a copy of the plans of the Plant, as built, (the
“ As Built Plans ”) conditioned on Owner’s
express understanding that its use of the Work Product and its
acceptance of the As Built Plans is at Owner’s sole risk and
without liability or legal exposure to Design-Builder or anyone
working by or through Design-Builder, including Design Consultants
of any tier (collectively the “ Indemnified Parties
”); provided, however, that any warranties (of equipment or
otherwise) shall remain in effect according to the terms of this
Agreement.
5.2.1 Design-Builder is utilizing certain proprietary
property and information of ICM in the design and construction of
the Project and Design-Builder may incorporate proprietary property
and information of ICM into the Work Product. Owner’s use of
the proprietary property and information of ICM shall be governed
by the terms and provisions of the ICM License Agreement, to be
executed by Owner and ICM in connection with the execution of this
Agreement. Owner shall be entitled to use the Work Product solely
for
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
13
purposes
relating to the Plant, but shall not be entitled to use the Work
Product for any other purposes whatsoever, including without
limitation, expansion of the Plant. Notwithstanding the foregoing
sentence, Owner shall be entitled to use the Work Product for the
operation, maintenance and repair of the plant including the
interconnection of, but not the design of, any future expansions to
the Plant. The limited license granted to Owner under Sections 5.2,
5.3 or 5.4 to use the Work Product shall be limited by and
construed according to the same terms contained in the ICM License
Agreement, attached hereto as Exhibit D and incorporated
herein by reference thereto, except (i) references in such ICM
License Agreement to ICM and Proprietary Property shall refer to
Design-Builder and Work Product, respectively, (ii) the Laws
of the State of Minnesota shall govern such limited license, and
(iii) the dispute resolution provisions contained in
Article 19 hereof shall apply to any breach or threatened
breach of Owner’s duties or obligations under such limited
license, except that Design-Builder shall have the right to seek
injunctive relief in a court of competent jurisdiction against
Owner or its Representatives for any such breach or threatened
breach. This paragraph also applies to Sections 5.3 and 5.4
below.
5.3
Owner’s Limited License Upon Owner’s Termination for
Convenience or Design-Builder’s Election to Terminate. If
Owner terminates the Project for its convenience as set forth in
Section 15.3 hereof, or if Design-Builder elects to terminate
this Agreement in accordance with Section 15.5, Design-Builder
shall, upon Owner’s payment in full of the amounts due
Design-Builder under this Agreement, grant Owner a limited license
to use the Work Product to complete the Plant and subsequently
occupy, operate, maintain and repair the Plant, subject to the
following:
|
|
(a)
|
|
Use
of the Work Product is at Owner’s sole risk without liability
or legal exposure to any Indemnified Party; provided, however, that
any Pass Through Warranties regarding equipment or express
warranties regarding equipment provided by this Agreement shall
remain in effect according to their terms; and
|
|
|
|
|
|
|
|
(b)
|
|
If
the termination for convenience is by Owner in accordance with
Section 15.3 hereof, or if Design-Builder elects to terminate
this Agreement in accordance with Section 15.5, then Owner
agrees to pay Design-Builder the additional sum of Two Million Five
Hundred Thousand Dollars ($2,500,000.00) as compensation for the
limited right to use the Work Product completed “as is”
on the date of termination in accordance with this
Article 5.
|
5.4
Owner’s Limited License Upon Design-Builder’s
Default. If this Agreement is terminated due to
Design-Builder’s default pursuant to Section 15.2 and
(i) it is adjudged that Design-Builder was in default, and
(ii) Owner has fully satisfied all of its obligations under
the Contract Documents through the time of Design-Builder’s
default, then Design-Builder shall grant Owner a limited license to
use the Work Product in connection with Owner’s completion
and occupancy, operation, maintenance and repair of the Plant. This
limited license is conditioned on Owner’s express agreement
that its use of the Work Product is at Owner’s sole risk
without liability or legal exposure to any Indemnified Party;
provided, however, that any Pass Through Warranties regarding
equipment or express warranties regarding equipment provided by
this Agreement shall remain in effect according to their terms.
This limited license grants Owner the ability to repair the Plant
at Owner’s discretion.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
14
5.5
Owner’s Indemnification for Use of Work Product. If Owner
uses the Work Product or Plant under any of the circumstances
identified in this Article 5, to the fullest extent allowed by
Law, Owner shall defend, indemnify and hold harmless the
Indemnified Parties from and against any and all claims, damages,
liabilities, losses and expenses, including attorneys’ fees,
arising out of or resulting from the use of the Work Product and
Plant; provided, however, that any Pass Through Warranties
regarding equipment or express warranties regarding equipment
provided by this Agreement shall remain in effect according to
their terms.
5.6 Risk of
Loss. Design-Builder shall have no liability for a physical
loss of or damage to the Work unless such loss or damage is caused
by the willful misconduct or the negligence of Design-Builder or
someone acting under its direction or control. Design-Builder shall
not be liable for physical loss of or damage to the Work where such
loss or damage is caused by the willful misconduct or the
negligence of Owner’s employees or third parties who are not
Subcontractors. Design-Builder shall have no liability for a
physical loss of or damage to the Work occurring after Final
Completion. Design-Builder shall have no liability for losses or
damages for which insurance coverage under this Agreement is
available to Owner; in such circumstances, any liability for losses
and damages as described in this Section 5.6 shall be limited
to losses or damages which exceed insurance coverage available to
the Owner without the application of any reductions from such
coverages due to deductible, retention, or retrospective
premiums.
Commencement and Completion of
the Project
6.1 Phase I
and Phase II Engineering. Owner has entered into a Phase I and
Phase II Engineering Services Agreement dated December 13,
2005 between Owner and Fagen Engineering, LLC (“ Fagen
Engineering ”) which is attached hereto as Exhibit L
(“ Phase I and Phase II Engineering Services Agreement
”). The Phase I and Phase II Engineering Services Agreement
provides for Fagen Engineering to commence work on the Phase I and
Phase II engineering for the Project as set forth therein. Owner
has agreed to pay Fagen Engineering Ninety-two Thousand Five
Hundred Dollars ($92,500.00) for such engineering services pursuant
to the terms of that agreement, the full amount of which shall be
included in and credited to the Contract Price. Notwithstanding the
foregoing sentence, if a Notice to Proceed is not issued pursuant
to Section 6.2, or Financial Closing is not obtained pursuant
to Section 4.3, then no amount paid under the Phase I and
Phase II Engineering Services Agreement shall be refunded to
Owner.
6.2 Notice to
Proceed; Commencement. The Work shall commence within five
(5) Days of Design-Builder’s receipt of Owner’s
written valid notice to proceed (“ Notice to Proceed
”) unless the Parties mutually agree otherwise in writing.
The Parties agree that a valid Owner’s Notice to Proceed
cannot be given until: (1) Owner has title to the real estate
on which the Project will be constructed; (2) the Phase I and
Phase II Site work required of Owner, as described in
Exhibit L is sufficiently completed, at Design-Builder’s
reasonable determination, so as to permit Design-Builder to
commence construction along with redline drawings and such Phase I
and Phase II Site work and redline drawings have been reviewed by
Owner and deemed adequate by Design-Builder; (3) the air
permit(s) and/or other applicable local, state or
federal
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
15
permits
necessary so that construction can begin, as listed on
Exhibit G, have been obtained; (4) Owner has obtained
Financial Closing pursuant to Section 4.3; (5) if
applicable, Owner has executed a sales tax exemption certificate
and provided the same to Design-Builder; (6) Owner has
provided the name of its property/all-risk insurance carrier and
the specific requirements for fire protection; (7) Owner has
provided an insurance certificate or copy of insurance policy
demonstrating that Owner has obtained builder’s risk
insurance pursuant to Section 17.4.3 hereof, and
(8) Design-Builder provides Owner written notification of its
acceptance of the Notice to Proceed, provided that Design-Builder
shall not be required to accept the Notice to Proceed prior to
April 30, 2007. Owner and Design-Builder mutually agree that
time is of the essence with respect to the dates and times set
forth in the Contract Documents. Owner must complete the
prerequisites to the issuance of a valid Notice to Proceed, as
listed in items number (1) through (7) of this
Section 6.2 and submit a Notice to Proceed to Design-Builder
for Design-Builder’s acceptance by April 30, 2007;
otherwise, this Agreement may be terminated, at
Design-Builder’s sole option. If Design-Builder chooses to
terminate this Agreement pursuant to its right under the
immediately preceding sentence, then Design-Builder shall have no
further obligations hereunder.
6.2.1 Notice to Proceed shall be delivered by Owner to
Design-Builder pursuant to the notice requirements set forth in
Section 21.7 hereof, with a copy to:
Fagen, Inc.
501 W. Highway 212
P. O. Box 159
Granite Falls, MN 56241
Attention: Becky Dahl
Fax: (320) 564-5190
Within five
(5) days of receipt by Design-Builder of the notice provided
hereunder, Design-Builder shall deliver to Owner notice of either
acceptance or rejection of the notice including the reasons for
rejection, if applicable.
6.3 Project
Start-Up and Testing. Owner shall provide, at Owner’s
cost, equipment, tools, instruments and materials necessary for
Owner to comply with its obligations under Exhibit C, raw
materials, consumables and personnel necessary for start-up and
testing of the Plant, and Design-Builder shall provide supervision,
standard and special test instruments, tools, equipment and
materials required to perform component and equipment checkout and
testing, initial start-up, operations supervision and corrective
maintenance of all permanent Plant equipment within the scope of
the Work. Notwithstanding the foregoing sentence, Design-Builder
shall be responsible for raw materials and consumables to the
extent such amounts provided by Owner are destroyed or damaged (as
opposed to consumed in the ordinary course of start-up and testing)
by Design-Builder or its personnel during start-up and testing.
Design-Builder shall supervise and direct Owner’s employees
and Owner Operator’s personnel who shall participate in the
start-up activities with Design-Builder’s personnel to become
familiar with all aspects of the Plant. Owner and the Independent
Engineer may witness start-up and testing activities. Performance
testing will be conducted in accordance with the provisions of
Section 7.2 hereof.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
16
6.4
Substantial Completion.
6.4.1 Substantial Completion of the entire Work shall be
achieved no later than five hundred forty-five (545) Days
after the date of the Notice to Proceed, subject to adjustment in
accordance with the Contract Documents hereof (the “
Scheduled Substantial Completion Date ”).
6.4.2 “ Substantial Completion ” shall be
deemed to occur on the date on which the Work is sufficiently
complete so that Owner can occupy and use the Plant for its
intended purposes. Substantial Completion shall be attained at the
point in time when the Plant is ready to grind the first batch of
corn and begin operation for its intended use. No production is
guaranteed on the date of Substantial Completion.
6.4.3 Procedures . Design-Builder shall notify Owner in
writing when it believes Substantial Completion has been achieved
with respect to the Work. Within five (5) Days of
Owner’s receipt of Design-Builder’s notice, Owner and
Design-Builder will jointly inspect such Work to verify that it is
substantially complete in accordance with the requirements of the
Contract Documents. If such Work is deemed substantially complete,
Design-Builder shall prepare and issue a “ Certificate of
Substantial Completion ” for the Work that will set forth
(i) the date of Substantial Completion, (ii) the
remaining items of Work that have to be completed before Final
Payment (“ Punch List ”), (iii) provisions
(to the extent not already provided in this Agreement) establishing
Owner’s and Design-Builder’s responsibility for the
Project’s security, maintenance, utilities and insurance
pending Final Payment, and (iv) an acknowledgment that
warranties with respect to the Work commence on the date of
Substantial Completion, except as may otherwise be noted in the
Certificate of Substantial Completion. Upon Substantial Completion
of the entire Work and satisfaction of the Performance Guarantee
Criteria listed in Exhibit A, Owner shall release to
Design-Builder all retained amounts, less an amount equal to one
hundred and fifty percent (150%) of the reasonable value of all
remaining or incomplete items of Work as noted in the Certificate
of Substantial Completion, and less an amount equal to the value of
any Subcontractor lien waivers not yet obtained.
6.4.4 Early Completion Bonus . If Substantial Completion is
attained within five hundred forty-five (545) Days after the
date of the Notice to Proceed, Owner shall pay Design-Builder at
the time of Final Payment under Section 10.3 hereof an early
completion bonus (“ Early Completion Bonus
”) of Ten Thousand Dollars ($10,000.00) per Day for each Day
that Substantial Completion occurred in advance of said five
hundred forty-five (545) Days, provided however, that such
Early Completion Bonus shall be capped at and shall not exceed One
Million Dollars ($1,000,000).
6.4.5 In all events, payment of said bonus, if applicable,
at the time of Final Payment is subject to release of funds by
senior lender. If senior lender does not allow release of funds at
the time of Final Payment to pay said early completion bonus in
full, any unpaid balance shall be converted to an unsecured
promissory note payable by Owner to Design-Builder, accruing
interest at Ten Percent (10%) per annum. On each anniversary of the
note, any unpaid accrued interest shall be converted to principal
and shall accrue interest as principal thereafter. Owner shall pay
said promissory note as soon as allowed by senior lender; in any
event, the note, plus accrued interest, shall be paid in full
before Owner pays or makes any distributions to or for
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
17
the benefit of
its owners (shareholders, members, partners, etc.). All payments
shall be applied first to accrued interest and then to
principal.
6.5.1 Final Completion of the Work shall be achieved within
ninety (90) Days after the earlier of the actual date of
Substantial Completion or the Scheduled Substantial Completion Date
(the “ Final Completion Date ”).
6.5.2 “ Final Completion ” shall be
achieved when the Owner reasonably determines that the following
conditions have been met:
|
|
(a)
|
|
Substantial Completion has been
achieved;
|
|
|
|
|
|
|
|
(b)
|
|
any
outstanding amounts owed by Design-Builder to Owner have been paid
in full;
|
|
|
|
|
|
|
|
(c)
|
|
the
items identified on the Punch List have been completed by
Design-Builder;
|
|
|
|
|
|
|
|
(d)
|
|
clean-up of the Site has been
completed;
|
|
|
|
|
|
|
|
(e)
|
|
all
permits required to have been obtained by Design-Builder have been
obtained;
|
|
|
|
|
|
|
|
(f)
|
|
the
information in Section 6.5.4 has been provided to
Owner;
|
|
|
|
|
|
|
|
(g)
|
|
release and waiver of all claims and
liens from Design-Builder and Subcontractors have been provided;
and
|
|
|
|
|
|
|
|
(h)
|
|
the
Performance Tests have been successfully completed.
|
6.5.3 After receipt of a Final Application for Payment from
Design-Builder, Owner shall make Final Payment in accordance with
Section 10.3, less an amount equal to the value of any
Subcontractor lien waivers not yet obtained.
6.5.4 At the time of submission of its Final Application for
Payment, Design-Builder shall provide the following
information:
|
|
(a)
|
|
an
affidavit that there are no claims, obligations or liens
outstanding or unsatisfied for labor, services, material,
equipment, taxes or other items performed, furnished or incurred
for or in connection with the Work which will in any way affect
Owner’s interests;
|
|
|
|
|
|
|
|
(b)
|
|
a
general release executed by Design-Builder waiving, upon receipt of
final payment by Design-Builder, all claims for payment, additional
compensation, or damages for delay, except those previously made to
Owner in writing and remaining unsettled at the time of Final
Payment provided such general release shall not waive defenses to
claims that may be asserted by Owner after payment or claims
arising after payment;
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
18
|
|
(c)
|
|
consent of Design-Builder’s
surety, if any, to Final Payment; and
|
|
|
|
|
|
|
|
(d)
|
|
a
hard copy of the As Built Plans; provided, however, that such plans
will remain the Work Product of the Design-Builder and subject in
all respects to Article 5.
|
6.5.5 Upon making Final Payment, Owner waives all claims
against Design-Builder except claims relating to
(i) Design-Builder’s failure to satisfy its payment
obligations, (ii) Design-Builder’s failure to complete
the Work consistent with the Contract Documents, including defects
appearing within one (1) year after Substantial Completion,
and (iii) the terms of any warranties required by the Contract
Documents.
6.6 Post
Completion Support. Adequate personnel to complete all Work
within the Contract Time(s) will be maintained on-Site by
Design-Builder or a Subcontractor until Final Completion has been
achieved. In addition to prosecuting the Work until Final
Completion has been achieved, Design-Builder or its Subcontractor
will provide one (1) month of on-Site operational support for
Owner’s and Owner Operator’s personnel after successful
completion of the Performance Tests and, from the date of
Substantial Completion, will provide six (6) months of
off-Site technical and operating procedure support by telephone and
other electronic data transmission and communication.
Performance Testing and
Liquidated Damages
7.1
Performance Guarantee. The Design-Builder guarantees that the
Plant will meet the performance criteria listed in Exhibit A
(the “ Performance Guarantee Criteria ”) during
a performance test conducted and concluded pursuant to the terms
hereof not later than ninety (90) Days after the date of
Substantial Completion. If there is a performance shortfall,
Design-Builder will pay all design and construction costs
associated with making the necessary corrections. Design-Builder
retains the right to use its sole discretion in determining the
method (which shall be in accordance with generally accepted
construction and design-build standards of the fuel ethanol
industry in the Midwest United States) to remedy any performance
related issues.
7.2.1 The Design-Builder shall direct and supervise the
tests and, if necessary, the retests of the Plant using
Design-Builder’s supervisory personnel and the Air Emissions
Tester shall conduct the air emissions test, in each case, in
accordance with the testing procedures set forth in Exhibit A
(the “ Performance Tests ”), to demonstrate, at
a minimum, compliance with the Performance Guarantee Criteria.
Owner is responsible for obtaining Air Emissions Tester and for
ensuring Air Emissions Tester’s timely performance.
Design-Builder shall cooperate with the Air Emissions Tester to
facilitate performance of all air emissions tests. Design-Builder
shall not be held responsible for the actions of Owner’s
employees and third parties involved in the Performance Testing,
including but not limited to Air Emissions Tester.
7.2.2 No later than thirty (30) Days prior to the
earlier of the Scheduled Substantial Completion Date or Substantial
Completion, Design-Builder shall provide to Owner
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
19
for review a
detailed testing plan for the Performance Tests (other than for air
emissions). Owner and Design-Builder shall agree upon a testing
plan that shall be consistent with the Performance Test Protocol
contained in Exhibit A hereto. After such agreement has been
reached, Design-Builder shall notify the Owner five
(5) business days prior to the date Design-Builder intends to
commence the Performance Tests and shall notify the Owner upon
commencement of the Performance Tests. Owner and Independent
Engineer each have the right to witness all testing, including the
Performance Tests and any equipment testing, whether at the Site or
at the Subcontractor’s or equipment supplier’s premises
during the course of this Agreement. Notwithstanding the foregoing
sentence, Owner shall bear the costs of providing a witness to any
such testing and all such witnesses shall comply at all times with
Design-Builder’s, Subcontractor’s or equipment
supplier’s safety and security procedures and other
reasonable requirements, and otherwise conduct themselves in a
manner that does not interfere with Design-Builder’s,
Subcontractor’s or equipment supplier’s activities or
operations.
7.2.3 Design-Builder shall provide to Owner a Performance
Test report (excluding results from air emissions testing),
including all applicable test data, calculations and certificates
indicating the results of the Performance Tests and, within five
(5) business days of Owner’s receipt of such results,
Owner, Independent Engineer and Design-Builder will jointly inspect
such Work and review the results of the Performance Tests to verify
that the Performance Guarantee Criteria have been met. If Owner or
Independent Engineer reasonably determines that the Performance
Guarantee Criteria have not been met, Owner shall notify
Design-Builder the reasons why Owner determined that the
Performance Guarantee Criteria have not been met and Design-Builder
shall promptly take such action or perform such additional work as
will achieve the Performance Guarantee Criteria and shall issue to
the Owner another notice in accordance with Section 7.2.2;
provided however that if the notice relates to a retest, the notice
may be provided no less than two (2) business days prior to the
Performance Tests. Such procedure shall be repeated as necessary
until Owner and Independent Engineer verifies that the Performance
Guarantee Criteria have been met.
7.2.4 If Owner, for whatever reason, prevents Design-Builder
from demonstrating the Performance Guarantee Criteria within thirty
(30) Days of Design-Builder’s notice that the Plant is
ready for Performance Testing, then Design-Builder shall be excused
from demonstrating compliance with the Performance Guarantee
Criteria during such period of time that Design-Builder is
prevented from demonstrating compliance with the Performance
Guarantee Criteria; provided however that Design-Builder will be
deemed to have fulfilled all of its obligations to demonstrate that
the Plant meets the Performance Guarantee Criteria should such
period of time during which Design-Builder is prevented from
demonstrating the Performance Criteria exceed thirty (30) Days
or extend beyond the Final Completion Date.
7.3.1 Design-Builder understands that if Final Completion is
not attained by the Final Completion Date, Owner will suffer
damages which are difficult to determine and accurately specify.
Design-Builder agrees that if Final Completion is not attained by
the end of the Final Completion Date, Design-Builder shall pay
Owner Ten Thousand Dollars ($10,000.00) as liquidated damages, and
not as a penalty, for each Day that Final Completion extends beyond
the Final Completion Date. Owner, at its discretion, may elect to
offset any such liquidated damages from any retainage. Liquidated
damages shall be paid by Design-Builder by the
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
20
fifteenth
(15 th
) Day of the month following the
month in which the liquidated damages were incurred. The liquidated
damages provided herein shall be in lieu of all liability for any
and all extra costs, losses, loss of profits, expenses, claims,
penalties and any other damages, whether special or consequential,
and of whatsoever nature incurred by Owner which are occasioned
solely by any delay in achieving Final Completion.
7.3.2 Maximum Liquidated Damages. Design-Builder’s
liability for liquidated damages under Section 7.3.1 shall be
capped at and shall not exceed One Million Dollars
($1,000,000).
7.3.3 The liquidated damages provided herein shall be in
lieu of all liability for any and all extra costs, losses, loss of
profits, expenses, claims, penalties and any other damages, whether
special or consequential, and of whatsoever nature incurred by
Owner which arise solely due to a delay in achieving Final
Completion by the Final Completion Date; provided that such
liquidated damages shall not in any way detract from or limit
Owner’s remedies or Design-Builder’s liabilities in
connection with any default by Design-Builder under
Section 15.2 hereof.
7.3.4 Design-Builder shall not be liable for liquidated
damages during any period of time for which an extension of the
Scheduled Substantial Completion Date and/or Final Completion Date
is available pursuant to Article 12.
7.4 Bonds and
Other Performance Security.
7.4.1 On or prior to the date of Financial Closing, if
requested by Owner, the Design-Builder shall deliver to Owner a
bond substantially in the form attached as Exhibit H (the
“ Performance Bond ”) in an initial amount
equivalent to the Contract Price. Owner shall pay on the date of
Financial Closing all costs of obtaining such bond, plus pay
Design-Builder a fee of seven and one half percent (7.5%) for
obtaining such bond, such fee to be calculated by multiplying seven
and one half percent (7.5%) times the cost of the Performance Bond.
Any amounts payable to the surety due to Design-Builder’s
default under this Agreement or the Performance Bond shall be for
the account of Design-Builder.
|
|
(a)
|
|
Design-Builder shall post additional
bonds or security (which must be in form and substance satisfactory
to Owner and the Lenders) or shall increase the amount of the
Performance Bond by the amount of any increases to the Contract
Price; provided, however, that Owner shall pay all costs of
obtaining such bonds or security, plus pay Design-Builder a fee of
seven and one half percent (7.5%) for obtaining such bonds or
security, such fee to be calculated by multiplying seven and one
half percent (7.5%) times the cost of the bonds or
security.
|
|
|
|
|
|
|
|
(b)
|
|
The
Performance Bond shall secure the Design-Builder’s
obligations to complete the Work in accordance with this
Agreement.
|
7.4.2 On or prior to the date of Financial Closing, if
requested by Owner, the Design-Builder shall deliver to Owner a
bond substantially in the form attached as Exhibit I (the
“ Payment Bond ”) in an initial amount
equivalent to the Contract Price. Owner shall pay on the date of
Financial Closing all costs of obtaining such bond, plus pay
Design-Builder a fee of seven and one half percent (7.5%) for
obtaining such bond, such fee to be calculated by
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
21
multiplying
seven and one half percent (7.5%) times the cost of the Payment
Bond but any amounts payable to the surety due to
Design-Builder’s default under this Agreement or the Payment
Bond shall be for the account of Design-Builder.
|
|
(a)
|
|
Design-Builder shall post additional
bonds or security (which must be in form and substance reasonably
satisfactory to Owner and the Lenders) or shall increase the amount
of the Payment Bond by the amount of any increase to the Contract
Price.
|
|
|
|
|
|
|
|
(b)
|
|
The
Payment Bond shall secure the Design-Builder’s obligations to
pay its Subcontractors, vendors and suppliers.
|
|
|
|
|
|
|
|
(c)
|
|
The
Payment Bond shall provide the conditions upon which
Subcontractors, vendors and suppliers may draw upon such Payment
Bond following Design-Builder’s failure to pay amounts due
such Subcontractors, vendors and suppliers.
|
8.1
Design-Builder Warranty. Design-Builder warrants to Owner that
the construction, including all materials and equipment furnished
as part of the construction, shall be new, of good quality, in
conformance with the Contract Documents and all Legal Requirements,
free of defects in materials and workmanship.
Design-Builder’s warranty obligation excludes defects caused
by abuse, alterations, or failure to maintain the Work by persons
other than Design-Builder or anyone for whose acts Design-Builder
may be liable. Nothing in this warranty is intended to limit any
Manufacturer’s Warranty which provides Owner with greater
warranty rights than set forth in this Section 8.1 or the
Contract Documents. Design-Builder will provide to Owner all
manufacturers’ and Subcontractors’ warranties upon the
earlier of Substantial Completion or termination of this Agreement.
Owner’s failure to comply with all Operating Procedures shall
void those guarantees, representations and warranties, whether
expressed or implied, that were given by Design-Builder to Owner,
concerning the performance of the Plant that are reasonably
determined by Design-Builder to be affected by such failure. If
Design-Builder reasonably determines that all damage caused by such
failure can be repaired and Owner makes all repairs needed to
correct such damage, as reasonably determined by Design-Builder,
all guarantees, representations and warranties shall be reinstated
for the remaining term thereof, if any, from the date of the
repair.
8.2 Correction
of Defective Work.
8.2.1 Design-Builder agrees to correct any Work that is
found to not be in conformance with the Contract Documents,
including that part of the Work subject to Section 8.1, within
a period of one (1) year from the date of Substantial
Completion of the Work; provided that Owner must report such
non-conformance within seven (7) days of the appearance of
such failure or non-conformance and that such one (1)-year period
shall be extended one (1) Day for any part of the Work that is
found to be not in conformance with the Contract Documents for each
Day that such part of the Work is not operating in conformity with
the Contract Documents, including any time during which any part of
the Work is repaired or replaced pursuant to this
Article 8.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
22
8.2.2 Design-Builder shall, within seven (7) Days of
receipt of written notice from Owner that the Work is not in
conformance with the Contract Documents, take meaningful steps to
commence correction of such nonconforming Work, including the
correction, removal or replacement of the nonconforming Work and
correction or replacement of any Work damaged by such nonconforming
Work. If Design-Builder fails to commence the necessary steps
within such seven (7) Day period or fails to continue to
perform such steps through completion, Owner, in addition to any
other remedies provided under the Contract Documents, may provide
Design-Builder with written notice that Owner will commence or
assume correction of such nonconforming Work and repair of such
damaged Work with its own resources. If, following such written
notice, Owner performs such corrective and repair Work,
Design-Builder shall be responsible for all reasonable costs
incurred by Owner in performing the correction. The seven
(7) Day periods identified herein shall be inapplicable and
Design-Builder shall immediately correct, remove, or replace the
nonconforming Work under the following circumstances: (1) the
nonconforming Work causes operations to cease at no fault of Owner:
or (2) the nonconforming Work creates an emergency or direct
safety hazard to Owner’s employees or the surrounding
community requiring an immediate response.
8.3 Warranty
Period Not Limitation to Owner’s Rights. The one (1)-year
period referenced in Section 8.2 above applies only to
Design-Builder’s obligation to correct nonconforming Work and
is not intended to constitute a period of limitations for any other
rights or remedies Owner may have regarding Design-Builder’s
other obligations under the Contract Documents.
9.1 Contract
Price. As full consideration to Design-Builder for full and
complete performance of the Work and all costs incurred in
connection therewith, Owner shall pay Design-Builder in accordance
with the terms of Article 10, the sum of One Hundred Five
Million Nine Hundred Ninety-seven Thousand Dollars
($105,997,000.00) (“ Contract Price ”), subject
to adjustments made in accordance with Article 13. The
Contract Price does not include the water pre-treatment system and
the fire protection system which shall be provided by
Design-Builder pursuant to a separate side-letter agreement
executed by Owner and Design-Builder at Design-Builder’s
standard time plus material rates during the relevant time period
and at the relevant locale. Owner acknowledges that it has taken no
action which would impose a union labor or prevailing wage
requirement on Design-Builder, Owner or the Project. The Parties
acknowledge and agree that if after the date hereof, an
Owner’s action, a change in Applicable Law, or a Governmental
Authority acting pursuant to a change in Applicable Law shall
require Design-Builder to employ union labor or compensate labor at
prevailing wages, the Contract Price shall be adjusted upwards to
include any increased costs associated with such labor or wages.
Such adjustment shall include, but not be limited to, increased
labor, subcontractor, and material and equipment costs resulting
from any union or prevailing wage requirement; provided, however,
that if an option is made available to either employ union labor,
or to compensate labor at prevailing wages, such option shall be at
Design-Builder’s sole discretion and that if such option is
executed by Owner without Design-Builder’s agreement,
Design-Builder shall have the right to terminate this agreement and
shall be entitled to compensation pursuant to Section 15.3.1
hereof.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
23
9.2 Effect of
Construction Cost Index Increase on Contract Price. If between
the Effective Date and the date on which a Notice to Proceed is
given to Design-Builder the Construction Cost Index published by
Engineering News-Record Magazine (“ CCI ”)
increases over the Baseline Index established in
Section 9.2.1, Design-Builder shall notify Owner in writing
that it is adjusting the Contract Price.
9.2.1 The Baseline Index for this Agreement shall be 7540.38
(September 2005) (“ Baseline Index
”).
9.2.2 In the event that the CCI as of the date on which the
Notice to Proceed is given increases over the Baseline Index, the
Contract Price shall be increased by a percentage amount equal to
the percentage increase in the CCI.
10.1 Payment
at Financial Closing. As part of the Contract Price, Owner
shall pay Design-Builder Eight Million Dollars ($8,000,000.00), as
a mobilization fee, as soon as allowed by its organizational
documents and any other agreements or Laws and at the latest, at
the earlier to occur of Financial Closing or the issuance of a
Notice to Proceed. The Eight Million Dollar ($8,000,000.00)
mobilization fee payment shall be subject to retainage as provided
by Section 10.2.7.
10.2.1 Application for Payment. Following the issuance of
Notice to Proceed pursuant to Section 6.2, Design-Builder
shall submit to Owner, on or before the twenty-fifth (25
th ) Day of each month, its request for payment for
all Work performed and not paid for during the previous Pay Period
(the “ Application for Payment ”). The
Application for Payment shall be substantially in the form attached
hereto as Exhibit M. Design-Builder shall submit to Owner,
along with each Application for Payment, signed lien waivers,
substantially in the form attached hereto as Exhibit N,
received from Design-Builder, Subcontractors and suppliers for the
Work included in the Application for Payment submitted for the
immediately preceding Pay Period and for which payment has been
received.
10.2.2 The Application for Payment shall constitute
Design-Builder’s representation that the Work has been
performed consistent with the Contract Documents and has progressed
to the point indicated in the Application for Payment. The Parties
agree that the work completed at the Site, the comparison of the
Application for Payment against the work schedule, and the Schedule
of Values shall provide sufficient substantiation of the accuracy
of the Application for Payment and that no additional documentation
will be provided to Owner or Independent Engineer in support of an
Application for Payment. Title to the Work, including Work
reflected in an Application for Payment which is in process, is in
transit, is in storage, or has been incorporated into the Site,
shall pass to Owner free and clear of all claims, liens,
encumbrances, and security interests upon Design-Builder’s
receipt of payment therefor.
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
24
10.2.3 Within ten (10) Days after Owner’s receipt
of each Application for Payment, Owner shall pay Design-Builder all
amounts properly due, but in each case less the total of payments
previously made, and less amounts properly withheld under this
Agreement.
10.2.4 The Application for Payment may request payment for
equipment and materials not yet incorporated into the Project;
provided that (i) Owner is satisfied that the equipment and
materials are suitably stored at either the Site or another
acceptable location, (ii) the equipment and materials are
protected by suitable insurance, and (iii) upon payment, Owner
will receive the equipment and materials free and clear of all
liens and encumbrances except for liens of the Lenders and other
liens and encumbrances permitted under the Financing
Documents.
10.2.5 Schedule of Values. The schedule of values attached
hereto as Exhibit E (the “ Schedule of Values
”) (i) subdivides the Work into its respective parts,
(ii) includes values for all items comprising the Work, and
(iii) serves as the basis for monthly progress payments made
to Design-Builder throughout the Work.
10.2.6 Withholding of Payments. On or before the date set
forth in Section 10.2.3, Owner shall pay Design-Builder all
amounts properly due. If Owner determines that Design-Builder is
not entitled to all or part of an Application for Payment, it will
notify Design-Builder in writing at least five (5) Days prior
to the date payment is due. The notice shall indicate the specific
amounts Owner intends to withhold, the reasons and contractual
basis for the withholding, and the specific measures Design-Builder
must take to rectify Owner’s concerns. Design-Builder and
Owner will attempt to resolve Owner’s concerns prior to the
date payment is due. If the Parties cannot resolve such concerns,
Design-Builder may pursue its rights under the Contract Documents,
including those under Article 19. Notwithstanding anything to
the contrary in the Contract Documents, Owner shall pay
Design-Builder all undisputed amounts in an Application for Payment
within the times required by the Agreement.
10.2.7 Retainage on Progress Payments. Owner will retain ten
percent (10%) of each payment up to a maximum of Five Million Two
Hundred Ninety-nine Thousand Eight Hundred Fifty Dollars
($5,299,850.00). The maximum retainage set forth herein shall
increase if the Contract Price is increased pursuant to
Section 9.2 of this Agreement, such that the maximum retainage
will equal five (5%) of the Contract Price as adjusted. Once Five
Million Two Hundred Ninety-nine Thousand Eight Hundred Fifty
Dollars ($5,299,850.00) has been retained, in total, Owner will not
retain any additional amounts from any subsequent payments. Owner
will also reasonably consider reducing retainage for Subcontractors
completing their work early in the Project. Upon Substantial
Completion of the Work Owner shall release to Design-Builder all
retained amounts less an amount equal to one hundred fifty percent
(150%) of the reasonable value of all remaining or incomplete items
of Work and less an amount equal to the value of any Subcontractor
lien waivers not yet obtained, as noted in the Certificate of
Substantial Completion, provided that such payment shall only be
made if Design-Builder has met the Performance Guarantee Criteria
listed in Exhibit A.
10.3 Final
Payment. Design-Builder shall deliver to Owner a request for
final payment (the “ Final Application for Payment
”) when Final Completion has been achieved in accordance with
Section 6.5. Owner shall make final payment within thirty
(30) Days after Owner’s receipt of the Final Application
for Payment (“ Final Payment ”).
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
25
10.4 Failure
to Pay Amounts Due.
10.4.1 Interest . Payments which are due and unpaid by Owner
to Design-Builder, whether progress payments or Final Payment,
shall bear interest commencing five (5) Days after payment is
due at the rate of eighteen percent (18%) per annum, or the maximum
rate allowed by Law.
10.4.2 Right to Suspend Work. If Owner fails to pay
Design-Builder any undisputed amount that becomes due,
Design-Builder, in addition to all other remedies provided in the
Contract Documents, may stop Work pursuant to Section 15.4
hereof. All payments properly due and unpaid shall bear interest at
the rate set forth in Section 10.4.1.
10.4.3 Failure to Make Final Payment. Owner’s failure
to make Final Payment pursuant to section 10.3 hereof shall void
any and all warranties, whether express or implied, provided by
Design-Builder pursuant to this Agreement.
10.5
Design-Builder’s Payment Obligations. Design-Builder will
pay Design Consultants and Subcontractors, in accordance with its
contractual obligations to such parties, all the amounts
Design-Builder has received from Owner on account of their work.
Design-Builder will impose similar requirements on Design
Consultants and Subcontractors to pay those parties with whom they
have contracted. Design-Builder will indemnify and defend Owner
against any claims for payment and mechanic’s liens as set
forth in Section 14.2 hereof.
10.6 Record
Keeping and Finance Controls. With respect to changes in the
Work performed on a cost basis by Design-Builder pursuant to the
Contract Documents, Design-Builder shall keep full and detailed
accounts and exercise such controls as may be necessary for proper
financial management, using accounting and control systems in
accordance with generally accepted accounting principles and as may
be provided in the Contract Documents. During the performance of
the Work and for a period of three (3) years after Final
Payment, Owner and Owner’s accountants shall be afforded
access from time to time, upon reasonable notice, to
Design-Builder’s records, books, correspondence, receipts,
subcontracts, purchase orders, vouchers, memoranda and other data
relating to changes in the Work performed on a cost basis in
accordance with the Contract Documents, all of which Design-Builder
shall preserve for a period of three (3) years after Final
Payment.
Hazardous Conditions and
Differing Site Conditions
11.1 Hazardous
Conditions.
11.1.1 Unless otherwise expressly provided in the Contract
Documents to be part of the Work, Design-Builder is not responsible
for any Hazardous Conditions encountered at the Site. Upon
encountering any Hazardous Conditions, Design-Builder will stop
Work immediately in the affected area and as promptly as
practicable notify Owner and, if Design-Builder is specifically
required to do so by Legal Requirements, all Governmental
Authorities having jurisdiction over the Project or Site.
Design-Builder shall not remove, remediate or
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
26
handle in any
way (except in case of emergency) any Hazardous Conditions
encountered at the Site without prior written approval of
Owner.
11.1.2 Upon receiving notice of the presence of suspected
Hazardous Conditions, Owner shall take the necessary measures
required to ensure that the Hazardous Conditions are remediated or
rendered harmless. Such necessary measures shall include Owner
retaining Qualified Independent Experts to (i) ascertain
whether Hazardous Conditions have actually been encountered, and,
if they have been encountered, (ii) prescribe the remedial
measures that Owner is required under applicable Legal Requirements
to take with respect to such Hazardous Conditions in order for the
Work to proceed. Owner’s choice of such Qualified Independent
Experts shall be subject to the prior approval of Design-Builder,
which approval shall not be unreasonably withheld or
delayed.
11.1.3 Design-Builder shall be obligated to resume Work at
the affected area of the Project only after Owner’s Qualified
Independent Expert provides it with written certification that
(i) the Hazardous Conditions have been removed or rendered
harmless, and (ii) all necessary approvals have been obtained
from all government entities having jurisdiction over the Project
or Site and a remediation plan has been undertaken permitting the
Work to proceed.
11.1.4 Design-Builder will be entitled, in accordance with
this Article 11, to an adjustment in its Contract Price and/or
Contract Time(s) to the extent Design-Builder’s cost and/or
time of performance have been adversely impacted by the presence of
Hazardous Conditions, provided that such Hazardous Materials were
not introduced to the Site by Design-Builder, Subcontractors or
anyone for whose acts they may be liable.
11.1.5 To the fullest extent permitted by Law, Owner shall
indemnify, defend and hold harmless Design-Builder, Design
Consultants, Subcontractors, anyone employed directly or indirectly
for any of them, and their officers, directors, employees and
agents, from and against any and all claims, losses, damages,
liabilities and expenses, including attorneys’ fees and
expenses, arising out of or resulting from the presence, removal or
remediation of Hazardous Conditions at the Site.
11.1.6 Notwithstanding the preceding provisions of this
Section 11.1, Owner is not responsible for Hazardous
Conditions introduced to the Site by Design-Builder, Subcontractors
or anyone for whose acts they may be liable. Design-Builder shall
indemnify, defend and hold harmless Owner and Owner’s
officers, directors, employees and agents from and against all
claims, losses, damages, liabilities and expenses, including
attorneys’ fees and expenses, arising out of or resulting
from those Hazardous Conditions introduced to the Site by
Design-Builder, Subcontractors or anyone for whose acts they may be
liable.
11.2 Differing
Site Conditions; Inspection.
11.2.1 Concealed or latent physical conditions or subsurface
conditions at the Site that (i) differ from the conditions
indicated in the Contract Documents, or (ii) are of an unusual
nature, differing from the conditions ordinarily encountered and
generally recognized as inherent in the Work are collectively
referred to herein as “ Differing Site Conditions
.” If Design-Builder encounters a Differing Site Condition,
Design-Builder will be entitled to an
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
27
adjustment in
the Contract Price and/or Contract Time(s) to the extent
Design-Builder’s cost and/or time of performance are
adversely impacted by the Differing Site Condition.
11.2.2 Upon encountering a Differing Site Condition,
Design-Builder shall provide prompt written notice to Owner of such
condition, which notice shall not be later than fourteen (14)
business days after such condition has been encountered.
Design-Builder shall, to the extent reasonably possible, provide
such notice before the Differing Site Condition has been
substantially disturbed or altered.
Force Majeure; Change in Legal
Requirements
12.1 Force
Majeure Event. A Force Majeure event shall mean a cause or
event beyond the reasonable control of, and without the fault or
negligence of a Party claiming Force Majeure, including, without
limitation, an emergency, floods, earthquakes, hurricanes,
tornadoes, adverse weather conditions not reasonably anticipated or
acts of God; sabotage; vandalism beyond that which could reasonably
be prevented by a Party claiming Force Majeure; terrorism; war;
riots; fire; explosion; blockades; insurrection; strike; slow down
or labor disruptions (even if such difficulties could be resolved
by conceding to the demands of a labor group); economic hardship or
delay in the delivery of materials or equipment that is beyond the
control of a Party claiming Force Majeure, and action or failure to
take action by any Governmental Authority after the Effective Date
(including the adoption or change in any rule or regulation or
environmental constraints lawfully imposed by such Governmental
Authority), but only if such requirements, actions, or failures to
act prevent or delay performance; and inability, despite due
diligence, to obtain any licenses, permits, or approvals required
by any Governmental Authority (any such event, a “ Force
Majeure Event ”).
12.2 Effect of
Force Majeure Event. Neither Party shall be considered in
default in the performance of any of the obligations contained in
the Contract Documents, except for the Owners or the
Design-Builder’s obligations to pay money (including but not
limited to, Progress Payments and payments of liquidated damages
which become due and payable with respect to the period prior to
the occurrence of the Force Majeure Event), when and to the extent
the failure of performance shall be caused by a Force Majeure
Event. If either Party is rendered wholly or partly unable to
perform its obligations under the Contract Documents because of a
Force Majeure Event, such Party will be excused from performance
affected by the Force Majeure Event to the extent and for the
period of time so affected; provided that:
|
|
(a)
|
|
the
nonperforming Party, within forty-eight (48) hours after the
nonperforming Party actually becomes aware of the occurrence and
impact of the Force Majeure Event, gives the other Party written
notice describing the event or circumstance in detail, including an
estimation of its expected duration and probable impact on the
performance of the affected Party’s obligations hereunder and
continues to furnish timely regular reports with respect thereto
during the continuation of and upon the termination of the Force
Majeure Event;
|
|
|
|
|
|
|
|
(b)
|
|
the
suspension of performance is of no greater scope and of no longer
duration than is reasonably required by the Force Majeure
Event;
|
|
|
|
|
|
|
|
|
|
Cardinal
Ethanol, LLC
|
|
December 14, 2006
|
28
|
|
(c)
|
|
the
obligations of either Party that arose before the occurrence
causing the suspension of performance and the performance that is
not prevented by the occurrence, shall not be excused as a result
of such occurrence;
|
|
|
|
|
|
|
|
(d)
|
|
the
nonperforming Party uses its best efforts to remedy its inability
to perform and mitigate the effect of such event and resumes its
performance at the earliest practical time after cessation of such
occurrence or until such time that performance is
practicable;
|
|
|
|
|
|
|
|
(e)
|
|
when the nonperforming Party is able
to resume performance of its obligations under the Contract
Documents, that Party shall give the other Party written notice to
that effect; and
|
|
|
|
|
|
|
|
(f)
|
|
Design-Builder shall be entitled to
a Day-for-Day time extension for those events set forth in
Section 12.1 to the extent the occurrence of such event
delayed Design-Builder’s performance of its obligations under
this Agreement.
|
12.3 Change in
Legal Requirements. The Contract Price and/or the Contract
Time(s) shall be adjusted to compensate Design-Builder for the
effects of any changes to the Legal Requirements that occur after
the date of this Agreement and as a result of such change, the
performance of the Work is adversely affected. Such effects may
include, without limitation, revisions Design-Builder is required
to make to the Construction Documents because of changes in Legal
Requirements.
|