CONSTRUCTION CONTRACT | Document Parties: ZEOLITE EXPLORATION CO | Shandong  Bangsheng Chemical Co., Ltd | Shandong Bangsheng Chemical Co.,  Ltd You are currently viewing:
This Construction Agreement involves

ZEOLITE EXPLORATION CO | Shandong Bangsheng Chemical Co., Ltd | Shandong Bangsheng Chemical Co., Ltd

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: CONSTRUCTION CONTRACT
Date: 11/16/2006

CONSTRUCTION CONTRACT, Parties: zeolite exploration co , shandong  bangsheng chemical co.  ltd , shandong bangsheng chemical co.   ltd
50 of the Top 250 law firms use our Products every day

                                                                   Exhibit 10.31

                             Construction Contract

In accordance   with the principle of openness,   impartiality   and fairness,   the
public bidding meeting on the Triamine Project - Refinery   Workshop and Relevant
Structures and Earth Hardening Project of Shandong   Bangsheng Chemical Co., Ltd.
was a full success.   Through friendly   negotiation,   Shandong Bangsheng Chemical
Co.,   Ltd. and Chen   Houzhi,   the   successful   bidder,   agree to establish   this
contract. The parties hereby agree as follows:

Party A:   Shandong   Bangsheng   Chemical Co.,   Ltd.   (hereinafter   referred to as
"Party A")
Party B: Chen Houzhi (hereinafter referred to as "Party B")

I.     Project Name: Triamine Refinery Workshop and Relevant Structures and Earth
      Hardening Project

II.    Type of Contract: Contract for labor and materials

III.   Projected Engineering Work Load:
      Construction   Cost:   Construction   payment   shall be done in line with the
      State's current construction flat rate and other related documents.
      Projected   construction   cost of   refinery   workshop:   RMB   455,000   (four
      hundred and fifty-five thousand) yuan;
      Projected    construction   cost   of   related   structures:    RMB10,000   (ten
      thousand) yuan;
      Projected   construction   cost   of   Earth   Hardening   Project:   RMB   35,000
      (thirty-five thousand) yuan.
      Total: RMB 500,000 (five hundred thousand) yuan.      
      The final payment shall be based on the actual volume of works.



<PAGE>

IV.    Construction   Period: At the request of Party A, the construction shall be
      completed within 30 days after the signing of this contract

V.     Mode of Payment:
      30(C)++ of the total   construction cost shall be paid within 10 days after
      the equipment and staff of the unit in charge of   construction   arrive the
      construction    site   and   come   into   operation;    30(C)++   of   the   total
      construction cost shall be paid after the main body of the construction is
      completed;   30(C)++ of the total construction cost shall be paid after the
      construction has been checked and accepted; the remaining 10(C)++ shall be
      paid off at a single   payment   within   one year   after the   completion   of
      construction, henceforward this contract shall become self-annulled.

VI.    Quality Requirement and Acceptance Criterion:
      1.     Quality Grade Standard: superior  
      2.     Party A provides   construction   site featured "three put through one
            level",   and a construction map. Party A is also responsible for the
            joint checkup of the blueprint before star


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more