EXHIBIT 10.28
|
|
|
|
|
|
|
|
|
OWNER
|
|
x
|
CONSTRUCTION
MANAGER - ADVISER EDITION
|
|
CONSTRUCTION
MANAGER
|
|
x
|
AIA Document
G701/CMa - Electronic Format
|
|
ARCHITECT
|
|
x
|
|
|
|
CONTRACTOR
|
|
x
|
|
|
|
FIELD
|
|
o
|
|
|
|
OTHER
|
|
o
|
THIS DOCUMENT HAS IMPORTANT LEGAL
CONSEQUENCES; CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH
RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION OF THIS
ELECTRONICALLY DRAFTED AIA DOCUMENT MAY BE MADE BY USING AIA
DOCUMENT D401.
|
|
|
|
|
|
|
CHANGE ORDER
NO: 2
|
|
|
|
|
Advanced
Neuromodulation Systems, Inc. at Legacy
|
|
INITIATION
DATE: December 15, 2003
|
|
|
|
|
|
|
|
PROJECT NOS.:
General Construction
|
|
|
|
|
|
|
|
CONTRACT
FOR:
|
|
|
|
|
|
|
|
CONTRACT DATE:
30 April, 2003
|
|
|
|
|
|
|
|
|
|
|
|
|
Rogers
O’Brien Construction Co., Inc.
|
|
|
|
|
|
|
|
|
|
|
The Contract is changed as
follows:
Add for interior construction at
high bay building and office building (reference attached Exhibit
“A” for complete list of plans & specifications. In
accordance with accepted alternates & contractor’s
clarifications (ref. Exhibit “B”).
Add for interior construction at
2 story office building = $3,095,733
Add for interior construction at
High Bay Building = $491,657
Net Add for all revisions: Three
million five hundred eighty seven thousand three hundred ninety
dollars $3,587,390
Not valid until signed by the
Owner, Construction Manager, Architect and Contractor.
|
|
|
|
|
|
The original (Guaranteed Maximum Price)
was
|
|
$
|
7,811,128
|
|
|
|
|
|
|
|
Net change by previously authorized Change
Orders
|
|
$
|
153,376
|
|
|
|
|
|
|
|
The (Guaranteed Maximum Price) prior to this
Change Order was
|
|
$
|
7,964,504
|
|
|
|
|
|
|
|
The (Guaranteed Maximum Price) will be
(increased) by this Change Order
|
|
$
|
3,587,390
|
|
|
|
|
|
|
|
The new (Guaranteed Maximum Price) including
this Change Order will be
|
|
$
|
11,551,894
|
|
|
|
|
|
|