Exhibit 10.3
|
|
|
|
|
|
|
|
|
PORTIONS OF THIS EXHIBIT MARKED
BY * * * HAVE BEEN OMITTED PURSUANT TO A REQUEST FOR CONFIDENTIAL
TREATMENT FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE
COMMISSION
|
|
FOIA CONFIDENTIAL TREATMENT
REQUESTED
|
Final Execution
ENGINEERING AND CONSTRUCTION
AGREEMENT
between
DUKE ENERGY CAROLINAS, LLC, as
Owner
and
SHAW NORTH CAROLINA, INC, as
Contractor
for the
CONSTRUCTION OF A COMBUSTION
TURBINE COMBINED CYCLE ELECTRICAL GENERATION FACILITY AT THE BUCK
GENERATING FACILITY IN ROWAN COUNTY, NORTH CAROLINA
Dated May 5,
2008
Confidential
Table of Contents
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page
|
|
1.
|
|
DEFINITIONS
|
|
1
|
|
|
|
|
|
2.
|
|
GENERAL
PROVISIONS
|
|
14
|
|
|
|
|
|
|
|
|
2.1
|
|
Intent of
Contract Documents
|
|
14
|
|
|
|
2.2
|
|
Independent
Contractor
|
|
14
|
|
|
|
2.3
|
|
Subcontracting;
Approved Subcontractors
|
|
14
|
|
|
|
2.4
|
|
Assignment of
Subcontracts
|
|
15
|
|
|
|
2.5
|
|
Interpretation
|
|
15
|
|
|
|
2.6
|
|
Inclusion;
Order of Precedence
|
|
16
|
|
|
|
2.7
|
|
Days
|
|
17
|
|
|
|
|
|
3.
|
|
CONTRACTOR
RESPONSIBILITIES
|
|
17
|
|
|
|
|
|
|
|
|
3.1
|
|
Performance of
the Services; Commencement of Work
|
|
17
|
|
|
|
3.2
|
|
Professional
Standards
|
|
19
|
|
|
|
3.3
|
|
Sufficient
Personnel
|
|
20
|
|
|
|
3.4
|
|
Supervision and
Discipline
|
|
20
|
|
|
|
3.5
|
|
Contractor’s Key Personnel
|
|
20
|
|
|
|
3.6
|
|
Design and
Engineering
|
|
20
|
|
|
|
3.7
|
|
Quality
Assurance Plan
|
|
21
|
|
|
|
3.8
|
|
Safety
Management Plan
|
|
21
|
|
|
|
3.9
|
|
Training
|
|
21
|
|
|
|
3.10
|
|
Utility
Use
|
|
21
|
|
|
|
3.11
|
|
Spare
Parts
|
|
22
|
|
|
|
3.12
|
|
Subcontractor
Presence
|
|
22
|
|
|
|
3.13
|
|
Current
Records; Record Drawings
|
|
23
|
|
|
|
3.14
|
|
Transportation
Costs
|
|
23
|
|
|
|
3.15
|
|
Facility
Manuals
|
|
23
|
|
|
|
3.16
|
|
Control of
Work
|
|
23
|
|
|
|
3.17
|
|
Emergencies
|
|
24
|
|
|
|
3.18
|
|
Local
Conditions
|
|
24
|
|
|
|
3.19
|
|
Use of Site;
Owner Access
|
|
24
|
|
|
|
3.20
|
|
Compliance with
Laws
|
|
24
|
|
|
|
3.21
|
|
Permits and
Approvals
|
|
25
|
|
|
|
3.22
|
|
Periodic
Reports and Meetings
|
|
25
|
|
|
|
3.23
|
|
Signage
|
|
26
|
|
|
|
3.24
|
|
Interference
with Traffic
|
|
26
|
|
|
|
3.25
|
|
Supply of Water
and Disposal of Sewage
|
|
26
|
|
|
|
3.26
|
|
Housekeeping
|
|
26
|
|
|
|
|
|
4.
|
|
OWNER
RESPONSIBILITIES
|
|
26
|
|
|
|
|
|
|
|
|
4.1
|
|
Owner’s
Representative
|
|
26
|
i
|
|
|
|
|
|
|
|
|
|
|
4.2
|
|
Access
|
|
27
|
|
|
|
4.3
|
|
Permits
|
|
27
|
|
|
|
4.4
|
|
Owner
Equipment
|
|
27
|
|
|
|
4.5
|
|
Fuel and
Utilities
|
|
27
|
|
|
|
4.6
|
|
Operation and
Maintenance Staff
|
|
27
|
|
|
|
4.7
|
|
Job Site
Rules
|
|
28
|
|
|
|
4.8
|
|
Payment
|
|
28
|
|
|
|
|
|
5.
|
|
EQUIPMENT AND
WORKMANSHIP
|
|
28
|
|
|
|
|
|
|
|
|
5.1
|
|
Quality of
Equipment and Workmanship
|
|
28
|
|
|
|
5.2
|
|
Cost of
Tests
|
|
28
|
|
|
|
5.3
|
|
Samples
|
|
28
|
|
|
|
5.4
|
|
Inspection of
Operations
|
|
28
|
|
|
|
5.5
|
|
Examination of
Work before Covering
|
|
29
|
|
|
|
5.6
|
|
Uncovering and
Making Openings
|
|
29
|
|
|
|
|
|
6.
|
|
SCHEDULE
|
|
29
|
|
|
|
|
|
|
|
|
6.1
|
|
Commencement of
Work
|
|
29
|
|
|
|
6.2
|
|
Schedule
Requirements; Updates
|
|
29
|
|
|
|
6.3
|
|
[*]
|
|
29
|
|
|
|
|
|
7.
|
|
CONTRACT PRICE;
COMPENSATION AND PAYMENT
|
|
30
|
|
|
|
|
|
|
|
|
7.1
|
|
[*]
|
|
30
|
|
|
|
7.2
|
|
[*]
|
|
32
|
|
|
|
7.3
|
|
[*]
|
|
34
|
|
|
|
7.4
|
|
Deficient
Invoices and Payments
|
|
34
|
|
|
|
7.5
|
|
[*]
|
|
35
|
|
|
|
7.6
|
|
Final
Payment
|
|
36
|
|
|
|
7.7
|
|
Certification
by Contractor
|
|
36
|
|
|
|
7.8
|
|
No Acceptance
by Payment
|
|
36
|
|
|
|
7.9
|
|
Revenue from
Use of Facility
|
|
37
|
|
|
|
|
|
8.
|
|
CHANGE
ORDERS
|
|
37
|
|
|
|
|
|
|
|
|
8.1
|
|
Changes
|
|
37
|
|
|
|
8.2
|
|
Change
Proposals
|
|
37
|
|
|
|
8.3
|
|
Change
Orders
|
|
38
|
|
|
|
8.4
|
|
Owner Caused
Changes
|
|
38
|
|
|
|
8.5
|
|
Contractor
Proposed Changes
|
|
38
|
|
|
|
|
|
9.
|
|
FORCE
MAJEURE
|
|
38
|
|
|
|
|
|
|
|
|
9.1
|
|
Event of Force
Majeure
|
|
38
|
|
|
|
9.2
|
|
Notice
|
|
39
|
|
|
|
9.3
|
|
Suspension;
Termination Due to Force Majeure
|
|
39
|
ii
|
|
|
|
|
|
|
|
|
10.
|
|
MECHANICAL
COMPLETION; PERFORMANCE TESTING; SUBSTANTIAL COMPLETION; FINAL
COMPLETION
|
|
39
|
|
|
|
|
|
|
|
|
10.1
|
|
Mechanical
Completion Inspection
|
|
39
|
|
|
|
10.2
|
|
Simple Cycle
Mechanical Completion
|
|
39
|
|
|
|
10.3
|
|
Performance
Testing
|
|
40
|
|
|
|
10.4
|
|
Satisfaction of
Performance Testing
|
|
41
|
|
|
|
10.5
|
|
Substantial
Completion Punch List
|
|
41
|
|
|
|
10.6
|
|
Simple Cycle
Substantial Completion
|
|
41
|
|
|
|
10.7
|
|
Combined Cycle
Mechanical Completion
|
|
42
|
|
|
|
10.8
|
|
Combined Cycle
Substantial Completion
|
|
43
|
|
|
|
10.9
|
|
Final
Completion
|
|
44
|
|
|
|
|
|
11.
|
|
OWNER’S
RIGHT TO OPERATE
|
|
45
|
|
|
|
|
|
|
|
|
11.1
|
|
Owner Operation
and Combined Cycle Tie-In Access Date
|
|
45
|
|
|
|
11.2
|
|
Owner’s
Right to Operate Prior to Satisfaction of Performance
Guarantees
|
|
45
|
|
|
|
|
|
12.
|
|
[*]
|
|
46
|
|
|
|
|
|
|
|
|
12.1
|
|
[*]
|
|
46
|
|
|
|
12.2
|
|
[*]
|
|
47
|
|
|
|
12.3
|
|
[*]
|
|
48
|
|
|
|
12.4
|
|
Payment
|
|
48
|
|
|
|
|
|
13.
|
|
WARRANTY
|
|
48
|
|
|
|
|
|
|
|
|
13.1
|
|
Services
Warranty Period
|
|
48
|
|
|
|
13.2
|
|
Equipment
Warranty Period
|
|
49
|
|
|
|
13.3
|
|
Extension of
Warranty Periods
|
|
49
|
|
|
|
13.4
|
|
Defects
|
|
49
|
|
|
|
13.5
|
|
Responsibility
for Warranty Work
|
|
49
|
|
|
|
13.6
|
|
Title
Warranty
|
|
50
|
|
|
|
13.7
|
|
Intellectual
Property Warranty
|
|
50
|
|
|
|
13.8
|
|
Warranty
Assistance
|
|
50
|
|
|
|
13.9
|
|
Conditions of
Warranty
|
|
50
|
|
|
|
13.10
|
|
Exclusive
Warranties
|
|
50
|
|
|
|
|
|
14.
|
|
INDEMNIFICATION
|
|
51
|
|
|
|
|
|
|
|
|
14.1
|
|
Contractor’s Indemnity
|
|
51
|
|
|
|
14.2
|
|
Owner’s
Indemnity
|
|
51
|
|
|
|
14.3
|
|
Intellectual
Property Indemnity
|
|
52
|
|
|
|
14.4
|
|
Indemnity
Procedures for Third Party Claims
|
|
52
|
|
|
|
|
|
15.
|
|
INSURANCE
|
|
53
|
|
|
|
|
|
|
|
|
15.1
|
|
[*]
Builder’s Risk
|
|
53
|
iii
|
|
|
|
|
|
|
|
|
|
|
15.2
|
|
[*]
|
|
54
|
|
|
|
15.3
|
|
Contractor’s and Subcontractor’s
Standard Insurance Requirements
|
|
56
|
|
|
|
15.4
|
|
General
Insurance Requirements
|
|
58
|
|
|
|
15.5
|
|
Insurance
Pricing Assumptions
|
|
59
|
|
|
|
|
|
16.
|
|
PROJECT CREDIT
SUPPORT
|
|
60
|
|
|
|
|
|
|
|
|
16.1
|
|
Financial
Information
|
|
60
|
|
|
|
16.2
|
|
[*]
|
|
60
|
|
|
|
16.3
|
|
[*]
|
|
60
|
|
|
|
|
|
17.
|
|
LIMITATION OF
LIABILITY
|
|
62
|
|
|
|
|
|
|
|
|
17.1
|
|
[*]
|
|
62
|
|
|
|
17.2
|
|
[*]
|
|
62
|
|
|
|
|
|
18.
|
|
LIENS
|
|
63
|
|
|
|
|
|
|
|
|
18.1
|
|
Liens
|
|
63
|
|
|
|
18.2
|
|
Discharge or
Bond
|
|
63
|
|
|
|
|
|
19.
|
|
INTELLECTUAL
PROPERTY
|
|
63
|
|
|
|
|
|
|
|
|
19.1
|
|
Delivery of
Documentation
|
|
63
|
|
|
|
19.2
|
|
Ownership of
Rights in Documentation
|
|
63
|
|
|
|
19.3
|
|
Ownership of
Invention Rights
|
|
63
|
|
|
|
19.4
|
|
Disclosure of
Documentation
|
|
64
|
|
|
|
19.5
|
|
Other
Licenses
|
|
64
|
|
|
|
|
|
20.
|
|
CONFIDENTIAL
INFORMATION
|
|
64
|
|
|
|
|
|
|
|
|
20.1
|
|
Confidentiality
Obligations
|
|
64
|
|
|
|
20.2
|
|
Permitted
Disclosures
|
|
64
|
|
|
|
20.3
|
|
Publicity
|
|
65
|
|
|
|
|
|
21.
|
|
ENVIRONMENTAL;
HAZARDOUS MATERIALS
|
|
65
|
|
|
|
|
|
|
|
|
21.1
|
|
Material Safety
Data Sheets
|
|
65
|
|
|
|
21.2
|
|
Facility Use,
Storage Removal
|
|
65
|
|
|
|
21.3
|
|
Notice of
Presence
|
|
65
|
|
|
|
21.4
|
|
Labeling;
Training
|
|
65
|
|
|
|
21.5
|
|
Handling,
Collection, Removal Transportation and Disposal
|
|
65
|
|
|
|
21.6
|
|
Notice of
Discovery
|
|
66
|
|
|
|
21.7
|
|
Policies and
Procedures
|
|
66
|
|
|
|
21.8
|
|
Asbestos
Containing Products
|
|
66
|
|
|
|
21.9
|
|
Pre-Existing
Hazardous Material
|
|
66
|
iv
|
|
|
|
|
|
|
|
|
22.
|
|
TITLE; RISK OF
LOSS
|
|
67
|
|
|
|
|
|
|
|
|
22.1
|
|
Transfer of
Title; Security Interest
|
|
67
|
|
|
|
22.2
|
|
Risk of
Loss
|
|
67
|
|
|
|
22.3
|
|
Contractor
Tools
|
|
67
|
|
|
|
|
|
23.
|
|
SUSPENSION;
DEFAULT; TERMINATION
|
|
67
|
|
|
|
|
|
|
|
|
23.1
|
|
Suspension
|
|
67
|
|
|
|
23.2
|
|
Contractor
Events of Default
|
|
68
|
|
|
|
23.3
|
|
Owner
Remedies
|
|
69
|
|
|
|
23.4
|
|
Owner Event of
Default
|
|
69
|
|
|
|
23.5
|
|
Contractor
Remedies
|
|
70
|
|
|
|
23.6
|
|
Termination for
Convenience
|
|
70
|
|
|
|
23.7
|
|
Termination for
Force Majeure
|
|
71
|
|
|
|
23.8
|
|
Effect of
Termination
|
|
71
|
|
|
|
|
|
24.
|
|
SAFETY;
INCIDENT REPORTING
|
|
71
|
|
|
|
|
|
|
|
|
24.1
|
|
Environmental,
Health and Safety Programs
|
|
71
|
|
|
|
24.2
|
|
OSHA and Other
Laws
|
|
72
|
|
|
|
24.3
|
|
Worksite
Safety
|
|
72
|
|
|
|
24.4
|
|
Dangerous
Materials
|
|
73
|
|
|
|
24.5
|
|
Loading
|
|
74
|
|
|
|
24.6
|
|
Cooperation in
Governmental Investigation
|
|
74
|
|
|
|
24.7
|
|
Audit
|
|
74
|
|
|
|
|
|
25.
|
|
QUALIFICATIONS
AND PROTECTION OF ASSIGNED PERSONNEL
|
|
74
|
|
|
|
|
|
|
|
|
25.1
|
|
Contractor’s Personnel
|
|
74
|
|
|
|
25.2
|
|
Drug and
Alcohol Testing
|
|
75
|
|
|
|
25.3
|
|
Training of
Employees
|
|
75
|
|
|
|
25.4
|
|
Compliance with
Employment Laws; Policies
|
|
75
|
|
|
|
25.5
|
|
Substitution
|
|
75
|
|
|
|
|
|
26.
|
|
RECORDS AND
AUDIT
|
|
76
|
|
|
|
|
|
|
|
|
26.1
|
|
Technical
Documentation
|
|
76
|
|
|
|
26.2
|
|
Accounting
Records
|
|
76
|
|
|
|
26.3
|
|
Owner’s
Right to Audit
|
|
76
|
|
|
|
26.4
|
|
Sales Tax and
Privilege Tax Records
|
|
76
|
|
|
|
|
|
27.
|
|
TAXES
|
|
77
|
|
|
|
|
|
|
|
|
27.1
|
|
Employment
Taxes
|
|
77
|
|
|
|
27.2
|
|
Sales and Use
Taxes on Contractor Tools
|
|
77
|
|
|
|
27.3
|
|
Sales and Use
Tax on Equipment; Privilege Tax
|
|
77
|
|
|
|
27.4
|
|
State Property
Taxes
|
|
78
|
v
|
|
|
|
|
|
|
|
|
|
|
27.5
|
|
Tax
Indemnification
|
|
79
|
|
|
|
27.6
|
|
Pollution
Control Equipment Information
|
|
79
|
|
|
|
|
|
28.
|
|
DISPUTE
RESOLUTION
|
|
79
|
|
|
|
|
|
|
|
|
28.1
|
|
Resolution by
the Parties
|
|
79
|
|
|
|
28.2
|
|
Arbitration
Proceedings
|
|
79
|
|
|
|
28.3
|
|
Continuation of
Work
|
|
80
|
|
|
|
28.4
|
|
Confidentiality
|
|
80
|
|
|
|
|
|
29.
|
|
MISCELLANEOUS
PROVISIONS
|
|
80
|
|
|
|
|
|
|
|
|
29.1
|
|
Governing
Laws
|
|
80
|
|
|
|
29.2
|
|
Entire
Agreement
|
|
80
|
|
|
|
29.3
|
|
Successors and
Assigns
|
|
81
|
|
|
|
29.4
|
|
No Third Party
Beneficiaries
|
|
81
|
|
|
|
29.5
|
|
Rights
Exclusive
|
|
81
|
|
|
|
29.6
|
|
No
Waiver
|
|
81
|
|
|
|
29.7
|
|
Crisis
Response
|
|
81
|
|
|
|
29.8
|
|
Survival
|
|
82
|
|
|
|
29.9
|
|
Severability
|
|
82
|
|
|
|
29.10
|
|
Notices
|
|
82
|
|
|
|
29.11
|
|
Vienna
Convention
|
|
83
|
|
|
|
29.12
|
|
Counterparts
|
|
83
|
vi
EXHIBITS
|
|
|
Exhibit A
Technical Documentation
|
|
|
|
Exhibit A-1
Specifications, Scope of Work and
Drawings
|
|
|
|
Exhibit A-2 Performance
Test Procedures and Guarantees
|
|
|
|
Exhibit A-3 Schedule of
Drawings (SORVD)
|
|
|
|
Exhibit A-4 Site
Description
|
|
|
|
Exhibit B
Schedule (Including Key Contractor Schedule
Milestones)
|
|
|
|
Exhibit C
[*]
|
|
|
|
Exhibit D
List of Contractor Supplied
Permits
|
|
|
|
Exhibit E
List of Owner Supplied Permits
|
|
|
|
Exhibit F
List of Contractor Key Personnel
|
|
|
|
Exhibit
G
|
|
|
|
Exhibit G-1 List of
Approved Subcontractors
|
|
|
|
Exhibit G-2 List of
Subcontracts under [*]
|
|
|
|
Exhibit H
Credit Support
|
|
|
|
Exhibit H-1
[*]
|
|
|
|
Exhibit H-2
[*]
|
|
|
|
Exhibit I
[*]
|
|
|
|
Attachment 1
[*]
|
|
|
|
Attachment 2
[*]
|
|
|
|
Attachment 3
[*]
|
|
|
|
Attachment 4
[*]
|
|
|
|
Attachment 5
[*]
|
|
|
|
Exhibit J
Contractor’s T&M Rate
Sheet
|
|
|
|
Exhibit K
Owner’s Drug and Alcohol Testing
Policy
|
vii
Duke:
Shaw:
ENGINEERING AND CONSTRUCTION
AGREEMENT
This ENGINEERING AND CONSTRUCTION
AGREEMENT (the “Agreement” ) is entered into as
of the 5th day of May, 2008 (the “Effective
Date” ), between DUKE ENERGY CAROLINAS, LLC, a North
Carolina limited liability company having its principal place of
business in Charlotte, North Carolina ( “Owner”
), and SHAW NORTH CAROLINA, INC., a North Carolina corporation
having its principal place of business in Charlotte, North Carolina
( “Contractor” and, together with Owner,
collectively the “Parties” and individually a
“Party” ).
RECITALS
WHEREAS, Owner has announced its intent to procure,
construct, install and commission a new nominally rated 620 MW
combustion turbine combined cycle electric power plant at the Buck
Generating Facility (the “Facility” ) in Rowan
County, North Carolina, which will consist of (i) two
combustion turbine generators, (ii) two natural circulation,
duct fired, heat recovery steam generators and (iii) one
reheat condensing steam turbine generator (the
“Project” );
WHEREAS , Contractor is engaged in the business of
designing, engineering, constructing and commissioning power
generating facilities; and
WHEREAS , Owner has entered into the Owner Equipment
Contracts for the supply of the Owner Equipment, which is intended
to be installed and commissioned by Contractor;
NOW, THEREFORE
, in consideration of the recitals,
the mutual promises herein and other good and valuable
consideration, the receipt and sufficiency of which the Parties
acknowledge, the Parties, intending to be legally bound, stipulate
and agree as follows:
1. DEFINITIONS
The following capitalized words and
phrases used in this Agreement shall have the following meanings
unless otherwise noted:
“Affiliate” shall mean, with respect to any Person, any
other Person that, directly or indirectly, through one or more
intermediaries, Controls, is Controlled by, or is under common
Control with such first Person at such time, where
“Control” shall mean (a) the possession,
directly or indirectly, of the power to direct or cause the
direction of management and policies of a Person, whether through
the ownership of voting securities, as a trustee or executor, by
contract or credit arrangement, or otherwise, or (b) the
ownership, directly or indirectly, of fifty percent (50%) or
more of the equity interest in a Person.
“Business
Day” shall mean
every Day other than Saturday, Sunday or a legal holiday recognized
by the State.
“[*]”
shall have the meaning set forth in
Section 7.5(a) .
“Change”
shall have the meaning set forth in
Section 8.1 .
1
“Change in Law”
shall mean a change to a Law, or a
change in the binding interpretation or application of a Law after
the Effective Date that results in an increase in [*] for
Contractor to perform the Work, which increase in [*] Contractor
would not have incurred but for this Agreement; provided ,
however , that a “Change in Law” shall not
include any change to a Law that is enacted by any Government
Authority prior to the Effective Date but, by its terms, does not
come into effect until after the Effective Date.
“Change
Order” shall have
the meaning set forth in Section 8.3 .
“[*]”
shall have the meaning set forth in
Section 12.1(b) .
“Combined Cycle
Facility” shall
mean that portion of the Facility that will be “tied
into” the Simple Cycle Facility in order to complete the
Facility, as described in the Specifications.
“Combined Cycle Mechanical
Completion” shall
mean that the Combined Cycle Facility shall have achieved all of
the conditions set forth in Section 10.7 .
“Combined Cycle Substantial
Completion” shall
mean that the Combined Cycle Facility shall have achieved all of
the conditions set forth in Section 10.8 .
“Combined Cycle Substantial
Completion Date” shall mean the date on which Combined Cycle
Substantial Completion actually occurs.
“Combined Cycle
Tie-In” shall mean
the process required to connect the Combined Cycle Facility to the
interface points of the Simple Cycle Facility.
“Combined Cycle Tie-In
Access Date” shall
mean the date upon which Owner makes the Simple Cycle Facility
available to Contractor for the Combined Cycle Tie-In.
“Commissioning”
shall mean, with respect to each of
the Simple Cycle Facility and the Combined Cycle Facility, the
activities required to be conducted by Contractor pursuant to the
terms of this Agreement in order to bring the Simple Cycle Facility
or the Combined Cycle Facility (as applicable) from an inactive
condition, when construction is essentially complete, to a state
where the Simple Cycle Facility or the Combined Cycle Facility (as
applicable) is ready for the commencement of operation, including
pre-commissioning, start-up, individual system and integrated,
functional verification and synchronization of all equipment within
the Simple Cycle Facility or the Combined Cycle Facility (as
applicable).
“Confidential
Information” shall
mean, with respect to any Party, all written, verbal, electronic
and other information and documents such Party provides or makes
available to the other Party relating in any way to this Agreement
which are marked as being “Proprietary” to such Party
at the time of disclosure, or for verbal information reduced to a
writing and marked or designated as being “Proprietary”
to a such Party within seven (7) Days after such verbal
disclosure. “Confidential Information” shall not
include any Documentation or any other information that:
(a) was already known to the other Party at the time it was
disclosed by such Party; (b) was available to the public at
the time it was disclosed by such Party; (c) becomes available
to the public after being disclosed by such Party through no
wrongful act of, or breach of this Agreement by, the other Party;
(d) is received by the other Party without restriction as to
use or disclosure from a third party; or (e) is
2
Duke:
Shaw:
independently developed by the other Party
without benefit of any disclosure of information by such
Party.
[*]
[*]
“Contract Price
” shall mean [*]
“Contractor” shall have the meaning set forth in the first
paragraph above and shall include respective successors and
permitted assigns.
“Contractor
Default” shall have
the meaning set forth in Section 23.2 .
“Contractor
Permits” shall have
the meaning set forth in Section 3.21 .
“ Contractor’s
T&M Rate Sheet ” shall mean Contractor’s
T&M Rate Sheet attached hereto as Exhibit J .
“Contractor’s Project
Manager” shall mean
the Person whom Contractor designates in Exhibit F to issue
and receive communications on Contractor’s behalf under this
Agreement.
“Contractor’s Site
Representative” shall mean the Person whom Contractor designates
in Exhibit F to represent Contractor at the Site.
[*]
“Cost Comparison
Report” shall mean
either, as the context may require:
(a) a report for a specified period
which compares the [*] during such period against the [*] or such
period, including a breakdown of [*]
3
Duke:
Shaw:
(b) a report for a specified period
which compares the [*] such date against the [*],
in each case, together with evidence
reasonably required in order for Owner to [*]
“Day”
shall mean a calendar day, including
Saturdays, Sundays, and holidays.
“Defects”
shall have the meaning set forth in
Section 13.4 .
“[*]”
shall mean the [*] and the
[*].
“[*]”
shall mean:
(a) For Simple Cycle [*] of the
Contract Price;
(b) For Combined Cycle [*] of the
Contract Price; and
(c) For the combined aggregate of
the [*] and [*] of the Contract Price.
“Design
Documents” shall
have the meaning set forth in Section 3.6 .
“Dispute”
shall have the meaning set forth in
Section 28.1 .
“Documentation”
shall mean such materials in printed
or electronic format that are or are to be delivered hereunder or
otherwise agreed by the Parties to be delivered by Contractor to
Owner, including Design Documents, specifications (including the
Specifications), schedules (including the Schedule), schematics,
drawings (including Final Completion “as built”
drawings as specified in Exhibit A-3 ), blueprints,
memoranda, letters, notes, isometrics, computer programs and
software, flow charts, logic diagrams, graphs, studies, system
descriptions, lists, charts, diagrams, standards, criteria,
assumptions, measurements, procedures (including the Testing
Procedure), instructions, reports, test data and results, analyses,
calculations, formulas, computations, plans, empirical and other
correlations, models, manuals (including software manuals and
Facility Manuals) and training materials, that are necessary for
the design, Commissioning, operation, maintenance, modification or
decommissioning of the Facility.
“Effective
Date” shall mean
the date set forth in the first paragraph of this
Agreement.
“Electrical
Output” shall mean
the net electrical power, as measured at the high side of the main
step-up transformer, that is produced by the Simple Cycle Facility
or the Combined Cycle Facility, as the case may be, in kilowatts
(kW) during the Performance Testing, at the test specified
operating conditions, and corrected to the base performance
conditions set forth herein and in Exhibit A-2 .
[*]
4
Duke:
Shaw:
[*]
“[*]
Payments” shall
mean those payments which have been made or that are due and
payable by Owner to Contractor prior to the Effective Date for
those Services as more fully described in the [*].
“Equipment” shall mean any and all material, structure,
buildings, apparatus, equipment, spare parts, hardware, goods,
tools, supplies, and other personal property, all as intended to
become a permanent part of the Facility, that Contractor furnishes,
or is required to furnish, hereunder in accordance with this
Agreement, including the Specifications, or otherwise for the
Facility. “Equipment” includes all of the foregoing
items that Contractor furnishes through a Subcontractor. For the
purposes of this Agreement, “Equipment” shall not
include any Owner Equipment.
“Equipment Warranty
Period” shall have
the meaning set forth in Section 13.2 .
[*]
“Facility”
shall have the meaning set forth in
the Recitals, provided that, as the context may require where the
combustion turbine combined cycle electric power plant described in
the Specifications has not been completed,
“Facility” shall mean only the combustion
turbine simple cycle electric power plant, as described in the
Specifications.
“Facility
Manuals” shall mean
those manuals prepared by or on behalf of Contractor for use by
Owner or its designated Facility operator in connection with the
operation, maintenance of and training on the Facility that conform
to the requirements of Exhibit A-1 .
[*]
“Final
Completion” shall
mean that the Facility shall have achieved all of the conditions
set forth in Section 10.9 .
“Final Completion
Date” shall mean
the date on which Final Completion of the Facility
occurs.
“Final Payment
Invoice” shall have
the meaning set forth in Section 7.6 .
[*]
5
Duke:
Shaw:
“Force Majeure”
shall mean an unforeseeable event or
cause that is beyond the reasonable control of a Party, including
by way of example, but not limited to:
(a) acts of God, war, riots,
insurrection, terrorism, rebellion, floods, hurricanes, tornadoes,
earthquakes, lightning, pandemic, epidemics, and other natural
calamities;
(b) explosions or fires;
(c) strikes, lockouts, or other
labor disputes, but excluding strikes, lockouts or work stoppages
involving only employees of Contractor;
(d) a Change in Law, but only to the
extent such Change in Law delays a Party or increases its cost, as
demonstrated by credible evidence, in its performance of its
obligations under this Agreement;
(e) actions or inactions of any
Government Authority; and
(f) delays in obtaining goods or
services from any Subcontractor caused by the occurrence of any
Force Majeure event;
provided , however , that an event or cause shall
not be an event of Force Majeure unless it: (i) directly
impacts the Work under this Agreement, (ii) is not
attributable to an act or omission of, including a breach of this
Agreement by, such Party, or its employees, officers, agents or
Subcontractors, unless such act or omission is itself a result of
Force Majeure, and (iii) cannot be cured, remedied, avoided,
offset, or otherwise overcome by the prompt exercise of reasonable
diligence by such Party (or any Person over whom such Party has
control). For the avoidance of doubt, “Force Majeure”
shall not include (i) changes in general economic conditions
such as inflation, interest rates or other factors of general
application, and Contractor shall not be entitled to equitable
relief therefor, and (ii) Owner’s inability to meet any
of its payment obligations for whatever reason when due, and Owner
shall not be excused from such obligation.
“Full Notice to
Proceed” shall mean
the written notice that Owner gives to Contractor fully authorizing
Contractor to proceed with the Work hereunder, which is anticipated
to be given no later than [*]
“Government
Authority” shall
mean any federal, state, county, city, local, municipal, foreign or
other government or quasi-governmental authority or any department,
agency, subdivision, court or other tribunal of any of the
foregoing.
“Government
Approvals” shall
mean all permits, licenses, authorizations, consents, decrees,
waivers, privileges and approvals from and filings with any
Government Authority required for or material to the development,
financing, ownership, construction, operation or maintenance of the
Facility in accordance with this Agreement, including the CPCN and
other work permits, environmental permits, licenses and
construction permits.
“Gross
Negligence” shall
mean a conscious and voluntary disregard of the need to use
reasonable care, which is likely to cause foreseeable grave injury
or harm to persons, property or both.
“Guaranteed Combined Cycle
Substantial Completion Date” shall mean the date of [*] (as such date may be
adjusted by Change Order), provided that such date shall be
extended on a
6
Duke:
Shaw:
day- for-day basis to the extent Owner fails to
issue a Full Notice to Proceed on [*] until such Day Owner issues
such Full Notice to Proceed.
“Guaranteed Final
Completion Date” shall mean the date of [*] (as such date may be
adjusted by Change Order), provided that such date shall be
extended on a day-for-day basis to the extent Owner fails to issue
a Full Notice to Proceed on [*] until such Day Owner issues such
Full Notice to Proceed.
“Guaranteed Simple Cycle
Substantial Completion Date” shall mean the date of [*] (as such date may be
adjusted by Change Order), provided that such date shall be
extended on a day-for-day basis to the extent Owner fails to issue
a Full Notice to Proceed on [*] until such Day Owner issues such
Full Notice to Proceed.
“Guarantor” shall mean [*]
“Hazardous
Materials” shall
mean substances defined as “hazardous substances”
pursuant to Section 101(14) Comprehensive Environmental
Response, Compensation and Liability Act of 1980, as amended by the
Superfund Amendments and Reauthorization Act of 1986 (42 U.S.C.
Sections 9601 et seq .); those substances defined as
“hazardous waste” pursuant to Section 1004(5) of
the Resource, Conservation and Recovery Act (42 U.S.C.
Section 6901 et seq .); those substances
designated as a “hazardous substance” pursuant to
Section 311 (b )(2)(A) or as a “toxic pollutant”
pursuant to Section 307(a)(1) of the Clean Water Act (33
U.S.C. Sections 1251 et seq.); those substances defined as
“hazardous materials” pursuant to Section 103 of
the Hazardous Materials Transportation Act (49) U.S.C.
Sections 1801 et seq .); those substances regulated
as a “chemical substance or mixture” or as an
“imminently hazardous chemical substance or mixture”
pursuant to Section 6 or 7 of the Toxic Substances Control Act
(15 U.S.C. Sections 2601 et seq .); those substances
defined as “contaminants” pursuant to Section 1401
of the Safe Drinking Water Act (42 U.S.C. Sections 300f et seq.),
if present in excess of permissible levels; those substances
regulated pursuant to the Oil Pollution Act of 1990 (33 U.S.C.
Sections 2701 et seq .); those substances defined as
a “pesticide” pursuant to Section 2(u) of the
Federal Insecticide, Fungicide, and Rodenticide Act as amended by
the Federal Environmental Pesticide Control Act of 1972 and by the
Federal Pesticide Act of 1978 (7 U.S.C. Sections 136 et
seq .); those substances defined as “toxic
materials” or “harmful physical agents” pursuant
to Section 6 of the Occupational Safety and Health Act (29
U.S.C. Section 651 et seq .); those substances
defined as “hazardous air pollutants” pursuant to
Section 112(a)(6), or “regulated substance”
pursuant to Section 112(a)(2)(B) of the Clean Air Act (42
U.S.C. Sections 7401 et seq .); those substances
defined as “extremely hazardous substances” pursuant to
Section 302(a)(2) of the Emergency Planning &
Community Right-to-Know Act of 1986 (42 U.S.C. Sections 11001
et seq .); and those other hazardous substances,
hazardous wastes, toxic pollutants, hazardous materials, chemical
substances or mixtures, imminently hazardous chemical substances or
mixtures, contaminants, pesticides, by-product materials, toxic
materials, harmful physical agents, air pollutants, regulated
substances, or extremely hazardous substances defined in any
regulations promulgated pursuant to any of the foregoing
environmental Laws, and all other contaminants, toxins, pollutants,
hazardous substances, substances, materials and contaminants,
polluted, toxic and hazardous materials, the use, disposition,
possession or control of which is regulated by one or more
Laws.
“Heat
Rate” shall mean
the test calculated net heat rate in BTU/kW-hr in HHV for the
Simple Cycle Facility or the Combined Cycle Facility, as the case
may be, during the Performance Testing at the
7
Duke:
Shaw:
test specified operating conditions and
corrected to the base performance conditions set forth in
Exhibit A-2 .
[*]
[*]
“Insolvent” shall mean, with respect to either Party, that
such Party becomes insolvent, or fails generally to pay its debts
as they become due, or admits in writing its inability to pay its
debts as they become due, or makes a general assignment for the
benefit of creditors; commences any case, proceeding or other
action seeking reorganization, arrangement, adjustment,
liquidation, dissolution or composition of itself or its debts or
assets, or adopts an arrangement with creditors, under any
bankruptcy, moratorium, rearrangement, insolvency, reorganization
or similar law of the United States or any state thereof for the
relief of creditors or affecting the rights or remedies of
creditors generally.
“Key Contractor Schedule
Milestone” shall
mean a Milestone set forth in Exhibit B that is identified
as a “Key Contractor Schedule Milestone.”
“Laws”
shall mean, at any date of
determination, all statutes, laws, codes, ordinances, orders,
judgments, decrees, injunctions, licenses, rules, permits,
approvals, agreements, and regulations, including all applicable
codes, standards, rules and regulations of the State, in effect on
such date, including all Government Approvals.
“Lien”
shall mean any lien, mortgage,
pledge, encumbrance, charge, security interest, defect in title, or
other claim filed or asserted in connection with the Project by or
through Contractor, a Subcontractor or any other third party under
the control or supervision of Contractor or any Subcontractor
against the Facility, the Site, the Equipment, the Owner Equipment
or any other structure or equipment at the Site.
“[*]”
shall mean the [*] and the
[*].
“Limited Notice to
Proceed” shall mean
a written notice that Owner gives to Contractor authorizing
Contractor to proceed with the Work hereunder in a limited
manner.
“Major
Subcontractor” shall mean any Subcontractor who is engaged by
Contractor: (i) to perform any Services or provide any
Equipment that exceeds or is expected to exceed, in the aggregate
with all prior provision of Services or Equipment by that
Subcontractor, $[*] or (ii) that, although not exceeding $[*]
in the aggregate for Equipment or Services, is performing Services
or providing Equipment that is expressly listed in the table
attached hereto as Exhibit G-2 .
8
Duke:
Shaw:
“Make Right Performance
Guarantees” shall
mean those Performance Guarantees designated as such in Exhibit
A-2 for which the payment of a Performance Liquidated damage as
a remedy shall not be an option for Contractor, which shall include
the Simple Cycle Performance Guarantees and the Permitted Emission
Limits.
“Milestone” shall mean an event or series of events in the
execution of the Work as set forth in Exhibit B .
“Minimum Performance
Guarantees” shall
mean:
(a) with respect to [*] the
achievement by the [*] under the performance conditions set forth
in Exhibit A-2 of (i) a [*] not exceeding [*] of
the applicable Performance Guarantees (or [*]BTU/kW-hr HHV) and
(ii) an [*] not less than [*] of the applicable
Performance Guarantees (or [*]W) (both of which are achieved while
meeting the Permitted Emission Limits); and
(b) with respect to [*], the
achievement by the [*] under the performance conditions set forth
in Exhibit A-2 of (i) a [*] not exceeding [*] of
the applicable Performance Guarantees (or [*]BTU/kW-hr HHV), and
(ii) an [*] not less than [*] of the applicable
Performance Guarantees (or [*]W) (both of which are achieved while
meeting the Permitted Emission Limits).
The Parties recognize and agree that
the above guarantee values shall be [*]
“[*]”
shall have the meaning set forth in
Section 7.5(a) .
“[*] Payment
Invoice” shall have
the meaning set forth in Section 7.2(a) .
“Monthly Progress and Cost
Report” shall mean
the written report Contractor delivers to Owner each month
describing the total amount of progress in the Work achieved during
the prior month, as provided in Section 3.22(a)
.
“OSHA”
shall have the meaning set forth in
Section 24.2 .
“OSHA
Standards” shall
have the meaning set forth in Section 24.2(a)
.
“Owner”
shall have the meaning set forth in
the first paragraph above and shall include its successors and
assigns.
“[*]”
shall mean the [*] including
specifically the following items:
(a) [*] and features from the
[*];
(b) [*];
9
Duke:
Shaw:
(c) [*] from the [*]; and
(d) [*].
“Owner Equipment
Contracts” shall
mean, collectively, the [*] and any other contract executed between
Owner and a third-party supplier of equipment, including the Owner
Equipment, for the Project, as each contract may be updated and
amended from time to time.
“Owner
Permits” shall have
the meaning set forth in Section 4.3 .
“Owner’s Project
Director” shall
mean the Person that Owner designates in writing to issue and
receive communications on Owner’s behalf under this
Agreement.
“Performance
Guarantees” shall
mean:
(a) with respect to the [*], the
achievement by the [*] under the applicable performance conditions
set forth in Exhibit A-2 of (i) a [*] not exceeding [*]
and (ii) an [*] not less than [*] (both of which are achieved
while meeting the Permitted Emission Limits); and
(b) with respect to the [*], the
achievement by the [*] under the applicable performance conditions
set forth in Exhibit A-2 of (i) a [*] not exceeding [*]
and (ii) an [*] not less than [*]kW (both of which are
achieved while meeting the Permitted Emission Limits).
The Parties recognize and agree that
the above guarantee values shall be [*]
“[*]”
shall mean, with respect to Combined
Cycle operations, (a) [*] per each [*] measured as [*] over
the applicable [*] for [*] and (b) [*] per each kW under the
applicable [*] for [*]
“[*]”
shall mean [*] of the Contract
Price.
“Performance
Testing” shall mean
the tests, conducted in accordance with this Agreement, including
the Testing Procedures, by which Contractor demonstrates that the
Facility meets, for Simple Cycle Substantial Completion or Combined
Cycle Substantial Completion, the applicable Minimum Performance
Guarantees, or for Final Completion, the Performance
Guarantees.
“Permitted Emission
Limits” shall mean
those specific emission limits for each regulated pollutant set
forth in the Prevention of Significant Deterioration (PSD)
construction permit issued by the North Carolina Department of
Environment and Natural Resources (NCDENR) Division of Air Quality
authorizing the construction and operation of the Facility and
which specifies the methods of measurement, recordation, and
compliance and which are designated as such and set forth in
Exhibit A-2 .
10
Duke:
Shaw:
“Person” shall mean any individual, company, corporation,
partnership, joint venture, association, joint stock company,
limited liability company, trust, estate, unincorporated
organization, Government Authority or other entity having legal
capacity.
“[*]”
shall mean [*].
[*] shall have the meaning set forth in Section
7.1 .
“[*]”
shall have the meaning set forth in
Section 7.1 .
“Prime Interest
Rate” shall mean,
as of a particular date, the prime rate of interest as published on
that date in The Wall Street Journal , and generally defined
therein as “the base rate on corporate loans posted by at
least 75% of the nation’s 30 largest banks.” If The
Wall Street Journal is not published on a date for which the
interest rate must be determined, the prime interest rate shall be
the prime rate published in The Wall Street Journal on the
nearest-preceding date on which The Wall Street Journal was
published. If The Wall Street Journal discontinues
publishing a prime rate, the prime interest rate shall be the prime
rate announced publicly from time to time by Bank of America, N.A.
or its successor.
“Progress
Meetings” shall
have the meaning set forth in Section 3.22(b)
.
“Project”
shall have the meaning set forth in
the Recitals.
“Prudent Industry
Practice” shall
mean those practices, methods, equipment, specifications and
standards of safety and performance, as the same may change from
time to time, as are commonly used, or are generally accepted, in
construction or operations of electric power generation facilities
similar to the Facility, which in the exercise of reasonable
judgment and in light of the facts known at the time the decision
was made, after due and diligent inquiry, are considered good, safe
and prudent practices in connection with the engineering, design,
construction, commissioning, testing, operation and maintenance of
facilities similar to the Facility with commensurate standards of
safety, performance, dependability, efficiency, and economy, and as
are in accordance with generally accepted standards of professional
care, skill, diligence, and competence applicable to engineering,
design, construction, commissioning, testing, operation,
maintenance and construction practices in the United
States.
“Quality Assurance
Plan” shall have
the meaning as set forth in Section 3.7 .
[*]
[*]
11
Duke:
Shaw:
[*]
[*]
[*]
[*]
“Sales
Tax” shall mean any
current or future sales, use or similar tax imposed on Contractor,
any Subcontractor or Owner with respect to the Work by the State or
any other Government Authority.
“Schedule”
shall mean the critical schedule of
key dates and Milestones, including the Key Contractor Schedule
Milestones, for completion of the Work, as set forth in Exhibit
B , as modified or updated from time to time in accordance with
the terms of this Agreement.
“Scope of
Work” shall mean
all Work on the Project as set forth in Exhibit A-1
.
“Screening
Measures” shall
mean all applicable immigration checks (including compliance with
the Immigration Reform Control Act of 1986 and I-9 requirements),
drug and alcohol tests in compliance with MICCS, a terrorist watch
database search, a social security trace, criminal background
checks (including but not limited to checks for any felony
convictions for the past seven years) and such other screening
measures as a reasonably prudent employer would deem appropriate;
provided that, nothing shall require Contractor to perform
any screening activities that violate the federal Fair Credit
Reporting Act, Title VII of the Civil Rights Act of 1964 or any
other applicable Law.
“Services”
shall mean all labor,
transportation, packaging, storage, designing, drawing,
engineering, demolition, Site preparation, manufacturing,
construction, commissioning, installation, testing, equipping,
verification, training, procurement (whether procurement of
Equipment, Documentation, licenses to intellectual property granted
herein or otherwise) and other work, services and actions
(including pursuant to any warranty obligations) to be performed by
Contractor under this Agreement [*] (whether at the Site or
otherwise) in connection with, or relating to, the Facility (or any
component thereof, including any Equipment and any Owner
Equipment). “Services” includes (a) all of the
foregoing items that Contractor provides through a Subcontractor
and (b) the services that Contractor provides with respect to
Owner Equipment pursuant to Section 3.1(a)(ii)
.
“Services Warranty
Period” shall have
the meaning set forth in Section 13.1 .
“[*]”
shall have the meaning set forth in
Section 12.1(a) .
“Simple Cycle
Facility” shall
mean that portion of the Facility necessary or prudent for the
operation of a combustion turbine simple cycle electric power
plant, as described in the Specifications.
“Simple Cycle Mechanical
Completion” shall
mean that the Simple Cycle Facility shall have achieved all of the
conditions set forth in Section 10.2 .
12
Duke:
Shaw:
“Simple Cycle Substantial
Completion” shall
mean that the Simple Cycle Facility shall have achieved all of the
conditions set forth in Section 10.6 .
“Simple Cycle Substantial
Completion Date” shall mean the date on which Simple Cycle
Substantial Completion actually occurs.
“Site”
shall mean the physical location as
described in Exhibit A-4 upon which Contractor shall
construct the Facility and perform related Work.
“Specifications”
shall mean the Facility
specifications in Exhibit A-1 .
“[*]”
shall have the meaning set forth in
Section 16.3 .
“State”
shall mean the State of North
Carolina.
“Subcontractor”
shall mean a Person, including any
vendor, materialman or supplier, who has a contract (whether
written or oral, a purchase order or otherwise) with Contractor or
a contract with any Person hired by Contractor or with a Person of
any lower tier to Contractor (e.g., a second- or third-tier
subcontractor) to perform any of the Services or to furnish any
Equipment, at the Site or elsewhere.
“Substantial Completion
Punch List” shall
mean the written list of items of Work (which Contractor prepares
and with which Owner agrees prior to Simple Cycle Substantial
Completion or Combined Cycle Substantial Completion (as
applicable)) that remain to be completed by Contractor after Simple
Cycle Substantial Completion or Combined Cycle Substantial
Completion (as applicable) but prior to Final Completion and which
shall not affect the safety, reliability, operability or mechanical
or electrical integrity of the Facility.
“[*] Combined Cycle
Substantial Completion Date” shall mean the date of [*] (as such date may be
adjusted by Change Order), provided that such date shall be
extended on a day-for-day basis to the extent Owner fails to issue
a Full Notice to Proceed on [*] until such Days Owner issues such
Full Notice to Proceed.
“[*] Simple Cycle
Substantial Completion Date” shall mean the date of [*] (as such date may be
adjusted by Change Order), provided that such date shall be
extended on a day-for-day basis to the extent Owner fails to issue
a Full Notice to Proceed on [*] until such Days Owner issues such
Full Notice to Proceed.
[*]
“Taxes”
shall mean all present and future
license, documentation, recording and registration fees, all taxes
(including income, gross receipts, unincorporated business income,
payroll, sales, use, privilege, personal property (tangible and
intangible), real estate, excise and stamp taxes), levies, imports,
duties, assessments, fees (customs or otherwise), charges and
withholdings of any nature whatsoever, and all penalties, fines,
additions to tax, and interest imposed by any Government
Authority.
13
Duke:
Shaw:
“Testing Procedures”
shall mean those procedures prepared
for the Performance Testing by Contractor in accordance with
Exhibit A-2 and reasonably acceptable to Owner.
“Third Party
Claim” shall mean
any claim, demand or cause of action of every kind and character by
any Person other than Owner or Contractor. For the avoidance of
doubt, a claim, demand or cause of action by an employee of Owner
or Contractor (unless made on behalf of Owner or Contractor) shall
be considered a Third Party Claim hereunder.
“Warranty
Period” shall mean,
as the context may require, the Services Warranty Period or the
Equipment Warranty Period, as each may be extended from time to
time with respect to any Service or Equipment as provided in
Section 13.3 .
“Work”
shall mean, as the context may
require, either (a) the Equipment and the Services or
(b) the Equipment or the Services.
2. GENERAL
PROVISIONS
2.1 Intent of Contract
Documents . It is the intent of the Parties that Contractor
provide the Equipment and perform the Services and all of its other
obligations under this Agreement for the Contract Price, [*] which
shall not be increased, except in accordance with Article 7
, Article 8 or as otherwise expressly set forth
herein.
2.2 Independent Contractor .
Contractor shall perform and execute the provisions of this
Agreement as an independent contractor to Owner and shall not in
any respect be deemed or act, or hold itself out, as an agent of
Owner for any purpose or reason whatsoever, except as contemplated
in Section 3.1(a)(ii) .
2.3 Subcontracting; Approved
Subcontractors .
(a) The Parties have agreed upon the
list of approved Subcontractors set forth in Exhibit G-1 for
the Services and Equipment listed in Exhibit G-1 .
Contractor shall have the right to have that portion of the
Services identified in Exhibit G-1 performed by the approved
Subcontractor for such Service, and the right to purchase Equipment
identified in Exhibit G-1 from the approved Subcontractor
for such Equipment. For all Major Subcontractors that are listed in
Exhibit G-1 and for the scope of Services and Equipment that
are listed in Exhibit G-2 , Contractor shall provide Owner
with an opportunity to participate in Contractor’s bid
process, including but not limited to, review of Contractor’s
bid proposals, participation in vendor presentations and meetings,
review of proposed subcontractor’s bid responses, review and
participation in Contractor’s technical and commercial
evaluations of bid responses, and participation in
Contractor’s meetings to discuss bid selection. In addition,
not less than [*] prior to such time as Contractor desires to award
or execute a subcontract with a proposed Major Subcontractor,
Contractor shall provide notice to Owner of such intention. If,
prior to execution of a subcontract with such Major Subcontractor,
Owner desires that Contractor engage an alternative Major
Subcontractor in lieu of the Major Subcontractor that is preferred
by Contractor, Owner shall consult in good faith with Contractor on
the difference in value, if any, between the bid price of the Major
Subcontractor desired by Owner and the Major Subcontractor
preferred by Contractor, plus any additional impacts to Schedule or
warranties attributable to selecting the alternative Major
Subcontractor in lieu of the preferred Major Subcontractor. If
desired by Owner, Contractor shall engage such alternative approved
Major
14
Duke:
Shaw:
Subcontractor but shall be entitled to a Change
Order for the schedule, cost, warranty or other impacts in
selecting the alternative Major Subcontractor.
(b) If Contractor desires to engage
a Subcontractor that is not identified in Exhibit G-1 as an
approved Subcontractor that will be providing Equipment or
Services, then Contractor shall provide Owner with an opportunity
to participate in Contractor’s bid process, including but not
limited to, review of Contractor’s bid proposals,
participation in vendor presentations and meetings, review of
proposed subcontractor’s bid responses, review and
participation in Contractor’s technical and commercial
evaluations of bid responses, and participation in
Contractor’s meetings to discuss bid selection. Before
Contractor enters into any contract with, or otherwise engages,
such Subcontractor to perform such Services, Contractor shall
deliver to Owner for Owner’s review and approval (w) the
name of the Subcontractor that Contractor proposes to use in the
performance of such on-Site Services, (x) a statement in
reasonable detail of the reasons why the proposed Subcontractor is
preferred over any approved Subcontractor, (y) a description
of any impacts to Schedule, warranties, interconnection with other
Equipment or otherwise attributable to selecting the Subcontractor
and (z) the information (and any additional information as
Owner may reasonably request) on which Contractor is basing its
desire to engage such Subcontractor. Owner shall have the right to
reject any such Subcontractor; provided that Owner’s
rejection shall be reasonable and shall occur within ten
(10) Business Days after Contractor submits to Owner all of
the information noted in clauses (w) through
(z) above.
(c) Contractor shall not allow any
Subcontractor that Owner rejects to perform any portion of the
Services. Unless otherwise mutually agreed in writing, no
contractual relationship shall exist between Owner and any
Subcontractor with respect to any of the Services or the Equipment.
Contractor shall be fully responsible for all acts, omissions,
failures and faults of all Subcontractors as fully as if they were
the acts, omissions, failures and faults of Contractor. The
exercise of this right by Contractor to subcontract shall not in
any way increase the costs, expenses or liabilities of
Owner.
2.4 Assignment of
Subcontracts . All subcontracts between Contractor and its
Subcontractors shall be in writing and shall, to the extent
commercially reasonable, contain provisions, which Contractor shall
not waive, release, modify or impair (a) obligating each
Subcontractor that may receive access to any Owner Confidential
Information, to protect such Owner Confidential Information in
accordance with the provisions of this Agreement; (b) as
applicable, sufficient to ensure that Contractor has the right to
grant the intellectual property licenses and assignments that are
granted to Owner herein; and (c) giving Contractor an
unrestricted right to assign the subcontract and all benefits,
interests, rights and causes of action arising under it to Owner,
an Affiliate of Owner or an operator of the Facility, as designated
by Owner. At the request of Owner, Contractor shall provide Owner
with copies of all warranties of each Subcontractor relating to any
of the Work, and Contractor shall comply with any request by Owner
upon the termination of this Agreement pursuant to Article
23 or prior to the expiration of the Warranty Period to assign
the benefit of any Subcontractor warranty to Owner, an Affiliate of
Owner or an operator of the Facility, as designated by Owner;
provided that , unless otherwise agreed, Contractor shall
not be required to assign any rights to claims that Contractor may
have against such Subcontractor at the time of the assignment of
such benefit.
2.5 Interpretation
.
15
Duke:
Shaw:
(a) Headings . The titles and
headings in this Agreement are inserted for convenience only and
shall not be used for the purposes of construing or interpreting
this Agreement.
(b) References . References
to natural persons include Persons. References to
“Articles” and “Sections” are references to
Articles and Sections of this Agreement. References to
“Exhibits” are references to the Exhibits attached to
this Agreement, including all attachments to and documents and
information incorporated therein, and all Exhibits are incorporated
into this Agreement by reference.
(c) Gender . Words importing
one gender include the other gender.
(d) Without Limitation . The
words “include” and “including” are not
words of limitation and shall be deemed to be followed by the words
“without limitation.”
(e) Amendments . All
references in this Agreement to contracts, agreements or other
documents shall be deemed to mean those contracts, agreements or
documents as the same may be modified, supplemented or amended from
time to time.
(f) Industry Meanings . Words
and abbreviations not otherwise defined in this Agreement which
have well-known technical or design, engineering or construction
industry meanings in the United States are used in this Agreement
in accordance with those recognized meanings.
(g) Agreement . Provisions
including the word “agree”, “agreed” or
“agreement” require the agreement to be recorded in
writing.
(h) Written . Provisions
including the word “written” or “in
writing” mean hand-written, type-written, printed or
electronically made and resulting in a permanent record.
(i) Drafting . Neither
Contractor nor Owner shall assert or claim a presumption
disfavoring the other by virtue of the fact that this Agreement was
drafted primarily by legal counsel for the other, and this
Agreement shall be construed as if drafted jointly by Owner and
Contractor and no presumption or burden of proof will arise
favoring or disfavoring any Party by virtue of the authorship of
any of the provisions of this Agreement.
(j) [*]
2.6 Inclusion; Order of
Precedence . This Agreement (excluding the Exhibits) and the
Exhibits shall be considered complementary, and what is required by
one shall be binding as if required by all. The Parties shall
attempt to give effect to all provisions. The failure to list a
requirement specifically in one document, once that requirement is
specifically listed in another, shall not imply the inapplicability
of that requirement, and Contractor shall provide as part of its
obligations hereunder all items required to conform the Work to the
Specifications and the other standards in this Agreement. In the
event of a conflict between this Agreement (excluding the Exhibits)
and the
16
Duke:
Shaw:
Exhibits, this Agreement (excluding the
Exhibits) shall control and the conflicting provisions shall be
interpreted so as to accord with the provisions of this Agreement
(excluding the Exhibits). Notwithstanding the foregoing, conflicts
regarding Scope of Work matters shall be governed by Exhibit
A-1 . Later dated amendments, Exhibits or Change Orders shall
take precedence over earlier dated amendments, Exhibits or Change
Orders.
2.7 Days . If a payment
obligation falls due on a Day other than a Business Day, the
obligation shall be deemed to be due on the next Business
Day.
3. CONTRACTOR
RESPONSIBILITIES
3.1 Performance of the Services;
Commencement of Work .
(a) Performance of the
Services .
(i) Scope of Services for
Work . With respect to all Work, Contractor shall diligently,
duly and properly perform and complete the Services in accordance
with this Agreement; procure, provide and pay for all items (other
than Owner Equipment) and services necessary for the proper
execution and completion of the Services, whether temporary or
permanent and whether or not incorporated or to be incorporated
into the Facility, including all procurement, design and
engineering services (except for such services for the Owner
Equipment), all installation and construction services,
administration, management, training and coordination, all
Commissioning and verification services, and all labor, Equipment,
construction aids, furnishings, equipment, supplies, insurance
(other than Owner insurance), permits (other than Owner Permits),
licenses, inspections, storage and transportation, Facility
Manuals, and all other items, facilities and services necessary to
perform or provide the Work and complete the Facility. Contractor
shall design, construct and install the Equipment on an engineering
and construction basis pursuant to this Agreement, including
providing all necessary civil, structural, mechanical, and
electrical engineering services, all control equipment necessary
for the design, construction and operation of the Equipment, all
interconnections set forth in the Specifications, and all equipment
not specifically described in the Specifications (other than Owner
Equipment) which is customary and necessary to meet the
requirements of the Specifications and the Performance Guarantees.
Work not specifically delineated in this Section or elsewhere shall
be performed and provided by Contractor to the extent customary and
necessary to complete the Facility (other than procurement, supply
and provision of Owner Equipment) in accordance with Prudent
Industry Practices. [*] Contractor shall execute the entire
Services in a manner that will enable Contractor to achieve Simple
Cycle Substantial Completion by the Guaranteed Simple Cycle
Substantial Completion Date, Combined Cycle Substantial Completion
by the Guaranteed Combined Cycle Substantial Completion Date and
Final Completion by the Guaranteed Final Completion
Date.
(ii) Scope of Services Relating
to Owner Equipment . Owner shall be responsible for procuring,
supplying and providing the Owner Equipment by the dates set forth
in the Schedule. The Owner Equipment shall be provided pursuant to
contracts between Owner and the suppliers of such Owner Equipment
(collectively, the “ Owner Equipment Contracts
”). Owner shall provide Contractor with the relevant portions
of the Owner Equipment Contract
17
Duke:
Shaw:
in order for Contractor to perform
its obligations under this Section. With respect to such Owner
Equipment, the Parties hereby agree as follows:
(A) Owner hereby authorizes
Contractor to, and Contractor hereby agrees to, act as
Owner’s agent for the purpose of generally administering the
Owner Equipment Contracts on behalf of Owner and assuring
compliance by Owner and suppliers with the terms thereof.
Contractor shall perform such services in the manner that a
reasonably prudent contractor experienced in the design and
construction of combined cycle electric-generating facilities would
perform if such contractor, instead of Owner, were a party to such
Owner Equipment Contracts. Such agency services shall include but
shall not be limited to reviewing design documents, obtaining
design interface and delivery schedule information, coordinating
and expediting delivery of such Owner Equipment, diligently
asserting Owner’s rights, maintaining appropriate records,
providing to Owner any notices delivered to Contractor by the
supplier of the Owner Equipment, regularly updating Owner with
respect to the status of the performance of the suppliers of the
Owner Equipment, assisting Owner in pursuing available remedies
against the suppliers of the Owner Equipment, including assistance
to Owner in the administration and coordination of warranty claims
for such Owner Equipment and enforcing the repair, replacement or
refurbishment of such Owner Equipment as necessary, consulting with
Owner with respect to any material issues, attending meetings and
otherwise interfacing with the suppliers of the Owner Equipment,
and carrying out the directions of Owner, all as necessary in order
to ensure performance by the respective suppliers under the Owner
Equipment Contracts in accordance with the terms and condition set
forth in such Owner Equipment Contracts. Notwithstanding the
foregoing, Contractor shall have no authority to, and shall not,
take any of the following actions under or with respect to the
Owner Equipment Contracts absent prior direction from
Owner: (1) consent to any change order; (2) agree to
or permit any amendment, modification, or supplement;
(3) waive any of Owner’s rights or the obligations of
the suppliers of the Owner Equipment; (4) increase any of
Owner’s obligations or the rights of the suppliers of the
Owner Equipment; (5) initiate or conduct any litigation or
other similar proceedings; (6) take any action that would
cause a default or breach by Owner of an Owner Equipment Contract;
or (7) agree to or consent to termination or suspension of
work or activities thereunder. Owner shall consult with Contractor
on any performance or schedule concerns before making payments to
the suppliers of the Owner Equipment after the Effective
Date.
(B) In addition to the agency
services set forth in Section 3.1(a)(ii)(A) ,
Contractor shall also provide timely review and response to all
Owner Equipment designs, specifications and drawings, provide all
on-site storage and transportation, provide on-site administration
and coordination and reasonable office space, provide installation
and integration services with respect to the Owner Equipment in
accordance with the Schedule, perform inspections of such Owner
Equipment, perform all installation, commissioning and Performance
Testing for all such Owner Equipment, conduct quality surveillance
and start-up of such Owner Equipment to the extent permitted under
the Owner Equipment Contracts, coordinate training, incorporate
Owner Equipment manuals into the Facility Manual, and provide other
related services reasonably necessary to install and interconnect
such Owner
18
Duke:
Shaw:
Equipment to the Equipment and the
Facility as contemplated by Contractor’s Scope of
Work.
(C) For the avoidance of doubt,
notwithstanding anything to the contrary, Contractor shall have no
liability to Owner for payment of any performance liquidated
damages specified within the Owner Equipment Contracts for any
shortfall in the performance of such Owner Equipment (including
failure to meet performance guarantees) or for the payment of any
delay liquidated damages specified within the Owner Equipment
Contracts for the late delivery of such Owner Equipment. Contractor
shall be entitled to a Change Order granting equitable relief from
any impact on Contractor’s cost or schedule of performance
under this Agreement attributable to a breach by the suppliers of
the Owner Equipment of the terms of the Owner Equipment Contracts,
except to the extent that such breach is caused by Contractor
failing to fulfill its obligations under this Agreement.
(D) Owner and Contractor hereby
acknowledge that the Work is only a portion of the work required
for the completion of the entire Project and that the successful
and timely completion of the Project will require the good faith,
prompt and courteous coordination and collaboration among many
contractors, subcontractors and other Persons, including Owner and
the suppliers of Owner Equipment. Owner and Contractor also
acknowledge that both parties are entering into this Agreement in
material reliance on the agreement by each other to provide such
good faith, prompt and courteous coordination and collaboration and
to perform the Work in accordance with the terms and conditions set
forth herein in order to achieve the successful and timely
completion of the Project.
(b) Work Under Limited Notices to
Proceed . From the Effective Date until such time that Owner
issues a Full Notice to Proceed with respect to the Facility, Owner
shall from time to time issue Limited Notices to Proceed for
Contractor to perform certain portions of the Work with respect to
the Facility as set forth in each such Limited Notice to Proceed.
Such portions of the Work shall be performed for the price and in
the manner set forth in such Limited Notice to Proceed. Each
Limited Notice to Proceed shall expire upon the earlier of
(i) the date set forth in such Limited Notice to Proceed,
(ii) issuance of the Full Notice to Proceed or
(iii) termination of this Agreement in accordance with
Article 23 .
(c) Work After Full Notice to
Proceed . Upon the issuance by Owner of the Full Notice to
Proceed, such notice shall be deemed to be authorization for
Contractor to commence the remainder of the Work relating to the
Facility on the date set forth in such Full Notice to Proceed,
which shall continue until such Work is completed unless this
Agreement is earlier terminated in accordance with Article
23 . The Parties acknowledge that this Agreement sets forth a
specific date for the anticipated delivery of the Full Notice to
Proceed for the Facility. The failure by Owner to issue the Full
Notice to Proceed by the date set forth in this Agreement will
constitute a Change, with respect to which Article 8 shall
apply. Contractor shall perform its obligations under this
Agreement in accordance with the agreed upon Schedule, as such
Schedule may be modified or updated from time to time in accordance
with the terms of this Agreement.
3.2 Professional Standards .
Contractor shall perform and complete the Services and its other
obligations under this Agreement, and all Equipment shall be, in
accordance with all applicable Laws, this Agreement and Prudent
Industry Practices. In the event of any conflict between any of
the
19
Duke:
Shaw:
authorities in the foregoing sentence, all
applicable Laws shall control over the terms of this Agreement and
Prudent Industry Practices, and the terms of this Agreement shall
control over Prudent Industry Practices.
3.3 Sufficient Personnel . At
all times during the term of this Agreement, Contractor shall
employ a sufficient number of qualified Persons, who shall be
licensed if required by applicable Laws, so that Contractor may
complete the Services and Contractor’s other obligations
under this Agreement in an efficient, prompt, economical and
professional manner and in accordance with the Schedule. Without in
any way limiting the foregoing, Contractor shall, for example,
employ a sufficient number of qualified buyers, inspectors, and
expediters necessary to provide all equipment, materials and
supplies to be provided by Contractor hereunder in a timely manner
consistent with the Schedule. Contractor shall provide all
technical services and supervision for Commissioning and
verification. Contractor shall also provide all construction
services and craft personnel as required for system adjustments
during Commissioning and verification. Owner shall provide and pay
for its own operations and maintenance staff during Commissioning
and verification.
3.4 Supervision and
Discipline . Contractor shall supervise, coordinate and direct
the Services using Contractor’s best skill, judgment and
attention. Contractor shall enforce strict discipline and good
order among Contractor’s employees, Subcontractors’
employees and all other Persons carrying out the Services.
Contractor shall at all times take all necessary reasonable
precautions to prevent any unlawful or disorderly conduct by or
among its employees, employees of Subcontractors and other Persons
performing the Services and for the preservation of the peace and
the protection of Persons and property at, or in the immediate
vicinity of, the Site. Contractor shall only permit the employment
of Persons who are fit at the time they are employed and on each
Day they perform the Services, who are skilled in the tasks
assigned to them, and who are qualified to perform the tasks
assigned to them. Contractor shall be responsible for labor peace
on the Site and Contractor shall at all times implement policies
and practices designed to avoid work stoppages, slowdowns, disputes
and strikes where reasonably possible and practical under the
circumstances.
3.5 Contractor’s Key
Personnel . Exhibit F contains a list of
Contractor’s key personnel who shall be responsible for
supervising the performance of Contractor’s obligations under
this Agreement. That list includes the designation of
Contractor’s Project Manager and Contractor’s Site
Representative. Any replacement of the key personnel listed in
Exhibit F shall be subject to the prior written approval of
Owner, which consent Owner shall not unreasonably withhold or
delay. Contractor’s Project Manager shall act as
Contractor’s liaison with Owner and shall have the authority
(a) to administer this Agreement on behalf of Contractor,
(b) to perform the responsibilities of Contractor under this
Agreement, and (c) to bind Contractor as to the day-to-day
project management operations under the Agreement.
Contractor’s Site Representative or other Contractor
supervisory personnel shall be present at the Site at all times
when the Services are being performed at the Site.
3.6 Design and Engineering .
Prior to the Effective Date, Contractor shall have scrutinized, and
satisfied itself as to the adequacy of, the Specifications
(including design criteria and calculations, if any) for completion
of the Facility. Contractor shall be responsible for the design of
the Facility and for the accuracy of the Specifications. Any data
or information received by Contractor, from Owner or otherwise,
shall not relieve Contractor from its responsibility for the design
of the Facility and execution of the Services. Contractor shall
engage all supervisors, engineers, designers, draftsmen and other
Persons necessary for the preparation of all Documentation required
for the Work. In connection with the Documentation, Contractor
shall prepare working drawings and specifications
20
Duke:
Shaw:
setting forth in detail the requirements for the
construction of the Facility in accordance with this Agreement (the
“Design Documents” ). Contractor shall submit
those Design Documents identified in Exhibit A-3 for
Owner’s review, and Owner shall complete its review of, and
provide any comments to Contractor with respect to, the Design
Documents within ten [*] of receiving such Design Documents from
Contractor (and such Design Documents shall be deemed reviewed
without comment if Contractor does not receive any comments from
Owner within such time period). If Owner notifies Contractor that
the Design Documents fail to comply with this Agreement, Contractor
shall correct such Design Documents and shall resubmit them for
Owner’s prompt review within five (5) Business Days in
accordance herewith. Owner shall be entitled, but not obligated, to
review and comment on all other Design Documents not identified in
Exhibit A-3 . Any review by Owner of any Design Documents
pursuant to this Section shall not relieve Contractor from any
obligation or responsibility under this Agreement. If errors,
omissions, ambiguities, inconsistencies, inadequacies or other
defects are found in the Design Documents, they and the Work shall
be corrected as part of the [*] notwithstanding any prior consent
or approval of Owner of any such Design Documents or
Work.
3.7 Quality Assurance Plan .
Contractor shall develop, implement and maintain a written plan for
quality assurance of the Services (the “ Quality Assurance
Plan ”), which shall include: work safety; security at
the Site; fitness for duty; management and control of the design,
engineering, and construction services; management and control of
Subcontractors; and such other matters as Owner may reasonably
request. Such plan shall meet Owner’s corporate and
Site-specific policies and requirements and the requirements of all
applicable Laws. Contractor shall deliver the plan to Owner within
[*] after the Effective Date for Owner’s review and comment,
and Contractor shall thereafter incorporate Owner’s
reasonable comments therein. Following Owner’s review of and
comment to such plan, Contractor shall have the right to rely on
such plan in performing the Services. Contractor shall also require
all Subcontractors to establish, implement and maintain appropriate
quality control and safety programs with respect to their
respective portions of the Services. Contractor shall provide Owner
and its employees, agents, representatives and invitees with
reasonable access to the Work wherever located for observation and
inspection, including but not limited to auditing of all activities
for conformance with the requirements of the plan and all
requirements of the Agreement. Inspections and audits of
Contractor’s Subcontractors will be coordinated with
Contractor.
3.8 Safety Management Plan .
Contractor shall develop, implement and maintain a written safety
management plan that complies with the requirements set forth in
Article 24 . Contractor shall deliver such plan to Owner for
its review and approval (which approval shall not be unreasonably
withheld or delayed) at least [*] prior to the date Contractor
mobilizes to the Site.
3.9 Training . Contractor
shall develop and implement a program to instruct and train
Owner’s personnel adequately in accordance with the
provisions of Exhibit A-1 . Contractor shall deliver to
Owner in accordance with Section 3.15 substantially
complete versions of the Facility Manuals that are sufficient for
training Owner’s maintenance and operating personnel, and
Contractor shall thereafter use the Facility Manuals to train such
Owner personnel. The training, together with the Facility Materials
and the training that any supplier of Owner Equipment is required
to provide, will be sufficient, once provided, to enable Owner to
develop operating procedures compliant with the requirements of
Government Authorities.
3.10 Utility Use . Subject to
Section 4.5 , from the Effective Date until Final
Completion, Contractor shall be responsible in connection with its
scope of Work and as part of the [*]
21
Duke:
Shaw:
to maintain and pay for all temporary
construction utilities required to perform the Services, including
electricity (from the designated Owner tie-in points), fuel (other
than gas fuel used for Commissioning, Performance Testing and
operation), communication systems for Contractor’s temporary
office facilities (including telephones for Owner’s staff),
water (potable and raw), construction waste disposal and wastewater
disposal.
3.11 Spare Parts .
(a) Erection, Start-up and
Commissioning Spare Parts . Owner and Contractor shall consult
in good faith on an ‘open book’ basis to determine the
nature and quantity of spare parts required for installation,
erection, start-up, commissioning and performance testing for the
Equipment for each of the Simple Cycle Facility and the Combined
Cycle Facility, including all gases, gaskets, fuses, instruments,
etc. and other consumable, expendable and engineered items that may
be required during construction, start-up, commissioning or
performance testing of such Equipment. Contractor shall recommend
to Owner for approval the spare parts to be purchased by Contractor
for such installation, erection, start-up and commissioning, with
such Owner approval not to be unreasonably withheld or delayed.
Owner shall own all such spare parts for which it has made payment,
and, prior to Simple Cycle Substantial Completion or Combined Cycle
Substantial Completion (as applicable), Contractor shall provide
Owner with a complete list of all such spare parts (including
manufacturer name and part number and other descriptive
information) that were not used during construction, start-up,
commissioning or performance testing of such Equipment.
(b) Recommended Operation and
Maintenance (O&M) Spare Parts . At least ninety-days Days
prior to Simple Cycle Substantial Completion, Contractor shall
provide a list of spare parts that Contractor (or its
Subcontractors) recommends as necessary for Owner to have on hand
to maintain operability of the Equipment (taking into account the
length of time required to obtain such spare parts) to enable
prompt repair of the Equipment for the Simple Cycle Facility for a
period of [*] following Simple Cycle Substantial Completion and to
enable prompt repair of the Equipment for the Combined Cycle
Facility for a period of [*] following Combined Cycle Substantial
Completion. Summary and detailed information on each spare part
shall be listed by Contractor in a format as reasonably requested
by Owner. Each spare part listed shall include all items for which
the spare part is intended to support. All spare parts shall comply
with the requirements of the Specifications and shall be identical
or equivalent to the original specified, including documentation
identical in kind and format to that required for the original
equipment or material. Pricing, delivery lead times and any
limitations on shelf life shall be included for each spare part.
Owner shall procure such spare parts as it determines in its sole
discretion.
(c) Owner Equipment Spare
Parts . Acting as Owner’s agent pursuant to
Section 3.1(a)(ii)(A) , Contractor shall coordinate,
expedite and manage delivery from each supplier of Owner Equipment
a recommended list of spare parts required for Commissioning and
start-up of such Owner Equipment at such times as shall be
necessary to permit Contractor to remain in compliance with the
Schedule. Owner shall timely acquire, pay and deliver for all such
spare parts. Owner shall make available at no cost to Contractor to
utilize for Owner Equipment during start-up and testing, spare
parts acquired by Owner for the Owner Equipment.
3.12 Subcontractor Presence .
Contractor shall be responsible for notifying and paying any
Subcontractor representative that it deems necessary to be present
for technical assistance at (a) any training session,
(b) erection supervision, (c) Commissioning, or
(d) the Performance Testing. Similarly, Owner, at its cost,
shall ensure that an adequate number of qualified representatives
from
22
Duke:
Shaw:
those suppliers supplying Owner Equipment are
present for technical assistance at the above-listed
events.
3.13 Current Records; Record
Drawings . Contractor shall maintain in good order and make
available to Owner, for inspection at the Site at all times, at
least one record copy of the Documentation marked currently to
record all material changes made during construction. Before, and
as a condition to, Final Completion of the Facility, Contractor
shall deliver to Owner the Documentation, including one set of
reproducible as-built drawings listed in Exhibit A-3 (in
hard copy and electronic formats (non-native files) reasonably
requested by Owner), showing all material changes made during
construction with respect to the Facility.
3.14 Transportation Costs .
Contractor shall arrange and pay for all transportation, storage
and transfer costs incurred in connection with the Work, except for
the transportation and storage costs attributable to Owner
Equipment, which transportation and storage costs shall be paid by
Owner.
3.15 Facility Manuals .
Contractor shall deliver to Owner substantially complete versions
of the Facility Manuals relating to the Simple Cycle Facility no
less than one hundred and twenty (120) Days prior to the
Simple Cycle Substantial Completion Date in accordance with the
requirements of this Agreement, with such first draft containing
sufficient operational and technical information to allow Owner to
develop Simple Cycle Facility operating and maintenance procedures
in order for Contractor to provide operator training. Contractor
shall deliver to Owner substantially complete versions of the
Facility Manuals relating to the entire Facility no less than one
hundred and twenty (120) Days prior to the Combined Cycle
Substantial Completion Date in accordance with the requirements of
this Agreement, with such first draft containing sufficient
operational and technical information to allow Owner to develop
Facility operating and maintenance procedures in order for
Contractor to provide operator training. Contractor shall deliver
to Owner the final version of the Facility Manuals, in hard copy
and electronic format, prior to Final Completion of the
Facility.
3.16 Control of Work .
Contractor shall have care, custody and control over that portion
of the Site at which it performs construction Work and shall be
solely responsible for all construction means, methods, techniques,
sequences, procedures, safety and quality assurance, and quality
control programs in connection with the performance of the
Services. Contractor shall, [*] provide all necessary security at
that portion of the Site under Contractor’s care, custody and
control, including a suitable fence around such portion of the
Site, and the prohibition and prevention of access and entrance to
such portion of the Site by all unnecessary and unauthorized
Persons. Contractor shall strictly control the admission of Persons
to such portion of the Site and no such Person (other than the
employees, officers or directors of the Parties or their
Affiliates) who is not required for the performance or supervision
of the Services shall be admitted without the prior approval of
Owner (such approval not to be unreasonably withheld or delayed).
To the extent any damages to the Site or property thereon,
including the Facility, are covered by Owner’s
Builder’s Risk policy or other property insurance [*]. To the
extent any damages to the Site or property thereon, including the
Facility, are not covered by Owner’s Builder’s Risk
policy or other property insurance and if such damages arise from
theft or vandalism due to Contractor’s or its
Subcontractor’s negligence, then Contractor shall be liable
for such damages up to the amount of the loss incurred, which shall
be included [*]
23
Duke:
Shaw:
[*]
3.17 Emergencies . In the
event of any emergency endangering life or property, Contractor
shall take all actions as may be reasonable and necessary to
prevent, avoid or mitigate injury, damage or loss and shall
promptly report each such emergency, and Contractor’s
responses thereto, to Owner.
3.18 Local Conditions .
Contractor has reviewed the Site and the access to the Site, all as
described in Exhibit A-4 , and acknowledges that they are
sufficient for the performance of the Services. Contractor warrants
that it has taken all steps necessary to ascertain the nature and
location of the Services and that it has investigated and satisfied
itself as to the general and local conditions that can affect the
Facility, the Site or the performance of the Services, including:
(a) conditions bearing on access, egress, transportation,
waste disposal, handling, lay down, parking and storage of
materials; (b) the availability of labor, water, electric
power, other utilities and roads needed for construction;
(c) uncertainties of normal weather or other observable
physical conditions at the Site; and (d) the character of
equipment and facilities needed before and during the performance
of the Services. For the avoidance of doubt, Contractor
acknowledges that Contractor has included reasonable estimates in
the [*] to account for the sub-surface Site conditions identified
within the [*].
3.19 Use of Site; Owner
Access . Contractor shall confine its operations at the Site to
areas permitted by applicable Laws, this Agreement and the Exhibits
hereto. Contractor shall prepare, implement and enforce written
Site rules necessary for the safe, efficient and proper prosecution
of the Work. Those rules shall, at a minimum, comply with Owner
Environmental Health and Safety manual and all applicable Laws.
Contractor shall provide Owner, the suppliers of the Owner
Equipment, and their respective employees, agents, representatives
and invitees with reasonable access to the Work wherever located
for observation and inspection; provided , that Contractor
may provide, and Owner, the suppliers of the Owner Equipment and
shall accept, an escort or other safety measures that Contractor,
in its reasonable discretion, deems necessary or advisable. As a
[*] and as part of the [*] Contractor shall provide Owner and its
Owner Equipment vendors with [*] office spaces on the Site
which shall be outfitted in a customary manner (including a
conference room) as more fully described in Exhibit A-1 .
Those office facilities shall be connected to and serviced by the
usual utilities, subject to Sections 3.10 and 4.5
.
3.20 Compliance with Laws .
Contractor shall comply, and shall cause all Subcontractors to
comply, with all applicable Laws and Change Orders that relate to
Changes in Law relating to the Work or the Facility, and Contractor
shall give all applicable notices with respect to, and in
accordance with, any applicable Laws. Contractor shall ensure that
the Facility, as designed and constructed, complies, and, when
operated in accordance with Prudent Industry Practices, shall
comply with all applicable Laws. Notwithstanding the foregoing, or
anything else in this Agreement to the contrary, Contractor’s
obligation with respect to water, air and other emissions of the
Facility shall be limited to the requirements set forth in the
Specifications. If not otherwise exempted by Title 48 and to the
extent applicable, Contractor will make a good faith effort to
comply with 48 CFR §52.219-8, Utilization of Small, Small
Disadvantaged, and Women-Owned Small Business
24
Duke:
Shaw:
Concerns, and 48 CFR §52.219-9, Small,
Small Disadvantaged, and Women-Owned Small Business Subcontracting
Plan.
3.21 Permits and Approvals .
Contractor shall be responsible for obtaining, renewing and
maintaining all permits, licenses, approvals and certifications
customary and necessary for Contractor to demolish, Site prepare,
engineer, detail, fabricate, furnish, deliver, unload, store,
erect, install, commission (but only those permits exclusively used
for commissioning) and inspect the Work, all as described in
Exhibit D (collectively, the “Contractor
Permits” ). Contractor shall provide reasonable
assistance and documents to Owner in connection with Owner’s
efforts to obtain the Owner Permits. Contractor represents that, to
the best of its knowledge, the Contractor Permits listed in
Exhibit D are the customary permits, approvals and
certifications required to be obtained by Contractor for its
performance of the Services. Upon Contractor’s request, Owner
shall provide Contractor reasonable cooperation and assistance in
obtaining and maintaining Contractor Permits.
3.22 Periodic Reports and
Meetings .
(a) Monthly Progress and Cost
Report . Prior to or concurrently with the delivery of each
Monthly Payment Invoice provided in accordance with
Section 7.2(a) , Contractor shall prepare and submit to
Owner a written status report covering the previous calendar month,
which report shall be prepared in a manner and format (hard copy
and electronic) reasonably acceptable to Owner and shall include
(i) a detailed description of the progress of the Work,
including an up-to-date Work Schedule depicting all critical path
activities and Key Contractor Schedule Milestones and illustrating
the progress which has been made against such activities and Key
Contractor Schedule Milestones, (ii) if the description of the
progress of the Work indicates that the Work does not comply with
the Schedule, a brief description of the steps and actions that
Contractor proposes to take in order to comply with the Schedule,
(iii) a statement of any significant issues which remain
unresolved and Contractor’s recommendations for resolving the
same, (iv) a summary of any significant Facility events which
are scheduled or expected to occur during the following thirty
(30) Days, (v) a Cost Comparison Report for the previous
calendar month and as of the end of such month and (vi) all
additional information reasonably requested by Owner (the
“Monthly Progress and Cost Report” ). Contractor
shall provide copies of such documentation and materials as Owner
may reasonably require to substantiate the amounts claimed by
Contractor in such Cost Comparison Report.
(b) Attendance and Participation
at Meetings . From the Effective Date until the Final
Completion Date, Contractor shall attend and participate in regular
meetings with Owner which shall occur monthly (or upon such other
interval as the Parties agree in writing) for the purpose of
discussing the status of the Work and anticipating and resolving
any problems ( “Progress Meetings” ). The
Progress Meetings may also include, at the request of Owner,
consultants and other Persons. Contractor shall prepare and
promptly deliver to Owner written minutes of each meeting;
provided , that the publication or distribution of such
minutes shall not constitute a permitted basis for providing
notice, or otherwise asserting claims, under this Agreement by any
Party. No implication whatsoever shall be drawn as consequence of a
failure by any Party to comment on or object to any minutes
prepared or distributed by Contractor. Unless otherwise mutually
agreed, Contractor’s Site Representative shall attend all
Progress Meetings after Contractor mobilizes to the Site. In
addition to the above monthly Progress Meetings, Contractor shall
hold regularly scheduled (but not less frequently than weekly
during construction) status or scheduling meetings with its
Subcontractors as appropriate, and Owner shall have the right but
not the obligation to attend and participate in such weekly status
meetings; provided , that, if Contractor determines in its
reasonable discretion that
25
Duke:
Shaw:
Owner’s attendance at the meeting would
prohibit Contractor from effectively addressing confidential or
sensitive issues, Contractor shall have the right to bar Owner from
that portion of such meetings.
3.23 Signage . Neither
Contractor nor its Subcontractors shall display, install, erect or
maintain any advertising or other signage at the Site without
Owner’s prior written approval, other than signs and notices
required by applicable Laws, related safety or work rules, site
identification, or used to solicit employees for the performance of
the Services.
3.24 Interference with
Traffic . Contractor shall carry out the Services so as not to
interfere unnecessarily or improperly with (a) Owner’s
operations at or in the vicinity of the Site, including the
existing Buck coal facility located adjacent to the Site, (after
Owner has assumed custody and control of the Simple Cycle Facility)
or (b) access to, use of or occupation of public or private
roads, footpaths or properties in the possession of Owner or any
other Person. Contractor shall communicate with, and ascertain the
requirements of, all Government Authorities in relation to
vehicular access to and egress from the Site and shall comply with
any such requirements. Contractor shall be deemed to have satisfied
itself as to, and shall be fully responsible for, the routing for
delivery of heavy or large loads to the Site so as to satisfy any
requirements of Government Authorities with respect
thereto.
3.25 Supply of Water and Disposal
of Sewage . Contractor shall provide, within the Site, an
adequate supply of drinking and other water for the use of those
Persons working on the Site. Contractor shall dispose of, either
off-Site or through the Facility’s septic system or other
approved method, all on-Site sewage effluent during performance of
the Services.
3.26 Housekeeping . At all
times during the term of this Agreement, Contractor shall keep the
Site and surrounding area adjacent to where the Services are
actually being performed, free from waste materials, equipment,
rubbish, debris and other garbage, and liquid and non-liquid
materials whether spilled, dropped, discharged, blown out or
leaked. Contractor shall employ adequate dust control measures. To
the extent practicable, Contractor and all Subcontractors shall
utilize reasonable waste reduction and recycling techniques at the
Site. Before the Final Completion Date, Contractor shall remove
from the Site all tools, trailers, surplus and waste materials, and
rubbish, and shall otherwise leave the Facility and the Site in a
neat and clean condition. If Contractor fails to perform such
housekeeping services, Owner, following notice and a reasonable
opportunity for Contractor to cure, may perform such services, and
all reasonable and necessary costs incurred in connection therewith
shall be assessed against the [*].
4. OWNER
RESPONSIBILITIES
Owner shall perform the
responsibilities set forth in this Article at its own expense and
at those reasonable times as may be required by Contractor for the
successful completion of the Work in accordance with the
Schedule.
4.1 Owner’s
Representative . Owner shall appoint Owner’s Project
Director with whom Contractor may consult at all reasonable times,
and whose instructions, requests and decisions shall be binding
upon Owner as to all matters pertaining to this Agreement and the
performance of the Parties under this Agreement; provided ,
that no amendment or modification of this Agreement shall be
effected except by an Amendment, and no Change shall be effected
except as provided in Article 8 .
26
Duke:
Shaw:
4.2 Access . Subject to
Section 11.1 , from the time of the issuance of the
Full Notice to Proceed hereunder until the Combined Cycle
Substantial Completion Date, Owner shall provide Contractor, at no
additional cost to Contractor, unrestricted right of access to such
portion of the Site as Contractor may reasonably require for the
construction of the Facility and for Contractor’s office,
warehouse, shop buildings, welding facilities, Contractor’s
equipment storage, lay down area, and employee parking. After the
Combined Cycle Substantial Completion Date, Owner shall allow
Contractor reasonable access to the applicable portion of the Site
in order to achieve Final Completion.
4.3 Permits . Owner shall be
responsible for obtaining, renewing and maintaining the permits,
licenses, approvals and certifications necessary for the operation,
maintenance, use and ownership of the Facility, including the
permits listed in Exhibit E (collectively, the
“Owner Permits” ). Contractor shall provide
Owner with all reasonably necessary information, documents, data,
criteria and performance characteristics of the Facility requested
or required by Owner to assist Owner in obtaining Owner
Permits.
4.4 Owner Equipment . Owner
shall procure and provide Owner Equipment by the dates set forth in
the Schedule to prevent delay. Except to the extent that the
failure of any Owner Equipment to be provided by the dates set
forth in the Schedule or to perform in accordance with its
manufacturer’s specifications is caused by Contractor’s
failure to perform its obligations in accordance with this
Agreement, any impact to Contractor from the delay (or re-sequence)
in delivery or performance of Owner Equipment shall give rise to a
Change.
4.5 Fuel and Utilities .
Owner shall provide, at no cost to Contractor, the electrical
interconnect for power export from the Facility at the
interconnection points identified in Exhibit A-1 , and all
fuel necessary for Commissioning and Performance Testing when
requested by Contractor and as required in accordance with the
Schedule. Commencing on the Simple Cycle Substantial Completion
Date, [*] for the operation of the Simple Cycle Facility.
Commencing on the Combined Cycle Substantial Completion Date,
[*]
4.6 Operation and Maintenance
Staff . Not less than [*] prior to the [*] Date as set forth in
the Schedule, Owner shall provide, under the direction of
Contractor through Simple Cycle Substantial Completion, at no cost
to Contractor, the complement of qualified operation and
maintenance personnel for applicable Commissioning, Performance
Testing and operation of the Simple Cycle Facility. At the earlier
of: (a) six months prior to the [*] Completion Date as set
forth in the Schedule, or (b) the actual date of Combined
Cycle Mechanical Completion, Owner shall provide, under the
direction of Contractor through Combined Cycle Substantial
Completion, at no cost to Contractor, the complement of qualified
operation and maintenance personnel for applicable Commissioning,
Performance Testing and operation of the Combined Cycle Facility.
In addition, Owner, at its cost, shall ensure that an adequate
number of qualified representatives from those suppliers supplying
Owner Equipment are present at Commissioning or Performance Testing
as necessary for technical assistance.
27
Duke:
Shaw:
4.7 Job Site Rules . From the date on
which Owner provides Contractor access to the Site to perform the
Work until the Simple Cycle Substantial Completion Date and from
the Combined Cycle Tie-In Access Date until the Combined Cycle
Substantial Completion Date, Owner, its representatives and agents
shall abide by all reasonable Site safety rules promulgated by
Contractor.
4.8 Payment . In accordance
with the terms and conditions of this Agreement, Owner shall pay
Contractor the Contract Price. Owner shall make all payments
promptly when due.
5. EQUIPMENT AND
WORKMANSHIP
5.1 Quality of Equipment and
Workmanship . All Equipment and workmanship shall be subject to
such tests as Owner may reasonably require at the place of
manufacture, fabrication or preparation, or at the Site or at such
other place or places as may be mutually agreed upon by the
Parties, including any place of an independent third party.
Contractor shall provide such assistance, labor, electricity,
fuels, stores, apparatus and instruments as are reasonably required
for examining, measuring and testing any Equipment and Owner
Equipment (other than specialty tools as listed in Owner Equipment
Contracts) and workmanship, before incorporation into the
Facility.
5.2 Cost of Tests
.
(a) Subject to the last sentence of
Section 10.4 , the cost of conducting any test related
to the Work shall be [*]
(b) If the results of any such test
indicate that the applicable Equipment or workmanship do not
conform to the requirements of this Agreement (including the
Specifications and Prudent Industry Practices) and Owner has
reasonable grounds to suspect that any other similar Equipment or
workmanship may not conform to the requirements of this Agreement
(including the Specifications and Prudent Industry Practices),
Owner may require Contractor to carry out further tests, which in
the reasonable opinion of Owner are necessary to verify that such
other similar Equipment or workmanship conforms to the requirements
of this Agreement (including the Specifications and Prudent
Industry Practices). The costs of any such tests shall be borne by
[*] and shall be borne by [*]
5.3 Samples . At the
reasonable request of Owner and at Owner’s cost, Contractor
shall supply Owner with samples of Equipment (for which samples can
reasonably be provided). The manufacturer’s standard samples
(with relevant information) and any additional samples shall be
labeled as to origin and intended use in the Facility.
5.4 Inspection of Operations
. Owner (and its representatives) shall at all reasonable times
have access to the Site and to all workshops and places where
Equipment or Owner Equipment is being manufactured, fabricated or
prepared for the Facility. Contractor shall provide Owner a
reasonable opportunity to be present for any tests of any Equipment
or Owner Equipment.
28
Duke:
Shaw:
5.5 Examination of Work before Covering .
For certain agreed parts of the Work as set forth in Exhibit
A-1 , Contractor shall give notice to Owner whenever any such
part of the Equipment or Owner Equipment, as applicable, or
foundations is or are ready or about to be ready for examination
and Owner shall, without unreasonable delay, attend (or inform
Contractor that it is unnecessary for it to attend) for the purpose
of examining and measuring such part of the Equipment or Owner
Equipment, as applicable, or of examining such Work. No part of
such Equipment or Owner Equipment shall be covered up or put out of
view without affording Owner a reasonable opportunity to examine
and measure any such part of the Equipment or Owner
Equipment.
5.6 Uncovering and Making
Openings . If, following discovery of defective workmanship or
materials in any part of the Work, Owner has reasonable grounds to
suspect that further parts of the Work may be similarly defective,
Contractor shall, upon the reasonable request of Owner, provide
Owner clear evidence that such other parts are not defective to the
reasonable satisfaction of Owner or shall uncover such further
parts of the Work or make further openings, in or through the same,
and Contractor shall inspect and repair, if necessary, any such
parts. The costs of such work carried out by Contractor under this
Section shall be part of the [*] unless the parts of the Work so
uncovered turn out to be not defective, in which case Owner shall
bear such costs.
6. SCHEDULE
6.1 Commencement of Work .
Upon receipt of the Limited Notice to Proceed, Contractor shall
commence the performance of the Work described in such Limited
Notice to Proceed, or, if no Limited Notice to Proceed is given,
Contractor shall commence the performance of the Work upon its
receipt of the Full Notice to Proceed, and thereafter continuously
and diligently fulfill its obligations under this Agreement.
Contractor shall perform its obligations under this Agreement in
accordance with the Schedule set forth in Exhibit B , as
such may be modified and updated from time to time in accordance
with the terms of this Agreement.
6.2 Schedule Requirements;
Updates . A true and correct copy of a summary level Schedule,
along with Key Contractor Schedule Milestones, is attached as
Exhibit B . The Parties agree that the Schedule and the Key
Contractor Schedule Milestones within the Schedule reflect dates
for completion of Work activities by Contractor in order to meet
the Targeted Simple Cycle Substantial Completion Date and the
Targeted Combined Cycle Substantial Completion Date. In addition,
Contractor shall prepare and make available to Owner at all times
at the Site, or such other location mutually agreed upon by the
Parties, a current, working copy of the detailed Schedule depicting
all critical path activities and illustrating the progress which
has been made on the Work against the Schedule (in hard copy and
electronic format), including critical path activities
interconnected by schedule logics, for Owner’s review and
comment. Unless otherwise mutually agreed upon by the Parties,
Contractor shall update the working copy of the Schedule monthly
and shall provide a copy to Owner at the Progress Meeting;
provided , however , that no update of or revisions
to the working copy of the Schedule shall be deemed to alter,
revise or otherwise change the date for any Key Contractor Schedule
Milestones, the Guaranteed Simple Cycle Substantial Completion
Date, the Guaranteed Combined Cycle Substantial Completion Date or
the Guaranteed Final Completion Date, all of which shall be amended
only by a duly executed Change Order or amendment
hereto.
6.3 [*]
(a) [*]
29
Duke:
Shaw:
[*]
(b) [*]
(c) [*]
7. CONTRACT PRICE; COMPENSATION
AND PAYMENT
7.1 [*]
(a) [*]
30
Duke:
Shaw:
[*]
(b) Limited Notice to Proceed
Work . Upon receipt of a Limited Notice to Proceed from Owner,
Contractor shall commence the performance of the Services as agreed
in such Limited Notice to Proceed and shall continuously and
diligently perform such Services pursuant to this Agreement as
outlined in such Limited Notice to Proceed until such time as Owner
issues a Full Notice to Proceed. Contractor hereby acknowledges and
agrees that a portion of the Work includes Work performed by
Contractor under the [*], which Work has already been paid by Owner
thereunder and is not included as part of the [*] or
[*].
(c) Full Notice to Proceed
Work . Each Party shall, in good faith, cooperate with the
other and use all commercially reasonable efforts to expeditiously
update, in accordance with the
31
Duke:
Shaw:
[*], the [*] in order to [*] Upon issuance of
the Full Notice to Proceed by Owner, Contractor shall commence the
performance of all Services and shall continuously and diligently
perform all Services and its other obligations under this
Agreement.
(d) [*]
(e) [*]
7.2 Determination of Monthly
Payments of Contract Price .
32
Duke:
Shaw:
(a) [*] Payment
Invoice . [*] shall submit to Owner [*] for payment of the
amount set forth in the Cash Flow Plan for such month and any other
additions or deductions that may have become due, and subject to
any limitations, under this Agreement, including those under
Sections 7.2(b) , 7.3(a) , 7.3(b) and
7.5 . Submittal of each Monthly Payment Invoice shall
constitute a representation by Contractor that (x) Contractor
has performed and completed all Work included in each Cost
Comparison Report previously provided hereunder, (y) [*]
previously provided hereunder have been calculated and determined
in accordance with the requirements of this Agreement, and
(z) the amounts included in such [*] Payment Invoice for the
current month are the correct amounts due and owing to Contactor in
accordance with this Article 7 and [*]
(b) [*]
(c) [*]
33
Duke:
Shaw:
[*]
7.3 [*]
7.4 Deficient Invoices and
Payments .
34
Duke:
Shaw:
(a) If any [*] is deficient,
Contractor shall be required to resubmit that [*] in proper form;
provided , however , that Owner shall pay any portion
of it that is not deficient or subject to dispute. Owner shall
review each [*] and shall endeavor to make exceptions, if any, by
providing Contractor with written notice by the earlier of
(i) such date the Monthly Payment Invoice is paid by Owner or
(ii) [*] Days after Owner receives the [*].
Notwithstanding anything in this Article to the contrary, the
failure of Owner to raise an exception shall not preclude Owner
from subsequently seeking, and Contractor from paying, a refund of
any amounts to which Contractor was not entitled under this
Agreement, and Owner may, by any payment pursuant to
Section 7.2 , make any correction or modification that
should properly be made to any amount previously considered
due.
(b) If Owner provides no exceptions
within such time period, Owner shall pay Contractor, within
[*] Days of its receipt of such [*] and such substantiating
documentation and materials as Owner may have reasonably required,
in U.S. dollars the amounts designated in such [*], plus any
additions and less any deductions which may have become due under
this Agreement, as reflected in such [*]. Any amount of a [*] that
Owner disputes shall be resolved promptly in accordance with
Article 28 . Once the dispute is resolved, Owner or
Contractor, as applicable, shall pay any amount owing promptly
after the date of the final resolution. If for any reason Owner
fails to pay Contractor for all sums due and owing (other than sums
that are the subject of a good faith dispute or permitted to be
withheld pursuant to this Section 7.4(b) ) within
[*] Days after receipt of a substantiated [*] which complies
with the requirements of this Article, interest shall thereafter
accrue on such sums due and owing at the [*] until
paid.
(c) If any Services performed or
Equipment supplied by Contractor for which payment has been made
hereunder is not in accordance with this Agreement, Owner may
withhold from any Monthly Payment Invoice the cost of rectification
or replacement until such rectification or replacement has been
completed, and, if Contractor is failing to perform any Services or
provide any Equipment in accordance with this Agreement and Owner
has so notified Contractor in writing, Owner may withhold from any
Monthly Payment Invoice the estimated value of such Work until it
has been performed or provided in accordance with this
Agreement.
7.5 [*]
(a) [*]
35
Duke:
Shaw:
Contractor in prior [*] and the amount of such
[*] that exceeds the [*] threshold, together with the total
cumulative amounts for all prior Monthly Payment Invoices, will not
cause the Contractor to exceed the total cumulative value of the
Cash Flow Plan through such month, then Owner shall pay such
Monthly Payment Invoice in full. [*]
(b) The Parties acknowledge that
nothing in this Section limits, and the Parties shall not construe
this Section as limiting, Contractor’s ability to accelerate
Key Contractor Schedule Milestones, provided that Owner shall not
be obligated to pay more than the [*] Amount for any given month.
The Parties also acknowledge and agree that nothing in this Section
limits, and the Parties shall not construe this Section as
limiting, Contractor’s ability to update the Schedule, other
than delaying the Key Contractor Schedule Milestones, in accordance
with Section 6.2 .
7.6 Final Payment . Upon
achievement of Final Completion, Contractor shall submit to Owner
an invoice for the final payment and other payments due under this
Agreement (the “Final Payment Invoice” ) which
shall set forth all remaining amounts due to it pursuant to this
Agreement. When submitting the Final Payment Invoice, Contractor
shall submit a written notice, reasonably satisfactory to Owner,
confirming that the total of the applicable Final Payment Invoice
represents full and final settlement of all monies due to
Contractor under this Agreement. If requested by Owner, the Final
Payment Invoice shall also include a waiver (or a bond if a Lien
exists to indemnify Owner against such Lien) of any Liens;
provided , that the waiver or bond may contain a requirement
that Owner pay such Final Payment Invoice. The procedures set forth
in Section 7.2(b) (including application of any late
payment charge) shall be followed for payment of the applicable
Final Payment Invoice, and Owner shall be entitled to offset
against any Monthly Payment Invoice or Final Payment Invoice any
amounts owing by Contractor to Owner under this Agreement,
including any Liquidated Damages owed after application of the cost
sharing provisions in Section 7.3 .
7.7 Certification by
Contractor . In each Monthly Payment Invoice and in the Final
Payment Invoice, Contractor shall certify as follows:
“There are no known Liens (or
such Liens are bonded over) outstanding at the date of this
invoice, all amounts that are due and payable to any third party
(including Subcontractors) with respect to the Work as of the date
of this invoice have been paid or are included in the amount
requested in this invoice, and, except for those bills not paid but
so included and amounts disputed between Owner and Contractor,
there is no known basis for the creation of any Liens, except in
respect to payments to any Subcontractor withheld for proper
reasons in accordance with the contract with such Subcontractor.
Contractor hereby waives and releases, to the extent of the receipt
of payment requested in this invoice, any right to any Lien with
respect to payment for such portion of the Work included in this
invoice.”
7.8 No Acceptance by Payment
. Owner’s payment of any invoice, including a Final Payment
Invoice, does not constitute approval or acceptance of any item or
cost in that invoice nor shall be construed to relieve Contractor
of any of its obligations under this Agreement.
36
Duke:
Shaw:
7.9 Revenue from Use of Facility . Owner
shall be entitled to all revenue derived from or in connection with
operation or use of the Facility before and after each of the
Simple Cycle Substantial Completion Date and the Combined Cycle
Substantial Completion Date.
8. CHANGE ORDERS
8.1 Changes . Without
invalidating this Agreement, Owner may order changes in the
Specifications or the Work consisting of additions, deletions or
other revisions (each, a “Change” ),
provided , that Owner may not delete all Work through this
Article.
8.2 Change Proposals . If
Owner desires to make a Change, it shall submit a written proposal
to Contractor describing the Change requested. Contractor shall
promptly review Owner’s proposal and submit to Owner an
estimate of the cost to develop a Change Order for such Change,
such development costs to be determined [*] the estimated costs to
develop the Change Order are reasonably acceptable to Owner, Owner
shall promptly provide notice thereof to Contractor in writing.
Upon receipt of such notice, Contractor’s Project Manager
shall promptly notify Owner in writing, as soon as practicable,
either by giving reasons why Contractor, either directly or
indirectly through a Subcontractor, could not effect such Change
(if this is the case) or by submitting a proposed Change Order,
which shall include in reasonable detail:
(a) the effect and impact, if any,
that the Change would have, in Contractor’s reasonable
judgment, on the Work, [*] the Schedule, any warranties herein and
the operation or maintenance of the Facility,
(b) Contractor’s proposal for
any necessary modifications to Work, [*] the Schedule or any
warranties herein, and
(c) Contractor’s proposal for
any necessary modifications to any other provisions of this
Agreement, including the Specifications, the Milestones, the Cash
Flow Plan or the Performance Guarantees.
Contractor shall provide Owner such
supporting documentation for the foregoing as Owner may reasonably
request. Notwithstanding the foregoing, Contractor shall not, as a
result thereof, be entitled to any payment hereunder or any
extension of the Schedule if such Change was necessary as a result
of the fault of Contractor, including any breach by Contractor of
this Agreement. For all proposed Change Orders to the scope of Work
which occur after the [*] the Parties agree that the Contractor
shall apply or deduct, as applicable, [*] to implement or remove
such scope of Work, as applicable. Owner shall, as soon as
practicable after receipt of such submittal and supporting
documentation, respond with any comments or questions. Contractor
shall not delay any Work while awaiting a response. If Owner
responds with comments or questions, Contractor shall endeavor to
address such comments or answer such questions as soon as
practicable. If Owner decides not to proceed with a Change, it
shall reimburse Contractor for its efforts in developing the
estimates and other information regarding the potential Change, [*]
(such reimbursement to be either outside the Contract Price or
through
37
Duke:
Shaw:
a separate Change Order); provided , that
Owner shall only be required to reimburse Contractor if Contractor
has complied with the cost proposal requirements set forth
above.
8.3 Change Orders . If Owner
wishes to proceed with the Change, Owner shall issue a written
order to Contractor authorizing the Change and setting forth any
revisions to this Agreement that it deems, in good faith, necessary
or appropriate to effect the Change (the “ Change
Order ”). If Contractor refuses to accept such revisions
in the Change Order, Contractor shall provide Owner written notice
thereof within ten (10) Business Day of its receipt of the
Change Order, describing in reasonable detail its objections to the
Change Order. Owner shall be entitled, despite such notice from
Contractor, to require Contractor to continue to perform its
obligations hereunder as would be modified by the Change Order;
provided, that, if Owner requires Contractor to so perform and
Contractor has provided Owner timely notice objecting to such
Change Order, (x) the Parties shall resolve the Dispute over
the necessary or appropriate revisions in accordance with the
dispute resolution procedures set forth in Article 28 and
(y) if the Change involves additional or disputed Work, Owner
shall continue to pay Contractor pursuant to the payment terms
hereof based, subject to resolution of the Dispute pursuant to
Article 28 (Owner may require any dispute over price to be
resolved pursuant to an “open book” process), on the
[*] Once the Dispute is resolved, any amount owing will be paid
within thirty (30) Days after the date of resolution.
Contractor shall furnish to Owner such receipts or other vouchers
as may be necessary to prove the amounts paid and labor performed
[*] and, before ordering materials, shall submit to Owner
quotations for the same for Owner’s approval (such approval
not to be unreasonably delayed or withheld). Promptly after the end
of each month, Contractor shall deliver to Owner a priced statement
of the labor and materials used during such month associated with
such Change performed on a [*] basis.
8.4 Owner Caused Changes . If
Contractor experiences an increase in costs or a delay in
Contractor’s ability to perform the Work due to Owner or due
to a delay in the delivery of any Owner Equipment or a delay
resulting from a defect in any Owner Equipment or a breach of the
Owner Equipment Contracts by the suppliers of the Owner Equipment,
and such delay or defect is not the result of Contractor’s
failure to comply with the requirements of this Agreement,
Contractor shall be entitled to a Change and an equitable
adjustment in the [*] and/or the Schedule.
8.5 Contractor Proposed
Changes . Contractor shall have the right to request a Change
but shall have no right to require a Change which is not
contemplated by this Agreement without the prior written consent of
Owner; however, nothing herein shall be construed to restrict
Contractor’s right to request an equitable adjustment in the
[*] and Schedule to mitigate impacts caused by events such as, but
not limited to, Force Majeure and Change in Law.
9. FORCE MAJEURE
9.1 Event of Force Majeure .
The performance by Owner or Contractor under this Agreement shall
be excused to the extent that such Party’s performance is
delayed or prevented by reason of an event of Force Majeure. If a
Party is or will be reasonably prevented from performing its
obligations under this Agreement by an event of Force Majeure, such
Party shall use all commercially reasonable efforts to remove the
cause affecting such non-performance and to minimize and mitigate
any delay in or impact upon the performance of this Agreement or
any damage to or other impact upon the Equipment or the Owner
Equipment. If an event of Force Majeure occurs, the Parties shall
[*] to: (a) [*] for a period of time reasonably necessary to
overcome
38
Duke:
Shaw:
the effect of the delay, and (b) the
Contract Price, [*] provided , that Contractor shall [*] on
Change Orders which result from an event of Force
Majeure.
9.2 Notice . If a Party is or
will be reasonably prevented from performing its obligations under
this Agreement by an event of Force Majeure, then it shall notify
the other Party of the obligations, the performance of which is or
will be prevented, and the nature and cause of the event in writing
within [*] after the notifying Party or its Project Manager becomes
aware, through the exercise of reasonable diligence, of the event
of Force Majeure. The Party affected by an event of Force Majeure
shall provide the other Party with weekly updates
(a) estimating its expected duration, the cost of any remedial
action, and the probable impact on the performance of its
obligations hereunder, (b) of the actions taken to remove or
overcome the event of Force Majeure and (c) of the efforts
taken to mitigate or limit damages to the other Party. The Party
affected by an event of Force Majeure shall also provide written
notice to the other Party when it ceases to be so
affected.
9.3 Suspension; Termination Due
to Force Majeure . If any event of Force Majeure claimed by
Contractor delays Contractor’s performance for an aggregate
time period greater than [*] consecutive Days, then Owner, in
its sole and absolute discretion, shall have the right to terminate
this Agreement (or the affected portion of the Work) without
penalty in accordance with Section 23.7 . If any event
of Force Majeure claimed by Owner delays Contractor’s
performance of substantially all of the Work for an aggregate time
period greater than [*] consecutive Days, then Contractor, in
its sole and absolute discretion, shall have the right to suspend
performance and demobilize under this Agreement without penalty in
accordance with Section 23.7 . If any event of Force
Majeure claimed by Owner delays Contractor’s performance of
substantially all of the Work in any [*] time period for an
aggregate time period greater than [*] Days, then Contractor,
in its sole and absolute discretion, shall have the right to
terminate this Agreement without penalty in accordance with
Section 23.7 .
10. MECHANICAL COMPLETION;
PERFORMANCE TESTING; SUBSTANTIAL COMPLETION; FINAL
COMPLETION
10.1 Mechanical Completion
Inspection . At least thirty (30) Days prior to the date
upon which Contractor expects Simple Cycle Mechanical Completion
and Combined Cycle Mechanical Completion, respectively, Contractor
shall notify Owner in writing thereof and shall take necessary
measures to allow a preliminary inspection of the Simple Cycle
Facility or the Combined Cycle Facility (as applicable) to be
conducted by Owner and its representatives. Contractor shall
include with such notice documents and information prudent or
convenient for Owner to determine whether Simple Cycle Mechanical
Completion or Combined Cycle Mechanical Completion, respectively,
is achieved. If Owner notifies Contractor of any deficiencies in
the Work, Contractor shall immediately remedy such deficiencies as
part of the [*] and provide Owner with the relevant documentary
evidence of the correction.
10.2 Simple Cycle Mechanical
Completion . “Simple Cycle Mechanical
Completion” shall be deemed to have occurred upon
satisfaction of all of the following conditions:
(a) All materials, equipment and
systems related to the safe start-up and testing of the Simple
Cycle Facility shall have been constructed and installed in
accordance with this Agreement, including the Specifications and
applicable Laws, and in a manner that does not void any warranties,
and the Equipment and Owner Equipment for the Simple Cycle Facility
shall be mechanically and
39
Duke:
Shaw:
electrically sound, all required pre-operational
testing for the Simple Cycle Facility shall have been
satisfactorily completed, and all systems for the Simple Cycle
Facility shall have been checked for alignment, lubrication,
rotation and hydrostatic and pneumatic pressure
integrity;
(b) All systems and components for
the Simple Cycle Facility shall have been flushed and cleaned out
as necessary, and the Equipment and Owner Equipment for the Simple
Cycle Facility shall be ready to support the commencement of
Performance Testing for the Simple Cycle Facility;
(c) The Parties shall have agreed
upon the Testing Procedures for the Simple Cycle
Facility;
(d) The Equipment and Owner
Equipment for the Simple Cycle Facility shall be capable of being
tested in accordance with Exhibit A-2 without damage thereto
or any other portion of the Facility or to any property or injury
to any Person and in compliance with all applicable Laws and all
permits and licenses required by such Laws;
(e) Contractor shall have provided
the applicable Documentation that is needed to start-up, operate
and maintain the Simple Cycle Facility (including the Facility
Manuals), which Documentation shall have been approved, in the
reasonable determination of Owner, as adequate for the start-up,
operation and maintenance of the Simple Cycle Facility (such
approval not to be unreasonably withheld or delayed);
(f) Contractor shall have provided
the training of Owner’s personnel and representatives as
required by Exhibit A-1 for operation of the Simple Cycle
Facility; and
(g) Contractor shall have delivered
to Owner a certificate signed by Contractor certifying that all of
the preceding conditions in this Section 10.2 have been
satisfied.
Contractor shall not commence
Performance Testing for the Simple Cycle Facility until all of the
above conditions for Simple Cycle Mechanical Completion have been
satisfied and Contractor shall have provided the required prior
notice to Owner of the applicable Performance Testing and given
Owner an opportunity to attend.
10.3 Performance Testing . As
soon as reasonably practicable following each of Simple Cycle
Mechanical Completion and Combined Cycle Mechanical Completion and
after providing Owner at least five (5) Business Days prior
written notice (unless Owner agrees to a shorter notice period or
regulatory requirements necessitate a longer notice period),
Contractor shall commence Performance Testing of the Simple Cycle
Facility or the Combined Cycle Facility, as applicable. Owner and
its agents, representatives and invitees, including any independent
third party inspector and any of its other contractors for the
Project or their respective agents, representatives and invitees,
shall have the right to attend and witness the Performance Testing.
After the completion of each Performance Testing for each of the
Simple Cycle Facility and the Combined Cycle Facility, Contractor
shall determine and submit to Owner, in writing and electronically,
the raw data and completed results of such Performance Testing,
together with a comparison of such results to the applicable
Performance Guarantees and a statement whether such results satisfy
the applicable Performance Guarantees. By submitting such raw data
and completed results, Contractor represents that such raw data,
and the conversion of such raw data into the test results, is
accurate.
40
Duke:
Shaw:
10.4 Satisfaction of Performance Testing
. Within [*] Days after it receives the results for all of the
Performance Testing for each of the Simple Cycle Facility and the
Combined Cycle Facility, including the underlying raw data and
other information required by Section 10.3 , Owner
shall respond in writing to Contractor stating whether
(a) such Performance Testing was performed according to the
Testing Procedures, and (b) the results of such Performance
Testing satisfied the applicable Performance Guarantees, or, if
Owner does not believe that is the case, Owner shall provide its
reasons. Upon its receipt of any such response from Owner that is
not in the affirmative, Contractor shall promptly take whatever
action shall be necessary to cure the defect in such Performance
Testing, adjust or modify any of the Equipment, or require
adjustment or modification of Owner Equipment in accordance with
Section 3.1(a)(ii) , or otherwise in order to satisfy
the applicable Performance Guarantees so noted by Owner and shall
promptly repeat such Performance Testing in accordance with
Section 10.3 and this Section. If, following such
Performance Testing, either: (a) Owner agrees that the
applicable Performance Guarantees have been satisfied and that such
Performance Testing was performed according to the Testing
Procedures, (b) the failure to meet any applicable Performance
Guarantee is attributable to the performance of Owner Equipment
(other than due to Contractor’s failure to fulfill its
obligations set forth in Section 3.1(a) ), or
(c) Owner fails to respond within the time period set forth
above, then the applicable Performance Guarantees shall be deemed
to have been satisfied on the date of completion of such
Performance Testing for the purposes of calculating the applicable
Delay Liquidated Damages. Notwithstanding anything in this Article
to the contrary, no agreement, confirmation, statement or otherwise
of, or the lack thereof from, Owner relating to whether such
Performance Testing was performed according to the Testing
Procedures or whether the results of such Performance Testing
satisfied the applicable Performance Guarantees shall relieve
Contractor of any of its obligations under this Agreement. All
costs that Contractor incurs in satisfying its obligations under
this Article are part of the [*] except that Contractor shall be
reimbursed through a Change Order for additional costs it may incur
due to defects in Owner Equipment that are not the result of
Contractor’s failure to comply with the requirements set
forth in this Agreement or damage to Equipment included in the
Simple Cycle Facility that was not the fault of Contractor or any
Subcontractor, including for any repeat Performance Testing and the
consumables and spare parts associated therewith.
10.5 Substantial Completion Punch
List . Prior to each of Simple Cycle Substantial Completion and
Combined Cycle Substantial Completion, Contractor shall submit to
Owner, for Owner’s review and approval (not to be
unreasonably withheld or delayed), the Substantial Completion Punch
List. Following review and approval of such Substantial Completion
Punch List, Contractor shall work diligently to complete all items
contained thereon in a timely manner in accordance with this
Agreement.
10.6 Simple Cycle Substantial
Completion . “Simple Cycle Substantial
Completion” shall be deemed to have occurred upon
satisfaction of all of the following conditions:
(a) Simple Cycle Mechanical
Completion shall have been achieved;
(b) The Simple Cycle Facility shall
be capable of being operated in accordance with the Specifications
without damage thereto or to any property or injury to any Person
and in compliance with all Owner Permits, Laws and orders of all
Government Authorities then in effect;
(c) Contractor shall have completed
the Performance Testing for the Simple Cycle Facility and the
results of such Performance Testing shall have satisfied the
applicable Minimum
41
Duke:
Shaw:
Performance Guarantees, all according to the
applicable Testing Procedures and the requirements of this
Article 10 ;
(d) Contractor shall have completed
the performance of the Services for the Simple Cycle Facility
according to all of the provisions of this Agreement, with the
exception of those items specified in the Substantial Completion
Punch List, which Contractor shall have prepared and for which
Contractor shall have received approval from Owner (such approval
not to be unreasonably withheld or delayed);
(e) Contractor shall have delivered
to Owner all Documentation for the Simple Cycle Facility that
Contractor is required to deliver to Owner pursuant to Exhibit
A-3 ; and
(f) Contractor shall have delivered
to Owner a certificate signed by Contractor certifying that all of
the preceding conditions in this Section have been
satisfied.
Upon satisfaction of all of the
foregoing conditions for Simple Cycle Substantial Completion, Owner
shall accept the Simple Cycle Facility, subject to Combined Cycle
Substantial Completion and Final Completion according to this
Article 10 , by delivering to Contractor notice of that
acceptance promptly, and Contractor shall turn over risk of loss
and care, custody, control and operation of the Simple Cycle
Facility to Owner. For the purposes of calculating Simple Cycle
Liquidated Damages, the date upon which Contractor submits the
certifying notice required by this Section 10.6 (if
such notice is accurate) shall be deemed the Simple Cycle
Substantial Completion Date.
To the extent that Simple Cycle
Substantial Completion is not achieved by the Guaranteed Simple
Cycle Substantial Completion Date as a result of the improper
performance of any Owner Equipment or any other fault of any
supplier of any Owner Equipment and Contractor has complied with
its obligations relating to such Owner Equipment in accordance with
Section 3.1(a)(ii) , Contractor shall be entitled to a
Change Order providing, in addition to reimbursement of any
increased costs incurred by Contractor, for an equitable extension
to the Guaranteed Simple Cycle Substantial Completion
Date.
10.7 Combined Cycle Mechanical
Completion . “Combined Cycle Mechanical
Completion” shall be deemed to have occurred upon
satisfaction of all of the following conditions:
(a) All materials, equipment and
systems related to the safe start-up and testing of the Facility
shall have been constructed and installed in accordance with this
Agreement, including the Specifications and applicable Laws, and in
a manner that does not void any warranties, and the Equipment and
Owner Equipment for the Combined Cycle Facility shall be
mechanically and electrically sound, all required pre-operational
testing for the Combined Cycle Facility shall have been
satisfactorily completed, and all systems for the Combined Cycle
Facility shall have been checked for alignment, lubrication,
rotation and hydrostatic and pneumatic pressure
integrity;
(b) All systems and components for
the Combined Cycle Facility shall have been flushed and cleaned out
as necessary, and the Equipment and Owner Equipment for the
Combined Cycle Facility shall be ready to support the Combined
Cycle Tie-In and the commencement of Performance Testing for the
Combined Cycle Facility;
(c) The Parties shall have agreed
upon the Testing Procedures for the Combined Cycle
Facility;
42
Duke:
Shaw:
(d) The Equipment and Owner
Equipment for the Combined Cycle Facility shall be capable of being
tested in accordance with Exhibit A-2 without damage thereto
or any other portion of the Facility or to any property or injury
to any Person and in compliance with all applicable Laws and all
permits and licenses required by such Laws;
(e) Contractor shall have provided
the applicable Documentation that is needed to start-up, operate
and maintain the Facility (including the Facility Manuals), which
Documentation shall have been approved, in the reasonable
determination of Owner, as adequate for the start-up, operation and
maintenance of the Facility (such approval not to be unreasonably
withheld or delayed);
(f) Contractor shall have provided
the training of Owner’s personnel and representatives as
required by Exhibit A-1 for operation of the Facility;
and
(g) Contractor shall have delivered
to Owner a certificate signed by Contractor certifying that all of
the preceding conditions in this Section 10.7 have been
satisfied.
Contractor shall not commence
Performance Testing for the Combined Cycle Facility until all of
the above conditions for Combined Cycle Mechanical Completion have
been satisfied and Contractor shall have provided the required
prior notice to Owner of the applicable Performance Testing and
given Owner an opportunity to attend.
If Contractor is unable to satisfy
any of the foregoing conditions as a result of any event or
circumstance for which neither Contractor nor any Subcontractor is
responsible that occurs during the period between the Simple Cycle
Substantial Completion Date and the Combined Cycle Tie-In Access
Date or as a result of the improper performance of any Owner
Equipment or any other fault of any supplier of any Owner
Equipment, and Contractor has complied with its obligations
relating to such Owner Equipment in accordance with
Section 3.1(a)(ii) , Contractor shall be entitled to a
Change Order providing, at Owner’s election, that such
condition is deemed to have been satisfied (but only to the extent
Contractor is unable to satisfy such condition) or for an equitable
adjustment to the Work, the [*] and the Schedule or otherwise as
may be reasonable under the circumstances.
10.8 Combined Cycle Substantial
Completion . “Combined Cycle Substantial
Completion” shall be deemed to have occurred upon
satisfaction of all of the following conditions:
(a) Combined Cycle Mechanical
Completion and Combined Cycle Tie-In shall have been
achieved;
(b) The Combined Cycle Facility
shall be capable of being operated in accordance with the
Specifications without damage thereto or to any property or injury
to any Person and in compliance with all Owner Permits, Laws and
orders of all Government Authorities then in effect;
(c) Contractor shall have performed
Performance Testing for the Combined Cycle Facility and the results
of such Performance Testing shall have satisfied the applicable
Minimum Performance Guarantees, all according to the applicable
Testing Procedures and the requirements of Article 10
;
43
Duke:
Shaw:
(d) Contractor shall have completed
the performance of the Services according to all of the provisions
of this Agreement, with the exception of those items specified in
the Substantial Completion Punch List, which Contractor shall have
prepared and for which Contractor shall have received approval from
Owner (such approval not to be unreasonably withheld or
delayed);
(e) Contractor shall have delivered
to Owner all Documentation that Contractor is required to deliver
to Owner pursuant to Exhibit A-3 ; and
(f) Contractor shall have delivered
to Owner a certificate signed by Contractor certifying that all of
the preceding conditions in this Section have been
satisfied.
Upon satisfaction of all of the
foregoing conditions for Combined Cycle Substantial Completion,
Owner shall accept the Combined Cycle Facility, subject to Final
Completion according to this Article 10 , by delivering to
Contractor notice of that acceptance promptly, and Contractor shall
turn over risk of loss and care, custody, control and operation of
the Combined Cycle Facility to Owner. For the purposes of
calculating Combined Cycle Liquidated Damages, the date upon which
Contractor submits the certifying notice required by this
Section 10.8 (if such notice is accurate) shall be
deemed the Combined Cycle Substantial Completion Date.
If Contractor is unable to satisfy
any of the foregoing conditions as a result of any event or
circumstance for which neither Contractor nor any Subcontractor is
responsible or as a result of the improper performance of any Owner
Equipment or any other fault of any supplier of any Owner Equipment
and Contractor has complied with its obligations relating to such
Owner Equipment in accordance with Section 3.1(a)(ii) ,
Contractor shall be entitled to a Change Order providing, at
Owner’s election, that such condition is deemed to have been
satisfied (but only to the extent Contractor is unable to satisfy
such condition) or for an equitable adjustment to the Work, the [*]
or otherwise as may be reasonable under the
circumstances.
10.9 Final Completion .
“ Final Completion ” shall be deemed to have
occurred upon satisfaction of all of the following
conditions:
(a) Contractor shall have achieved
all conditions for Simple Cycle Substantial Completion and Combined
Cycle Substantial Completion;
(b) Contractor shall have completed
all Performance Testing and either (i) all Performance
Guarantees shall have been satisfied according to the Testing
Procedures, or (ii) Contractor shall have satisfied all of the
Make Right Performance Guarantees and shall have satisfied its
Performance Liquidated Damage obligations as required by
Section 12.2 for those Performance Guarantees that
allow a performance buy-down;
(c) The performance of the Services
(except for Services relating to any warranty Work) shall be one
hundred percent (100%) complete, including the completion (or
buying down) by Contractor of all items on the Substantial
Completion Punch List in accordance with this Agreement;
(d) Contractor shall have delivered
to Owner the Documentation that Contractor is required to deliver
to Owner pursuant to Exhibit A-3 dated as of the Final
Completion Date;
44
Duke:
Shaw:
(e) There shall exist no Contractor
Default and no event which, with the passage of time or the giving
of notice or both, would be a Contractor Default; and
(f) Contractor shall have delivered
to Owner a certificate signed by Contractor certifying that all of
the preceding conditions in this Section have been
satisfied.
11. OWNER’S RIGHT TO
OPERATE
11.1 [*] Upon
the Simple Cycle Substantial Completion Date, Owner shall take
care, custody and control of the Simple Cycle Facility and shall
have the right, in its sole and absolute discretion, to operate the
Simple Cycle Facility without interference from the Work for up to
[*] Days, provided that Owner shall continue to
provide Contractor reasonable access to the Site, in order for
Contractor to complete the Work listed on the Substantial
Completion Punch List and to complete the Work necessary in order
to complete the Combined Cycle portion of the Work. Owner shall
notify Contractor of the Combined Cycle Tie-In Access Date, which
shall occur no later than such [*] Day, at which time
Contractor shall, as expeditiously as reasonably practicable,
effect the Combined Cycle Tie-In. Notwithstanding the foregoing, if
Contractor is not ready to effect the Combined Cycle Tie-In by such
[*] Day, Owner shall have the right to continue to operate
the Simple Cycle Facility until such date as Contractor is, and has
notified Owner that it is, prepared to effect the Combined Cycle
Tie-In. If Owner elects to operate the Simple Cycle Facility
without permitting the Combined Cycle Tie-In for a period in excess
of [*] Days or otherwise notifies Contractor in writing that
it is not ready for Contractor to effect the Combined Cycle Tie-In
by such [*] Day, Contractor shall be entitled to a Change
Order providing for an equitable extension to the Guaranteed
Combined Cycle Substantial Completion Date.
11.2 Owner’s Right to
Operate Prior to Satisfaction of Performance Guarantees . If
the Simple Cycle Facility or the Combined Cycle Facility fails to
satisfy the applicable Performance Guarantees during the applicable
Performance Testing or fails to achieve Simple Cycle Substantial
Completion by the Guaranteed Simple Cycle Substantial Completion
Date or Combined Cycle Substantial Completion by the Guaranteed
Combined Cycle Substantial Completion Date and the Simple Cycle
Facility or the Combined Cycle Facility can be operated in
compliance with applicable Laws, Owner, in its sole discretion,
shall have the right nonetheless to operate the Simple Cycle
Facility or the Combined Cycle Facility and shall give Contractor
written notice of its decision. If Owner elects to operate the
Simple Cycle Facility or the Combined Cycle Facility and, during
such time, does not permit Contractor to cure the Defects necessary
to satisfy the applicable Minimum Performance Guarantees, then the
Guaranteed Simple Cycle Substantial Completion Date, Guaranteed
Combined Cycle Substantial Completion Date and Guaranteed Final
Completion Date (if such dates have not passed) shall be extended
on an equitable basis until such time as Owner tenders the Simple
Cycle Facility or the Combined Cycle Facility to Contractor for
further Services and Performance Testing, and Contractor shall be
entitled to a Change Order for equitable schedule and/or price
adjustment. Owner shall bear the risk of loss during such time as
it operates the Simple Cycle Facility or the Combined Cycle
Facility. Owner’s operation of the Simple Cycle Facility or
the Combined Cycle Facility under this Section shall not reduce
Contractor’s obligations under this Agreement, including
Contractor’s obligation to cause each of the Simple Cycle
Facility and the Combined Cycle Facility to satisfy the
Specifications and applicable Performance Guarantees, except for
normal wear and tear and operation not in accordance with the
Specifications or Prudent Industry Practices. Notwithstanding
anything to the contrary, if Owner elects to operate the Facility
for more than [*] as contemplated in this Section 11.2,
and such election to operate
[*] Redacted type.
45
Duke:
Shaw:
prevents Contractor from proceeding timely with
curing any Defects during such operating time, then the degradation
curves set forth in Exhibit A-2 shall apply.
12. [*]
12.1 [*]
[*] Redacted type.
46
Duke:
Shaw:
[*]
12.2 [*]
[*] Redacted type.
47
Duke:
Shaw:
[*]
12.3 [*]
12.4 Payment . The [*]
specified in Sections 12.1 and 12.2 , if owing
following the application of the provision of
Section 12.3 , shall be due and payable [*]
after written demand by Owner. [*] that remain unpaid after
the expiration of such ten-Day period shall bear interest at the
Prime Interest Rate plus 4% per annum or the highest rate
allowed by applicable Law, whichever is less. Any [*]
disputed by Contractor and determined to be payable pursuant to the
resolution of such dispute in accordance with this Agreement shall
also bear interest from the expiration of the ten-Day period
referred to above at the Prime Interest Rate plus 4% per annum
or the highest rate allowed by applicable Law, whichever is less.
Notwithstanding the assessment of interest, and in addition to its
other rights and remedies, Owner shall have the right to offset the
amount of any [*] plus interest against any amounts due or
that may become due to Contractor under this Agreement. Any amounts
of [*] determined to be wrongfully assessed against
Contractor by Owner shall bear interest, from the time such amounts
were paid by Contractor or offset by Owner, at the Prime Interest
Rate plus 4% per annum or the highest rate allowed by
applicable Law, whichever is less.
13. WARRANTY
13.1 Services Warranty Period
. Contractor warrants that all Services will be performed in a
professional and workmanlike manner, will conform to the
requirements of this Agreement, including the requirements set
forth in Section 3.1(a)(ii) , and will reflect
competent professional knowledge and judgment for a period
commencing on the date such Service was performed and ending
[*] after the Combined Cycle Substantial Completion Date
(the “Services Warranty Period” ), provided that
the Services Warranty Period for each Service performed with
respect to the Substantial Completion Punch List shall commence
upon Contractor’s completion of, and Owner’s acceptance
of, such Service and shall continue for a period of [*]
thereafter or after the Combined Cycle Substantial Completion Date,
whichever is later.
[*] Redacted type.
48
Duke:
Shaw:
13.2 Equipment Warranty Period .
Contractor warrants that the following Equipment furnished to Owner
will be free from Defects in workmanship and material and will
conform to this Agreement, including the Specifications:
(a) for Equipment t