Exhibit 10.1
No.: XQ-IV0510D30
Construction
Contract
Engineering No.: Reform 22-4
(03)
Engineering Name: Fire System in
2150ASP Hot Continuous Rolling Engineering of
Anshan Iron & Steel Group
Corp.
Contract-issuing Party: Anshan
Iron & Steel Group Corp.
Contractor: Sureland Industrial Fire
Safety Co., Ltd.
Contract-signing Date: Oct.
2005
Party 1 Agreement
Legal Person (Full Name): Anshan
Iron & Steel Group Corp.
Legal Person (Full Name): Sureland
Industrial Fire Safety Co., Ltd.
In accordance with Contract Law
of the People’s Republic of China, Construction Law of the
People’s Republic of China , other relevant laws and
administrative regulations, and following the principle of
equality, fairness, honesty and credibility, both parties have
reached assent on the construction work, and then concluded the
contract.
I General Situation of the
Engineering
Engineering No.: Reform 22-4
(03)
Engineering Name: Name: Fire System
in 2150ASP Hot Continuous Rolling Engineering of Anshan
Iron & Steel Group Corp.
Engineering Site: In Anshan
Iron & Steel Plant
Design Unit: Sureland Industrial
Fire Safety Co., Ltd.
Unit with Property Right: Hot-rolled
Strip Steel Plant of Anshan Iron & Steel Group
Corp.
Quality Evaluation Department:
Quality Surveillance Station for Engineering of Anshan
Iron & Steel Group Corp. of Metallurgy Bureau
Engineering Content: Fire system in
2150ASP hot continuous rolling engineering of Anshan
Iron & Steel Group Corp., including design modification
and acceptance inspection cost (see technical appendix)
II Engineering-contracting
Scope
Design, equipment assembly,
engineering implementation, acceptance inspection and other
contents in the engineering scope regulated in the technical
appendix
III Contract Time Limit
The absolute time limit of
installing and debugging (75 days)
IV Quality Standard
Engineering quality standard:
conformity rate is 100%, and excellent rate is more than
80%
V Contract Price
Amount: (in capital) twenty three
million only (RMB)
¥: 23,000,000
VI Document Composing the
Contract
The documents composing the contract
include:
|
3.
|
Bid document
and its appendices
|
|
4.
|
Special
articles of the contract
|
|
5.
|
General
Articles of the contract
|
|
6.
|
Standards,
codes and relevant technical documents
|
|
8.
|
Engineering
quantity list
|
|
9.
|
Engineering
quotation or budget statement
|
Both parties’ written
agreements or documents about engineering negotiation and change,
etc are the necessary parts of the contract.
VII The meanings of relevant words
in the agreement are same with those in the part 2 of the contract
(general articles).
VIII The contractor promises the
contract-issuing party to construct and complete the engineering in
accordance with the contract, and assume the responsibility of
maintenance in the guarantee period of engineering.
IX The contract-issuing party promises the
contractor to pay the contract price and other payables in
accordance with the time limit and mode regulated in the
contract.
X Execution of Contract
Contract-concluding place: Technical
Reform Department of Anshan Iron & Steel Group
The contract will go into effect
after signed and sealed by both parties.
Part 2 General Articles
4. Completion of the
Engineering
4.1 The contractor must complete the
engineering based on the date of completion in the agreement or the
postponed time limit approved by engineers.
4.2 The contractor should assume the
liabilities for breach of contract if he cannot complete the
engineering based on the date of completion in the agreement or the
postponed time limit approved by engineers due to him.
4.3 If it’s necessary for the
contract-issuing party to complete the engineering in advance, both
parties should sign the agreement about advance completion after
reaching assent as a part of the contract. Besides, the agreement
about advance completion should include the measures took by the
contractor to guarantee engineering quality and safety, the
conditions provided by the contract-issuing party to complete in
advance, and the additional contract price required for completing
in advance, etc.
5. Engineering Quality
5.1 The engineering quality should
reach the quality standard regulated in the agreement, which is
evaluated based on national or industrial quality
inspection
standards. The contractor should assume the
liabilities for breach of contract if the engineering quality
cannot reach the appointed quality standard due to him.
26. Payment of Engineering Fund
(Progress Fund)
26.4 Under conditions that the
contract-issuing party does not pay the engineering fund (progress
fund) in accordance with the contract, and both parties cannot
reach the agreement about deferred payment, so that the engineering
cannot be constructed, the contractor can stop the construction,
and the contract-issuing party should assume the liabilities for
breach of contract.
33. Completion Settlement
Price
33.3 If the contract-issuing party
has not paid the completion settlement price without fair reasons
in 28 days after receiving completion settlement report and
settlement data, he should pay the interests of arrears on basis of
the interest rate loaned by the contractor from the 29
th
day, and assume the
liabilities for breach of contract.
(Other articles are omitted, and are
same with the general articles in the model construction
contract)
Party 3 Special Articles
I There is contractual document
about definitions of words
2. The sequence of contractual
documents and interpretations: 1, 2, 3, 4, 5, 6, 7, 8, 9
3. Language and applied laws,
standards and codes;
3.2 Applicable laws and regulations
should be indicated laws, administrative regulations, contract law,
construction law and rules for engineering quality
control.
3.3 Applicable standar