CONSTRUCTION MANAGEMENT
AGREEMENT
NETWORK APPLIANCE, INC.
(“NAI”)
BNP PARIBAS LEASING
CORPORATION
(“BNPPLC”)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
ENGAGEMENT AND AUTHORIZATION
|
|
|
1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
GENERAL
TERMS AND CONDITIONS
|
|
|
2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1
|
|
Additional
definitions
|
|
|
2
|
|
|
|
|
“
97-10/Event ”
|
|
|
2
|
|
|
|
|
“
97-10/Maximum Permitted Prepayment ”
|
|
|
2
|
|
|
|
|
“
97-10/Prepayment ”
|
|
|
3
|
|
|
|
|
“
97-10/Project Costs ”
|
|
|
3
|
|
|
|
|
“
97-10/Pronouncement ”
|
|
|
4
|
|
|
|
|
“
NAI’s Estimate of Force Majeure Delays
”
|
|
|
4
|
|
|
|
|
“
NAI’s Estimate of Force Majeure Excess Costs
”
|
|
|
4
|
|
|
|
|
“
Accrued Construction Period Interest Expense
”
|
|
|
4
|
|
|
|
|
“
Affiliate’s Contract ”
|
|
|
5
|
|
|
|
|
“
Arrangement Fee ”
|
|
|
5
|
|
|
|
|
“
Administrative Fee ”
|
|
|
5
|
|
|
|
|
“
Capital Adequacy Charges ”
|
|
|
5
|
|
|
|
|
“
Carrying Costs ”
|
|
|
5
|
|
|
|
|
“
Commitment Fees ”
|
|
|
5
|
|
|
|
|
“
Complete Taking ”
|
|
|
5
|
|
|
|
|
“
Completion Date ”
|
|
|
5
|
|
|
|
|
“
Completion Notice ”
|
|
|
5
|
|
|
|
|
“
Construction Advances ”
|
|
|
5
|
|
|
|
|
“
Construction Advance Request ”
|
|
|
6
|
|
|
|
|
“
Construction Allowance ”
|
|
|
6
|
|
|
|
|
“
Construction Budget ”
|
|
|
6
|
|
|
|
|
“
Construction Project ”
|
|
|
6
|
|
|
|
|
“
Covered Construction Period Losses ”
|
|
|
6
|
|
|
|
|
“
Defective Work ”
|
|
|
6
|
|
|
|
|
“ FOCB
Notice ”
|
|
|
6
|
|
|
|
|
“
Force Majeure Event ”
|
|
|
7
|
|
|
|
|
“
Funded Construction Allowance ”
|
|
|
7
|
|
|
|
|
“
Future Work ”
|
|
|
7
|
|
|
|
|
“
Ground Lease Rents ”
|
|
|
7
|
|
|
|
|
“
Increased Cost Charges ”
|
|
|
7
|
|
|
|
|
“
Increased Commitment ”
|
|
|
7
|
|
|
|
|
“
Increased Funding Commitment ”
|
|
|
7
|
|
|
|
|
“
Increased Time Commitment ”
|
|
|
7
|
|
|
|
|
“
Initial Advance ”
|
|
|
7
|
|
|
|
|
“
Maximum Construction Allowance ”
|
|
|
7
|
|
TABLE OF CONTENTS
(Continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
“
Notice of NAI’s Intent to Terminate ”
|
|
|
7
|
|
|
|
|
“
Notice of NAI’s Intent to Terminate Because of a Force
Majeure Event ”
|
|
|
8
|
|
|
|
|
“
Notice of Termination By NAI ”
|
|
|
8
|
|
|
|
|
“
Outstanding Construction Allowance ”
|
|
|
8
|
|
|
|
|
“
Owner’s Election to Continue Construction
”
|
|
|
8
|
|
|
|
|
“
Pre-lease Casualty ”
|
|
|
8
|
|
|
|
|
“
Pre-lease Force Majeure Delays ”
|
|
|
8
|
|
|
|
|
“
Pre-lease Force Majeure Event ”
|
|
|
8
|
|
|
|
|
“
Pre-lease Force Majeure Event Notice ”
|
|
|
8
|
|
|
|
|
“
Pre-lease Force Majeure Excess Costs ”
|
|
|
8
|
|
|
|
|
“
Pre-lease Force Majeure Losses ”
|
|
|
9
|
|
|
|
|
“
Prior Work ”
|
|
|
10
|
|
|
|
|
“
Projected Cost Overruns ”
|
|
|
10
|
|
|
|
|
“
Reimbursable Construction Period Costs ”
|
|
|
10
|
|
|
|
|
“
Remaining Proceeds ”
|
|
|
10
|
|
|
|
|
“
Scope Change ”
|
|
|
10
|
|
|
|
|
“
Target Completion Date ”
|
|
|
10
|
|
|
|
|
“
Termination of NAI’s Work ”
|
|
|
10
|
|
|
|
|
“
Third Party Contract ”
|
|
|
11
|
|
|
|
|
“
Third Party Contract/Termination Fees ”
|
|
|
11
|
|
|
|
|
“
Timing or Budget Shortfall ”
|
|
|
11
|
|
|
|
|
“
Work ”
|
|
|
11
|
|
|
|
|
“
Work/Suspension Event ”
|
|
|
11
|
|
|
|
|
“
Work/Suspension Notice ”
|
|
|
12
|
|
|
|
|
“
Work/Suspension Period ”
|
|
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
|
Construction and
Management of the Property by NAI
|
|
|
12
|
|
|
|
|
(A)
|
|
The
Construction Project
|
|
|
12
|
|
|
|
|
|
|
(1)
|
|
Construction
Approvals by BNPPLC
|
|
|
12
|
|
|
|
|
|
|
|
|
(a)
|
|
Preconstruction
Approvals by BNPPLC
|
|
|
12
|
|
|
|
|
|
|
|
|
(b)
|
|
Approval of
Scope Changes
|
|
|
12
|
|
|
|
|
|
|
(2)
|
|
NAI’s
Right to Possession and to Control Construction
|
|
|
13
|
|
|
|
|
|
|
|
|
(c)
|
|
Adequacy of
Drawings, Specifications and Budgets
|
|
|
14
|
|
|
|
|
|
|
|
|
(d)
|
|
Existing
Condition of the Land and Improvements
|
|
|
14
|
|
|
|
|
|
|
|
|
(e)
|
|
Correction of
Defective Work
|
|
|
14
|
|
|
|
|
|
|
|
|
(f)
|
|
Clean
Up
|
|
|
15
|
|
|
|
|
|
|
|
|
(g)
|
|
No Damage for
Delays
|
|
|
15
|
|
|
|
|
|
|
|
|
(h)
|
|
No Fee For
Construction Management
|
|
|
15
|
|
|
|
|
|
|
(3)
|
|
Quality of
Work
|
|
|
15
|
|
(ii)
TABLE OF CONTENTS
(Continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
(B)
|
|
Completion
Notice
|
|
|
15
|
|
|
|
|
(C)
|
|
Status of
Property Acquired With BNPPLC’s Funds
|
|
|
16
|
|
|
|
|
(D)
|
|
Insurance
|
|
|
16
|
|
|
|
|
|
|
(1)
|
|
Liability
Insurance
|
|
|
16
|
|
|
|
|
|
|
(2)
|
|
Property
Insurance
|
|
|
17
|
|
|
|
|
|
|
(3)
|
|
Failure of NAI
to Obtain Insurance
|
|
|
17
|
|
|
|
|
|
|
(4)
|
|
Waiver of
Subrogation
|
|
|
17
|
|
|
|
|
(E)
|
|
Condemnation
|
|
|
18
|
|
|
|
|
(F)
|
|
Additional
Representations, Warranties and Covenants of NAI Concerning the
Property
|
|
|
18
|
|
|
|
|
|
|
(1)
|
|
Payment of
Local Impositions
|
|
|
18
|
|
|
|
|
|
|
(2)
|
|
Operation and
Maintenance
|
|
|
19
|
|
|
|
|
|
|
(3)
|
|
Debts for
Construction, Maintenance, Operation or Development
|
|
|
20
|
|
|
|
|
|
|
(4)
|
|
Permitted
Encumbrances and the Ground Lease
|
|
|
20
|
|
|
|
|
|
|
(5)
|
|
Books and
Records Concerning the Property
|
|
|
20
|
|
|
|
|
(G)
|
|
BNPPLC’s
Right of Access
|
|
|
21
|
|
|
|
|
|
|
(1)
|
|
Access
Generally
|
|
|
21
|
|
|
|
|
|
|
(2)
|
|
Failure of NAI
to Perform
|
|
|
21
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
|
Amounts to be Added to
the Lease Balance (in Addition to Construction
Advances)
|
|
|
22
|
|
|
|
|
(A)
|
|
Initial
Advance
|
|
|
22
|
|
|
|
|
(B)
|
|
Carrying
Costs
|
|
|
23
|
|
|
|
|
(C)
|
|
Commitment
Fees
|
|
|
23
|
|
|
|
|
(D)
|
|
Future
Administrative Fees and Out-of-Pocket Costs
|
|
|
24
|
|
|
|
|
(E)
|
|
Increased Cost
Charges and Capital Adequacy Charges
|
|
|
24
|
|
|
|
|
(F)
|
|
Ground Lease
Payments
|
|
|
25
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
|
Construction
Advances
|
|
|
25
|
|
|
|
|
(A)
|
|
Costs Subject
to Reimbursement Through Construction Advances
|
|
|
25
|
|
|
|
|
(B)
|
|
Exclusions From
Reimbursable Construction Period Costs
|
|
|
27
|
|
|
|
|
(C)
|
|
Conditions to
NAI’s Right to Receive Construction Advances
|
|
|
27
|
|
|
|
|
|
|
(1)
|
|
Construction
Advance Requests
|
|
|
27
|
|
|
|
|
|
|
(2)
|
|
Amount of the
Advances
|
|
|
28
|
|
|
|
|
|
|
|
|
(a)
|
|
The Maximum
Construction Allowance
|
|
|
28
|
|
|
|
|
|
|
|
|
(b)
|
|
Costs
Previously Incurred by NAI
|
|
|
28
|
|
|
|
|
|
|
|
|
(c)
|
|
Limits During
any Work/Suspension Period
|
|
|
29
|
|
|
|
|
|
|
|
|
(d)
|
|
Restrictions
Imposed for Administrative Convenience
|
|
|
29
|
|
|
|
|
|
|
(3)
|
|
No Advances
After Certain Dates
|
|
|
29
|
|
|
|
|
(D)
|
|
Breakage Costs
for Construction Advances Requested But Not Taken
|
|
|
29
|
|
(iii)
TABLE OF CONTENTS
(Continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
(E)
|
|
No Third Party
Beneficiaries
|
|
|
30
|
|
|
|
|
(F)
|
|
No
Waiver
|
|
|
30
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5
|
|
Application of
Insurance and Condemnation Proceeds
|
|
|
30
|
|
|
|
|
(A)
|
|
Collection and
Application Generally
|
|
|
30
|
|
|
|
|
(B)
|
|
Advances of
Escrowed Proceeds to NAI
|
|
|
31
|
|
|
|
|
(C)
|
|
Status of
Escrowed Proceeds After Commencement of the Term of the
Lease
|
|
|
31
|
|
|
|
|
(D)
|
|
Special
Provisions Applicable After a 97-10/Event or Event of
Default
|
|
|
31
|
|
|
|
|
(E)
|
|
NAI’s
Obligation to Restore
|
|
|
31
|
|
|
|
|
(F)
|
|
Special
Provisions Concerning a Complete Taking
|
|
|
32
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6
|
|
Notice of Cost Overruns
and Pre-lease Force Majeure Events
|
|
|
32
|
|
|
|
|
(A)
|
|
Notice of
Projected Cost Overruns
|
|
|
32
|
|
|
|
|
(B)
|
|
Pre-lease Force
Majeure Event Events and Notices
|
|
|
32
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7
|
|
Suspension and
Termination of NAI’s Work
|
|
|
32
|
|
|
|
|
(A)
|
|
Rights and
Obligations During a Work/Suspension Period
|
|
|
32
|
|
|
|
|
(B)
|
|
NAI’s
Election to Terminate NAI’s Work
|
|
|
32
|
|
|
|
|
(C)
|
|
BNPPLC’s
Election to Terminate NAI’s Work
|
|
|
36
|
|
|
|
|
(D)
|
|
Surviving
Rights and Obligations
|
|
|
36
|
|
|
|
|
(E)
|
|
Cooperation
After a Termination of NAI’s Work
|
|
|
37
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8
|
|
Continuation of
Construction by BNPPLC
|
|
|
38
|
|
|
|
|
(A)
|
|
Owner’s
Election to Continue Construction
|
|
|
38
|
|
|
|
|
|
|
(1)
|
|
Take Control of
the Property
|
|
|
39
|
|
|
|
|
|
|
(2)
|
|
Continuation of
Construction
|
|
|
39
|
|
|
|
|
|
|
(3)
|
|
Arrange for
Turnkey Construction
|
|
|
40
|
|
|
|
|
|
|
(4)
|
|
Suspension or
Termination of Construction by BNPPLC
|
|
|
40
|
|
|
|
|
(B)
|
|
Powers Coupled
With an Interest
|
|
|
40
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9
|
|
NAI’s Obligation
for 97-10/Prepayments
|
|
|
40
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10
|
|
Indemnity for Covered
Construction Period Losses
|
|
|
41
|
|
|
|
|
(A)
|
|
Covenant to
Indemnify Against Covered Construction Period Losses
|
|
|
41
|
|
|
|
|
(B)
|
|
Certain Losses
Included or Excluded
|
|
|
42
|
|
|
|
|
|
|
(1)
|
|
Environmental
|
|
|
42
|
|
|
|
|
|
|
(2)
|
|
Failure to
Maintain a Safe Work Site
|
|
|
43
|
|
|
|
|
|
|
(3)
|
|
Failure to
Complete Construction
|
|
|
43
|
|
|
|
|
|
|
(4)
|
|
Fraud
|
|
|
43
|
|
(iv)
TABLE OF CONTENTS
(Continued)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
|
|
|
|
|
(5)
|
|
Excluded
Taxes and Established Misconduct
|
|
|
43
|
|
|
|
|
(C)
|
|
Express
Negligence Protection
|
|
|
44
|
|
|
|
|
(D)
|
|
Survival of
Indemnity
|
|
|
44
|
|
|
|
|
(E)
|
|
Due Date for
Indemnity Payments
|
|
|
44
|
|
|
|
|
(F)
|
|
Order of
Application of Payments
|
|
|
44
|
|
|
|
|
(G)
|
|
Defense of
BNPPLC
|
|
|
44
|
|
|
|
|
|
|
(1)
|
|
Assumption
of Defense
|
|
|
44
|
|
|
|
|
|
|
(2)
|
|
Indemnity
Not Contingent
|
|
|
45
|
|
|
|
|
(H)
|
|
When Payments
Are Due
|
|
|
45
|
|
|
|
|
(I)
|
|
Survival
|
|
|
45
|
|
|
|
|
(J)
|
|
Notice of
Claims
|
|
|
45
|
|
|
|
|
(K)
|
|
Withholding of
Consent to Settlements Proposed by NAI
|
|
|
46
|
|
|
|
|
(L)
|
|
Settlements
Without the Prior Consent of NAI
|
|
|
46
|
|
|
|
|
|
|
(1)
|
|
Election to
Pay Reasonable Settlement Costs in Lieu of Actual
|
|
|
46
|
|
|
|
|
|
|
(2)
|
|
Conditions
to Election
|
|
|
46
|
|
|
|
|
|
|
(3)
|
|
Indemnity
Survives Settlement
|
|
|
47
|
|
|
|
|
(M)
|
|
No Authority to
Admit Wrongdoing on the Part of NAI
|
|
|
47
|
|
|
|
|
(N)
|
|
Refunds of
Covered Construction Period Losses Paid by NAI
|
|
|
47
|
|
|
|
|
|
|
(2)
|
|
Meaning of
Refund
|
|
|
48
|
|
|
|
|
|
|
(3)
|
|
Conditions
to Payment
|
|
|
48
|
|
(v)
TABLE OF CONTENTS
(Continued)
|
|
|
|
|
|
|
|
|
Exhibit A
|
|
Legal Description
|
|
|
|
|
|
Exhibit B
|
|
Description of the Construction
Project and Budget
|
|
|
|
|
|
Exhibit C
|
|
Construction Advance Request
Form
|
|
|
|
|
|
Exhibit D
|
|
Pre-lease Force Majeure Event
Notice
|
|
|
|
|
|
Exhibit E
|
|
Notice of Termination by NAI’s
Work
|
|
|
|
|
|
Exhibit F
|
|
Notice of NAI’s Intent to
Terminate
|
|
|
|
|
|
Exhibit G
|
|
Notice of Increased Funding
Commitment by BNPPLC
|
|
|
|
|
|
Exhibit H
|
|
Notice of Increased Time Commitment
by BNPPLC
|
|
|
|
|
|
Exhibit I
|
|
Notice of Rescission of NAI’s
Intent to Terminate
|
(vi)
CONSTRUCTION MANAGEMENT
AGREEMENT
This CONSTRUCTION
MANAGEMENT AGREEMENT (this “ Agreement ”), dated
as of December 14, 2006 (the “ Effective Date
”), is made by and between BNP PARIBAS LEASING CORPORATION
(“ BNPPLC ”), a Delaware corporation, and
NETWORK APPLIANCE, INC. (“ NAI ”), a Delaware
corporation.
Contemporaneously
with the execution of this Agreement, BNPPLC and NAI are executing
a Common Definitions and Provisions Agreement dated as of the
Effective Date (the “ Common Definitions and Provisions
Agreement ”), which by this reference is incorporated
into and made a part of this Agreement for all purposes. As
used in this Agreement, capitalized terms defined in the Common
Definitions and Provisions Agreement and not otherwise defined in
this Agreement are intended to have the respective meanings
assigned to them in the Common Definitions and Provisions
Agreement.
At the request of
NAI and to facilitate the transaction contemplated in the other
Operative Documents, contemporaneously with this Agreement BNPPLC
is executing and accepting a Ground Lease from NAI (the “
Ground Lease ”), pursuant to which BNPPLC is acquiring
a leasehold estate in the Land described in Exhibit A
and any existing Improvements on such Land.
Also
contemporaneously with this Agreement, BNPPLC and NAI are executing
a Lease Agreement (the “ Lease ”), pursuant to
which the parties expect that NAI will lease the Improvements on
the Land described in Exhibit A from BNPPLC for a lease
term that will commence on the Completion Date (as defined
below).
In anticipation of
the construction of new or additional Improvements for NAI’s
use pursuant to the Lease, BNPPLC and NAI have agreed upon the
terms and conditions upon which BNPPLC is willing to authorize NAI
to arrange and manage such construction and upon which BNPPLC is
willing to provide funds for such construction, and by this
Agreement BNPPLC and NAI desire to evidence such
agreement.
ENGAGEMENT AND
AUTHORIZATION
Subject to the
terms and conditions set forth in this Agreement, BNPPLC does
hereby engage and authorize NAI — and NAI does hereby accept
such engagement and authorization, as an independent contractor for
BNPPLC — to construct the Construction Project on the Land
and to manage such construction for BNPPLC. As more particularly
provided in subparagraph 2(A)(2) below, NAI will take possession
and control of the Land and all Improvements on the Land to
accomplish such construction. However, the rights and authority
granted to NAI by this Agreement are expressly made subject and
subordinate to the terms and condition hereinafter set
forth and to
the Ground Lease, to the Permitted Encumbrances and to any other
claims or encumbrances affecting the Land or the Property that may
be asserted by third parties other than Liens Removable by
BNPPLC.
GENERAL TERMS AND
CONDITIONS
1
Additional
definitions . As used in this Agreement, capitalized
terms defined above will have the respective meanings assigned to
them above; as indicated above, capitalized terms that are defined
in the Common Definitions and Provisions Agreement and that are
used but not defined herein will have the respective meanings
assigned to them in the Common Definitions and Provisions
Agreement; and, the following terms will have the following
respective meanings:
“
97-10/Event ” means any of the following:
(a)
NAI gives a Notice of NAI’s Intent to Terminate and
thereafter (i) fails to rescind the same as described in
subparagraph 7(B)(7) within ten days after BNPPLC responds with any
Increased Commitment, or (ii) gives a Notice of Termination as
provided in subparagraph 7(B)(1); or
(b)
NAI gives a notice to terminate the
Supplemental Payment Obligation as described in subparagraph
6(B) of the Purchase Agreement; or
(c)
BNPPLC gives notice to NAI as
described in subparagraph 7(C) to cause a Termination of
NAI’s Work; or
(d)
NAI fails for any reason whatsoever
to substantially complete the Construction Project and give a
Completion Notice to BNPPLC prior to the Target Completion Date;
or
(e)
for any reason whatsoever (including the accrual of Carrying
Costs), the Funded Construction Allowance exceeds the Maximum
Construction Allowance.
“
97-10/Maximum Permitted Prepayment ” as of any date
means the amount equal to eighty-nine and nine-tenths of one
percent (89.9%) of the aggregate of all 97-10/Project Costs paid or
incurred on or prior to such date.
Construction Management Agreement
— Page 2
“
97-10/Prepayment ” means any payment to BNPPLC
required by Paragraph 9, which in each case will equal
(A) the 97-10/Maximum Permitted Prepayment, computed as of the
date on which the payment becomes due, less (B) the sum of
(1) the accreted value of any prior payments actually received
by BNPPLC from NAI constituting 97-10/Prepayments, and
(2) amounts (if any) then owed by BNPPLC to NAI pursuant to
this Agreement as reimbursements for 97-10 Project Costs paid by
NAI and not theretofore reimbursed. For purposes of the preceding
sentence, “accreted value” of a payment means the
amount of the payment plus an amount equal to the interest that
would have accrued on the payment if it bore interest at the
Effective Rate plus the Spread.
“
97-10/Project Costs ” means the following:
(a)
costs incurred for the Work, including not only hard costs incurred
for the new Improvements described in Exhibit B , but
also the following costs to the extent reasonably incurred in
connection with the Construction Project:
|
|
•
|
|
soft costs, such as architectural
fees, engineering fees and fees and costs paid in connection with
obtaining project permits and approvals required by governmental
authorities or any Permitted Encumbrance,
|
|
|
|
|
|
|
|
•
|
|
site preparation costs,
and
|
|
|
|
|
|
|
|
•
|
|
costs of offsite and other public
improvements required as conditions of governmental approvals for
the Construction Project or required by any Permitted
Encumbrances;
|
(b)
costs incurred to maintain insurance required by (and consistent
with the requirements of) this Agreement prior to the Completion
Date;
(c)
Local Impositions that have accrued or become due prior to the
Completion Date;
(d)
Accrued Construction Period Interest Expense; and
(e)
any costs in addition to those described in clauses
(a) through (d) preceding that GAAP (as it exists on the
Effective Date) would allow BNPPLC to capitalize as part of the
cost of the Property or that the 97-10/Pronouncement would allow
BNPPLC to characterize as project costs, including:
(1) cancellation or termination fees or other compensation
payable by NAI or BNPPLC pursuant to any contract concerning the
Construction Project made by NAI or BNPPLC with any general
contractor, architect, engineer or other third party because of any
election by NAI or BNPPLC to cancel or
Construction Management Agreement
— Page 3
terminate such
contract, and (2) any costs that BNPPLC incurs and is allowed
to capitalize to continue or complete the Construction Project
after any Owner’s Election to Continue Construction as
provided in subparagraph 8(A).
However,
notwithstanding the foregoing, 97-10/Project Costs will not include
Pre-lease Force Majeure Losses, Administrative Fees, the
Arrangement Fee, or any legal fees which are included in
Transaction Expenses.
“
97-10/Pronouncement ” means the pronouncement issued
by the Emerging Issues Task Force of the Financial Accounting
Standards Board in 1998 titled “EITF 97-10: The Effect of
Lessee Involvement in Construction”, which provides that
certain kinds of involvement by a lessee in pre-lease commencement
construction will cause the lessee to be considered as the owner of
the leased property during the construction period and then will
require application of the appropriate sale and leaseback
accounting rules.
“
NAI’s Estimate of Force Majeure Delays ” has the
meaning indicated in subparagraph 7(B)(4).
“
NAI’s Estimate of Force Majeure Excess Costs ”
has the meaning indicated in subparagraph 7(B)(3).
“
Accrued Construction Period Interest Expense ” means
interest that has accrued and that BNPPLC has paid or is obligated
to pay on Funding Advances for any period prior to the Completion
Date. Such interest will include a percentage, equal to the
aggregate Percentages of all Participants (under and as defined in
the Participation Agreement), of Carrying Costs and Commitment Fees
that accrue after the execution of any Participation Agreement and
that are added to the Outstanding Construction Allowance as
provided in this Agreement, it being understood that the additional
amounts BNPPLC must pay to the Participants under the Participation
Agreement because of the accrual of Carrying Costs and Commitment
Fees effectively constitute construction period interest on
advances the Participants make to BNPPLC under the Participation
Agreement. Accrued Construction Period Interest Expense will also
include any interest and other finance charges that accrue prior to
the Completion Date because of Funding Advances provided to BNPPLC
by BNPPLC’s Parent in the form of loans, regardless of
whether BNPPLC’s obligation in respect of such loans is
limited to BNPPLC’s interest in the Property. However, any
such interest and other finance charges accruing on Funding
Advances provided by BNPPLC’s Parent and included in Accrued
Construction Period Interest Expense will not exceed the Carrying
Costs attributable to the portion of the Lease Balance funded or
maintained by such Funding Advances. Further, Accrued Construction
Period Interest will not include any portion of Carrying Costs
included in Pre-lease Force Majeure Losses (as set forth in the
definition thereof below) or interest or finance charges that
BNPPLC must pay to the
Construction Management Agreement
— Page 4
Participants
under the Participation Agreement because of the accrual of such
portion of Carrying Costs.
“
Affiliate’s Contract ” has the meaning indicated
in subparagraph 2(A)(2)(b).
“
Arrangement Fee ” has the meaning indicated in
subparagraph 3(A).
“
Administrative Fee ” has the meanings indicated in
subparagraph 3(A) and subparagraph 3(D).
“
Capital Adequacy Charges ” has the meaning indicated
in subparagraph 3(E)(1).
“
Carrying Costs ” has the meaning indicated in
subparagraph 3(B).
“
Commitment Fees ” has the meaning indicated in
subparagraph 3(C).
“
Complete Taking ” means a taking by eminent domain
prior to the Completion Date over NAI’s objection of all of
the Land or the Property, or so much thereof as to make it
impossible to complete the Construction Project for its intended
uses on the Land regardless of any Scope Changes BNPPLC may be
willing to approve or any Increased Commitment that BNPPLC may be
willing to provide.
“
Completion Date ” means the the date upon which NAI
gives the notice to BNPPLC which is required by subparagraph 2(B),
after having substantially completed the Construction Project and
having obtained any certificate of substantial completion or other
permit (temporary or permanent) required for the commencement of
NAI’s use of the Improvements.
“
Completion Notice ” means the notice required by
subparagraph 2(B) from NAI to BNPPLC, advising BNPPLC that NAI has
substantially completed construction of the Construction Project
and has obtained any certificate of substantial completion or other
permit (temporary or permanent) required for the commencement of
NAI’s use of the Improvements. (Any such Completion Notice
will also confirm the amounts required to compute the Projected
Economic Depreciation of Equipment, consistent with BNPPLC’s
determination of the projected future value as provided in
subparagraph ?, for use in calculating Amortizing Rent as provided
in the Lease.)
“
Construction Advances ” means (1) actual advances
of funds made by or on behalf of BNPPLC to or on behalf of NAI as
provided in Paragraph 4, which sets forth NAI’s rights
to receive advances for Reimbursable Construction Period Costs, and
(2) other amounts paid or incurred by BNPPLC that subparagraph
8(A) or other provisions of this
Construction Management Agreement
— Page 5
Agreement allow
BNPPLC to characterize as Construction Advances. The term
“Construction Advances” will not, however, include
advances of insurance proceeds, condemnation proceeds or other
Escrowed Proceeds to pay or reimburse costs of repairs or
restoration.
“
Construction Advance Request ” has the meaning
indicated in subparagraph 4(C)(1).
“
Construction Allowance ” means the allowance to be
provided by BNPPLC for the design and construction of the
Construction Project, against which and from which Carrying Cost,
Construction Advances and other amounts will be or may be charged
and paid as provided in various provisions of this Agreement
(including Paragraphs 3, 4 and 8).
“
Construction Budget ” means the budget for the
Construction Project set forth in Exhibit B .
“
Construction Project ” means the new buildings or
other substantial Improvements to be constructed, or the alteration
of existing Improvements, as described generally in
Exhibit B .
“
Covered Construction Period Losses ” has the meaning
indicated in subparagraph 10(A).
“
Defective Work ” has the meaning indicated in
subparagraph 2(A)(2)(e).
“ FOCB
Notice ” means a notice from BNPPLC to NAI advising NAI
of any of the following events or circumstances, and also advising
NAI that because of any of the following events or circumstances
BNPPLC will be entitled to make the election described in
subparagraph 7(C), which will constitute a Termination of
NAI’s Work and a 97-10/Event:
(1) NAI has taken
action to cancel or terminate or reduce the coverage available to
BNPPLC under the builder’s risk insurance obtained for the
Construction Project as required by this Agreement, or NAI has
otherwise failed to maintain any insurance or to provide insurance
certificates to BNPPLC as required by this Agreement and not cured
such failure within ten days after receiving notice thereof,
or
(2)
NAI has given any Pre-lease Force Majeure Event Notice to BNPPLC,
or
(3)
an Event of Default has occurred and is continuing; or
Construction Management Agreement
— Page 6
(4)
a Work/Suspension Event has occurred
and continued for more than thirty consecutive days after
NAI’s receipt of a Work/Suspension Notice advising NAI of
such Work/Suspension Event, and subsequent to such thirty day
period the Work/Suspension Event has not been rectified by
NAI.
“
Force Majeure Event ” means (A) any taking of any
part of the Property by eminent domain prior to the Completion
Date, and (B) any damage to the Improvements or disruption of
the Work that occurs prior to the Completion Date and that is
caused by fire or acts of God (such as flood, lightning, earthquake
or hurricane), war, strikes and other labor disputes, or riot or
similar civil disturbance, but only to the extent such damage or
disruption (i) is beyond the control of and not caused in whole or
in part by negligence, illegal acts or willful misconduct on the
part of NAI or of its employees or of any other party acting under
NAI’s control or with the approval or authorization of NAI,
and (ii) could not have been avoided or overcome by the
exercise of due diligence or reasonable foresight on the part of
NAI or of any other such party.
“
Funded Construction Allowance ” means on any day the
Outstanding Construction Allowance on that day, including all
Construction Advances and Carrying Costs added to the Outstanding
Construction Allowance on or prior to that day, plus the amount of
any Qualified Prepayments deducted on or prior to that day in the
calculation of such Outstanding Construction Allowance.
“
Future Work ” has the meaning indicated in
subparagraph 4(C)(2)(b).
“
Ground Lease Rents ” has the meaning indicated in
subparagraph 3(F).
“
Increased Cost Charges ” has the meaning indicated in
subparagraph 3(E)(1).
“
Increased Commitment ” has the meaning indicated in
subparagraph 7(B)(6).
“
Increased Funding Commitment ” has the meaning
indicated in subparagraph 7(B)(6)(a).
“
Increased Time Commitment ” has the meaning indicated
in subparagraph 7(B)(6)(b).
“
Initial Advance ” has the meaning indicated in
subparagraph 3(A).
“
Maximum Construction Allowance ” means an amount equal
to $65,000,000, less the Initial Advance.
“
Notice of NAI’s Intent to Terminate ” has the
meaning indicated in
Construction Management Agreement
— Page 7
“
Notice of NAI’s Intent to Terminate Because of a Force
Majeure Event ” has the meaning indicated in subparagraph
7(B)(5).
“
Notice of Termination By NAI ” has the meaning
indicated in subparagraph 7(B)(1).
“
Outstanding Construction Allowance ” means, as of any
date, the difference (but not less than zero) of (A) the total
Construction Advances made by or on behalf of BNPPLC on or prior to
such date in question, plus (B) all Carrying Costs, Commitment
Fees, Administrative Fees, Increased Cost Charges and Capital
Adequacy Charges added on or prior to the date as provided in
Paragraph 3, less (C) any funds received and applied as
Qualified Prepayments on or prior to such date.
“
Owner’s Election to Continue Construction ” has
the meaning indicated in subparagraph 8(A).
“
Pre-lease Casualty ” has the meaning indicated in
subparagraph 2(A)(2)(a).
“
Pre-lease Force Majeure Delays ” means delays in the
completion of the Work to the extent (but only to the extent)
caused solely by a Pre-lease Force Majeure Event.
“
Pre-lease Force Majeure Event ” means a Force Majeure
Event that occurs prior to the Completion Date; provided,
however, that if NAI does not notify BNPPLC of any such Force
Majeure Event by the delivery of a Pre-lease Force Majeure Event
Notice within thirty days after the Force Majeure Event first
occurs or commences, then such Force Majeure Event will not qualify
as a “Pre-lease Force Majeure Event” for purposes of
this Agreement or the other Operative Documents.
“
Pre-lease Force Majeure Event Notice ” has the meaning
indicated in subparagraph 6(B).
“
Pre-lease Force Majeure Excess Costs ” means the
amount (if any) by which the increase in the costs of the Work
resulting directly and solely from a Pre-lease Force Majeure Event
(such as, for example, the costs of repairing damage to the
Improvements caused by a Pre-lease Force Majeure Event) exceed the
amounts available to pay or reimburse NAI for such increased costs.
Amounts available to pay or reimburse such increased costs will
include (a) insurance proceeds or any recovery from a third
party (including any Escrowed Proceeds held by BNPPLC), and
(b) any part of the Construction Allowance (including any
unused contingency amount in the Construction Budget) not used or
needed to cover other Reimbursable Construction Period
Costs.
Construction Management Agreement
— Page 8
“
Pre-lease Force Majeure Losses ” means any of the
following Losses that BNPPLC suffers by reason of damage to the
Improvements caused by a Pre-lease Force Majeure Event:
(a)
the costs of repairing such damage to the extent that such costs
have, as of the date of any required determination of Pre-lease
Force Majeure Losses, (i) been paid or reimbursed from a
Construction Advance (and thus are included in the Lease Balance as
of that date), to be distinguished from costs of repairs paid or
reimbursed from insurance proceeds or from any recovery from a
third party, and (ii) exceeded amounts (if any) available in the
NAI’s original Construction Budget for contingencies and thus
would not have been covered by the Construction Allowance but for
an Increased Funding Commitment;
(b)
any diminution in the value of the Improvements resulting from any
such damage that has not, as of the date of the required
determination of Pre-lease Force Majeure Losses, been
repaired;
(c)
any increase in the total amount of
Carrying Costs, Commitment Fees, Administrative Fees, Increased
Cost Charges, Capital Adequacy Charges and Ground Lease Rents (and
any other amounts) added to the Lease Balance as provided in
Paragraph 3 solely by reason of Pre-lease Force Majeure
Delays; and
(d)
to the extent not already included in
the increase described in the preceding clause, all increases in
Carrying Costs that are attributable to the amounts included in
Pre-lease Force Majeure Losses pursuant to the preceding clause
(a);
but in each
case such amounts will constitute Pre-lease Force Majeure Losses
only to the extent, if any, that they are not offset by insurance
proceeds which are (1) paid by reason of such Pre-lease Force
Majeure Event (including insurance proceeds paid to compensate
BNPPLC or NAI for increased financing costs, the lost time value of
BNPPLC’s investment in the Project or business interruption)
and (2) applied as a Qualified Prepayment to reduce the Lease
Balance.
Also, for
purposes of this definition, the diminution in the value of the
Improvements, as described in the preceding clause (b), will not
exceed the amount thereof estimated in good faith by any
independent appraiser or insurance adjuster engaged by BNPPLC to
determine such amount after BNPPLC has received a Notice of
Pre-lease Force Majeure Event as provided in subparagraph 6(B), nor
will it exceed the cost of repairing the damage described in the
preceding clause (b) as estimated in good faith by any such
independent insurance adjuster or as indicated by any bona fide
written bid to make the repairs that BNPPLC obtains from a
reputable contractor capable of making the repairs.
Construction Management Agreement
— Page 9
“
Prior Work ” has the meaning indicated in subparagraph
4(C)(2)(b).
“
Projected Cost Overruns ” means the excess (if any),
calculated as of the date of each Construction Advance Request, of
(1) the total of projected Reimbursable Construction Period
Costs yet to be incurred or for which NAI has yet to be reimbursed
hereunder (including projected Reimbursable Construction Period
Costs for Future Work), over (2) the balance of the remaining
Construction Allowance then projected to be available to cover such
costs. The balance of the remaining Construction Allowance then
projected to be available will equal: (i) the amount (if any)
by which the Maximum Construction Allowance exceeds the Funded
Construction Allowance, plus (ii) any Escrowed Proceeds
then available or expected to be available to cover costs of
repairs and restoration that NAI will perform as part of the Work
after a casualty or condemnation, less (iii) all
projected future Carrying Costs, Commitment Fees, Administrative
Fees and other amounts to be added to the Outstanding Construction
Allowance as provided in Paragraph 3.
“
Reimbursable Construction Period Costs ” has the
meaning indicated in subparagraph 4(A).
“
Remaining Proceeds ” has the meaning indicated in
subparagraph 5(A).
“
Scope Change ” means a change to the Construction
Project that, if implemented, will make the quality, function or
capacity of the Improvements “materially different” (as
defined below in this subparagraph) than as described or inferred
by the site plan or plans and renderings referenced in
Exhibit B . The term “ Scope Change
” is not intended to include the mere refinement, correction
or detailing of the site plan, plans or renderings submitted to
BNPPLC by NAI. As used in this definition, a “material
difference” means a difference that could reasonably be
expected to (a) cause the Lease Balance to exceed the fair
market value of the Property when the Construction Project is
completed and all Construction Advances required in connection
therewith have been funded, or significantly increase any such
excess, (b) change the general character of the Improvements
from that needed to accommodate the uses to be permitted by
subparagraph 2(A) of the Lease, or (c) cause or
exacerbate Projected Cost Overruns.
“
Target Completion Date ” means the last day of the
24 th
calendar month following the
Effective Date.
“
Termination of NAI’s Work ” means a termination
of NAI’s rights and obligations to continue the Work because
of an election to terminate made by NAI pursuant to subparagraph
7(B) or because of an election by BNPPLC made pursuant to
subparagraph 7(C).
Construction Management Agreement
— Page 10
“
Third Party Contract ” has the meaning indicated in
subparagraph 2(A)(2)(b).
“
Third Party Contract/Termination Fees ” means any
amounts, however denominated, for which NAI will be obligated under
a Third Party Contract as a result of any election or decision by
NAI to terminate such Third Party Contract, including
demobilization costs; provided, however, amounts payable only by
reason of Prior Work as of the date any such termination will not
be characterized as Third Party Contract/Termination Fees. If NAI
reserves an absolute express right in a Third Party Contract to
terminate such contract at any time, without cause, for a specified
U.S. dollar amount, such amount will constitute a Third Party
Contract/Termination Fee. If no such right is reserved in a Third
Party Contract, the amount of damages that NAI is required to pay
(in addition to payments required for Prior Work) upon a
repudiation of the Third Party Contract by NAI will qualify as a
“Third Party Contract/Termination Fee” applicable to
such contract for purposes of this Agreement.
“
Timing or Budget Shortfall ” has the meaning indicated
in subparagraph 7(B).
“
Work ” has the meaning indicated in subparagraph
2(A)(2)(a).
“
Work/Suspension Event ” means any of the
following:
(1) Projected
Cost Overruns have become more likely than not, in BNPPLC’s
good faith judgment (taking into account any notices or
Construction Draw Requests from NAI indicating that a Pre-lease
Force Majeure Event may result in Projected Cost Overruns), and
BNPPLC has notified NAI of such judgement and the reasons
therefor.
(2) Delays in
the Work (including any delays resulting from damage to the
Property by fire or other casualty or from any taking of any part
of the Property by condemnation) have made it substantially
unlikely, in BNPPLC’s good faith judgment, that NAI will be
able to complete the Construction Project in accordance with the
requirements of this Agreement prior to the Target Completion Date
using only the funds available to NAI under this Agreement, and
BNPPLC has notified NAI of such judgement and the reasons
therefor.
(3) BNPPLC
has requested with respect to any Construction Advance, but NAI has
failed to provide within thirty days after receipt of the request:
(1) invoices, requests for payment from contractors and other
evidence reasonably establishing that the costs and expenses for
which NAI has requested or is requesting reimbursement constitute
actual Reimbursable Construction Period Costs, and
(2) canceled checks, lien waivers or other evidence reasonably
establishing that all prior Construction Advances paid to NAI have
been used by NAI to pay the Reimbursable Construction Period
Costs
Construction Management Agreement
— Page 11
for which the
prior advances were requested and made.
“
Work/Suspension Notice ” means a notice from BNPPLC to
NAI advising NAI of any event or circumstances that constitute a
Work/Suspension Event and advising NAI that (1) before the
Work/Suspension Event is rectified BNPPLC may limit Construction
Advances to NAI as permitted by this Agreement, and (2) unless
NAI does rectify the Work/Suspension Event within thirty days after
NAI’s receipt of such notice, BNPPLC may elect to send an
FOCB Notice in anticipation of a Termination of NAI’s
Work.
“
Work/Suspension Period ” means any period
(1) beginning with the date of any Work/Suspension Notice,
FOCB Notice or Notice of NAI’s Intent to Terminate, and
(2) ending on the earlier of (a) the first date upon
which (i) no Work/Suspension Events are continuing,
(ii) all previous FOCB Notices and Notices of NAI’s
Intent to Terminate (if any) have been rescinded, and (iii) no
97-10/Events have occurred, or (b) the effective date of any
Termination of NAI’s Work as described in subparagraph 7(B)
or subparagraph 7(C).
|
2
|
|
Construction
and Management of the Property by NAI .
|
|
|
(A)
|
|
The Construction Project
.
|
|
|
(1)
|
|
Construction Approvals by
BNPPLC .
|
(a)
Preconstruction Approvals by BNPPLC . NAI submitted and
obtained BNPPLC’s approval of the site plan and descriptions
of the Construction Project referenced in Exhibit B .
Also set forth in Exhibit B is a general description of
the Construction Project. The Construction Project, as constructed
by NAI pursuant to this Agreement, and all construction contracts
and other agreements executed or adopted by NAI in connection
therewith, must not be inconsistent in any material respect with
the plans or other items referenced in Exhibit B ,
except to the extent otherwise provided by any Scope Change
approved by BNPPLC and except as otherwise provided in subparagraph
8(A) if BNPPLC should make an Owner’s Election to Continue
Construction after any Termination of NAI’s Work.
(b) Approval of
Scope Changes . Before making a Scope Change, NAI must provide
to BNPPLC a reasonably detailed written description of the Scope
Change, a revised Construction Budget and a copy of any changes to
the drawings, plans and specifications for the Improvements
required in connection therewith, all of which must be approved in
writing by BNPPLC before the Scope Change is implemented. After
receiving such items, BNPPLC will endeavor in good faith to respond
promptly (and in any event no later than thirty days
after
Construction Management Agreement
— Page 12
such receipt)
to any request by NAI for approval of the Scope Change. BNPPLC will
not, however, be liable for any failure to provide a prompt
response. Further, BNPPLC’s approval will not in any event
constitute a waiver of subparagraph 2(A)(3) or of any other
provision of this Agreement or other Operative
Documents.
(2)
NAI’s Right to Possession and to Control Construction
. Subject to the terms and conditions set forth in this Agreement,
and prior to any Termination of NAI’s Work as provided in
subparagraphs 7(B) and 7(C), NAI will have possession of the Land
and all Improvements on the Land to the exclusion of BNPPLC and
will have the sole right to control and the sole responsibility for
the design and construction of the Construction Project, including
the means, methods, sequences and procedures implemented to
accomplish such design and construction. Although title to all
Improvements will vest in BNPPLC (as more particularly provided in
subparagraph 2(C)), BNPPLC’s obligation with respect to the
Construction Project will be limited to the making of advances
under and subject to the conditions set forth in this Agreement.
Without limiting the foregoing, NAI acknowledges and agrees
that:
(a) Performance
of the Work . Except as provided in subparagraphs 7(A) and
7(D), NAI must, using its best skill and judgment and in an
expeditious and economical manner not inconsistent with the
interests of BNPPLC, perform or cause to be performed all work
required, and must provide or cause to be provided all supplies and
materials required, to design and complete construction of the
Construction Project (collectively “ Work ”) no
later than the Target Completion Date. The Work will include
obtaining all necessary building permits and other governmental
approvals required in connection with the design and construction
of the Construction Project, or required in connection with the use
and occupancy thereof ( e.g., final certificates of
occupancy). The Work will also include any repairs or restoration
required because of damage to Improvements by fire or other
casualty prior to the Completion Date (a “ Pre-lease
Casualty ”); provided, however , the cost of any
such repairs or restoration will be subject to reimbursement not
only through Construction Advances made to NAI on and subject to
the terms and conditions of this Agreement, but also through the
application of Escrowed Proceeds as provided in Paragraph 5;
and, provided further , like other Work, any such repairs
and restoration to be provided by NAI will be subject to
subparagraphs 7(A) and 7(D), which establish certain rights of NAI
to suspend or discontinue any Work. NAI will carefully schedule and
supervise all Work, will check all materials and services used in
connection with all Work and will keep full and detailed accounts
as may be necessary to document expenditures made or expenses
incurred for the Work.
Construction Management Agreement
— Page 13
|
|
(b)
|
|
Third Party Contracts
.
|
1) NAI will not
enter into any construction contract or other agreement with a
third party concerning the Work or the Construction Project (a
“ Third Party Contract ”) in the name of BNPPLC
or otherwise purport to bind BNPPLC to any obligation to any third
party.
2) In any Third
Party Contract between NAI and any of its Affiliates (an “
Affiliate’s Contract ”) NAI must reserve the
right to terminate such contract at any time, without cause, and
without subjecting NAI to liability for any Third Party
Contract/Termination Fee. Further, NAI must not enter into any
Affiliate’s Contract that obligates NAI to pay more than
would be required under an arms-length contract or that would
require NAI to pay its Affiliate any amount in excess of the sum of
actual, out-of-pocket direct costs and internal labor costs
incurred by the Affiliate to perform such contract.
(c)
Adequacy of Drawings, Specifications and Budgets . BNPPLC
has not made and will not make any representations as to the
adequacy of the Construction Budget or any other budget or any site
plans, renderings, plans, drawings or specifications for the
Construction Project, and no modification of any such budgets, site
plans, renderings, plans, drawings or specifications that may be
required from time to time will entitle NAI to any adjustment in
the Construction Allowance.
(d)
Existing Condition of the Land and Improvements . NAI is
familiar with the conditions of the Land and any existing
Improvements on the Land. NAI will have no claim for damages
against BNPPLC or for an increase in the Construction Allowance or
for an extension of the deadline specified in subparagraph
2(A)(2)(a) for completing the Work by reason of any condition
(concealed or otherwise) of or affecting the Land or
Improvements.
(e)
Correction of Defective Work . NAI will promptly correct all
Work performed prior to any Termination of NAI’s Work that
does not comply with the requirements of this Agreement for any
reason other than a Pre-lease Casualty (“ Defective
Work ”). If NAI fails to correct any Defective Work or
fails to carry out Work in accordance with this Agreement, BNPPLC
may (but will not be required to) order NAI to stop all Work until
the cause for such failure has been eliminated.
Construction Management Agreement
— Page 14
(f) Clean
Up . Upon the completion of all Work, NAI will remove all waste
material and rubbish from and about the Land, as well as all tools,
construction equipment, machinery and surplus materials. NAI will
keep the Land and the Improvements thereon in a reasonably safe and
sightly condition as Work progresses.
(g) No Damage
for Delays . NAI will have no claim for damages against BNPPLC
or for an increase in the Construction Allowance by reason of any
delay in the performance of any Work. Nor will NAI have any claim
for an extension of the deadline specified in subparagraph
2(A)(2)(a) for completing the Work because of any such period of
delay, except that (i) in the case of any Pre-lease Force
Majeure Delays, NAI will have certain rights as set forth in
subparagraph 7(B) and other provisions of this Agreement, and
(ii) in the event of intentional interference with the Work by
BNPPLC itself for which NAI provides written notice to cease, NAI
will be entitled to an extension of the deadline specified in
subparagraph 2(A)(2)(a) as needed because of any delays resulting
from such intentional interference. It is also understood that any
such intentional interference by BNPPLC will constitute a Force
Majeure Event. In no event, however, will BNPPLC’s exercise
of its rights and remedies permitted under this Agreement or the
other Operative Documents be construed as intentional interference
with NAI’s performance of any Work; and thus neither
BNPPLC’s exercise of its right to withhold Construction
Advances at any time when NAI has failed to satisfy all conditions
herein to such advances, nor BNPPLC’s exercise of its right
to terminate Work by NAI as provided in subparagraph 7(C), be
considered as intentional interference with the Work or a Pre-lease
Force Majeure Event.
(h) No Fee For
Construction Management . NAI will have no claim under this
Agreement for any fee or other compensation or for any
reimbursement of internal administrative or overhead expenses
(other than the out-of-pocket overhead expenses properly included
in the Construction Budget, if any), it being understood that NAI
is executing this Agreement in consideration of the rights
expressly granted to it herein and in the other Operative
Documents.
(3) Quality of
Work . NAI will cause the Work undertaken and administered by
it pursuant to this Agreement to be performed (a) in a safe
and good and workmanlike manner, (b) in accordance with
Applicable Laws, and (c) in compliance with the provisions of
this Agreement and the material provisions of the Permitted
Encumbrances.
(B)
Completion Notice . Within ten Business Days after NAI
substantially completes construction of the Construction Project
and obtains any certificate of occupancy or other permit
Construction Management Agreement
— Page 15
(temporary or
permanent) required by Applicable Laws for the commencement of
NAI’s use and occupancy of the Improvements, NAI must provide
a notice (a “ Completion Notice ”) to BNPPLC,
advising BNPPLC thereof, and thereby establish the Completion Date.
For purposes of this Agreement and the other Operative Documents,
BNPPLC will be entitled to rely without investigation upon any such
notice given by NAI as evidence that NAI has, in fact,
substantially completed the Construction Project and has obtained
any certificate of occupancy or other permit (temporary or
permanent) required for the commencement of NAI’s use of the
Improvements, and after giving any such notice NAI will be estopped
from later claiming that the Completion Date has not
occurred.
(C)
Status of Property Acquired With BNPPLC’s Funds . All
Improvements constructed on the Land as provided in this Agreement
will constitute “Property” for purposes of the Lease
and other Operative Documents. Further, to the extent heretofore or
hereafter acquired (in whole or in part) with any portion of the
Initial Advance or with any Construction Advances or with other
funds for which NAI receives reimbursement from the Initial Advance
or Construction Advances, all furnishings, furniture, chattels,
permits, licenses, franchises, certificates and other personal
property of whatever nature will be considered as having been
acquired on behalf of BNPPLC by NAI and will constitute
“Property” for purposes of the Lease and other
Operative Documents, as will all renewals or replacements of or
substitutions for any such Property. The parties intend that title
to the Improvements and to any other such Property will vest in
BNPPLC without passing through NAI or NAI’s Affiliates before
it is transferred to BNPPLC from contractors, suppliers, vendors or
other third Persons, but with the understanding that all such
Property will be accepted by BNPPLC subject to the terms and
conditions of the other Operative Documents, including
subparagraph 4(C)(1) of the Lease (concerning the
characterization of the Lease and other Operative Documents for tax
and certain other purposes). Although nothing herein constitutes
authorization of NAI by BNPPLC to bind BNPPLC to any construction
contract or other agreement with a third Person, any construction
contract or other agreement executed by NAI for the acquisition or
construction of Improvements or other components of the Property
may, as NAI deems appropriate, provide for the direct transfer of
title to BNPPLC as described in the preceding sentence.
(1) Liability
Insurance . Throughout the period prior to any Termination of
NAI’s Work, NAI must maintain commercial general liability
insurance against claims for bodily and personal injury, death and
property damage occurring in or upon or resulting from any
occurrence in or upon the Property under one or more insurance
policies that satisfy the Minimum Insurance Requirements, which are
set forth in an exhibit to the Common Definitions and Provisions
Agreement. NAI must deliver and maintain with BNPPLC for each
liability insurance policy required by this Agreement written
confirmation of the policy and the scope of the coverage provided
thereby issued by the
Construction Management Agreement
— Page 16
applicable
insurer or its authorized agent, which confirmation must also
satisfy the Minimum Insurance Requirements.
(2)
Property Insurance . Throughout the period prior to any
Termination of NAI’s Work, NAI must also keep all
Improvements (including all alterations, additions and changes made
to the Improvements) insured against fire and other casualty under
one or more property insurance policies that satisfy the Minimum
Insurance Requirements. NAI must deliver and maintain with BNPPLC
for each property insurance policy required by this Agreement
written confirmation of the policy and the scope of the coverage
provided thereby issued by the applicable insurer or its authorized
agent, which confirmation must also satisfy the Minimum Insurance
Requirements. If any of the Property is destroyed or damaged by
fire, explosion, windstorm, hail or by any other casualty against
which insurance has been required hereunder, (i) BNPPLC may,
but will not be obligated to, make proof of loss if not made
promptly by NAI after notice from BNPPLC, (ii) each insurance
company concerned is hereby authorized and directed to make payment
for such loss directly to BNPPLC for application as required by
Paragraph 5, and (iii) BNPPLC may settle, adjust or
compromise any and all claims for loss, damage or destruction under
any policy or policies of insurance (provided, that so long as no
97-10/Event has occurred and no Event of Default has occurred and
is continuing, BNPPLC must provide NAI with at least forty-five
days notice of BNPPLC’s intention to settle any such claim
before settling it unless NAI has already approved of the
settlement by BNPPLC). BNPPLC will not in any event or
circumstances be liable or responsible for failure to collect, or
to exercise diligence in the collection of, any insurance proceeds.
If any casualty results in damage to or loss or destruction of the
Property, NAI must give prompt notice thereof to BNPPLC and
Paragraph 5 will apply.
(3)
Failure of NAI to Obtain Insurance . If NAI fails to obtain
any insurance or to provide confirmation of any insurance as
required by this Agreement, BNPPLC will be entitled (but not
required) to obtain the insurance that NAI has failed to obtain or
for which NAI has not provided the required confirmation and,
without limiting BNPPLC’s other remedies under the
circumstances, BNPPLC may charge the cost of such insurance against
the Construction Allowance as if it were a Construction Advance
paid to NAI as hereinafter provided.
(4)
Waiver of Subrogation . NAI, for itself and for any Person
claiming through it (including any insurance company claiming by
way of subrogation), waives any and every claim which arises or may
arise in its favor against BNPPLC or any other Interested Party for
any and all Losses, to the extent that NAI is compensated by
insurance or would be compensated by the insurance policies
contemplated in this Agreement, but for any deductible or
self-insured retention maintained under such insurance or but for a
failure of NAI to maintain the insurance as required by
this
Construction Management Agreement
— Page 17
Agreement. NAI
agrees to have such insurance policies properly endorsed so as to
make them valid notwithstanding this waiver, if such endorsement is
required to prevent a loss of insurance.
(E)
Condemnation . Immediately upon obtaining knowledge of the
institution of any proceedings for the condemnation of the Property
or any portion thereof, or any other similar governmental or
quasi-governmental proceedings arising out of injury or damage to
the Property or any portion thereof, each party must promptly
notify the other (provided, however, BNPPLC will have no liability
for its failure to provide such notice) of the pendency of such
proceedings. Prior to any Termination of NAI’s Work, NAI
must, if requested by BNPPLC, diligently prosecute any such
proceedings and consult with BNPPLC, its attorneys and experts and
cooperate with them as reasonably requested in the carrying on or
defense of any such proceedings. All proceeds of condemnation
awards or proceeds of sale in lieu of condemnation with respect to
the Property and all judgments, decrees and awards for injury or
damage to the Property will be paid to BNPPLC as Escrowed Proceeds,
and all such proceeds will be applied as provided in
Paragraph 5. BNPPLC is hereby authorized, in its own name or
in the name of NAI or in the name of both, to settle and deliver
valid acquittances for, or to challenge and to appeal from, any
such judgment, decree or award concerning condemnation of any of
the Property (provided, that so long as no 97-10/Event has occurred
and no Event of Default has occurred and is continuing, BNPPLC must
provide NAI with at least forty-five days notice of BNPPLC’s
intention to settle any such claim before settling it unless NAI
has already approved of the settlement by BNPPLC). BNPPLC will not
in any event or circumstances be liable or responsible for failure
to collect, or to exercise diligence in the collection of, any such
proceeds, judgments, decrees or awards.
(F)
Additional Representations, Warranties and Covenants of NAI
Concerning the Property . Without limiting the rights granted
to NAI by other provisions of this Agreement to be reimbursed from
Construction Advances for the cost of complying with the following,
NAI represents, warrants and covenants as follows:
(1) Payment of
Local Impositions . Throughout the period prior to any
Termination of NAI’s Work, NAI must pay or cause to be paid
prior to delinquency all ad valorem taxes assessed against the
Property and other Local Impositions. If requested by BNPPLC from
time to time, NAI will furnish BNPPLC with receipts or other
appropriate evidence showing payment of all Local Impositions prior
to the applicable delinquency date therefor.
Notwithstanding
the foregoing, NAI may in good faith, by appropriate proceedings,
contest the validity, applicability or amount of any asserted Local
Imposition, and pending such contest NAI will not be deemed in
default under any of the provisions of this Agreement because of
the Local Imposition if (1) NAI diligently prosecutes
such
Construction Management Agreement
— Page 18
contest to
completion in a manner reasonably satisfactory to BNPPLC, and
(2) NAI promptly causes to be paid any amount adjudged by a
court of competent jurisdiction to be due, with all costs,
penalties and interest thereon, promptly after such judgment
becomes final; provided, however, in any event each such contest
must be concluded and the contested Local Impositions must be paid
by NAI prior to the earlier of (i) the date that any criminal
prosecution is instituted or overtly threatened against BNPPLC or
its directors, officers or employees because of the nonpayment
thereof, or (ii) the date any writ or order is issued under
which any property owned or leased by BNPPLC (including the
Property) may be seized or sold or any other action is taken or
overtly threatened against BNPPLC or against any property owned or
leased by BNPPLC because of the nonpayment thereof, or
(iii) any Designated Sale Date upon which, for any reason, NAI
or an Affiliate of NAI or any Applicable Purchaser does not
purchase BNPPLC’s interest in the Property pursuant to the
Purchase Agreement for a price to BNPPLC (when taken together with
any Supplemental Payment paid by NAI pursuant to the Purchase
Agreement, in the case of a purchase by an Applicable Purchaser)
equal to the Break Even Price.
(2)
Operation and Maintenance . Throughout the period prior to
any Termination of NAI’s Work, NAI must operate and maintain
the Property in a good and workmanlike manner and in compliance
with Applicable Laws in all material respects and pay or cause to
be paid all fees or charges of any kind in connection therewith.
(If NAI does not promptly correct any failure of the Property to
comply with Applicable Laws that is the subject of a written
complaint or demand for corrective action given by any Governmental
Authority to NAI, or to BNPPLC and forwarded by it to NAI, then for
purposes of the preceding sentence, NAI will be considered not to
have maintained the Property “in compliance with all
Applicable Laws in all material respects” whether or not the
noncompliance would be material in the absence of the complaint or
demand.) NAI must not use or occupy, or allow the use or occupancy
of, the Property in any manner which violates any Applicable Law or
which constitutes a public or private nuisance or which makes void,
voidable or cancelable any insurance then in force with respect
thereto. Without limiting the generality of the foregoing, NAI must
not conduct or permit others to conduct Hazardous Substance
Activities on the Property, except Permitted Hazardous Substance
Use and Remedial Work; and NAI must not discharge or permit the
discharge of anything (including Permitted Hazardous Substances) on
or from the Property that would require any permit under applicable
Environmental Laws, other than (1) storm water runoff,
(2) fume hood emissions, (3) waste water discharges
through a publicly owned treatment works, (4) discharges that
are a necessary part of any Remedial Work, and (5) other
similar discharges consistent with the definition herein of
Permitted Hazardous Substance Use which do not significantly
increase the risk of Environmental Losses to BNPPLC, in each case
in strict compliance with Environmental Laws. To the extent that
any of the following would, individually or in the aggregate,
increase the
Construction Management Agreement
— Page 19
likelihood of a
97-10/Event or materially and adversely affect the value of the
Property or the use of the Property for purposes permitted by this
Agreement, NAI must not, without BNPPLC’s prior consent:
(i) initiate or permit any zoning reclassification of the
Property; (ii) seek any variance under existing zoning
ordinances applicable to the Property; (iii) use or permit the
use of the Property in a manner that would result in such use
becoming a nonconforming use under applicable zoning ordinances or
similar laws, rules or regulations; (iv) execute or file any
subdivision plat affecting the Property; or (v) consent to the
annexation of the Property to any municipality. NAI will not cause
or permit any drilling or exploration for, or extraction, removal
or production of, minerals from the surface or subsurface of the
Property, and NAI must not do anything that could reasonably be
expected to significantly reduce the market value of the Property.
If NAI receives a notice or claim from any federal, state or other
governmental authority that the Property is not in compliance with
any Applicable Law, or that any action may be taken against BNPPLC
because the Property does not comply with any Applicable Law, NAI
must promptly furnish a copy of such notice or claim to
BNPPLC.
(3) Debts
for Construction, Maintenance, Operation or Development . NAI
must promptly pay or cause to be paid all debts and liabilities
incurred it or its contractors or subcontractors in the
construction, maintenance, operation or development of the
Property. Such debts and liabilities will include those incurred
for labor, material and equipment and all debts and charges for
utilities servicing the Property.
(4)
Permitted Encumbrances and the Ground Lease . NAI must
comply with and will cause to be performed all of the covenants,
agreements and obligations imposed upon the owner of any interest
in the Property by the Permitted Encumbrances or the Ground Lease
throughout the period prior to any Termination of NAI’s Work.
NAI must not, without the prior consent of BNPPLC, create any new
Permitted Encumbrance or enter into, initiate, approve or consent
to any modification of any Permitted Encumbrance that would create
or expand or purport to create or expand obligations or
restrictions encumbering BNPPLC’s interest in the Property.
(Whether BNPPLC must give any such consent requested by NAI prior
to the Completion Date will be governed by subparagraph 4(C)
of the Closing Certificate.)
(5) Books
and Records Concerning the Property . NAI must keep books and
records that are accurate and complete in all material respects for
NAI’s construction and management of the Property as
contemplated in this Agreement and must permit all such books and
records (including all contracts, statements, invoices, bills and
claims for labor, materials and services supplied for the
construction and operation of any Improvements) to be inspected and
copied by BNPPLC.
Construction Management Agreement
— Page 20
|
(G)
|
|
BNPPLC’s Right of
Access .
|
(1)
Access Generally . BNPPLC and BNPPLC’s representatives
may enter the Property at any time for the purpose of making
inspections or performing any work BNPPLC is authorized to
undertake by the next subparagraph or for the purpose confirming
whether NAI has complied with the requirements of this Agreement or
the other Operative Documents. However, prior to any Termination of
NAI’s Work, BNPPLC or BNPPLC’s representative will,
before making any entry upon the Property or performing any work on
the Property authorized by this Agreement, do the
following
(a) BNPPLC will
give NAI at least 24 hours notice, unless BNPPLC believes in good
faith that an emergency may exist or a Default has occurred and is
continuing, because of which significant damage to the Property or
other significant Losses may be sustained if BNPPLC delays entry to
the Property; and
(b) if then
requested to do so by NAI in order to maintain NAI’s
security, BNPPLC or its representative will: (i) sign in at
NAI’s security or information desk if NAI has such a desk on
the premises, (ii) wear a visitor’s badge or other
reasonable identification, (iii) permit an employee of NAI to
observe such inspection or work, and (iv) comply with other
similar reasonable nondiscriminatory security requirements of NAI
that do not, individually or in the aggregate, significantly
interfere with inspections or work of BNPPLC authorized by this
Agreement.
(2)
Failure of NAI to Perform . If NAI fails to perform any act
or to take any action required of it by this Agreement or other
Operative Documents, or to pay any money which NAI is required by
this Agreement or other Operative Documents to pay, and if such
failure or action constitutes an Event of Default or renders BNPPLC
or any director, officer, employee or Affiliate of BNPPLC at risk
of criminal prosecution or renders BNPPLC’s interest in the
Property or any part thereof at risk of forfeiture by forced sale
or otherwise, then in addition to any other remedies specified
herein or otherwise available, BNPPLC may, perform or cause to be
performed such act or take such action or pay such money. (To the
extent that expenses so incurred by BNPPLC, and money so paid by
BNPPLC, qualify as a Covered Construction Period Losses, NAI must
pay the same to BNPPLC upon demand. If any such expenses incurred
or money paid do not qualify as Covered Construction Period Losses,
but do constitute 97-10/Project Costs, BNPPLC may treat them as
Construction Advances hereunder. To the extent that any such
expenses incurred or money paid do not qualify as Covered
Construction Period Losses and do constitute 97-10/Project Costs,
they will be included — with interest — in the Balance
of Unpaid Covered Construction Period Losses under and as defined
in the Purchase Agreement.) Further, BNPPLC, upon making such
payment, will be subrogated
Construction Management Agreement
— Page 21
to all of the
rights of the person, corporation or body politic receiving such
payment. But nothing herein will imply any duty upon the part of
BNPPLC to do any work which, under any provision of this Agreement
or otherwise, NAI may be required to perform, and the performance
thereof by BNPPLC will not constitute a waiver of NAI’s
default. BNPPLC may during the progress of any such work permitted
by BNPPLC hereunder on or in the Property keep and store upon the
Property all necessary materials, tools, and equipment. BNPPLC will
not in any event be liable for inconvenience, annoyance,
disturbance, loss of business, or other damage to NAI or the
subtenants or invitees of NAI by reason of BNPPLC’s
performance of any such work, or on account of bringing materials,
supplies and equipment into or through the Property during the
course of such work, and the obligations of NAI under this
Agreement and the other Operative Documents will not thereby be
excused in any manner.
3
Amounts to be Added to
the Lease Balance (in Addition to Construction Advances)
.
(A)
Initial Advance . Upon execution and delivery of this
Agreement by BNPPLC, an advance (the “ Initial Advance
”) will be made by BNPPLC to cover the cost of certain
Transaction Expenses and other amounts described in this
subparagraph. The amount of the Initial Advance, which will be
included in the Lease Balance, may be confirmed by a separate
closing certificate executed by NAI as of the Effective Date. An
arrangement fee (the “ Arrangement Fee ”) and an
initial administrative agency fee (an “ Administrative
Fee ”) will be paid from the Initial Advance (and thus be
included in the Lease Balance) in the amounts provided in the Term
Sheet. To the extent that BNPPLC does not itself use the entire the
Initial Advance to pay such fees and Transaction Expenses incurred
by BNPPLC, the remainder thereof will be advanced to NAI, with the
understanding that NAI will use any such amount advanced for one or
more of the following purposes: (1) the payment or
reimbursement of Transaction Expenses incurred by NAI and all
“soft costs” incurred by NAI in connection with the
planning, design, engineering, construction and permitting of the
Construction Project; (2) the maintenance of the Property; or
(3) the payment of other amounts due pursuant to the Operative
Documents. (Before executing the separate closing certificate to
confirm the Initial Advance, NAI will make a reasonable effort to
determine all prior expenses incurred by it as described in clause
(1) of the preceding sentence and to
|