Back to top

CONSTRUCTION CONTRACT

Construction Agreement

CONSTRUCTION CONTRACT You are currently viewing:
This Construction Agreement involves

ZEOLITE EXPLORATION CO | Shandong Bangsheng Chemical Co., Ltd | Shandong Bangsheng Chemical Co., Ltd

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: CONSTRUCTION CONTRACT
Date: 11/16/2006

Search Construction Agreement by:

Document Title:

Entire Document: (optional)

50 of the Top 250 law firms use our Products every day
Exhibit 10

                                                                   Exhibit 10.31

                             Construction Contract

In accordance  with the principle of openness,  impartiality  and fairness,  the
public bidding meeting on the Triamine Project - Refinery  Workshop and Relevant
Structures and Earth Hardening Project of Shandong  Bangsheng Chemical Co., Ltd.
was a full success.  Through friendly  negotiation,  Shandong Bangsheng Chemical
Co.,  Ltd. and Chen  Houzhi,  the  successful  bidder,  agree to establish  this
contract. The parties hereby agree as follows:

Party A:  Shandong  Bangsheng  Chemical Co.,  Ltd.  (hereinafter  referred to as
"Party A")
Party B: Chen Houzhi (hereinafter referred to as "Party B")

I.    Project Name: Triamine Refinery Workshop and Relevant Structures and Earth
      Hardening Project

II.   Type of Contract: Contract for labor and materials

III.  Projected Engineering Work Load:
      Construction  Cost:  Construction  payment  shall be done in line with the
      State's current construction flat rate and other related documents.
      Projected  construction  cost of  refinery  workshop:  RMB  455,000  (four
      hundred and fifty-five thousand) yuan;
      Projected   construction  cost  of  related  structures:   RMB10,000  (ten
      thousand) yuan;
      Projected  construction  cost  of  Earth  Hardening  Project:  RMB  35,000
      (thirty-five thousand) yuan.
      Total: RMB 500,000 (five hundred thousand) yuan.     
      The final payment shall be based on the actual volume of works.



<PAGE>

IV.   Construction  Period: At the request of Party A, the construction shall be
      completed within 30 days after the signing of this contract

V.    Mode of Payment:
      30(C)++ of the total  construction cost shall be paid within 10 days after
      the equipment and staff of the unit in charge of  construction  arrive the
      construction   site  and  come  into  operation;   30(C)++  of  the  total
      construction cost shall be paid after the main body of the construction is
      completed;  30(C)++ of the total construction cost shall be paid after the
      construction has been checked and accepted; the remaining 10(C)++ shall be
      paid off at a single  payment  within  one year  after the  completion  of
      construction, henceforward this contract shall become self-annulled.

VI.   Quality Requirement and Acceptance Criterion: