Back to top

Exhibit 10 AGREEMENT

Construction Agreement

Exhibit 10 AGREEMENT | Document Parties: COMMUNITY BANKSHARES INC /SC/ | C. F. Evans & Company, Inc | Robert E. Moore You are currently viewing:
This Construction Agreement involves

COMMUNITY BANKSHARES INC /SC/ | C. F. Evans & Company, Inc | Robert E. Moore

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: Exhibit 10 AGREEMENT
Date: 5/13/2005
Industry: Regional Banks    

Exhibit 10 AGREEMENT, Parties: community bankshares inc /sc/ , c. f. evans & company  inc , robert e. moore
50 of the Top 250 law firms use our Products every day

 

                                   Exhibit 10

 

AGREEMENT   made as of the Twenty   Second   (22nd) day of March in the year of Two

Thousand and Five (In words, indicate day, month and year)

 

BETWEEN the Owner:

(Name, address and other information)

 

Community Bankshares, Inc.

791 Broughton Street

Orangeburg, South Carolina 29115

Telephone Number: (803) 535-1060

 

 

and the Contractor:

(Name, address and other information)

 

C. F. Evans & Company, Inc.

P. O. Box 1686

Orangeburg, South Carolina 29116-1686

Telephone Number: (803) 536-6443

Fax Number: (803) 531-4629

 

The Project is:

(Name and location)

 

Community Bankshares Corporate Headquarters

Orangeburg, South Carolina

 

The Architect is:

(Name, address and other information)

 

Robert E. Moore Architect

1800 Ashcraft Avenue

Monroe, North Carolina   28110

Telephone Number: (704) 283-1196

Fax Number: (704) 289-4422

 

The Owner and Contractor agree as follows.

 

 

<PAGE>

 

 

ARTICLE 1    THE CONTRACT DOCUMENTS

 

The Contract   Documents   consist of this   Agreement,   Conditions of the Contract

(General, Supplementary and other Conditions), Drawings, Specifications, Addenda

issued prior to   execution of this   Agreement,   other   documents   listed in this

Agreement and Modifications issued after execution of this Agreement; these form

the   Contract,   and are as fully a part of the   Contract   as if attached to this

Agreement or repeated herein. The Contract   represents the entire and integrated

agreement   between   the   parties   hereto   and   supersedes   prior    negotiations,

representations   or   agreements,   either   written or oral. An enumeration of the

Contract Documents, other than Modifications, appears in Article 8.

 

ARTICLE 2    THE WORK OF THIS CONTRACT

 

The Contractor shall fully execute the Work described in the Contract Documents,

except to the extent specifically   indicated in the Contract Documents to be the

responsibility of others.

 

ARTICLE 3    DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

 

Section   3.1 The   date of   commencement   of the   Work   shall be the date of this

Agreement   unless a different   date is stated below or provision is made for the

date to be fixed in a notice to proceed issued by the Owner. (Insert the date of

commencement   if it differs from the date of this   Agreement or, if   applicable,

state that the date will be fixed in a notice to proceed.)

 

  Date of Commencement will be ten (10) days after receipt of building permit

 

If,   prior to the   commencement   of the Work,   the Owner   requires   time to file

mortgages,   mechanic's   liens and other   security   interests,   the Owner's   time

requirement shall be as follows:

 

 

 

Section   3.2 The Contract Time shall be measured from the date of commencement.

 

Section 3.3 The Contractor   shall achieve   Substantial   Completion of the entire

Work not later than days from the date of commencement,   or as follows:   (Insert

number   of   calendar   days.   Alternatively,   a   calendar   date may be used   when

coordinated   with the   date of   commencement.   Unless   stated   elsewhere   in the

Contract Documents,   insert any requirements for earlier Substantial   Completion

of certain portions of the Work.)

 

Date of   Substantial   Completion   will be seven   (7)   months   after   receipt   of

building permit

 

        Portion of Work                Substantial Completion Date

 

 

, subject to   adjustments   of this   Contract   Time as provided   in the   Contract

Documents.   (Insert   provisions,   if any,   for   liquidated   damages   relating to

failure to complete on time or for bonus   payments for early   completion   of the

Work.)

 

Should the project not be complete by date of Substantial Completion, liquidated

damages will be assessed at the rate of Two Hundred Fifty Dollars   ($250.00) for

each day Owner is unable to assume occupancy.

 

The Contractor   will be paid a bonus of Two Hundred Fifty Dollars   ($250.00) for

every calendar day the project is completed ahead of the six-month   construction

schedule.

 

                                       2

<PAGE>

 

ARTICLE 4    CONTRACT SUM

 

Section 4.1 The Owner shall pay the Contractor the Contract Sum in current funds

for the Contractor's   performance of the Contract. The Contract Sum shall be One

Million Four Hundred   Seventy-five   Thousand Five Hundred Dollars and Zero Cents

($   1,475,500.00   ),   subject to   additions   and   deductions   as provided in the

Contract Documents.

 

Section 4.2 The Contract   Sum is based upon the   following   alternates,   if any,

which are   described in the Contract   Documents   and are hereby   accepted by the

Owner:   (State the numbers or other   identification of accepted   alternates.   If

decisions   on other   alternates   are to be made by the Owner   subsequent   to the

execution of this Agreement,   attach a schedule of such other alternates showing

the amount for each and the date when that amount expires)

 

 

 

Section   4.3 Unit prices, if any, are as follows:

 

        Description               Units               Price ($ 0.00)

 

 

ARTICLE 5    PAYMENTS

 

Section   5.1 PROGRESS PAYMENTS

 

Section 5.1.1 Based upon   Applications for Payment submitted to the Architect by

the Contractor and Certificates   for Payment issued by the Architect,   the Owner

shall make progress payments on account of the Contract Sum to the Contractor as

provided below and elsewhere in the Contract Documents.

 

Section 5.1.2 The period   covered by each   Application   for Payment shall be one

calendar month ending on the last day of the month, or as follows:

 

Section   5.1.3   Provided   that an   Application   for   Payment is   received by the

Architect not later than the twenty-fifth (25th) day of a month, the Owner shall

make payment to the   Contractor   not later than the tenth (10th) day of the next

month.   If an   Application   for Payment is received by the   Architect   after the

application date fixed above,   payment shall be made by the Owner not later than

fifteen (15) days after the Architect receives the Application for Payment.

 

Section   5.1.4 Each   Application   for Payment   shall be based on the most recent

sched


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more