Back to top

CONSTRUCTION CONTRACT

Construction Agreement

CONSTRUCTION CONTRACT You are currently viewing:
This Construction Agreement involves

ZEOLITE EXPLORATION CO | Shandong Bangsheng Chemical Co., Ltd

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: CONSTRUCTION CONTRACT
Date: 11/16/2006

Search Construction Agreement by:

Document Title:

Entire Document: (optional)

50 of the Top 250 law firms use our Products every day
Exhibit 10

                                                                   Exhibit 10.32

                             Construction Contract

In accordance  with the principle of openness,  impartiality  and fairness,  the
public bidding meeting on the Foundation for Equipments of the Triamine Workshop
of Shandong  Bangsheng  Chemical Co., Ltd. was a full success.  Through friendly
negotiation,  Shandong  Bangsheng  Chemical  Co.,  Ltd.  and  Chen  Houzhi,  the
successful bidder, agree to establish this contract. The parties hereby agree as
follows:

Party A:  Shandong  Bangsheng  Chemical Co.,  Ltd.  (hereinafter  referred to as
"Party A")
Party B: Chen Houzhi (hereinafter referred to as "Party B")

I.    Project Name: Foundation for Equipments of the Triamine Workshop

II.   Place of Construction: Within the premises of Party A

III.  Scope of Construction:
      All civil engineering works including  concrete pouring,  leveling blanket
      laying, steel binding, template support, float work and laying.

IV.   Type of Contract: Contract for labor and materials

V.    Projected Engineering Work Load:
      Independent  foundation:  concrete  pouring__ m3, earthwork  digging __m3,
      stone footing __m3, plastering __ m3, ironware burying __tons.

VI.   Construction  Period: At the request of Party A, the construction shall be
      completed within 30 days after the signing of this contract.
      Construction  Cost:  Construction  payment  shall be done in line with the
      State's current construction flat rate and other related documents.
      Projected Construction Cost: RMB 80,000 (eighty thousand) yuan.
      The final payment shall be based on the actual volume of works.



<PAGE>

VII.  Mode of Payment:
      30(C)++ of the total  construction cost shall be paid within 10 days after
      the equipment and staff of the unit in charge of  construction  arrive the
      construction   site  and  come  into  operation;   30(C)++  of  the  total
      construction cost shall be paid after the main body of the construction is
      completed;  30(C)++ of the total construction cost shall be paid after the
      construction has been checked and accepted; the remaining 10(C)++ shall be
      paid off at a single  payment  within  one year  after the  completion  of
      construction, henceforward this contract shall become self-annulled.

VIII. Quality Requirement and Acceptance Criterion:
      1.    Quality Grade Standard: superior