Construction
Agreement
Party
A: Weinan Hi-Tech Zone Meikegaote Goat Milk Product
Ltd.
Party
B: Huangli Town Construction Patrol
Based on the two
parties’ consultation, Party B agrees to undertake the civil
engineering and equipment installation project of Party A’s
Goat Breed Farm.
1
.
Project
information:
(1)
project name:
Weinan Meikegaote Milk Goat Breed Centre
(2)
project location:
Shanxi Province Fuping Town (for specific project address see
appendix)
(3)
project content:
goat barn, warehouse, refrigerating tank, milk station building
construction, hardened ground, ceiling, milking equipment (16
digit), purchase and installation of milk tank, installation of
water, well and circuit, purchase and installation of solar energy,
milk pump, heat exchanger, enclosure and inside fitment. (for
details see the Budget List)
(4)
contract form:
contract for labor and material
2.
Project
term
(1)
Main project: start
on June 20, 2009
(2)
Completion date:
complete on September 20, 2009
3.
Quality standard:
eligible
4.
The parties’
liabilities:
(1)
Party A: take
charge of three supplies and one leveling, shop drawing and
relative technical requirement, make payment in time according to
contract.
(2)
Party B: construct
according to the blueprint and specific requirements of Party
A,