Exhibit
10.47
SCHEDULE
D-1
CHANGE ORDER
FORM
(for use when the Parties
mutually agree upon and execute the Change Order pursuant to
Section 6.1B or 6.2C)
|
|
|
|
PROJECT NAME: Alternate Route
42” Single Line Option
Creole Trail Pipeline - Segment 3A
Project
OWNER: Cheniere Creole Trail
Pipeline, L.P.
CONTRACTOR: Sheehan Pipe Line
Construction Company
(SPLCC)
DATE OF AGREEMENT:
January 10, 2007
SUBJECT: Additional Clearing Crew
Move Around from
Station Number 1634+71 to 1648+71.
|
|
CHANGE ORDER NUMBER: CCT
3A-012
DATE OF CHANGE ORDER:
10-20-07
|
The Agreement between the Parties
listed above is changed as follows: Per the terms and
conditions outlined under Schedule D-3 per the construction
agreement between Cheniere Creole Trail Pipeline, L.P. and Sheehan
Pipe Line Construction Company dated January 10, 2007,
Cheniere will compensate SPLCC by line item M-38.
Cheniere had not secured agreements
necessary to clear this property therefore forcing the Clearing
Crew to move-around this location to continue clearing.
|
|
|
|
|
Adjustment to Estimated Contract
Price
|
|
|
|
|
The original Estimated Contract Price
was
|
|
$ |
65,605,739.22 |
|
|
|
|
|
Net change by previously authorized
Change Orders
|
|
$ |
4,548,491.02 |
|
|
|
|
|
The Estimated Contract Price prior to
this Change Order was
|
|
$ |
70,154,230.24 |
|
|
|
|
|
The Estimated Contract Price will be
increased by this Change Order in the amount of
|
|
$ |
16,000.00 |
|
|
|
|
|
The new Estimated Contract Price
including this Change Order will be
|
|
$ |
70,170,230.24 |
|
|
|
|
Adjustment to dates in Project
Schedule
The following dates are modified
(list all dates modified; insert N/A if no dates modified) :
N/A
The Guaranteed Mechanical Completion
Date will be unchanged.
The Guaranteed Mechanical Completion
Date as of the date of this Change Order therefore is
January 31 , 2008 .
The Guaranteed Substantial Completion
Date will be unchanged.
The Guaranteed Substantial Completion
Date as of the date of this Change Order therefore is
February 29 , 2008 .
The Guaranteed Final Completion Date
will be unchanged.
The Guaranteed Final Completion Date as
of the date of this Change Order therefore is March 31
, 2008 .
Adjustment to other Changed Criteria:
N/A
Upon execution of this Change Order by
Owner and Contractor, the above-referenced change shall become a
valid and binding part of the original Agreement without exception
or qualification, unless noted in this Change Order. Except as
modified by this and any previously issued Change Orders, all other
terms and conditions of the Agreement shall remain in full force
and effect. This Change Order is executed by each of the
Parties’ duly authorized representatives.
|
|
|
|
|
|
Cheniere Creole Trail Pipeline,
L.P.
|
|
|
|
Sheehan
Pipe Line Construction Company |
|
|
|
|
|
|
|
Owner
|
|
|
|
Contractor |
|
/s/ T. R. Hutton
|
|
|
|
/s/
Robert A. Riess, Sr. |
|
|
|
|
|
|
|
Signature
|
|
|
|
Signature |
|
T. R. Hutton
|
|
|
|
Robert A.
Riess, Sr. |
|
|
|
|
|
|
|
Name
|
|
|
|
Name |
|
Director - EPC
|
|
|
|
President
& COO |
|
|
|
|
|
|
|
Title
|
|
|
|
Title |
|
11/2/07
|
|
|
|
Nov. 26,
2007 |
|
|
|
|
|
|
|
Date of Signing
|
|
|
|
Date of
Signing |
SCHEDULE
D-1
CHANGE ORDER
FORM
(for use when the Parties
mutually agree upon and execute the Change Order pursuant to
Section 6.1B or 6.2C)
|
|
|
|
PROJECT NAME: Alternate Route
42” Single Line Option
Creole Trail Pipeline - Segment 3A
Project
OWNER: Cheniere Creole Trail
Pipeline, L.P.
CONTRACTOR: Sheehan Pipe Line
Construction Company
(SPLCC)
DATE OF AGREEMENT:
January 10, 2007
SUBJECT: Additional Clearing Crew
Move Around from
Station Number 1068+95 to 1083+68.
|
|
CHANGE ORDER NUMBER: CCT
3A-013
DATE OF CHANGE ORDER:
10-20-07
|
The Agreement between the Parties
listed above is changed as follows: Per the terms and
conditions outlined under Schedule D-3 per the construction
agreement between Cheniere Creole Trail Pipeline, L.P. and Sheehan
Pipe Line Construction Company dated January 10, 2007,
Cheniere will compensate SPLCC by line item M-38.
Cheniere had instructed crew to skip
area where there was an environmental restriction area for the Red
Headed Woodpecker from Station 1068+95 to 1083+68.
|
|
|
|
|
Adjustment to Estimated Contract
Price
|
|
|
|
|
The original Estimated Contract Price
was
|
|
$ |
65,605,739.22 |
|
|
|
|
|
Net change by previously authorized
Change Orders
|
|
$ |
4,564,491.02 |
|
|
|
|
|
The Estimated Contract Price prior to
this Change Order was
|
|
$ |
70,170,230.24 |
|
|
|
|
|
The Estimated Contract Price will be
increased by this Change Order in the amount of
|
|
$ |
16,000.00 |
|
|
|
|
|
The new Estimated Contract Price
including this Change Order will be
|
|
$ |
70,186,230.24 |
|
|
|
|
Adjustment to dates in Project
Schedule
The following dates are modified
(list all dates modified; insert N/A if no dates modified) :
N/A
The Guaranteed Mechanical Completion
Date will be unchanged.
The Guaranteed Mechanical Completion
Date as of the date of this Change Order therefore is
January 31 , 2008 .
The Guaranteed Substantial Completion
Date will be unchanged.
The Guaranteed Substantial Completion
Date as of the date of this Change Order therefore is
February 29 , 2008 .
The Guaranteed Final Completion Date
will be unchanged.
The Guaranteed Final Completion Date as
of the date of this Change Order therefore is March 31
, 2008 .
Adjustment to other Changed Criteria:
N/A
Upon execution of this Change Order by
Owner and Contractor, the above-referenced change shall become a
valid and binding part of the original Agreement without exception
or qualification, unless noted in this Change Order. Except as
modified by this and any previously issued Change Orders, all other
terms and conditions of the Agreement shall remain in full force
and effect. This Change Order is executed by each of the
Parties’ duly authorized representatives.
|
|
|
|
|
|
Cheniere Creole Trail Pipeline,
L.P.
|
|
|
|
Sheehan
Pipe Line Construction Company |
|
|
|
|
|
|
|
Owner
|
|
|
|
Contractor |
|
/s/ T.R. Hutton
|
|
|
|
/s/
Robert A. Riess, Sr. |
|
|
|
|
|
|
|
Signature
|
|
|
|
Signature |
|
T.R. Hutton
|
|
|
|
Robert A.
Riess, Sr. |
|
|
|
|
|
|
|
Name
|
|
|
|
Name |
|
Director - EPC
|
|
|
|
President
& COO |
|
|
|
|
|
|
|
Title
|
|
|
|
Title |
|
11/2/07
|
|
|
|
Nov. 26,
2007 |
|
|
|
|
|
|
|
Date of Signing
|
|
|
|
Date of
Signing |
SCHEDULE
D-1
CHANGE ORDER
FORM
(for use when the Parties
mutually agree upon and execute the Change Order pursuant to
Section 6.1B or 6.2C)
|
|
|
|
PROJECT NAME: Alternate Route
42” Single Line Option
Creole Trail Pipeline - Segment 3A
Project
OWNER: Cheniere Creole Trail
Pipeline, L.P.
CONTRACTOR: Sheehan Pipe Line
Construction Company
(SPLCC)
DATE OF AGREEMENT:
January 10, 2007
SUBJECT: Clearing Crew Stand by
Charges for Friday,
Oct. 19, 2007.
|
|
CHANGE ORDER NUMBER: CCT
3A-014
DATE OF CHANGE ORDER:
10-20-07
|
The Agreement between the Parties
listed above is changed as follows: Per the terms and
conditions outlined under Article 6.2-B of the Construction
Agreement for Segment 3A project between Cheniere Creole Trail
Pipeline, L.P. and Sheehan Pipe Line Construction Company dated
January 10, 2007; a Partial Clearing Crew Standby due to
various properties that had not been released for clearing. This
occurred on Friday, October 19, 2007. The clearing crew is
currently waiting on two tracks to be released at the north end of
the project.
|
|
|
|
|
Adjustment to Estimated Contract
Price
|
|
|
|
|
The original Estimated Contract Price
was
|
|
$ |
65,605,739.22 |
|
|
|
|
|
Net change by previously authorized
Change Orders
|
|
$ |
4,580,491.02 |
|
|
|
|
|
The Estimated Contract Price prior to
this Change Order was
|
|
$ |
70,186,230.24 |
|
|
|
|
|
The Estimated Contract Price will be
increased by this Change Order in the amount of
|
|
$ |
4,200.00 |
|
|
|
|
|
The new Estimated Contract Price
including this Change Order will be
|
|
$ |
70,190,430.24 |
|
|
|
|
Adjustment to dates in Project
Schedule
The following dates are modified
(list all dates modified; insert N/A if no dates modified) :
N/A
The Guaranteed Mechanical Completion
Date will be unchanged.
The Guaranteed Mechanical Completion
Date as of the date of this Change Order therefore is
January 31 , 2008 .
The Guaranteed Substantial Completion
Date will be unchanged.
The Guaranteed Substantial Completion
Date as of the date of this Change Order therefore is
February 29 , 2008 .
The Guaranteed Final Completion Date
will be unchanged.
The Guaranteed Final Completion Date as
of the date of this Change Order therefore is March 31
, 2008 .
Adjustment to other Changed Criteria:
N/A
Upon execution of this Change Order by
Owner and Contractor, the above-referenced change shall become a
valid and binding part of the original Agreement without exception
or qualification, unless noted in this Change Order. Except as
modified by this and any previously issued Change Orders, all other
terms and conditions of the Agreement shall remain in full force
and effect. This Change Order is executed by each of the
Parties’ duly authorized representatives.
|
|
|
|
|
|
Cheniere Creole Trail Pipeline,
L.P.
|
|
|
|
Sheehan Pipe Line Construction Company |
|
|
|
|
|
|
|
Owner
|
|
|
|
Contractor |
|
/s/ T. R. Hutton
|
|
|
|
/s/
Robert R. Riess, Sr. |
|
|
|
|
|
|
|
Signature
|
|
|
|
Signature |
|
T. R. Hutton
|
|
|
|
Robert R.
Riess, Sr. |
|
|
|
|
|
|
|
Name
|
|
|
|
Name |
|
Director - EPC
|
|
|
|
President
& COO |
|
|
|
|
|
|
|
Title
|
|
|
|
Title |
|
11/2/07
|
|
|
|
Nov. 26,
2007 |
|
|
|
|
|
|
|
Date of Signing
|
|
|
|
Date of
Signing |
SCHEDULE
D-1
CHANGE ORDER
FORM
(for use when the Parties
mutually agree upon and execute the Change Order pursuant to
Section 6.1B or 6.2C)
|
|
|
|
PROJECT NAME: Alternate Route
42” Single Line Option
Creole Trail Pipeline - Segment 3A
Project
OWNER: Cheniere Creole Trail
Pipeline, L.P.
CONTRACTOR: Sheehan Pipe Line
Construction Company
(SPLCC)
DATE OF AGREEMENT:
January 10, 2007
SUBJECT: Clearing Crew
Demobilization
|
|
CHANGE ORDER NUMBER: CCT
3A-015
DATE OF CHANGE ORDER:
11-01-07
|
The Agreement between the Parties
listed above is changed as follows: Per the terms and
conditions outlined under Article 6.2-B of the Construction
Agreement for Segment 3A project between Cheniere Creole Trail
Pipeline, L.P. and Sheehan Pipe Line Construction Company dated
January 10, 2007; a Clearing Crew demobilization on
October 19, 2007 due to various properties that had not been
released for clearing.
Cheniere and Sheehan Pipe Line Company
agree the Clearing Crew Demobilization is the most economical
decision.
|
|
|
|
|
Adjustment to Estimated Contract
Price
|
|
|
|
|
The original Estimated Contract Price
was
|
|
$ |
65,605,739.22 |
|
|
|
|
|
Net change by previously authorized
Change Orders
|
|
$ |
4,584,691.02 |
|
|
|
|
|
The Estimated Contract Price prior to
this Change Order was
|
|
$ |
70,190,430.24 |
|
|
|
|
|
The Estimated Contract Price will be
increased by this Change Order in the amount of
|
|
$ |
35,000.00 |
|
|
|
|
|
The new Estimated Contract Price
including this Change Order will be
|
|
$ |
70,225,430.24 |
|
|
|
|
Adjustment to dates in Project
Schedule
The following dates are modified
(list all dates modified; insert N/A if no dates modified) :
N/A
The Guaranteed Mechanical Completion
Date will be unchanged.
The Guaranteed Mechanical Completion
Date as of the date of this Change Order therefore is
January 31 , 2008 .
The Guaranteed Substantial Completion
Date will be unchanged.
The Guaranteed Substantial Completion
Date as of the date of this Change Order therefore is
February 29 , 2008 .
The Guaranteed Final Completion Date
will be unchanged.
The Guaranteed Final Completion Date as
of the date of this Change Order therefore is March 31
, 2008 .
Adjustment to other Changed Criteria:
N/A
Upon execution of this Change Order by
Owner and Contractor, the above-referenced change shall become a
valid and binding part of the original Agreement without exception
or qualification, unless noted in this Change Order. Except as
modified by this and any previously issued Change Orders, all other
terms and conditions of the Agreement shall remain in full force
and effect. This Change Order is executed by each of the
Parties’ duly authorized representatives.
|
|
|
|
|
|
Cheniere Creole Trail Pipeline,
L.P.
|
|
|
|
Sheehan
Pipe Line Construction Company |
|
|
|
|
|
|
|
Owner
|
|
|
|
Contractor |
|
/s/ R. Keith Teague
|
|
|
|
/s/
Robert A. Riess, Sr. |
|
|
|
|
|
|
|
Signature
|
|
|
|
Signature |
|
R. Keith Teague
|
|
|
|
Robert A.
Riess, Sr. |
|
|
|
|
|
|
|
Name
|
|
|
|
Name |
|
President
|
|
|
|
President
& COO |
|
|
|
|
|
|
|
Title
|
|
|
|
Title |
|
Nov 5/ 2007
|
|
|
|
Nov. 26,
2007 |
|
|
|
|
|
|
|
Date of Signing
|
|
|
|
Date of
Signing |
SCHEDULE
D-1
CHANGE ORDER
FORM
(for use when the Parties
mutually agree upon and execute the Change Order pursuant to
Section 6.1B or 6.2C)
|
|
|
|
PROJECT NAME: Alternate Route
42” Single Line Option
Creole Trail Pipeline - Segment 3A
Project
OWNER: Cheniere Creole Trail
Pipeline, L.P.
CONTRACTOR: Sheehan Pipe Line
Construction Company
(SPLCC)
DATE OF AGREEMENT:
January 10, 2007
SUBJECT: Furnish, install,
and remove Isolation Fencing
(Orange
Safety Fence, Item #M25)
|
|
CHANGE ORDER NUMBER: CCT
3A-016
DATE OF CHANGE ORDER:
11-01-07
|
The Agreement between the Parties
listed above is changed as follows: Per the terms and
conditions outlined under Article 6.1-B of the Construction
Agreement for Segment 3A project between Cheniere Creole Trail
Pipeline, L.P. and Sheehan Pipe Line Construction Company dated
January 10, 2007; Cheniere requested the installation of
safety fence installed on 10/09/07 from Station #1001+50 to Station
#1005+15 for a total of 365 feet installed.
Items M1 through M50 will only be
considered for payment if they are over and above the Scope of Work
requirements, and if specifically requested and/or authorized by
Owner via Change Order. This pricing is provided in Schedule D-3
and will be subject to Change Orders.
|
|
|
|
|
Adjustment to Estimated Contract
Price
|
|
|
|
|
The original Estimated Contract Price
was
|
|
$ |
65,605,739.22 |
|
|
|
|
|
Net change by previously authorized
Change Orders
|
|
$ |
4,619,691.02 |
|
|
|
|
|
The Estimated Contract Price prior to
this Change Order was
|
|
$ |
70,225,430.24 |
|
|
|
|
|
The Estimated Contract Price will be
increased by this Change Order in the amount of
|
|
$ |
2,555.00 |
|
|
|
|
|
The new Estimated Contract Price
including this Change Order will be
|
|
$ |
70,227,985.24 |
|
|
|
|
Adjustment to dates in Project
Schedule
The following dates are modified
(list all dates modified; insert N/A if no dates modified) :
N/A
The Guaranteed Mechanical Completion
Date will be unchanged.
The Guaranteed Mechanical Completion
Date as of the date of this Change Order therefore is
January 31 , 2008 .
The Guaranteed Substantial Completion
Date will be unchanged.
The Guaranteed Substantial Completion
Date as of the date of this Change Order therefore is
February 29 , 2008 .
The Guaranteed Final Completion Date
will be unchanged.
The Guaranteed Final Completion Date as
of the date of this Change Order therefore is March 31
, 2008 .
Adjustment to other Changed Criteria:
N/A
Upon execution of this Change Order by
Owner and Contractor, the above-referenced change shall become a
valid and binding part of the original Agreement without exception
or qualification, unless noted in this Change Order. Except as
modified by this and any previously issued Change Orders, all other
terms and conditions of the Agreement shall remain in full force
and effect. This Change Order is executed by each of the
Parties’ duly authorized representatives.
|
|
|
|
|
|
Cheniere Creole Trail Pipeline,
L.P.
|
|
|
|
Sheehan
Pipe Line Construction Company |
|
|
|
|
|
|
|
Owner
|
|
|
|
Contractor |
|
/s/ T. R. Hutton
|
|
|
|
/s/
Robert A. Riess, Sr. |
|
|
|
|
|
|
|
Signature
|
|
|
|
Signature |
|
T. R. Hutton
|
|
|
|
Robert A.
Riess, Sr. |
|
|
|
|
|
|
|
Name
|
|
|
|
Name |
|
Director - EPC
|
|
|
|
President
& COO |
|
|
|
|
|
|
|
Title
|
|
|
|
Title |
|
11/2/07
|
|
|
|
Nov. 26,
2007 |
|
|
|
|
|
|
|
Date of Signing
|
|
|
|
Date of
Signing |
SCHEDULE
D-1
CHANGE ORDER
FORM
(for use when the Parties
mutually agree upon and execute the Change Order pursuant to
Section 6.1B or 6.2C)
|
|
|
|
PROJECT NAME: Alternate Route
42” Single Line Option
Creole Trail Pipeline - Segment 3A
Project
|
|
CHANGE
ORDER NUMBER: CCT 3A-017 |
|
|
| OWNER: Cheniere Creole Trail Pipeline, L.P. |
|
DATE
OF CHANGE ORDER: 11-20-07 |
|
|
| CONTRACTOR: Sheehan Pipe Line Construction Company
(SPLCC) |
|
|
|
|
| DATE OF
AGREEMENT: January 10, 2007 |
|
|
|
|
| SUBJECT:
Clearing Crew Remobilization |
|
|
The Agreement between the Parties
listed above is changed as follows: Per the terms and
conditions outlined under Article 6.2-B of the Construction
Agreement for Segment 3A project between Cheniere Creole Trail
Pipeline, L.P. and Sheehan Pipe Line Construction Company dated
January 10, 2007; a Clearing Crew remobilization on
October 31, 2007 due to various properties that have been
released for clearing.
Cheniere and Sheehan Pipe Line Company
agreed the Clearing Crew Demobilization/Remobilization was the most
economical decision.
|
|
|
|
|
Adjustment to Estimated Contract
Price
|
|
|
|
|
The original Estimated Contract Price
was
|
|
$ |
65,605,739.22 |
|
Net change by previously authorized
Change Orders
|
|
$ |
4,622,246.02 |
|
The Estimated Contract Price prior to
this Change Order was
|
|
$ |
70,227,985.24 |
|
The Estimated Contract Price will be
increased by this Change Order in the amount of
|
|
$ |
35,000.00 |
|
The new Estimated Contract Price
including this Change Order will be
|
|
$ |
70,262,985.24 |
Adjustment to dates in Project
Schedule
The following dates are modified
(list all dates modified; insert N/A if no dates modified) :
N/A
The Guaranteed Mechanical Completion
Date will be unchanged.
The Guaranteed Mechanical Completion
Date as of the date of this Change Order therefore is
January 31, 2008.
The Guaranteed Substantial Completion
Date will be unchanged.
The Guaranteed Substantial Completion
Date as of the date of this Change Order therefore is
February 29, 2008.
The Guaranteed Final Completion Date
will be unchanged.
The Guaranteed Final Completion Date as
of the date of this Change Order therefore is March 31,
2008.
Adjustment to other Changed Criteria:
N/A
Upon execution of this Change Order by
Owner and Contractor, the above-referenced change shall become a
valid and binding part of the original Agreement without exception
or qualification, unless noted in this Change Order. Except as
modified by this and any previously issued Change Orders, all other
terms and conditions of the Agreement shall remain in full force
and effect. This Change Order is executed by each of the
Parties’ duly authorized representatives.
|
|
|
|
|
| Cheniere
Creole Trail Pipeline, L.P. |
|
|
|
Sheehan
Pipe Line Construction Company |
| Owner |
|
|
|
Contractor |
|
|
|
|
/s/ T.R.
Hutton
/s/ R. Keith Teague |
|
|
|
/s/ Robert A. Riess,
Sr. |
| Signature |
|
|
|
Signature |
|
|
|
| T.R.
Hutton
R. Keith Teague |
|
|
|
Robert A.
Riess, Sr. |
| Name |
|
|
|
Name |
|
|
|
| Director-EPC
President |
|
|
|
President & COO |
| Title |
|
|
|
Title |
|
|
|
| 11/26/07
11-26-07 |
|
|
|
Nov. 30,
2007 |
| Date of
Signing |
|
|
|
Date of
Signing |
SCHEDULE
D-1
CHANGE ORDER
FORM
(
|