Back to top

SECTION 00500 EJCDC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE EJCDC NO. 1910-8-A-1 (1996 EDITION)

Construction Agreement

SECTION 00500 EJCDC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE EJCDC NO. 1910-8-A-1 (1996 EDITION) | Document Parties: Volkmann Railroad Builders, Inc. | Town of Randolph You are currently viewing:
This Construction Agreement involves

Volkmann Railroad Builders, Inc. | Town of Randolph

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: SECTION 00500 EJCDC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE EJCDC NO. 1910-8-A-1 (1996 EDITION)
Date: 3/21/2005

SECTION 00500 EJCDC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE EJCDC NO. 1910-8-A-1 (1996 EDITION), Parties: volkmann railroad builders  inc. , town of randolph
50 of the Top 250 law firms use our Products every day

Exhibit 10.13

 

SECTION 00500

EJCDC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE EJCDC NO. 1910-8-A-1 (1996 EDITION)

 

THIS AGREEMENT is dated as of the 15 th day of October in the year 2004 by and between Town of Randolph (hereinafter called OWNER) and Volkmann Railroad Builders, Inc. (hereinafter called CONTRACTOR).

 

OWNER AND CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:

 

Article 1. WORK.

 

1.1                                  CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.  The Work is generally described as follows:

 

Turnouts, track, derails and earthen berm construction, including ballast and bonding and grounding of track.

 

1.2                                  The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:

 

Rail Yard Construction for UWGP, LLC

 

Article 2. ENGINEER.

 

2.1                                  The Project has been designed by Key Railroad Development, LLC. , who is hereinafter called ENGINEER and who is to act as OWNER’s representative, assume all duties and responsibilities and have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents.

 

Article 3. CONTRACT TIMES.

 

3.1                                  Work will be substantially completed by May 20, 2005, and completed and ready for final payment by May 31, 2005.

 

3.2                                  Liquidated Damages . OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions.  They also recognize the delays, expense and difficulties involved in proving the actual loss suffered by OWNER if the Work is not completed on time.  Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay Owner Five Hundred dollars ($ 500 ) for each day that expires after the time specified in paragraph 3.1 for Substantial Completion until the Work is substantially complete.  After Substantial Completion, if CONTRACTOR shall neglect, refuse or fail to complete the remaining Work within the time specified in paragraph 3.1 for completion and readiness for final payment or any proper

 

1



 

extension thereof granted by OWNER, CONTRACTOR shall pay OWNER Five Hundred dollars ($ 500 ) for each day that expires after the time specified in paragraph 3.1 for completion and readiness for final payment.

 

Article 4. CONTRACT PRICE.

 

OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to the following:

 

For all Unit Price Work, an amount equal to the sum of the established unit price for each separately identified item of Unit Price Work times the estimated quantity of that item as indicated below:

 

UNIT PRICE WORK

 

NO.

 

ITEM

 

UNIT

 

ESTIMATED
QUANTITY

 

UNIT
PRICE

 

TOTAL
ESTIMATED

 

1.

 

Mobilization/Demobilization

 

1

 

LS

 

$

12,800.00

 

$

12,800.00

 

2.

 

#8-112# Turnout Construction

 

1

 

EA

 

$

26,000.00

 

$

208,000.00

 

3.

 

112# Track Construction

 

8,021

 

TF

 

$

67.00

 

$

537,407.00

 

4.

 

Scale Track Construction

 

72

 

TF

 

$

60.00

 

$

4,320.00

 

5.

 

Concrete Pad Track Constr.

 

349

 

TF

 

$

118.00

 

$

41,182.00

 

6.

 

Sliding Derail Construction

 

2

 

EA

 

$

2,800.00

 

$

5,600.00

 

7.

 

Earthen Berm Construction

 

2

 

EA

 

$

500.00

 

$

1,000.00

 

8.

 

Close Clearance Signage

 

1

 

LS

 

$

400.00

 

$

400.00

 

9.

 

Track Bonding and Grounding

 

1

 

LS

 

$

4,830.00

 

$

4,830.00

 

 

TOTAL OF ALL UNIT PRICES Eight Hundred Fifteen Thousand Five Hundred Thirty-Nine Dollars (use words) $815,539.00 (Dollars)

 

As provided in Paragraph 11.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classification are to be made by ENGINEER as provided in Paragraph 9.10 of the General Conditions.  Unit prices have been computed as provided in Paragraph 11.03.B of the General Conditions.

 

Article 5. PAYMENT PROCEDURES.

 

CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions.  Applications for Payment will be processed by ENGINEER, as provided in the General Conditions.

 

5.1                                  Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR’s Applications for Payment, as recommended by ENGINEER, on or about the 24 th day of each month during construction as provided in paragraphs 5.1.1 and 5.1.2 below.  All such payments will be measured by the schedule of values established in paragraph 2.07.3 of the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements.

 

2



 

5.1.1                         Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with Paragraph 14.7 of the General Conditions.

 

90%    of Work completed (with the balance being retainage).

 

5.1.2                         Upon Substantial Completion, in an amount sufficient to increase total payments to CONTRACTOR to 95% of the Contract Price (with the balance being retainage), less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with Paragraph 14.7 of the General Conditions.

 

5.2                                  Final Payment .   Upon final completion and acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said Paragraph 14.13.

 

Article 6. INTEREST.

 

6.1                                  All moneys not paid when due, as provided in Article 14 of the General Conditions, shall bear interest at the maximum rate allowed by law at the place of the Project.

 

Article 7. CONTRACTOR’S REPRESENTATIONS.

 

In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations:

 

7.1                                  CONTRACTOR has examined and carefully studied the Contract Documents (including the Addenda listed in Paragraph 8) and the other related data identified in the Bidding Documents including “technical data.”

 

7.2                                  CONTRACTOR has visited the site and become familiar with and is satisfied as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work.

 

7.3                                  CONTRACTOR is familiar with and is satisfied as to all federal, state, and local laws and regulations that may affect cost, progress, performance, and furnishing of the Work.

 

7.4                                  CONTRACTOR has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more