Back to top

CONTRACT FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES

Construction Agreement

CONTRACT FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES | Document Parties: IDACORP INC | IDAHO POWER COMPANY | INDUSTRIAL COMPANY | Kiewit Power Engineers Co You are currently viewing:
This Construction Agreement involves

IDACORP INC | IDAHO POWER COMPANY | INDUSTRIAL COMPANY | Kiewit Power Engineers Co

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: CONTRACT FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES
Governing Law: Idaho     Date: 8/6/2009

CONTRACT FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES, Parties: idacorp inc , idaho power company , industrial company , kiewit power engineers co
50 of the Top 250 law firms use our Products every day

Portions of this exhibit marked "* * *" have been redacted and filed separately with the Securities and Exchange Commission in connection with a request for confidential treatment pursuant to Rule 24b-2 under the Securities Exchange Act of 1934, as amended.

 

Exhibit 10.64

 

CONTRACT

FOR

ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES
BETWEEN

BOISE POWER PARTNERS JOINT VENTURE
CONSISTING OF
KIEWIT POWER ENGINEERS CO.
AND
TIC - THE INDUSTRIAL COMPANY

AND
IDAHO POWER COMPANY
FOR
LANGLEY GULCH POWER PLANT

 

 


CONTRACT
FOR
ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES
BETWEEN
BOISE POWER PARTNERS JOINT VENTURE AND IDAHO POWER COMPANY

TABLE OF CONTENTS

Article 1

RESPONSIBILITIES OF CONTRACTOR

Article 2

RESPONSIBILITIES OF OWNER

Article 3

COMPENSATION

Article 4

PAYMENT TERMS

Article 5

NOTICE TO PROCEED

Article 6

INSPECTION OF THE WORK

Article 7

(Intentionally Deleted)

Article 8

FACILITY TESTS

Article 9

SUBSTANTIAL AND FINAL COMPLETION

Article 10

CHANGES

Article 11

WARRANTIES

Article 12

TITLE

Article 13

DEFAULT

Article 14

TERMINATION

Article 15

SUSPENSION

Article 16

FORCE MAJEURE

Article 17

INSURANCE

Article 18

RISK OF LOSS

Article 19

INDEMNIFICATION

Article 20

INTELLECTUAL PROPERTY INFRINGEMENT

 

 

Article 21

CONFIDENTIAL INFORMATION

Article 22

RIGHTS TO INTELLECTUAL WORK PRODUCT

Article 23

ASSIGNMENT

Article 24

LIENS

Article 25

NOTICES AND COMMUNICATIONS

Article 26

LIMITATIONS OF LIABILITY

Article 27

LIQUIDATED DAMAGES

Article 28

MISCELLANEOUS

Article 29

DISPUTE RESOLUTION

LIST OF EXHIBITS

DEFINITIONS

Exhibit A

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS

Exhibit B

SCHEDULE OF VALUES

Exhibit C

OWNER FURNISHED EQUIPMENT/OWNER’S SCOPE

Exhibit D

FACILITY SITE DATA/GEOTECHNICAL REPORT

Exhibit E

PERFORMANCE GUARANTEES

Exhibit F

CONTRACTOR’S OBLIGATIONS TOWARDS OFE

Exhibit G

PERMITS

Exhibit H

PRE-APPROVED EQUIPMENT SUPPLY SUBCONTRACTORS

Exhibit I

SAFETY MANUAL

Exhibit J

FORM OF CORPORATE GUARANTEE

Exhibit K

PROJECT SCHEDULE

Exhibit L

ENGINEERED EQUIPMENT

Exhibit M

FORM OF NOTICE OF SUBSTANTIAL COMPLETION

Exhibit N

FORM OF NOTICE OF FINAL COMPLETION

Exhibit O

T&M RATE SHEET

Exhibit P

FORM OF PARTIAL LIEN RELEASE

Exhibit Q

FORM OF FINAL LIEN RELEASE

Exhibit R

 

 


CONTRACT FOR
ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES
NEW PLYMOUTH POWER PLANT

THIS CONTRACT (“Contract”) is made and entered into this ______ day of April, 2009, by and between Idaho Power Company, an Idaho corporation with offices located at 1221 West Idaho Street, Boise, Idaho (“Owner”) and Boise Power Partners Joint Venture, a joint venture consisting of Kiewit Power Engineers Co., a Delaware corporation with offices located at 7311 W 132nd St., Suite 300, Overland Park, KS 66213, and TIC-The Industrial Company, a Delaware corporation with offices located at 2211 Elk River Road, Steamboat Springs, CO 80487 (“Contractor”), for the design, engineering, procurement and construction services, as more fully described herein.

RECITALS

WHEREAS, Owner wishes to have Contractor furnish certain engineering, procurement, construction management and construction services related to the Project, as more fully described in this Contract; and

WHEREAS, Owner desires to furnish certain plant equipment, interconnects, the Facility Site, and other items related to the Project, as more fully described in this Contract; and

WHEREAS, Contractor desires to engineer, procure materials, manage construction, construct and start up the Project, as more fully described in this Contract.

NOW THEREFORE, in consideration of the mutual covenants and agreements herein contained and other good and valuable consideration, the receipt of which is hereby acknowledged, and intending to be legally bound, the Parties hereto agree as follows:

ARTICLE 1 – RESPONSIBILITIES OF CONTRACTOR

1.1                 Performance of the Work. Contractor shall furnish or cause to be furnished all Work in accordance with the terms and conditions of this Contract, and in compliance with all Governmental Approvals and Governmental Rules applicable to the prosecution of the Work. Contractor shall design, install, and test Project systems in a safe manner, using qualified, competent and, where necessary, licensed personnel.

1.2 Design and Engineering. Contractor shall furnish detailed design and engineering of the Work including appropriate specification of equipment, materials and systems to be incorporated into the Work. Engineering shall be based on the preliminary engineering, design criteria, and other information contained in Exhibit B . Contractor’s engineering services shall include the preparation of drawings, specifications, schedules, calculations, documents, and estimates, and coordination with the engineering efforts of Subcontractors.

1.3 Procurement. Contractor shall procure and make payments for Engineered Equipment, materials, equipment, supplies, and services to be included in the Work by Subcontractors. Contractor shall also perform such inspection, expediting, quality surveillance, and traffic services as Contractor deems necessary in connection with such procurement.

 

1.4 Construction . Contractor shall perform services to construct the Work, including installation of OFE, furnishing management, labor, equipment, tools, and temporary facilities necessary for such construction. Contractor shall handle and warehouse materials, supplies and equipment required for such construction and materials, supplies and equipment supplied by Owner and used by Contractor and Subcontractors.

 

1.5                 Start-Up, Testing, and Initial Operation. Contractor shall perform the start-up, testing and initial operation as described in Exhibit B . Contractor shall conduct the Performance Tests as described in Exhibit F . Contractor shall provide first fill of all lubricants.

 

1.6       Spare Parts. Contractor shall have the right to use Owner’s operating spare parts on a “use and replace” basis. Contractor shall promptly replace at its expense any such spare parts Contractor uses from Owner’s inventory. Operating spare parts for OFE that are used by Contractor will be provided at Owner’s expense and not replaced by Contractor; provided, if Contractor must use a spare part for OFE because of negligence by Contractor, then Contractor may use such spare part, but must replace it.

 

1.7       Securing Governmental Approvals. Contractor shall secure those Governmental Approvals that are listed in Exhibit H as Contractor’s responsibility. Contractor shall on a timely basis provide all customary and reasonably necessary support to Owner in connection with Owner’s securing of Governmental Approvals under Section 2.5 and that are listed in Exhibit H as Owner’s responsibility.

 

1.8                 Compliance with Governmental Approvals. Contractor shall design and construct the Work so that, if properly operated and maintained, and if Owner meets its obligations under the Contract, the Work will be in compliance with the technical requirements of all applicable Governmental Approvals.

 

1.9       Independent Contractor. Except as may be expressly set forth herein to the contrary, Contractor is an independent contractor and nothing contained herein shall be construed as constituting any relationship with Owner other than that of Owner and independent contractor, nor shall it be construed as creating any relationship whatsoever between Owner or Owner’s Representative and Contractor’s employees. Except as expressly limited in this Contract, Contractor shall be entitled to exercise the right to hire, discharge, promote and transfer its employees; to select and remove foreman or other persons at other levels of supervision; to establish and enforce reasonable standards of production; to introduce, to the extent feasible, labor saving equipment and materials; to determine the number of craftsmen necessary to perform a task; and to establish, maintain, and enforce rules and regulations conducive to efficient and productive operations. Notwithstanding anything to the contrary herein, Owner reserves the right to prohibit such person(s) as it deems advisable from entering onto the Facility Site without liability to Contractor after notifying Contractor of the person(s) prohibited and the reasons therefore, provided however that any such decision by Owner shall entitle Contractor to an equitable adjustment to the Contract Price and/or Project Schedule pursuant to a Change.

 

1.10 Responsibility for Subcontractors and Agents. Contractor may subcontract portions of the Work to any Person without further approval by Owner. Notwithstanding any agreement with any Subcontractor(s), Contractor shall be solely responsible for the Work, and has complete and sole responsibility as a principal for its agents and all others it hires to perform or assist in performing the Work. However, Contractor will select from pre-approved first tier equipment supply Subcontractors as identified in Exhibit I . Equipment supply Subcontractors that are not on this list and which have a contract value greater than *** shall be submitted to Owner for approval, which shall not be unreasonably withheld.

 

 


1.11        Progress Reports. Contractor shall submit to the Owner monthly reports describing the status of the Work in reasonable detail, which shall include information showing actual progress against the Project Schedule. Contractor shall provide a budget update with each monthly report showing total amount expended and billed to date and remaining contract dollars.

 

1.12        Publicity. Contractor shall obtain Owner’s prior written approval of the text of any external announcement, publication, or other type of public communication concerning the Work or the Facility prior to the release of the same by Contractor. Contractor shall provide that a similar obligation is placed on Subcontractors.

 

1.13        Safety. Contractor shall implement and administer for the Project, a safety and health program subject to approval of Owner, and attached hereto as Exhibit J , including development of a safety manual for the Project establishing Contractor and Subcontractor safety guidelines and requirements. During performance of the Work, Contractor shall take reasonable precautions for the safety of persons. Contractor shall require Subcontractors working on the Facility Site to adhere to the safety and health program established for the Project. Owner shall require its employees and subcontractors working on the Facility Site to adhere to the safety and health program established for the Project, as well as any applicable OSHA requirements.

 

1.14        Site Security. Contractor shall be responsible for the security of the Work and the Facility Site after mobilization of Contractor’s forces at the Facility Site during such times that Contractor’s forces are physically present on the Facility Site, except as excused by a Force Maj eure event.

 

1.15        Contractor Representative. Contractor shall designate and identify by Notice to Owner its Project Manager, who shall act as Owner’s primary point of contact with Contractor with respect to the prosecution of the Work.

 

1.16        Corporate Guarantees. No later than thirty (30) Business Days after the date of execution of this

Contract, Contractor shall deliver to Owner, in a form attached hereto as Exhibit K , corporate guarantee from Kiewit Energy & Power Inc. guaranteeing the performance of Contractor.

 

1.17              OFE. Contractor shall act as an agent to administer the Siemens subcontract pursuant to Exhibit G .

 

ARTICLE 2 – RESPONSIBILITIES OF OWNER

 

2.1                 Owner Furnished Equipment. Owner shall furnish, at its expense, OFE, including the Siemens SGT-6-PAC5000F combustion turbine generator (“CTG”) and the SST-700HP – 900RH steam turbine generator (“STG”), which shall be delivered undamaged to the Facility Site or to the designated rail siding at the time specified in the Project Schedule, and shall be in compliance with the requirements of Exhibit D of this Contract and shall be free from defects and deficiencies. All OFE shall be in a condition which does not increase Contractor’s cost or delay the progress of the Work. Any increase in Contractor’s cost or time of performance due to a failure to comply with this Section 2.1 , including the timely delivery of the OFE, shall be treated as an event entitling Contractor to an equitable adjustment under Article 10 below. Owner shall retain payment obligations for OFE contracts, subcontracts or other items assigned by Owner to Contractor, if any; however, payments are not to be released without first providing Contractor prior notice and an opportunity to comment.

 

2.2       Cooperation with Contractor. Owner shall cooperate with Contractor during the performance of this Contract. Such cooperation shall include timely supply of all those items, personnel, services, and information required to be supplied by Owner under this Contract, including but not limited to the OFE; no material interference with Contractor’s agents, employees, or Subcontractors; and timely administration of all of Owner’s obligations under this Contract.

 

2.3                 General Responsibilities. Owner shall furnish the following with respect to the Project:

 

a) provide a Facility Site of sufficient size, free of Hazardous Wastes or Materials, including necessary easements, staging areas, and unrestricted access;

 

b) provide environmental remediation of the Facility Site, if required, except for any environmental remediation required due to the acts or omission of Contractor or any Subcontractor;

 

c) furnish available geological and other Facility Site data, including identification of any preexisting underground facilities, on which Contractor shall be entitled to rely, which shall be set forth in Exhibit E ;

 

d) Site Utilities / Consumables including Fuel:

 

i)     Construction Utilities / Consumables - Owner will provide adequate water for the Project in accordance with required specifications including related coordination with the applicable utilities. Construction power (including start-up, testing and commissioning) and related coordination with the local utilities is by Owner.

 

ii)   Start-up, Testing and Commissioning Utilities / Consumables - Owner will provide all fuel, reagents, consumables, lubricants (except first fill of lubricants by Contractor), chemicals, electrical power including back-feed, water, sanitary and firewater at required specifications, through start-up, testing and through to Final Completion.

 

e) Owner will provide start-up and operational spare parts in time to support start-up, testing and commissioning of the Project. Contractor shall be allowed to utilize these spares as needed pursuant to Section 1.6 above;

 

f) Owner will provide all necessary permits, licenses and other Governmental Approvals excluding those listed as Contractor’s responsibility pursuant to Exhibit H . Any development, start-up, operation, building, use, and environmental type Governmental Approvals not listed on Exhibit H shall be supplied by Owner;

 

g) Owner will coordinate and pay for any activities of the Owner Engineer, if any, and other required costs for development purposes;

 

h) Owner will coordinate and pay for all utility and interconnection related system studies and interface requirements and will provide available service utility and other interface data on which Contractor shall be entitled to rely and which shall be set forth in Exhibit E;

 

i) All interconnects, backfeed power, natural gas, water, construction power, chemicals, Owner- furnished Governmental Approvals, Owner-furnished spare parts, technical assistants, operators

and other Owner obligations shall be supplied by Owner in quantities and qualities as required, no later than dates indicated on the Project Schedule;

 

j)                 Owner will furnish any required demineralized water production mobile treatment system per the Project Schedule to support the start-up and commissioning activities of the Project;

 

k)               Owner will provide any shop equipment, tools, office furniture, and laboratory facilities necessary for operation of the Project;

 

l)                 Owner will arrange for disposal or sale of energy generated by the Project during commissioning and any Performance Test;

 

m)             Owner will provide other items as specifically detailed in Exhibit D as Owner’s obligations, or as otherwise specified in the Contract; and

 

n)               All OFE and Owner specified equipment of standard production configuration and proven technology.

 

2.4       Owner’s Representative. Owner shall designate and identify by Notice to Contractor its Owner’s representative, who shall act as Contractor’s primary point of contact with Owner with respect to the prosecution of the Work.

 

2.5                 Operations Personnel. After Notice from Contractor, Owner shall, within fifteen (15) days prior to commencement of the Performance Tests, provide qualified, competent, and, where necessary, licensed operations and maintenance personnel for testing, start-up and initial operation of the Facility. Owner shall provide that such personnel perform the duties to which they are assigned in accordance with generally accepted practices and standards of the industry. Owner shall supply, or cause to be supplied, sufficient small tools to facilitate on-the-job training of the operations and maintenance personnel. Owner shall be responsible for the negligent acts or omissions and willful misconduct of its operating and maintenance personnel.

 

ARTICLE 3 – COMPENSATION

 

3.1                 Contract Price. Owner shall pay Contractor the Contract Price, which shall be paid in accordance with Sections 4.1 and 4.2 , subject to increases or decreases only as specified in Changes approved in accordance with Article 10, or as set forth in Section 3.5 below.

 

3.2       Other Compensation. In addition, Owner shall pay to Contractor: (i) certain costs of termination

of this Contract in accordance with Article 14 ; (ii) reimbursement for certain costs of Changes pursuant to Article 10 ; (iii) interest on late payment as set forth in Section 4.3 ; and (iv) the ongoing suspension costs set forth in Section 15.4 .

 

3.3       Purchase of Surplus Materials. Subject to mutually agreeable terms, Owner shall have the option to purchase any or all surplus construction materials and any supplies remaining on the Facility Site at Substantial Completion.

 

 


3.4       Taxes. Contractor shall pay: (i) all payroll and other related employment compensation taxes for Contractor’s employees; (ii) all sales, use, and property taxes applicable to the Contractor’s ownership, purchase or use of small tools, consumables, expendables, and construction equipment required to perform the Work, (iii) all sales, use, gross receipts and excise taxes imposed on the Contractor’s purchase, sale, use or storage of equipment, materials, and any other items procured by Contractor for purposes of installation into, affixation or attachment to, or incorporation into the Facility to be constructed for Owner or to otherwise be provided by Contractor to Owner pursuant to this Contract unless Owner has provided written instructions to Contractor identifying specific items eligible for exemption from Idaho sales and use taxes; and (iv) federal, state and other taxes which may be assessed on Contractor’s net income from the Work (collectively, the “Contractor Taxes”). Owner is responsible for: (i) all sales, use, gross receipts and excise taxes imposed on OFE; and (ii) property taxes imposed on the Facility, the Facility Site, OFE and any other equipment, materials, and all other items delivered to the Facility Site for installation into, affixation or attachment to, or incorporation into the Facility (collectively, the “Project Taxes”). Contract Price includes Contractor Taxes and excludes all Project Taxes. Owner shall directly reimburse Contractor, in addition to Contract Price, for any and all Project Taxes incurred and actually paid by Contractor and for the actual cost incurred to post any necessary tax bond. Owner shall defend and indemnify Contractor from and against any and all claims for, and resulting liability for Project Taxes and any Idaho sales and use taxes relating to pollution control equipment and related penalties and interest, and any dispute resolution costs and attorneys’ fees (including costs of enforcement of this provision) that may be asserted on all items which Contractor purchased under exemption certificates or written instructions provided by Owner to Contractor and for which taxes are later assessed. At Owner’s expense and only with Contractor’s consent, Owner will have the right to direct the basis on which any tax assessment will be paid or contested and to control any contest leading to the settlement of assessed taxes. Owner retains the right to choose the attorneys who will represent Contractor’s and/or Owner’s interest regarding any tax assessments and/or litigation.

 

It is acknowledged between the Parties that the Owner believes the Work contains certain items of property that may qualify under Idaho Code Section 63-3622X as exempt from the State of Idaho’s sales and use tax as pollution control equipment. It is to the mutual advantage of both Parties to identify and claim these items of property as exempt prior to providing sales or use tax remittance to the State of Idaho. Contractor will use commercially reasonable efforts to identify, based on information provided by Owner, such property prior to placing orders to procure it. Owner shall provide written instructions to Contractor identifying materials, machinery, or devices that will be procured for the Work upon which Contractor is to exclude Idaho sales or use taxes on the basis of exemption pursuant to Idaho Code Section 63-3622X.

 

It is acknowledged by the Parties that, pursuant to Idaho law as of the date of this Contract, all shipping and handling charges do not attract Idaho sales or use tax and will be stated separately in all invoices issued to Contractor. Shipping refers to any charge incurred for the delivery, freight, and transportation. Handling refers to the fees imposed by the seller for the preparation of property for shipping.

 

Contractor shall, prior to Final Acceptance, and with the Owner’s assistance, provide to Owner a listing of equipment included in the Work that meets the requirements of Idaho Code Section 63-602P as property that contributes to the elimination, control or prevention of air or water pollution.

 

If a change order results in an increase or decrease in the Contract Price, the revised Contract Price (reflecting the increase or decrease as a result of the change order) shall include all Contractor Taxes and exclude all applicable Project Taxes. Owner shall reimburse Contractor for all applicable Project Taxes paid by Contractor in accordance with the provisions of this Section 3.4.

 

 


3.5       Engineered Equipment Target Price Adjustments. Purchase orders and subcontracts will be awarded by Contractor for the procurement of the Engineered Equipment. The value of the purchase orders and the subcontracts will be recorded and reported to the Owner monthly throughout the course of the Work. Monthly reporting will also include a projected Engineered Equipment Cost, that will be compared to the Engineered Equipment Target Price. The Parties shall reconcile the Engineered Equipment Cost with the Engineered Equipment Target Price no later than two weeks after Contractor’s last purchase of major Engineered Equipment, within thirty (30) days after each of the Substantial Completion Date, the Final Completion Date, and the conclusion of the Warranty Period, unless the Parties otherwise agree. Upon conclusion of each reconciliation, the Parties shall agree on a value for the Engineered Equipment Cost, as applicable, and, to the extent excess costs or shared savings have not yet been accounted for, either (i) the Contractor shall make a reimbursement to Owner subject to the limit set forth in Sections 3.6 (ii) Owner shall make a payment to Contractor subject to the limit set forth in Section 3.6, or (iii) no reimbursement will be required.

 

3.6       Engineered Equipment Target Price. The basis for the Engineered Equipment Target Price is as listed in Exhibit M and the technical specifications in Exhibit B applicable to the Engineered Equipment. The Engineered Equipment Target Price, as shown on Exhibit M , is ***. It is the intent of the Parties that Contractor and Owner share the potential risks and benefits associated with the Engineered Equipment Target Price. If the Engineered Equipment Cost exceeds the Engineered Equipment Target Price, up to seven million, nine hundred eight-two thousand, four hundred thirty-three dollars ($7,982,433), the Owner and the Contractor shall equally bear the excess costs. To the extent the Engineered Equipment Cost exceeds the Engineered Equipment Target Price by more than seven million, nine hundred eight-two thousand, four hundred thirty-three dollars ($7,982,433), the Owner shall be solely responsible for all costs above the seven million, nine hundred eight-two thousand, four hundred thirty-three dollar ($7,982,433) difference. If the Engineered Equipment Cost is less than the Engineered Equipment Target Price, up to eight million, seventeen thousand, five hundred sixty-seven dollars ($8,017,567), the Owner and the Contractor shall share equally in the savings difference. To the extent the savings difference is greater than eight million, seventeen thousand, five hundred sixty-seven dollars ($8,017,567), the Owner shall be solely entitled to all such savings .

 

The Engineered Equipment Target Price shall include the cost of the following items:

 

a)                Final detailed design scope adjustments required to provide a facility meeting all requirements of the Contract (without regard to any Changes).

 

b)               Vendor technical field services, required to support the Contractor.

 

c)                Revisions or re-order of equipment caused by Contractor’s engineering changes.

 

d)               Cost of all change orders issued to Engineered Equipment suppliers and subcontractors initiated by the Contractor.

 

The Engineered Equipment Target Price does not cover or incorporate the costs associated with any Change, and any such costs shall be the sole responsibility of Owner. In the event Contractor incurs any additional costs relating to the Engineered Equipment due to a Change or any additional sales or use tax, Contractor shall submit a Change Order in accordance with Article 10 .

 

 


3.7       Engineered Equipment Target Price Disclosure and Rights. The Contractor shall provide the Owner with copies of all purchase orders, material contracts and subcontracts, including all change orders and amendments, for all Engineered Equipment for the purpose of allowing Owner to audit the Engineered Equipment Cost.

 

Any liquidated damages paid by any Subcontractor or Subcontractor’s subcontractor shall not affect the Engineered Equipment Cost. The Owner shall not share in the benefit of any liquidated damages payable by any Engineered Equipment Subcontractor or Subcontractor’s subcontractor, as the damages are to compensate the Contractor for costs resulting from failure of the Engineered Equipment vendors to perform. Any back-charges, re-work or other such work associated with the Engineered Equipment shall not affect the Engineered Equipment Cost. The Owner shall not share in the reduction of any Engineered Equipment contracts related to Contractor’s back-charges, re-work or any other such work associated with Engineered Equipment.

 

3.8       Labor Adjustment. Contractor and Owner agree that portions of the Contract Price as set forth in Exhibit C were established on a firm price basis. Owner has requested and Contractor has agreed to a seven month delay in issuing the Notice to Proceed. There may be escalation on the labor portion of the Contract Price arising from this delay; if so, the labor portion of the Contract Price will qualify for adjustment as set forth in this Section. This shall be the sole adjustment to the Contract Price for the impacts to the labor portion of the Contract Price arising from the seven month delay in issuing the Notice to Proceed. This Section shall in no way limit Contractor's rights to other adjustments that are allowed per Article 10 , such as: (a) impacts arising from further delay, if any, in issuing the Notice to Proceed; and (b) impacts arising from any other events.

 

(a) Labor Indexes. For the purpose of this labor adjustment provision, the Labor Indexes used shall be based on labor cost surveys performed by a mutually acceptable independent third party firm. Such surveys shall be formulated to accurately reflect the cost of labor for the Project and the regional area, and shall consider wages for applicable craft labor groups. The Labor Indexes shall take into account the Labor Portion of each labor group as a fixed percentage of the labor portion of the Contract Price as provided below. The parties agree that labor cost surveys for the Northwestern United States prepared by PAS, Inc. of Saline, Michigan, are mutually acceptable.

 

A Base Labor Index (BLI) shall be established using actual Survey Labor Rates dated on or about March 1, 2009. For example:

 

 

 

 

Example Survey

 

 

Labor

 

Average

 

CRAFT

Portion

 

Hourly Wage Rate

 

Boilermakers

10%

X

$20.00 =

2.00

Electricians

20%

X

$20.00 =

4.00

Iron Workers, Structural

2%

X

$20.00 =

0.40

Millwrights

15%

X

$20.00 =

3.00

Pipefitters

16%

X

$20.00 =

3.20

Welders

17%

X

$20.00 =

3.40

Base Labor Index (BLI)

 

 

SUM =

16.00

 

A Periodic Labor Index (PLI) shall be established using actual Survey Labor Rates dated on or about September 1, 2009. For example:

 

 

Example Survey

Labor

Average

 

 


CRAFT

Portion

 

Hourly Wage Rate

 

Boilermakers

10%

X

$25.00 =

2.50

Electricians

20%

X

$18.00 =

3.60

Iron Workers, Structural

2%

X

$20.00 =

0.40

Millwrights

15%

X

$22.00 =

3.30

Pipefitters

16%

X

$30.00 =

4.80

Welders

17%

X

$20.00 =

3.40

Periodic Labor Index (PLI)

 

 

SUM =

18.00

 

The BLI and PLI shall be calculated to two decimal places.

 

(b) Adjustment Calculation. If the PLI is less than or equal to the BLI, the Contract Price shall not be adjusted. If the PLI is greater than the BLI, a Cost Increase to the Contract Price shall be calculated as follows:

 

•         Adjustment Percentage ( AP ) = ***

•         Cost Increase = ***

 

The AP shall be calculated to four decimal places. However, in no case shall the Cost Increase exceed ***. For example:

 

AP = ***

Computed Cost Increase = ***

*** (cap); therefore, a change order for the Cost Increase of *** would be executed.

 

(c) Price Adjustment & Billing. The price adjustment calculation shall be performed by Contractor within the pay period after the Survey Labor Rates dated on or about September 1 st , 2009, are published. If a Cost Increase results, the parties shall immediately execute a change order for the Cost Increase in accordance with Article 10 . The Contractor may submit an invoice for the Cost Increase at any time after execution of such change order and payment shall be made in accordance with Article 4 .

 

ARTICLE 4 – PAYMENT TERMS

 

4.1       Payment to Contractor.

 

a.                     Subject to the terms of this Contract, Owner shall make payments to Contractor on a monthly basis in accordance with the Schedule of Values set forth in Exhibit C, as it may be adjusted by a Change. Payments due Contractor under this Contract shall be electronically transferred by wire transfer to the bank account and in accordance with the bank instructions identified in Contractor’s most recent invoice in immediately available funds no later than the payment due date. Invoice number and project name shall be referenced in the bank wire reference fields. All payments shall be made in U.S. Dollars. To ensure that Contractor remains cash flow positive at all points during the Project, taking into account timing of payments and commitments to Subcontractors/vendors as may be required, Contractor requires significant payments upon receipt of the FNTP as set forth in the Schedule of Values. Payments made to Contractor pursuant to this Contract shall in no way imply approval or acceptance of the Work. Neither acceptance of the Work nor payment by Owner shall be deemed to be a waiver of Owner’s rights to enforce any obligations on Contractor hereunder or the recovery of damages for defective Work not

 

 


discovered by Owner at the time of final inspection. Except as set forth in Section 4.2(d) below, Owner shall not be entitled to retain any amount from Progress Payments due Contractor hereunder.

 

b.                  Owner shall pay Contractor the applicable milestone payments listed in the Schedule of Values upon receipt of documentation sufficient for Owner to verify that the corresponding milestone has been met.

 

c.                   Payment requests will be made monthly and shall not differ from the cash flow by more than *** without a minimum of thirty (30) days notice to the Owner. After receiving notice of the proposed expenditure difference, Owner shall review and approve the differing expenditure within seven (7) days, and such approval will not be unreasonably withheld. EPC Contractor shall update the projected cash flow monthly to reflect actual invoices. The cash flow shall be tied to the Project Schedule.

 

4.2       Invoicing and Withholding.

 

(a)                Subject to the provision of this Article 4 , Owner shall make monthly payments to Contractor equal in amount to the Progress Payment, in accordance with Exhibit C , for that portion of the Work that Contractor has completed through the end of the previous month and for which Contractor has not previously been paid. Each Progress Payment shall include documentary evidence of the completion of such portion of the Work described in such Contractor’s invoice sufficient for Owner to verify that the portion of the Work has been completed unless the completion of such portion of the Work is readily discernable without such documentary evidence.

 

(b)               On or before the first day of each calendar month, Contractor shall submit its progress report to Owner covering the previous calendar month, along with Contractor’s invoice for (i) the payment next due from Owner, (ii) any amount due for Work for which payment was to be deducted or for which an earlier Progress Payment was made in accordance with (i) above, (iii) any amount due on a price-to-be-determined basis as provided in Section 10.4 , and (iv) any other amounts due Contractor under this Contract. In connection with any invoice for amounts under (iii) or (iv) above, Contractor shall provide such supporting information as shall be reasonably necessary to evaluate such invoice, including such information as Owner may reasonably request to verify the accuracy of the data contained in the invoice.

 

(c)                Payments shall be made not later than fifteen (15) days after Owner’s receipt of Contractor’s invoice therefor.

 

(d)               If there is any dispute about any amount invoiced by Contractor, the amount not in dispute shall be promptly paid as described above, and any disputed amount which is ultimately determined to have been due shall be paid with interest from the date of withholding to the date of payment as set forth in Section 4.3 , provided that such dispute does not arise as a result of inadequate, improper or deficient supporting documentation of the invoiced amount. Owner will provide a Notice to Contractor within ten (10) days after receipt of Contractor’s invoice concerning any invoiced amounts disputed by Owner.

 

4.3       Interest on Late Payments. Late payments (excluding partially withheld payments for deficient work or delayed work) will be subject to interest at a rate equal to the lesser of ***, or the maximum amount allowed by law. A Party’s entitlement to interest under this Article 4 shall be in addition to such Party’s rights under other provisions of this Contract.

 

4.4       Contractor’s Right to Suspend Performance. Contractor will have the right to suspend work if Owner fails to make any reasonably undisputed payment to Contractor within ten (10) days of the date such payment is due, and such suspension shall entitle Contractor to equitable adjustment(s) to the Contract Price and Project Schedule.

 

4.5       Final Payment. The final Progress Payment shown in the Schedule of Values shall not be made until the following conditions have been satisfied or waived by Owner:

 

(a)                Subject to Article 24 , Contractor shall have furnished Owner with Contractor’s certification that all claims for payment for labor and materials for which Contractor is responsible in connection with the Work have been paid or satisfied, unless in dispute;

 

(b)               All Contractor’s and Subcontractors’ personnel, supplies, equipment, waste materials, rubbish and temporary facilities shall have been removed from the Facility Site except as may be needed for ongoing obligations;

 

(c)                The Punchlist items shall have been completed; and

 

(d)               Final Completion shall have occurred, as defined in Article 9 .

 

Contractor’s acceptance of the final payment listed on the Schedule of Values shall constitute a full waiver of any and all claims by Contractor against Owner for payment for Work performed that are known or should have been known by Contractor at the time of acceptance of final payment.

 

4.6       Prompt Payment to and by Subcontractors. Contractor shall promptly pay each Subcontractor in accordance with the terms of the applicable subcontract or purchase order for each Subcontractor’s performance of the Work. The Contractor’s subcontract agreements and purchase order agreements shall require each Subcontractor to make payment in a similar manner to the entities with which it has contracted for performance of the Work.

 

4.7       Owner Information. Owner shall provide information reasonably requested by Contractor to enable proper assessment of the risk of non-payment, which shall be updated upon any material changes to the information throughout the progress of the Work or upon periodic request by Contractor. Contractor shall have satisfactory assurance of payment; no amounts shall be included for risk of non-payment.

 

ARTICLE 5 – NOTICES TO PROCEED

 

5.1       Full Notice to Proceed. Owner will issue a Full Notice to Proceed (“FNTP”) to Contractor no later than September 1 st , 2009 which will authorize the Contractor to commence and complete all Work, and shall grant Contractor full and unrestricted access to the Jobsite no later than ***. Owner shall make a payment to Contractor in conjunction with the FNTP pursuant to the Schedule of Values. The FNTP shall be effective on the first Business Day following the date of its issuance.. Contractor shall commence the Work upon the effective date of the FNTP. If said FNTP has not been given by September 1 st , 2009, or if Contractor has not been given full and unrestricted access to the Jobsite by ***, Contractor shall be entitled to an equitable adjustment to both Project Schedule and Contract Price.

 

5.2       Termination by Contractor for Non-Issuance of FNTP. If the FNTP has not been issued by November 1 st , 2009, Contractor may terminate this Contract by written Notice to Owner. Any such termination shall be without liability to either Party and Contractor shall have no right to make a claim against Owner for payments required by or relating to the Contract, other than for Contractor’s costs properly incurred pursuant to any work performed under the Master Services Agreement, dated October 3 rd , 2008, by and between Client and Contractor.

 

5.3       Preliminary Access to Jobsite. Owner shall provide Contractor preliminary access to the Jobsite prior to *** so that Contractor may begin preliminary site work, including but not limited to geotechnical testing, grubbing, grading, or other activities as the Parties may reasonably agree.

 

ARTICLE 6 – INSPECTION OF THE WORK

 

6.1                 Right of Access. Owner’s authorized representatives and permitted assigns shall have the right at all reasonable times during performance of the Work to inspect the Work and the Facility and any item of equipment, material, design, engineering, or service or the workmanship associated therewith (but not including access to cost or pricing data associated therewith). Contractor shall arrange for any such inspection of equipment or material on the Facility Site, and at the point of significant fabrication off the Facility Site upon reasonable notice. All costs associated with Owner’s inspections shall be to Owner’s account. Contractor shall cooperate with Owner at any reasonable time that Owner shall determine that inspection of the Work is necessary or appropriate. Such cooperation shall include furnishing Owner with access to the Work, even to the extent of dismantling finished Work where necessary to permit such inspection. If such dismantling and subsequent inspection reveals defects all associated Work shall be corrected at the expense of Contractor. If such dismantling and subsequent inspection reveals no defects, such Work shall be restored at the expense of Owner and Contractor shall be entitled to an equitable adjustment to the Project Schedule.

 

6.2       Objection to Work. Owner shall inform Contractor promptly of any defects in the Work it

discovers in any inspection of the Work; provided that no inspection (or lack of inspection) of any part of the Work shall in any way affect Contractor’s obligations to perform the Work and correct defects in accordance with the Contract Documents. All such inspections shall be conducted in a manner that does not interfere with the normal performance and progress of the Work.

 

6.3                 No Acceptance of Work. Any rights asserted by Owner under this Article 6 shall in no way affect or reduce Contractor's obligations under this Contract and will not be deemed to constitute an acceptance by Owner with respect to such work.

 

ARTICLE 7 – Intentionally Deleted.

 

ARTICLE 8 – FACILITY TESTS

 

8.1                 Conduct of Facility Tests. Contractor shall conduct the Performance Tests in accordance with

the Performance Test Conditions. Contractor shall furnish reasonable advance Notices prior to, and test reports after, all Performance Tests, including unsuccessful tests and re-tests, as provided in Exhibit F .

 

 


Contractor shall maintain qualified personnel on the Facility Site to supervise the activities of operating personnel regarding the operation and maintenance of the Facility until Substantial Completion, and, to the extent necessary, to provide technical direction during the Performance Tests and any re-testing periods following Substantial Completion. The Contract Price includes one set of Performance Tests. Should re-testing be required, and such re-testing is not directly attributable to Contractor’s fault, Contractor shall be entitled to an equitable adjustment of either the Contract Price or the Project Schedule, or both as appropriate.

 

8.2                                     Minimum Performance Criteria. If Substantial Completion is achieved at less than the Guaranteed Net Power Output and/or more than the Guaranteed Net Heat Rate, Contractor shall have reasonable access to the Project for *** after Substantial Completion to attempt to achieve such Guaranteed Net Power Output and/or the Guaranteed Net Heat Rate. Contractor may buy down plant performance at any time after Substantial Completion by paying performance liquidated damages pursuant to Section 27.4 at its discretion. Only one guarantee point shall be provided for each performance guarantee.

 

8.3                 Notice; Commencement; Conduct. Contractor shall provide Owner with at least ten (10) Business Days’ prior written notice of the date upon which Contractor proposes to commence any of the Performance Tests. All Performance Tests shall be conducted in accordance with the Test Procedures. Owner shall provide qualified operating personnel for the conduct of all such tests, who shall work entirely under the technical direction and control of Contractor. Owner shall have the right to perform data collection for each Performance Test. The Parties shall agree on the data to be used for analysis and Contractor shall perform the analysis. If Owner observes any defects in the Work or its performance during any Performance Test, Owner shall promptly notify Contractor; provided that no observance of (or failure to observe) a defect by Owner shall affect any obligation of Contractor under the Contract. Owner and Contractor shall cooperate in good faith in determining when or to what extent the Project shall be taken out of service in order to take corrective measures. Test procedures and approvals shall be subject to Owner review without undue delay.

 

ARTICLE 9 – SUBSTANTIAL AND FINAL COMPLETION

 

9.1       Substantial Completion. Substantial Completion shall be met when:

 

i)                    The Project is materially complete, all essential equipment and systems are operational in accordance with the Contract, and has been fully designed, constructed and equipped in accordance with the Contract (except as provided in the Final Completion punchlist submitted by Contractor); and

 

ii)                  The Project demonstrates the following criteria after completion of a *** period during the Performance Tests:

 

a)                  No less than *** of Guaranteed Net Capacity ; and

 

b)                  No more than *** of Guaranteed Net Heat Rate; and

 

c)                  Air emission levels meeting the less stringent of the guaranteed levels in accordance with permit test procedures. Notwithstanding the foregoing, in the event the actual level exceeds the less stringent of the level set forth herein or the permit level but nonetheless the Project is not precluded from commercial operation by any Government Authority, air emission levels for the purposes of Substantial Completion shall be deemed to be achieved and the parties agree that Contractor shall not be liable for delay liquidated damages as a result of failure to meet the emissions requirements. In the event the Project is precluded from commercial operation by any Governmental Authority at any time prior to meeting the lesser of the guaranteed levels as a result of the actual air emission levels, Contractor shall immediately commence necessary modifications/repairs of the Project so as not to exceed the less stringent of aforementioned levels. For each day until such level is demonstrated, Contractor shall be liable for the delay liquidated damages; and

 

iii) Owner has received from Contractor all information necessary to secure permits, licenses, and approvals required at the time of commercial operation.

 

Substantial Completion shall also be deemed to occur in the event a) that Owner operates the Project for its commercial benefit or b) Contractor is prevented from conducting performance tests within thirty (30) days of the date Contractor provides notice to Owner it is ready to commence such tests.

 

9.2                 Notice of Substantial Completion. Promptly after successful completion of the Performance Tests in which, in Contractor’s judgment, all the conditions of Substantial Completion set forth in Section 9.1 have been satisfied, Contractor shall issue to Owner a Notice of Substantial Completion, which shall include copies of relevant test report(s) in reasonable detail and which shall set forth the date upon which the conditions set forth in Section 9.1 were satisfied. Within ten (10) Business Days after receipt of Notice of Substantial Completion, Owner shall respond to Contractor in writing and either accept such Notice or, within such period, identify any deficiencies, which shall be promptly corrected by Contractor and a Notice of Substantial Completion resubmitted to Owner. The date of Substantial Completion shall date back in time to the date Contractor first submits for such approval, provided that such submission is approved. Failure of Owner to respond within ten (10) Business Days shall be deemed an acceptance.

 

9.3       Punchlist. At a time designated by Owner and within seven (7) days of Substantial Completion, Owner and Contractor shall complete a joint inspection of the Work and Contractor shall deliver its proposed Punchlist to Owner. Within seven (7) days of the receipt of Contractor’s Punchlist, Owner shall respond to Contractor’s proposed Punchlist either confirming the list or specifying any disputed or missing items. Upon any such adjustment of the Punchlist, Contractor shall so notify Owner in writing. Within seven (7) days of Owner’s receipt of such adjusted Punchlist, Owner shall deliver to Contractor either its written acknowledgement that Punchlist is acceptable or a Notice specifying any disputed or missing items. In the latter instance, the foregoing procedure with respect to such items will be repeated until Punchlist is acceptable. Owner will release the milestone payment for achieving Substantial Completion as set forth in the Schedule of Values less *** the mutually agreed upon estimated value of remaining punchlist items (“Punchlist Retainage”). The Punchlist Retainage will be released upon full completion and Owner acceptance of the punchlist items.

 

9.4       Final Completion. Final Completion of the Work shall be defined to occur on the date when:

 

a)       The Project has achieved Substantial Completion; and

 

b)      The Project has completed a *** reliability test at nominal plant output;

 

 


c)       All Contractor’s personnel, supplies, equipment, waste materials, rubbish and temporary facilities have been removed from the Project and the Facility Site properly restored to an acceptable condition;

 

d)      All special tools required under the Contract have been delivered to Owner;

 

e)       Contractor has provided all required “As-Built” drawings; and

 

f)       Contractor has provided all Operation and Maintenance Manuals; and

 

g)       Contractor has provided and replaced all spare parts as required by Section 1.6 above; and

 

h)      Contractor has completed all Punchlist work, or made payment for incomplete work out of the Punchlist Retainage.

 

9.5                 Notice of Final Completion. Promptly after items in Section 9.4 above have b


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more