Standard construction document
CCDC
2
Stipulated price
contract
Project: CELEBRATIONS HOTEL AND
CASINO
Edmonton, Alberta
This agreement is
protected by
copyright and is intended by
the
parties to be an unaltered version
of
CCDC 2 -1994 except to the
extent
modifications are set forth
in
supplementary
conditions.
CC
DC Canadian construction documents committee
Reprint 1999
CC
DC Canadian construction documents
committee
The Canadian
Construction Documents Committee is a joint committee composed of
owners and representatives appointed by:
The Association
of Consulting Engineers of Canada
The Canadian
Construction Association
Construction
Specifications Canada
The Royal
Architectural Institute of Canada
Committee
policy and procedures are directed and approved by the constituent
organizations.
This document
has been endorsed by each of the above organizations.
Enquiries
should be directed to:
The
Secretary
Canadian
Construction Documents Committee
75 Albert
Street
Suite
400
Ottawa,
Ontario
KIP
5E7
Tel: (613)
236-9455
Fax:(613)236-9526
www.ccdc.org
|
AGREEMENT BETWEEN OWNER AND
CONTRACTOR
|
|
ALLOWANCES
|
|
|
A-1
The Work
|
GC
4.1
|
Cash
Allowances
|
|
|
A-2
Agreements and Amendments
|
GC
4.2
|
Contingency
Allowance
|
|
|
A-3
Contract Documents
A-4
Contract Price
|
|
PAYMENT
|
|
|
A-5
Payment
|
GC
5.1
|
Financing
Information Required of the Owner
|
|
|
A-6
Receipt of and Addresses for
Notices
|
GC
5.2
|
Applications
for Progress Payment
|
|
|
A-7
Language of the Contract
|
GC
5.3
|
Progress
Payment
|
|
|
A-8
Succession
|
GC
5.4
|
Substantial
Performance of the Work
|
|
|
|
GC
5.5
|
Payment of
Holdback upon Substantial Performance of the Work
|
|
|
DEFINITIONS
|
|
|
GC
5.6
|
Progressive
Release of Holdback
|
|
|
1.
Contract
|
GC
5.7
|
Final
Payment
|
|
|
2.
Contract Documents
|
GC
5.8
|
Withholding of
Payment
|
|
|
3.
Owner
|
GC
5.9
|
Non-conforming
Work
|
|
|
4.
Contractor
5.
Subcontractor
|
|
CHANGES IN THE WORK
|
|
|
6.
Supplier
|
GC
6.1
|
Changes
|
|
|
7.
Consultant
|
GC
6.2
|
Change
Order
|
|
|
8.
Project
|
GC
6.3
|
Change
Directive
|
|
|
9.
Work
|
GC
6.4
|
Concealed or
Unknown Conditions
|
|
|
10.
Place of The Work
|
|
Delays
|
|
|
11.
Product
12.
Provide
|
|
DEFAULT
NOTICE
|
|
|
13.
Contract Price
|
GC
7.1
|
Owner's Right
to Perform The Work. Stop The Work, or
|
|
|
14.
Contract Time
|
|
Terminate The
Contract
|
|
|
15.
Working Day
|
GC
7.2
|
Contractor's
Right to Stop the Work or Terminate The
|
|
|
16.
Supplemental Instruction
|
|
Contract
|
|
|
17.
Charge Order
18.
Change Directive
|
|
DISPUTE
RESOLUTION
|
|
|
19.
Substantial Performance of the
Work
|
GC
8.1
|
Authority of
The Consultant
|
|
|
20.
Value Added Taxes
|
GC
8.2
|
Negotiation,
Mediation, and Arbitration
|
|
|
|
GC
8.3
|
Retention of
Rights
|
|
|
|
|
|
GENERAL
CONDITIONS OF THE STIPULATED
PRICE
CONTRACT
|
|
PROTECTION OF PERSONS AND
PROPERTY
|
|
|
|
GC
9.1
|
Protection of
Work and Property
|
|
|
PART 1
|
GENERAL
PROVISIONS
|
|
|
GC
9.2
|
Damages and
Mutual Responsibility
|
|
|
GC
1.1
|
Contract
Documents
|
GC
9.3
|
Toxic and
Hazardous Substances and Materials
|
|
|
GC
1.2
|
Law of The
Contract
|
|
|
|
|
|
GC
1.3
|
Rights and
Remedies
|
PART
10 GOVERNING
REGULATIONS
|
|
|
GC
1.4
|
Assignment
|
GC
10.1
|
Taxes and
Duties
|
|
|
|
|
GC
10.2
|
Laws, Notices,
Permits, and Fees
|
|
|
PART
2
|
ADMINISTRATION OF THE
CONTRACT
|
GC
10.3
|
Patent
Fees
|
|
|
GC
2.1
|
Authority of
The Consultant
|
GC
10.4
|
Workers'
Compensation
|
|
|
GC
2.2
|
Role of The
Consultant
|
|
|
|
|
|
|
|
GC
2.3
|
Review and
Inspection of The Work
|
PART 11 INSURANCE -
BONDS
|
|
|
GC
2.4
|
Defective
Work
|
GC
11.1
|
Insurance
|
|
|
|
|
GC
11.2
|
Bonds
|
|
|
PART
3
GC
3.1
|
EXECUTION OF THE WORK
Control of the
Work
|
|
|
|
PART 12
INDEMNIFICATION - WAIVER - WARRANTY
|
|
|
GC
3.2
|
Construction by
Owner or Other Contractors
|
GC
12.1
|
Indemnification
|
|
|
GC
3.3
|
Temporary
Supports, Structures, and Facilities
|
GC
12.2
|
Waiver of
Claims
|
|
|
GC
3.4
|
Document
Review
|
GC
12.3
|
Warranty
|
|
|
GC
3.5
|
Construction
Schedule
|
|
|
|
|
GC
3.6
|
Construction
Safety
|
|
|
|
|
GC
3.7
|
Supervisor
|
|
|
|
|
GC
3.8
|
Subcontractors
and Suppliers
|
|
|
|
|
|
|
|
GC
3.9
|
Labour and
Products
|
|
|
|
GC
3.10
|
Documents at
The Site
|
|
|
|
GC
3.11
|
Shop
Drawings
|
|
|
|
GC
3.12
|
Use of the
Work
|
|
|
|
GC
3.13
|
Cutting and
Remedial Work
|
Must not be
copied in whole or in part without the written
permission
|
|
|
GC
3.14
|
Cleanup
|
|
|
Standard Construction Document CCDC
2 -1994
AGREEMENT BETWEEN OWNER AND
CONTRACTOR
For use
when a stipulated price is the basis of payment
This
Agreement made on
the 2nd day of December in the year 2005
Century Resorts
Alberta Inc.
hereinafter
called the "Owner"
Chandos
Construction Ltd.
hereinafter
called the "Contractor"
The
Owner and the Contractor agree as
follows:
1.1
perform the Work required
by the Contract Documents for
Celebrations
Hotel & Casino Edmonton, Alberta
13103 Fort Rd.,
Edmonton, Alberta, Canada
which have been signed by the parties, and for
which Unigroup Architecture & Interior Design Inc.
is acting as
and is hereinafter called the "Consultant" and
1.2 do and fulfill everything indicated by this
Agreement, and
|
1.3
|
commence the
Work by the 6th day of May in the year 2005 and, subject
to adjustment in Contract Time as provided for in the
Contract Documents, attain Substantial Performance of
the Work, by the 30th day of November in the year
2006
|
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC
2 - 1994 except to
the extent that any alterations, additions or modifications are set
forth in supplementary conditions.
|
2.1
|
The
Contract supersedes all prior negotiations,
representations, or agreements, either written or oral, relating in
any manner to the Work, including the bidding documents
that are not expressly listed in Article A-3 of the Agreement -
CONTRACT DOCUMENTS.
|
2.2 The Contract may be amended only as
provided in the Contract Documents.
3.1 The
following are the Contract Documents referred to in
Article A-1 of the Agreement - THE
WORK:
• Agreement Between Owner and
Contractor
• The General Conditions of the Stipulated Price
Contract
-Supplementary
General Conditions (labelled Appendix "A").
|
-List of
exclusions and clarifications dated Nov 29, 2005(labelled Appendix
"B").
|
-Drawings as
per the attached list (labelled Appendix "C")
|
-Specifications
as per the attached list (labelled Appendix "D")
|
-Contract set
of plans, specifications and addenda (labelled Appendix
"E").
|
-List of Labour
Rates for Chandos Construction Ltd. own forces work on change
notices and change directives (labelled Appendix "F").
|
-Tender Package
3 Addendum #1 dated Feb 22, 2005
|
-Tender Package
3 Addendum #2 dated Mar 24, 2005 containing Architectural Addendum
No. 1 dated Mar 23, 2005, Structural Addendum No. 1 dated Mar 23,
2005, Mechanical Addendum M-l dated Mar 22, 2005, and Electrical
Addendum E-l dated Mar 23, 2005.
|
-Tender Package
3 Structural Post Tender Addendum No. 1 dated Apr 7,
2005.
|
-Tender Package
4 Structural Addendum No. 1 dated Apr 27, 2005
|
-Tender Package
4 Addendum No. 2 dated May 5, 2005 containing Structural Post
Tender Addendum No. 2 dated Apr 27, 2005.
|
-Tender Package
4 Addendum No. 3 dated May 5, 2005
|
-Tender Package
4 Addendum No. 4 dated May 6, 2005 containing Structural Addendum
No. 2 dated May 6, 2005.
|
-Tender Package
5 Addendum No. 1 dated Oct 21, 2005
|
-Tender Package
5 Addendum No. 2 dated Oct 25, 2005 containing Architectural
Addendum No. 1 dated Oct 25, 2005, Mechanical Addendum M-l dated
Oct 25, 2005 and Electrical Addendum E-l dated Oct 24,
2005.
|
-Tender Package
5 Post Tender Addendum No. 1 dated Nov 7, 2005 containing
Architectural Addendum No. 2 dated Oct 28, 2005, Architectural
Addendum No. 3 dated Oct 31, 2005 and Post Tender Architectural
Addendum No. 1 dated Nov 2, 2005
|
(Insert here, attaching
additional pages if required, a list identifying all other Contract
Documents e.g. Supplementary Conditions; Specifications, giving a
list of contents with section numbers and titles, number of pages,
and date; Drawings, giving drawing number, title, date, revision
date or mark; Addenda, giving title, number, date)
CCDC 2-1994
File 00502
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 - 1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
ARTICLE
A-4
4.1
The Contract Price, which
excludes Value Added Taxes, is:
Twenty Two
Million Four Hundred Eighty Two Thousand dollars and
0 cents. $22,482,000.00
4.2
Value Added Taxes
(of 7 %) payable by the
Owner to the Contractor are:
One Million
Five Hundred Seventy Three Thousand Seven Hundred Forty dollars
and 0 cents. $ 1,573,740.00
4.3
Total amount payable by the
Owner to the Contractor for the construction of
the Work is:
Twenty Four
Million Fifty Five Thousand Seven Hundred Forty dollars and
0 cents. $24,055,740.00
4.4
All amounts are in Canadian
funds.
4.5
These amounts shall be subject to
adjustments as provided in the Contract
Documents.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign
this
contract if the document cover page bears a CCDC 2 copyright seal
to demonstrate that it is intended by the parties to be an accurate
and unamended version of
CCDC 2 -
1994 except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
ARTICLE
A-5 PAYMENT
|
|
Subject to the
provisions of the Contract Documents, and in accordance
with legislation and statutory
|
regulations respecting holdback percentages and,
where such legislation or regulations do not exist or
apply,
subject to a holdback of Ten ( 10 %) the Owner shall in
Canadian funds:
.1 make progress payments to the
Contractor on account of the Contract Price when
due in the amount certified by the Consultant together
with such Value Added Taxes as may be applicable to such
payment, and
.2 upon Substantial Performance of the
Work, pay to the Contractor the unpaid balance of the
holdback amount when due together with such Value Added
Taxes as may be applicable to such payment, and
.3 upon the issuance of the final certificate
for payment, pay to the Contractor the unpaid balance of
the Contract Price when due together with such Value
Added Taxes as may be applicable to such payment.
|
|
In the event of
loss or damage occurring where payment becomes due under the
property and boiler insurance
|
policies,
payments shall be made to the Contractor in accordance
with the provisions of GC 11.1 -
5.3
Interest
. 1 Should either party fail to make payments as
they become due under the terms of the Contract or in an
award by arbitration or court, interest at of Twelve percent ( 12 %) per annum above the bank rate on
such unpaid amounts shall also become due and payable until
payment. Such interest shall be compounded on a monthly basis. The
bank rate shall be the rate established by the Bank of Canada as
the minimum rate at which the Bank of Canada makes short term
advances to the chartered banks.
.2 Interest shall apply at the rate and in the
manner prescribed by paragraph 5.3.1 of this Article on the amount
of any claim settled pursuant to Part 8 of the General Conditions -
DISPUTE RESOLUTION from the date the amount would have been due and
payable under the Contract, had it not been in dispute, until the
date it is paid.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2-1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
ARTICLE
A-6 RECEIPT OF AND ADDRESSES FOR NOTICES
6.1 Notices in writing between the parties or
between them and the Consultant shall be considered to
have been received by the addressee on the date of delivery if
delivered to the individual, or to a member of the firm, or to an
officer of the corporation for whom they are intended by hand or by
registered post; or if sent by regular post, to have been delivered
within 5 Working Days of the date of mailing when
addressed as follows:
Century Resorts
Alberta Inc. P.O. Box 70071
137th Avenue
and 66th Street
Suite 202,
10408-124th Street
ARTICLE
A-7 LANGUAGE OF THE CONTRACT
|
|
When the
Contract Documents are prepared in both the English and
French languages, it is agreed that in the
|
event of any apparent discrepancy between the
English and French versions, the English language
•
Complete this statement by striking out inapplicable
term.
|
|
This Agreement
is drawn in English at the request of the parties hereto. La
presente convention est redigee en
|
anglais a la demande des parties.
ARTICLE
A-8 SUCCESSION
8.1 The
Contract Documents are to be read into and form part of.
this Agreement and the whole shall constitute the Contract
between the parties, and subject to the law and the provisions of
the Contract Documents shall enure to the benefit of and
be binding upon the parties hereto, their respective heirs, legal
representatives, successors, and assigns.
This
contract Li protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page hears
a CCDC 2 copyright seat to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
In
witness whereof the
parties hereto and by the hands of their duly authorized
representatives.
Century Resorts
Alberta Inc.
WITNESS
|
|
|
|
|
|
/s/ Josef
Wildling
|
|
|
/s/ Shawn
Gardener
|
|
signature
|
|
|
signature
|
|
Name: Josef
Wildling
Title: VP Project Development name and title of person signing
|
|
|
Name: Shawn
Gardener
Title: Project Manager, Chandos Contruction, LTD.
name and title of person signing
|
Chandos
Construction Ltd.
|
|
|
|
|
|
/s/ Roger Babichuck
|
|
|
|
|
signature
|
|
|
|
|
Name: Roger Babichuk
Title: Controller
name and title of person signing
|
|
|
|
|
|
|
|
|
|
/s/ Tom Redl
|
|
|
|
|
|
|
|
|
|
Name: Tom Redl
Title: President
|
|
|
|
N.B. Where
legal jurisdiction, local practice, or Owner or Contractor
requirement calls for:
|
(a)
|
proof of
authority to execute this document, attach such proof of authority
in the form of a certified copy of a resolution naming the
representative(s) authorized to sign the Agreement for and on
behalf of the corporation or partnership; or
|
(b) the affixing of a corporate seal, this Agreement
should be properly sealed.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 - 1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
Standard Construction Document CCDC
2 -1994
The following
Definitions shall apply to all Contract
Documents.
1.
Contract
The
Contract is the undertaking by the parties to perform
their respective duties, responsibilities, and obligations as
prescribed in the Contract Documents and represents the
entire agreement between the parties.
2.
Contract
Documents
The
Contract Documents consist of those documents listed in
Article A-3 of the Agreement - CONTRACT DOCUMENTS and amendments
agreed upon between the parties.
3.
Owner
The
Owner is the person or entity identified as such in the
Agreement. The term Owner means the Owner or the
Owner's authorized agent or representative as designated
to the Contractor in writing, but does not include the
Consultant.
4.
Contractor
The
Contractor is the person or entity identified as such in
the Agreement. The term Contractor means the
Contractor or the Contractor's authorized representative
as designated to the Owner in writing.
5.
Subcontractor
A
Subcontractor is a person or entity having a direct
contract with the Contractor to perform a part or parts of
the Work, or to supply Products worked to a special design
for the Work.
6.
Supplier
A
Supplier is a person or entity having a direct contract
with the Contractor to supply Products not worked
to a special design for the Work.
7.
Consultant
The
Consultant is the person or entity identified as such in
the Agreement. The Consultant is the Architect, the
Engineer, or entity licensed to practice in the province or
territory of the Place of the Work. The term
Consultant means the Consultant or the
Consultant's authorized representative.
8.
Project
The
Project means the total construction contemplated of which
the Work may be the whole or a part.
9.
Work
The
Work means the total construction and related services
required by the Contract Documents.
10.
Place of the
Work
The Place
of the Work is the designated site or location of the
Work identified in Article A-l of the Agreement -THE
WORK.
11.
Product
Product or
Products means material,
machinery, equipment, and fixtures forming the Work, but
does not include machinery and equipment used to prepare,
fabricate, convey, or erect the Work, which are referred
to as construction machinery and equipment.
12.
Provide
Provide means to supply and install.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this
contract if
the document cover page bears a CCDC 2 copyright seal to
demonstrate that it is intended by the parties to be an accurate
and unamended version of CCDC 2-
1994 except
to the extent that arty alterations, additions or modifications are
set forth in supplementary conditions.
13.
Contract
Price
The
Contract Price is the amount stipulated in Article A-4 of
the Agreement - CONTRACT PRICE.
14.
Contract
Time
The
Contract Time is the time stipulated in paragraph 1.3 of
Article A-l of the Agreement - THE WORK from commencement of the
Work to Substantial Performance of the
Work.
15.
Working
Day
Working
Day means a day other
than a Saturday, Sunday, or a holiday which is observed by the
construction industry in the area of the Place of the
Work.
16.
Supplemental
Instruction
A
Supplemental Instruction is an instruction, not involving
adjustment in the Contract Price or Contract
Time, in the form of specifications, drawings, schedules,
samples, models or written instructions, consistent with the intent
of the Contract Documents. It is to be issued by the
Consultant to supplement the Contract Documents
as required for the performance of the Work.
17.
Change
Order
A Change
Order is a written amendment to the Contract prepared
by the Consultant and signed by the Owner and the
Contractor stating their agreement upon:
the method of
adjustment or the amount of the adjustment in the Contract
Price, if any; and
the extent of
the adjustment in the Contract Time, if any.
18.
Change
Directive
A Change
Directive is a written instruction prepared by the
Consultant and signed by the Owner directing a
change in the Work within the general scope of the
Contract Documents.
19.
Substantial Performance of
the Work
Substantial
Performance of the Work is as defined in the lien legislation applicable
to the Place of the Work. If such legislation is not in
force or does not contain such definition, Substantial
Performance of the Work shall have been reached when the
Work is ready for use or is being used for the purpose
intended and is so certified by the Consultant.
20.
Value Added
Taxes
Value Added
Taxes means such sum as
shall be levied upon the Contract Price by the Federal or
any Provincial Government and is computed as a percentage of the
Contract Price and includes the Goods and Services Tax,
the Quebec Sales Tax and any similar tax, the payment or collection
of which is by the legislation imposing such tax an obligation of
the Contractor.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
Standard Construction Document CCDC
2-1994
GENERAL
CONDITIONS OF THE STIPULATED PRICE CONTRACT
PART I
GENERAL PROVISIONS
GC1.1
CONTRACT DOCUMENTS
|
1.1.1
|
The intent of
the Contract Documents is to include the labour,
Products, and services necessary for the performance of
the Work by the Contractor in accordance with
these documents. It is not intended, however, that the
Contractor shall supply products or perform work not
consistent with, not covered by, or not properly inferable from the
Contract Documents.
|
1.1.2 Nothing contained in
the Contract Documents shall create any contractual
relationship between:
.1 the Owner and a
Subcontractor, a Supplier, or their agent,
employee, or other person performing any of the
Work.
. 2the Consultant and the
Contractor, a Subcontractor, a Supplier,
or their agent, employee, or other person performing any of the
Work.
|
1.1.3
|
The
Contract Documents are complementary, and what is required
by any one shall be as binding as if required by all.
|
|
1.1.4
|
Words and
abbreviations which have well known technical or trade meanings are
used in the Contract Documents in accordance with such
recognized meanings.
|
|
1.1.5
|
References in
the Contract Documents to the singular shall be considered
to include the plural as the context requires.
|
|
1.1.6
|
The
specifications are that portion of the Contract Documents,
wherever located and whenever issued, consisting of the written
requirements and standards for Products, systems,
workmanship, and the services necessary for the performance of the
Work.
|
|
1.1.7
|
The drawings
are the graphic and pictorial portions of the Contract
Documents, wherever located and whenever issued, showing the
design, location, and dimensions of the Work, generally
including plans, elevations, sections, details, schedules, and
diagrams.
|
|
1.1.8
|
Neither the
organization of the specifications into divisions, sections, and
parts nor the arrangement of drawings shall control the
Contractor in dividing the work among
Subcontractors and Suppliers or in establishing
the extent of the work to be performed by a trade.
|
1.1.9 If there is a conflict within Contract
Documents:
. 1 the order of priority of documents, from highest
to lowest, shall be
• the Agreement between the Owner and the
Contractor,
• Supplementary Conditions,
• the General Conditions,
• Division 1 of the specifications,
• Divisions 2 through 16 of the
specifications,
• material and finishing schedules,
CCDC 2-1994
File 00712
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only s/j
contract if the document cover page bears a CCDC 2 copyright
seal to demonstrate that it is intended by the parties to be an
accurate and unamended version of 1994 except to the extent that
any alterations, additions or modifications are set forth in
supplementary conditions.
.2
drawings of larger scale shall
govern over those of smaller scale of the same date.
.3
dimensions shown on drawings shall
govern over dimensions scaled from drawings.
.4
later dated documents shall govern
over earlier documents of the same type.
|
1.1.10
|
The
Owner shall provide the Contractor, without
charge, sufficient copies of the Contract Documents to
perform the Work.
|
|
1.1.11
|
Specifications,
drawings, models, and copies thereof furnished by the
Consultant are and shall remain the Consultant's
property, with the exception of the signed Contract sets,
which shall belong to each party to the Contract. All
specifications, drawings, and models furnished by the
Consultant are to be used only with respect to the
Work and are not to be used on other work. These
specifications, drawings, and models are not to be copied or
altered in any manner without the written authorization of the
Consultant.
|
1.1.12 Models furnished by the Contractor at
the Owner's expense are the property of the
Owner.
GC1.2
LAW OF THE CONTRACT
1.2.1 The law
of the Place of the Work shall govern the interpretation
of the Contract.
GC1.3
RIGHTS AND REMEDIES
|
1.3.1
|
Except as
expressly provided in the Contract Documents, the duties
and obligations imposed by the Contract Documents and the
rights and remedies available thereunder shall be in addition to
and not a limitation of any duties, obligations, rights, and
remedies otherwise imposed or available by law.
|
|
1.3.2
|
No action or
failure to act by the Owner, Consultant, or
Contractor shall constitute a waiver of any right or duty
afforded any of them under the Contract, nor shall any
such action or failure to act constitute an approval of or
acquiescence in any breach thereunder, except as may be
specifically agreed in writing.
|
1.4.1 Neither party to the Contract
shall assign the Contract or a portion thereof without the
written consent of the other, which consent shall not be
unreasonably withheld.
PART 2
ADMINISTRATION OF THE CONTRACT
GC 2.1
AUTHORITY OF THE CONSULTANT
|
2.1.1
|
The
Consultant will have authority to act on behalf of the
Owner only to the extent provided in the Contract
Documents, unless otherwise modified by written agreement as
provided in paragraph 2.1.2.
|
|
2.1.2
|
The duties,
responsibilities, and limitations of authority of the
Consultant as set forth in the Contract Documents
shall be modified or extended only with the written consent of the
Owner, the Contractor, and the
Consultant.
|
|
2.1.3
|
If the
Consultants employment is terminated, the Owner
shall immediately appoint or reappoint a Consultant
against whom the Contractor makes no reasonable objection
and whose status under the Contract Documents shall be
that of the former Consultant.
|
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
GC2.2
ROLE OF THE CONSULTANT
|
2.2.1
|
The
Consultant will provide administration of the
Contract as described in the Contract Documents
during construction until issuance of the final certificate for
payment, and subject to GC 2.1 - AUTHORITY OF THE CONSULTANT and
with the Owner's concurrence, from time to time until the
completion of any correction of defects as provided in paragraph
12.3.3 of GC 12.3 - WARRANTY.
|
|
2.2.2
|
The
Consultant will visit the Place of the Work at
intervals appropriate to the progress of construction to become
familiar with the progress and quality of the work and to determine
if the Work is proceeding in general conformity with the
Contract Documents.
|
|
2.2.3
|
If the
Owner and the Consultant agree, the
Consultant will provide at the Place of the Work,
one or more project representatives to assist in carrying out the
Consultant's responsibilities. The duties,
responsibilities, and limitations of authority of such project
representatives shall be as set forth in writing to the
Contractor.
|
|
2.2.4
|
Based on the
Consultant's observations and evaluation of the
Contractor's applications for payment, the
Consultant will determine the amounts owing to the
Contractor under the Contract and will issue
certificates for payment as provided in Article A-5 of the
Agreement - PAYMENT, GC 5.3 - PROGRESS PAYMENT, and GC 5.7 - FINAL
PAYMENT.
|
|
2.2.5
|
The
Consultant will not be responsible for and will not have
control, charge, or supervision of construction means, methods,
techniques, sequences, or procedures, or for safety precautions and
programs required in connection with the Work in
accordance with the applicable construction safety legislation,
other regulations, or general construction practice. The
Consultant will not be responsible for the
Contractor's failure to carry out the Work in
accordance with the Contract Documents. The
Consultant will not have control over, charge of, or be
responsible for the acts or omissions of the Contractor,
Subcontractors, Suppliers, or their agents, employees, or any
other persons performing portions of the Work.
|
|
2.2.6
|
The
Consultant will be, in the first instance, the interpreter
of the requirements of the Contract Documents and shall
make findings as to the performance thereunder by both parties to
the Contract, except with respect to GC 5.1 - FINANCING
INFORMATION REQUIRED OF THE OWNER. Interpretations and findings of
the Consultant shall be consistent with the intent of the
Contract Documents. When making such interpretations and
findings the Consultant will not show partiality to either
the Owner or the Contractor.
|
|
2.2.7
|
Claims,
disputes, and other matters in question relating to the performance
of the Work or the interpretation of the Contract
Documents, except for GC 5.1 - FINANCING INFORMATION REQUIRED
OF THE OWNER, shall be referred initially to the
Consultant by notice in writing given to the
Consultant and to the other party for the
Consultants interpretation and finding which will be given
by notice in writing to the parties within a reasonable
time.
|
|
2.2.8
|
The
Consultant will have authority to reject work which in the
Consultant's opinion does not conform to the requirements
of the Contract Documents. Whenever the
Consultant considers it necessary or advisable, the
Consultant will have authority to require inspection or
testing of work, whether or not such work is fabricated, installed,
or completed. However, neither the authority of the
Consultant to act nor any decision either to exercise or
not to exercise such authority shall give rise to any duty or
responsibility of the Consultant to the Contractor,
Subcontractors, Suppliers, or their agents, employees, or
other persons performing any of the Work.
|
|
2.2.9
|
During the
progress of the Work the Consultant will furnish
Supplemental Instructions to the Contractor with
reasonable promptness or in accordance with a schedule for such
instructions agreed to by the Consultant and the
Contractor.
|
|
2.2.10
|
The
Consultant will review and take appropriate action upon
such Contractor's submittals as shop drawings,
Product data, and samples, as provided in the Contract
Documents.
|
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
|
2.2.11
|
The
Consultant will prepare Change Orders and
Change Directives as provided in GC 6.2 - CHANGE ORDER and
GC 6.3 - CHANGE DIRECTIVE.
|
|
2.2.12
|
The
Consultant will conduct reviews of the Work to
determine the date of Substantial Performance of the Work
as provided in GC 5.4 - SUBSTANTIAL PERFORMANCE OF THE
WORK.
|
|
2.2.13
|
All
certificates issued by the Consultant shall be to the best
of the Consultants knowledge, information, and belief. By
issuing any certificate, the Consultant does not guarantee
the Work is correct or complete.
|
|
2.2.14
|
The
Consultant will receive and review written warranties and
related documents required by the Contract and provided by
the Contractor and will forward such warranties and
documents to the Owner for the Owner's
acceptance.
|
GC2.3
REVIEW AND INSPECTION OF THE WORK
|
2.3.1
|
The
Owner and the Consultant shall have access to the
Work at all times. The Contractor shall provide
sufficient, safe, and proper facilities at all times for the review
of the Work by the Consultant and the inspection
of the Work by authorized agencies. If parts of the
Work are in preparation at locations other than the
Place of the Work, the Owner and the
Consultant shall be given access to such work whenever it
is in progress.
|
|
2.3.2
|
If work is
designated for tests, inspections, or approvals in the Contract
Documents, or by the Consultant's instructions, or
the laws or ordinances of the Place of the Work, the
Contractor shall give the Consultant reasonable
notice of when the work will be ready for review and inspection.
The Contractor shall arrange for and shall give the
Consultant reasonable notice of the date and time of
inspections by other authorities.
|
|
2.3.3
|
The
Contractor shall furnish promptly to the
Consultant two copies of certificates and inspection
reports relating to the Work.
|
|
|
|
If the Contractor covers or permits to
be covered, work that has been designated for special tests,
inspections, or approvals before such special tests, inspections,
or approvals are made, given or completed, the Contractor
shall, if so directed, uncover such work, have the inspections or
tests satisfactorily completed, and make good covering work at the
Contractor's expense.
|
|
|
The
Consultant may order any portion or portions of the
Work to be examined to confirm that such work is in
accordance with the requirements of the Contract
Documents. If the work is not in accordance with the
requirements of the Contract Documents, the
Contractor shall correct the work and pay the cost of
examination and correction. If the work is in accordance with the
requirements of the Contract Documents, the Owner
shall pay the cost of examination and restoration.
|
GC2.4
DEFECTIVE WORK
|
2.4.1
|
The
Contractor shall promptly remove from the Place of the
Work and replace or re-execute defective work that has been
rejected by the Consultant as failing to conform to the
Contract Documents whether or not the defective work has
been incorporated in the Work and whether or not the
defect is the result of poor workmanship, use of defective
products, or damage through carelessness or other act or omission
of the Contractor.
|
|
2.4.2
|
The
Contractor shall make good promptly other contractors'
work destroyed or damaged by such removals or replacements at the
Contractor's expense.
|
|
2.4.3
|
If in the
opinion of the Consultant it is not expedient to correct
defective work or work not performed as provided in the
Contract Documents, the Owner may deduct from the
amount otherwise due to the Contractor the difference in
value between the work as performed and that called for by the
Contract Documents. If the
|
This
contract is protected
by Copyright. Use of a CCDC 2 document not containing a CCDC 2
copyright seal constitutes an infringement of Copyright. Only sign
this contract if the document cover page bears a CCDC 2 copyright
seal to demonstrate that it is intended by the parties to be an
accurate and unamended version of CCDC 2 - 1994 except to
the extent that any alterations, additions or modifications are set
forth in supplementary conditions.
Owner and the Contractor do not agree on the
difference in value, they shall refer the matter to the
Consultant for a determination.
PART 3
EXECUTION OF THE WORK
GC3.1
CONTROL OF THE WORK
|
3.1.1
|
The
Contractor shall have total control of the Work
and shall effectively direct and supervise the Work so as
to ensure conformity with the Contract
Documents.
|
|
3.1.2
|
The
Contractor shall be solely responsible for construction
means, methods, techniques, sequences, and procedures and for
co-ordinating the various parts of the Work under the
Contract.
|
GC3.2
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS
|
3.2.1
|
The
Owner reserves the right to award separate contracts in
connection with other parts of the Project to other
contractors and to perform work with own forces.
|
|
3.2.2
|
When separate
contracts are awarded for other parts of the Project, or
when work is performed by the Owner's own forces, the
Owner shall:
|
.1 provide for the co-ordination of the
activities and work of other contractors and Owner's own
forces with the Work of the Contract;
.2 assume overall responsibility for compliance
with the applicable health and construction safety legislation at
the Place of the Work;
.3 enter into separate contracts with other
contractors under conditions of contract which are compatible with
the conditions of the Contract;
.4 ensure that insurance coverage is provided to
the same requirements as are called for in GC 11.1 -INSURANCE and
co-ordinate such insurance with the insurance coverage of the
Contractor as it affects the Work; and
.5 take all reasonable precautions to avoid
labour disputes or other disputes on the Project arising
from the work of other contractors or the Owner's own
forces.
|
|
3.2.3
|
When
separate contracts are awarded for other parts of the
Project, or when work is performed by the
Owner's
|
own forces, the Contractor
shall:
. 1 afford the Owner and other
contractors reasonable opportunity to introduce and store their
products and use their construction machinery and equipment to
execute their work;
.2 co-ordinate and schedule the Work
with the work of other contractors and Owner's own forces
and connect as specified or shown in the Contract
Documents;
.3 participate with other contractors and the
Owner in reviewing their construction schedules when
directed to do so; and
.4 where part of the Work is affected
by or depends upon for its proper execution the work of other
contractors or Owner's own forces, promptly report to the
Consultant in writing and prior to proceeding with that
part of the Work, any apparent deficiencies in such
work.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
Failure by the
Contractor to so report shall invalidate any claims
against the Owner by reason of the deficiencies in the
work of other contractors or Owner's own forces except
those deficiencies not then reasonably discoverable.
|
3.2.4
|
Where a change
in the Work is required as a result of the co-ordination
and connection of the work of other contractors or Owner's
own forces with the Work, the changes shall be authorized
and valued as provided in GC 6.1 - CHANGES, GC 6.2 - CHANGE ORDER,
and GC 6.3 - CHANGE DIRECTIVE.
|
|
3.2.5
|
Claims,
disputes, and other matters in question between the
Contractor and other contractors shall be dealt with as
provided in Part 8 of the General Conditions - DISPUTE RESOLUTION
provided the other contractors have reciprocal obligations. The
Contractor shall be deemed to have consented to
arbitration of any dispute with any other contractor whose contract
with the Owners contains a similar agreement to
arbitrate.
|
GC 3.3 TEMPORARY SUPPORTS, STRUCTURES, AND
FACILITIES
|
3.3.1
|
The
Contractor shall have the sole responsibility for the
design, erection, operation, maintenance, and removal of temporary
supports, structures, and facilities and the design and execution
of construction methods required in their use.
|
|
3.3.2
|
The
Contractor shall engage and pay for registered
professional engineering personnel skilled in the appropriate
disciplines to perform those functions referred to in paragraph
3.3.1 where required by law or by the Contract Documents
and in all cases where such temporary supports, structures, and
facilities and their method of construction are of such a nature
that professional engineering skill is required to produce safe and
satisfactory results.
|
|
3.3.3
|
Notwithstanding
the provisions of GC 3.1 - CONTROL OF THE WORK, paragraph 3.3.1,
and paragraph 3.3.2 or provisions to the contrary elsewhere in the
Contract Documents where such Contract Documents
include designs for temporary supports, structures, and facilities
or specify a method of construction in whole or in part, such
facilities and methods shall be considered to be part of the design
of the Work and the Contractor shall not be held
responsible for that part of the design or the specified method of
construction. The Contractor shall, however, be
responsible for the execution of such design or specified method of
construction in the same manner as for the execution of the
Work.
|
3.4.1 The
Contractor shall review the Contract Documents
and shall report promptly to the Consultant any error,
inconsistency, or omission the Contractor may discover.
Such review by the Contractor shall be to the best of the
Contractor's knowledge, information, and belief and in
making such review the Contractor does not assume any
responsibility to the Owner or the Consultant for
the accuracy of the review. The Contractor shall not be
liable for damage or costs resulting from such errors,
inconsistencies, or omissions in the Contract Documents,
which the Contractor did not discover. If the
Contractor does discover any error, inconsistency, or
omission in the Contract Documents, the
Contractor shall not proceed with the work affected until
the Contractor has received corrected or missing
information from the Consultant.
GC 3.5
CONSTRUCTION SCHEDULE
3.5.1 The
Contractor shall:
.1 prepare and submit to the Owner and
the Consultant prior to the first application for payment,
a construction schedule that indicates the timing of the major
activities of the Work and provides sufficient detail of
the critical events and their inter-relationship to demonstrate the
Work will be performed in conformity with the Contract
Time;
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
.2 monitor the progress of the Work
relative to the construction schedule and update the schedule on a
monthly basis or as stipulated by the Contract Documents;
and
.3 advise the Consultant of any revisions
required to the schedule as the result of extensions of the
Contract Time as provided in Part 6 of the General
Conditions - CHANGES IN THE WORK.
GC 3.6
CONSTRUCTION SAFETY
|
|
|
Subject to
paragraph 3.2.2.2 of GC 3.2 - CONSTRUCTION BY OWNER OR OTHER
CONTRACTORS, the Contractor shall be solely responsible
for construction safety at the Place of the Work and for
compliance with the rules, regulations, and practices required by
the applicable construction health and safety legislation and shall
be responsible for initiating, maintaining, and supervising all
safety precautions and programs in connection with the performance
of the Work.
|
|
3.7.1
|
The
Contractor shall employ a competent supervisor and
necessary assistants who shall be in attendance at the Place of
the Work while work is being performed. The supervisor shall
not be changed except for valid reason.
|
|
3.7.2
|
The supervisor
shall represent the Contractor at the Place of the
Work and notices and instructions given to the supervisor by
the Consultant shall be held to have been received by the
Contractor.
|
GC 3.8
SUBCONTRACTORS AND SUPPLIERS
|
|
The
Contractor shall preserve and protect the rights of the
parties under the Contract with respect to work
to
|
be performed under
subcontract, and shall:
.1 enter into contracts or written agreements
with Subcontractors and Suppliers to require them
to perform their work as provided in the Contract
Documents;
.2 incorporate the terms and conditions of the
Contract Documents into all contracts or written
agreements with Subcontractors and Suppliers;
and
.3 be as fully responsible to the Owner
for acts and omissions of Subcontractors, Suppliers, and
of persons directly or indirectly employed by them as for acts and
omissions of persons directly employed by the
Contractor.
|
3.8.2
|
The
Contractor shall indicate in writing, at the request of
the Owner, those Subcontractors or
Suppliers whose bids have been received by the
Contractor which the Contractor would be prepared
to accept for the performance of a portion of the Work.
Should the Owner not object before signing the
Contract, the Contractor shall employ those
Subcontractors or Suppliers so identified by the
Contractor in writing for the performance of that portion
of the Work to which their bid applies.
|
|
3.8.3
|
The
Owner may, for reasonable cause, at any time before the
Owner has signed the Contract, object to the use
of a proposed Subcontractor or Supplier and
require the Contractor to employ one of the other
subcontract bidders.
|
|
3.8.4
|
If the
Owner requires the Contractor to change a
proposed Subcontractor or Supplier, the
Contract Price and Contract Time shall be
adjusted by the differences occasioned by such required
change.
|
|
3.8.5
|
The
Contractor shall not be required to employ as a
Subcontractor or Supplier, a person or firm to
whom the Contractor may reasonably object.
|
CCDC 2-1994
File 00712
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
condition*.
3.8.6 The Owner, through the
Consultant, may provide to a Subcontractor or
Supplier information as to the percentage of the
Subcontractor's or Supplier's work which has been
certified for payment.
GC3.9
LABOUR AND PRODUCTS
|
3.9.1
|
The
Contractor shall provide and pay for labour,
Products, tools, construction machinery and equipment,
water, heat, light, power, transportation, and other facilities and
services necessary for the performance of the Work in
accordance with the Contract.
|
|
3.9.2
|
Products provided shall be new. Products which
are not specified shall be of a quality consistent with those
specified and their use acceptable to the
Consultant.
|
|
3.9.3
|
The
Contractor shall maintain good order and discipline among
the Contractor's employees engaged on the Work
and shall not employ on the Work anyone not skilled in the
tasks assigned.
|
GC 3.10
DOCUMENTS AT THE SITE
3.10.1 The Contractor shall keep one
copy of current Contract Documents, submittals, reports,
and records of meetings at the Place of the Work, in good
order and available to the Owner and the
Consultant.
|
3.11.1
|
Shop drawings
are drawings, diagrams, illustrations, schedules, performance
charts, brochures, Product, and other data which the
Contractor provides to illustrate details of a portion of
the Work.
|
|
3.11.2
|
The
Contractor shall provide shop drawings as described in the
Contract Documents or as the Consultant may
reasonably request.
|
|
3.11.3
|
The
Contractor shall review all shop drawings prior to
submission to the Consultant. The Contractor
represents by this review that: the Contractor has
determined and verified all field measurements and field
construction conditions, or will do so; Product
requirements; catalogue numbers; and similar data and that the
Contractor has checked and co-ordinated each shop drawing
with the requirements of the Work and of the Contract
Documents. The Contractor shall confirm this review
of each shop drawing by stamp, date, and signature of the person
responsible. At the time of submission the Contractor
shall notify the Consultant in writing of any deviations
in the shop drawings from the requirements of the Contract
Documents.
|
3.11 4The Contractor shall submit
shop drawings to the Consultant to review in orderly
sequence and sufficiently in advance so as to cause no delay in the
Work or in the work of other contractors. Upon request of
the Contractor or the Consultant, they jointly
shall prepare a schedule of the dates for submission and return of
shop drawings. Shop drawings which require approval of any legally
constituted authority having jurisdiction shall be submitted to
such authority by the Contractor for approval.
|
3.11.5
|
The
Contractor shall submit shop drawings in the form
specified or as the Consultant may direct. The
Consultant will review and return shop drawings in
accordance with the schedule agreed upon, or otherwise with
reasonable promptness so as to cause no delay. The
Consultant's review is for conformity to the design
concept and for general arrangement only. The Consultant's
review shall not relieve the Contractor of responsibility
for errors or omissions in the shop drawings or for meeting all
requirements of the Contract Documents unless the
Consultant expressly notes the acceptance of a deviation
on the shop drawings.
|
|
3.11.6
|
Upon the
Consultants request, the Contractor shall revise
and resubmit shop drawings which the Consultant rejects as
inconsistent with the Contract Documents unless otherwise
directed by the Consultant. The Contractor shall
notify the Consultant in writing of any revisions to the
resubmission other than those requested by the
Consultant.
|
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
|
3.12.1
|
The
Contractor shall confine construction machinery and
equipment, storage of Products, and operations of
employees to limits indicated by laws, ordinances, permits, or the
Contract Documents and shall not unreasonably encumber the
Work with Products.
|
|
3.12.2
|
The
Contractor shall not load or permit to be loaded any part
of the Work with a weight or force that will endanger the
safety of the Work.
|
GC 3.13
CUTTING AND REMEDIAL WORK
|
3.13.1
|
The
Contractor shall do the cutting and remedial work required
to make the several parts of the Work come together
properly.
|
3.13.2 The Contractor shall co-ordinate the
Work to ensure that this requirement is kept to a
minimum.
|
3.13.3
|
Should the
Owner, the Consultant, other contractors or
anyone employed by them be responsible for ill-timed work
necessitating cutting or remedial work to be performed, the cost of
such cutting or remedial work shall be valued as provided in GC 6.1
- CHANGES, GC 6.2 - CHANGE ORDER, and GC 6.3 - CHANGE
DIRECTIVE.
|
|
3.13.4
|
Cutting and
remedial work shall be performed by specialists familiar with the
Products affected and shall be performed in a manner to
neither damage nor endanger the Work.
|
|
3.14.1
|
The
Contractor shall maintain the Work in a tidy
condition and free from the accumulation of waste products and
debris, other than that caused by the Owner, other
contractors or their employees.
|
|
3.14.2
|
The
Contractor shall remove waste products and debris, other
than that resulting from the work of the Owner, other
contractors or their employees, and shall leave the Work
clean and suitable for occupancy by the Owner before
attainment of Substantial Performance of the Work. The
Contractor shall remove products, tools, construction
machinery, and equipment not required for the performance of the
remaining work.
|
|
3.14.3
|
Prior to
application for the final certificate for payment, the
Contractor shall remove products, tools, construction
machinery and equipment, and waste products and debris, other than
that resulting from the work of the Owner, other
contractors or their employees.
|
|
4.1.1
|
The
Contract Price includes cash allowances stated in the
Contract Documents, which allowances shall be expended as
the Owner directs through the
Consultant.
|
|
4.1.2
|
Cash allowances
cover the net cost to the Contractor of services,
Products, construction machinery and equipment, freight,
unloading, handling, storage, installation, and other authorized
expenses incurred in performing the work stipulated under the cash
allowances but do not include any Value Added Taxes
payable by the Owner to the
Contractor.
|
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this
contract if
the document cover page bears a CCDC 2 copyright seal to
demonstrate that it is intended by the parties to be an accurate
and unamended version of CCDC 2 -
1994 except
to the extent that any alterations, additions or modifications are
set forth in supplementary conditions.
4.1.3 The Contract Price, and not the cash
allowances, includes the Contractor's overhead and profit
in connection with such cash allowances.
|
4.1.4
|
Where costs
under a cash allowance exceed the amount of the allowance, the
Contractor shall be compensated for any excess incurred
and substantiated plus an amount for overhead and profit as set out
in the Contract Documents.
|
|
4.1.5
|
The
Contract Price shall be adjusted by Change Order
to provide for any difference between the actual cost and each cash
allowance.
|
4.1.6 The value of the work performed under a cash allowance
is eligible to be included in progress payments.
|
4.1.7
|
The
Contractor and the Consultant shall jointly
prepare a schedule that shows when the Consultant and
Owner must authorize ordering of items called for under
cash allowances to avoid delaying the progress of the
Work.
|
GC4.2
CONTINGENCY ALLOWANCE
4.2.1 The
Contract Price includes the contingency allowance, if any,
stated in the Contract Documents.
|
4.2.2
|
Expenditures
under the contingency allowance shall be authorized and valued as
provided in GC 6.1 -CHANGES, GC 6.2 - CHANGE ORDER, and GC 6.3 -
CHANGE DIRECTIVE.
|
|
4.2.3
|
The
Contract Price shall be adjusted by Change Order
to provide for any difference between the expenditures authorized
under paragraph 4.2.2 and the contingency allowance.
|
GC5.1
FINANCING INFORMATION REQUIRED OF THE OWNER
|
5.1.1
|
The
Owner shall, at the request of the Contractor,
prior to execution of the Agreement, and/or promptly from time to
time thereafter, furnish to the Contractor reasonable
evidence that financial arrangements have been made to fulfill the
Owner's obligations under the
Contract.
|
|
5.1.2
|
The
Owner shall notify the Contractor in writing of
any material change in the Owner's financial arrangements
during the performance of the Contract.
|
GC 5.2
APPLICATIONS FOR PROGRESS PAYMENT
|
5.2.1
|
Applications
for payment on account as provided in Article A-5 of the Agreement
- PAYMENT may be made monthly as the Work
progresses.
|
|
5.2.2
|
Applications
for payment shall be dated the last day of the agreed monthly
payment period and the amount claimed shall be for the value,
proportionate to the amount of the Contract, of work
performed and Products delivered to the Place of the
Work at that date.
|
|
5.2.3
|
The
Contractor shall submit to the Consultant, at
least 14 days before the first application for payment, a schedule
of values for the parts of the Work, aggregating the total
amount of the Contract Price, so as to facilitate
evaluation of applications for payment.
|
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
|
5.2.4
|
The schedule of
values shall be made out in such form and supported by such
evidence as the Consultant may reasonably direct and when
accepted by the Consultant, shall be used as the basis for
applications for payment, unless it is found to be in
error.
|
5.2.5 The Contractor shall include a
statement based on the schedule of values with each application for
payment.
|
5.2.6
|
Claims for
Products delivered to the Place of the Work but
not yet incorporated into the Work shall be supported by
such evidence as the Consultant may reasonably require to
establish the value and delivery of the
Products.
|
|
5.3.1
|
The
Consultant will issue to the Owner, no later than
10 days after the receipt of an application for payment from the
Contractor submitted in accordance with GC 5.2 -
APPLICATIONS FOR PROGRESS PAYMENT, a certificate for payment in the
amount applied for or in such other amount as the
Consultant determines to be properly due. If the
Consultant amends the application, the Consultant
will promptly notify the Contractor in writing giving
reasons for the amendment.
|
|
5.3.2
|
The
Owner shall make payment to the Contractor on
account as provided in Article A-5 of the Agreement -PAYMENT no
later than 5 days after the date of a certificate for payment
issued by the Consultant.
|
GC 5.4
SUBSTANTIAL PERFORMANCE OF THE WORK
|
5.4.1
|
When the
Contractor considers that the Work is
substantially performed, or if permitted by the lien legislation
applicable to the Place of the Work a designated portion
thereof which the Owner agrees to accept separately is
substantially performed, the Contractor shall prepare and
submit to the Consultant a comprehensive list of items to
be completed or corrected and apply for a review by the
Consultant to establish Substantial Performance of the
Work or substantial performance of the designated portion of
the Work. Failure to include an item on the list does not
alter the responsibility of the Contractor to complete the
Contract.
|
|
5.4.2
|
No later than
10 days after the receipt of the Contractor's list and
application, the Consultant will review the Work
to verify the validity of the application, and no later than 7 days
after completing the review, will notify the Contractor
whether the Work or the designated portion of the
Work is substantially performed.
|
|
5.4.3
|
The
Consultant shall state the date of Substantial
Performance of the Work or designated portion of the
Work in a certificate.
|
|
5.4.4
|
Immediately
following the issuance of the certificate of Substantial
Performance of the Work, the Contractor, in
consultation with the Consultant, will establish a
reasonable date for finishing the Work.
|
GC 5.5
PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE
WORK
5.5.1 After the
issuance of the certificate of Substantial Performance of the
Work, the Contractor shall:
. 1
submit an application for payment
of the holdback amount,
.2
submit a sworn statement that all
accounts for labour, subcontracts, Products, construction
machinery and equipment, and other indebtedness which may have been
incurred by the Contractor in the Substantial
Performance of the Work and for which the Owner might
in any way be held responsible have been paid in full, except for
amounts properly retained as a holdback or as an identified amount
in dispute.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to he an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
5.5.2 After the receipt of an application
for payment from the Contractor and the sworn statement as
provided in paragraph 5.5.1, the Consultant will issue a
certificate for payment of the holdback amount.
|
5.5.3
|
Where the
holdback amount has not been placed in a separate holdback account,
the Owner shall, 10 days prior to the expiry of the
holdback period stipulated in the lien legislation applicable to
the Place of the Work, place the holdback amount in a bank
account in the joint names of the Owner and the
Contractor.
|
|
5.5.4
|
The holdback
amount authorized by the certificate for payment of the holdback
amount is due and payable on the day following the expiration of
the holdback period stipulated in the lien legislation applicable
to the Place of the Work. Where lien legislation does not
exist or apply, the holdback amount shall be due and payable in
accordance with other legislation, industry practice, or provisions
which may be agreed to between the parties. The Owner may
retain out of the holdback amount any sums required by law to
satisfy any liens against the Work or, if permitted by the
lien legislation applicable to the Place of the Work,
other third party monetary claims against the Contractor
which are enforceable against the Owner.
|
GC5.6
PROGRESSIVE RELEASE OF HOLDBACK
|
5.6.1
|
Where
legislation permits and where, upon application by the
Contractor, the Consultant has certified that the
work of a Subcontractor or Supplier has been
performed prior to Substantial Performance of the Work,
the Owner shall pay the Contractor the holdback
amount retained for such subcontract work, or the Products
supplied by such Supplier, on the day following the
expiration of the holdback period for such work stipulated in the
lien legislation applicable to the Place of the
Work.
|
|
5.6.2
|
Notwithstanding
the provisions of the preceding paragraph, and notwithstanding the
wording of such certificates, the Contractor shall ensure
that such subcontract work or Products is protected
pending the issuance of a final certificate for payment and be
responsible for the correction of defects or work not performed
regardless of whether or not such was apparent when such
certificates were issued.
|
|
5.7.1
|
When the
Contractor considers that the Work is completed,
the Contractor shall submit an application for final
payment.
|
|
5.7.2
|
The
Consultant will, no later than 10 days after the receipt
of an application from the Contractor for final payment,
review the Work to verify the validity of the application.
The Consultant will, no later than 7 days after reviewing
the Work, notify the Contractor that the
application is valid or give reasons why it is not
valid.
|
|
5.7.3
|
When the
Consultant finds the Contractor's application for
final payment valid, the Consultant will issue a
final certificate for payment.
|
|
5.7.4
|
Subject to the
provision of paragraph 10.4.1 of GC 10.4 - WORKERS' COMPENSATION,
and any lien legislation applicable to the Place of the
Work, the Owner shall, no later than 5 days after the
issuance of a final certificate for payment, pay the
Contractor as provided in Article A-5 of the Agreement -
PAYMENT.
|
GC 5.8
WITHHOLDING OF PAYMENT
5.8.1 If because of climatic
or other conditions reasonably beyond the control of the
Contractor, there are items of work that cannot be
performed, payment in full for that portion of the Work
which has been performed as certified by the Consultant
shall not be withheld or delayed by the Owner on account
thereof, but the Owner may withhold, until the remaining
portion of the Work is finished, only such an amount that
the Consultant determines is sufficient and reasonable to
cover the cost of performing such remaining work.
This
contract is protected by Copyright. Use of a CCDC 2 document not
containing a CCDC 2 copyright seal constitutes an infringement of
Copyright. Only sign this contract if the document cover page bears
a CCDC 2 copyright seal to demonstrate that it is intended by the
parties to be an accurate and unamended version of CCDC 2 -1994
except to the extent that any alterations, additions or
modifications are set forth in supplementary
conditions.
GC 5.9
NON-CONFORMING WORK
5.9.1 No payment by the Owner under the
Contract nor partial or entire use or occupancy of the
Work by the Owner shall constitute an acceptance
of any portion of the Work or Products which are
not in accordance with the requirements of the Contract
Documents.
PART 6
CHANGES IN THE WORK
|
6.1.1
|
The
Owner, through the Consultant, without
invalidating the Contract, may make changes in the
Work consisting of additions, deletions, or other
revisions to the Work by Change Order or
Change Directive.
|
6.1.2 The Contractor shall not perform a
change in the Work without a Change Order or a
Change Directive.
|
6.2.1
|
When a change
in the Work is proposed or required, the
Consultant shall provide a notice describing the proposed
change in the Work to the Contractor. The
Contractor shall present, in a form acceptable to the
Consultant, a method of adjustment or an amount of
adjustment for the Contract Price, if any, and the
adjustment in the Contract Time, if any, for the proposed
change in the Work.
|
|
6.2.2
|
When the
Owner and Contractor agree to the adjustments in
the Contract Price and Contract Time or to the
method to be used to determine the adjustments, such agreement
shall be effective immediately and shall be recorded in a
Change Order, signed by Owner and
Contractor. The value of the work performed as the result
of a Change Order shall be included in applications for
progress payment.
|
|
6.3.1
|
If the
Owner requires the Contractor to proceed with a
change in the Work prior to the Owner and the
Contractor agreeing upon the adjustment in Contract
Price and Contract Time, the Owner, through
the Consultant, shall issue a Change
Directive.
|
|
6.3.2
|
Upon receipt of
a Change Directive, the Contractor shall proceed
promptly with the change in the Work. The adjustment in
the Contract Price for a change carried out by way of a
Change Directive shall be determined on the basis of the
cost of expenditures and savings to perform the work attributable
to the change. If a change in the Work results in a net
increase in the Contract Price, an allowance for overhead
and profit shall be included.
|
|
6.3.3
|
If a change in
the Work results in a net decrease in the Contract
Price, the amount of the credit shall be the net cost, without
deduction for overhead or profit. When both additions and deletions
covering related work or substitutions are involved in a change in
the Work, the allowance for overhead and profit shall be
calculated on the basis of the net increase, if any, with respect
to that change in the Work.
|
|
6.3.4
|
The
Contractor shall keep and present, in such fo
|
|