50 of the Top 250 law firms use our Products every day
Exhibit 10.1
SABINE PASS
LNG, L.P.
|
|
May 27,
2009
|
|
|
Response
Required: No x
|
|
Bechtel
Corporation
3000 Post Oak
Boulevard
Houston, Texas
77056
Attention: Mr. Mitchell
Clayman
|
Correspondence
No. SP2-BE-C-045
|
|
Subject:
|
|
Change Order
SP2/BE-011 – Adjustment to Contractor’s Fixed
Fee
|
Enclosed you
will find the signed original for Change Order SP2/BE-011 regarding
the Adjustment to Contractor’s Fixed Fee.
Should you have
any questions or concerns, please feel free to contact
us.
|
|
Regards,
|
|
|
|
|
|
|
|
|
/s/ Carlos
Macias
|
|
|
|
Carlos
Macias
|
|
|
Director,
Project Management
|
|
cc:
|
Ed
Lehotsky
|
|
|
David
Mitchell
|
|
|
Graham
McArthur
|
|
|
File
|
|
PROJECT NAME : Sabine Pass LNG Phase
2
Receiving,
Storage and Re-Gasification
Terminal
Expansion (“Phase 2 Project”)
|
|
CHANGE ORDER
NUMBER: SP2BE-011
DATE OF
CHANGE ORDER: May 5, 2009
|
|
|
|
|
|
COMPANY: Sabine Pass LNG, L.P.
|
|
ADJUSTMENT
TO CONTRACTOR’S FIXED FEE NO#011
|
|
|
|
|
|
CONTRACTOR: Bechtel Corporation
|
|
|
|
|
|
|
|
DATE OF
AGREEMENT: July 21,
2006
|
|
|
|
|
|
|
The
Agreement between the Parties listed above is changed as
follows:
|
|
Increase in the
Fixed Fee associated with the implementation of the following
agreed Scope Changes:
|
|
|
1.
|
|
Misc Client
Work Orders (Trend
F-2010)
Work Order
Request WR-00011 through WR-00024 from January 2008 through June
2008 covering various requests including Cheniere's Sign &
Billboard, the Noble Road Repairs and the Water Supply to the
Hydrant Pond.
|
|
$
|
71,828
|
|
|
|
|
|
|
|
|
|
|
|
|
2.
|
|
Firewater
Monitor Modifications (Trend F-2025)
Modify
firewater design to isolate firewater spray zone actuators to 18
existing valves for both Phase 1 &2. Also valves, including
field service to install 6 pneumatic hand actuation of the
firewater system for both phases. for each tank by adding add 6"
firewater butterfly switches to allow manual
|
|
$
|
696,505
|
|
|
|
|
|
|
|
|
|
|
|
|
3.
|
|
FERC
Requested LNG Spill Containment (Trend F-2061)
FERC required
LNG spill containment including concrete curbing and earthen dikes
around the AAV and SCV areas.
|
|
$
|
62,534
|
|
|
|
|
|
|
|
|
|
|
|
|
4.
|
|
Bypass for
Cool Down of Tanks S-104 and S105 (Trend F-2076)
Bypasses added
to the stop valves to allow a controlled initial cool down to the
downstream lines for tanks S-104 and S-105.
|
|
$
|
30,961
|
|
|
|
|
|
|
|
|
|
|
|
|
5.
|
|
Additional
Alarms to the UPS from the Metering Station (Trend F-3003)
Alarms from the
metering station routed to the UPS system to allow automatic
acknowledgement and mitigation.
|
|
$
|
28,340
|
|
|
|
|
|
|
|
|
|
|
|
|
6.
|
|
Additional
Earthen Ramns at Tanks S-104 and S-105 (Trend F-3011)
New earthen
ramps for Perlite truck access to the LNG tanks spill protection
area.
|
|
$
|
25,928
|
|
|
|
|
|
|
|
|
|
|
|
|
7.
|
|
2"d N2 Skid
Piling and Foundation (Trend F-3021)
Drive piles and
pour the foundation for a 2nd N2 Skid. 1
|
|
$
|
38, 980
|
|
|
|
|
|
|
|
|
|
|
|
|
8.
|
|
Ike Recovery
Assistance to SPLNG in the Phase I Area (Trend F-3018)
Post Hurricane
Ike work in the Phase I area to assist SPLNG with their recovery
effort. This work scope is in addition to the contractual scope of
Phase II.
|
|
$
|
121,272
|
|
|
|
|
|
|
|
|
|
|
|
|
9.
|
|
Use of Rigid
Conduit for all Light Stations (Trend F-3019)
Replace
existing %2" aluminum co
|
|