Exhibit 10.142
CONSTRUCTION AGREEMENT
(LIVERMORE/PARCEL 7)
BETWEEN
LAM
RESEARCH CORPORATION
(“LRC”)
AND
BNP
PARIBAS LEASING CORPORATION
(“BNPPLC”)
December 18, 2007
TABLE OF CONTENTS
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Page |
| ENGAGEMENT AND
AUTHORIZATION |
|
|
1 |
|
| GENERAL TERMS AND
CONDITIONS |
|
|
2 |
|
| 1 |
|
Additional
definitions |
|
|
2 |
|
| |
|
“ 97-10/Meltdown
Event ” |
|
|
2 |
|
| |
|
“
97-10/Prepayment ” |
|
|
2 |
|
| |
|
“ 97-10/Project
Costs ” |
|
|
3 |
|
| |
|
“
97-10/Pronouncement ” |
|
|
4 |
|
| |
|
“ Accrued
Construction Period Interest Expense ” |
|
|
4 |
|
| |
|
“ Administrative
Fee ” |
|
|
5 |
|
| |
|
“
Affiliate’s Contract ” |
|
|
5 |
|
| |
|
“ Arrangement
Fee ” |
|
|
5 |
|
| |
|
“ Capital
Adequacy Charges ” |
|
|
5 |
|
| |
|
“ Carrying
Costs ” |
|
|
5 |
|
| |
|
“ Commitment
Fees ” |
|
|
5 |
|
| |
|
“ Complete
Taking ” |
|
|
5 |
|
| |
|
“ Completion
Date ” |
|
|
5 |
|
| |
|
“ Completion
Notice ” |
|
|
5 |
|
| |
|
“ Construction
Advances ” |
|
|
6 |
|
| |
|
“ Construction
Advance Request ” |
|
|
6 |
|
| |
|
“ Construction
Allowance ” |
|
|
6 |
|
| |
|
“ Construction
Budget ” |
|
|
6 |
|
| |
|
“ Construction
Project ” |
|
|
6 |
|
| |
|
“ Covered
Construction Period Losses ” |
|
|
6 |
|
| |
|
“ Defective
Work ” |
|
|
6 |
|
| |
|
“ FOCB
Notice ” |
|
|
6 |
|
| |
|
“ Force Majeure
Event ” |
|
|
7 |
|
| |
|
“ Funded
Construction Allowance ” |
|
|
7 |
|
| |
|
“ Future
Work ” |
|
|
7 |
|
| |
|
“ Increased Cost
Charges ” |
|
|
7 |
|
| |
|
“ Increased
Commitment ” |
|
|
7 |
|
| |
|
“ Increased
Funding Commitment ” |
|
|
7 |
|
| |
|
“ Increased Time
Commitment ” |
|
|
8 |
|
| |
|
“ Initial
Advance ” |
|
|
8 |
|
| |
|
“ LRC’s
Estimate of Force Majeure Delays ” |
|
|
8 |
|
| |
|
“ LRC’s
Estimate of Force Majeure Excess Costs ” |
|
|
8 |
|
| |
|
“ Maximum
Construction Allowance ” |
|
|
8 |
|
| |
|
“ Notice of
LRC’s Intent to Terminate ” |
|
|
8 |
|
| |
|
“ Notice of
LRC’s Intent to Terminate Because of a Force Majeure
Event ” |
|
|
8 |
|
| |
|
“ Notice of
Termination by LRC ” |
|
|
8 |
|
| |
|
“ Outstanding
Construction Allowance ” |
|
|
8 |
|
| |
|
“ Pre-lease
Casualty ” |
|
|
8 |
|
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Page |
| |
|
“ Pre-lease
Force Majeure Delays ” |
|
|
8 |
|
| |
|
“ Pre-lease
Force Majeure Event ” |
|
|
8 |
|
| |
|
“ Pre-lease
Force Majeure Event Notice ” |
|
|
9 |
|
| |
|
“ Pre-lease
Force Majeure Excess Costs ” |
|
|
9 |
|
| |
|
“ Pre-lease
Force Majeure Losses ” |
|
|
9 |
|
| |
|
“ Prior Work
” |
|
|
10 |
|
| |
|
“ Projected Cost
Overruns ” |
|
|
10 |
|
| |
|
“ Reimbursable
Construction Period Costs ” |
|
|
10 |
|
| |
|
“ Remaining
Proceeds ” |
|
|
10 |
|
| |
|
“ Scope
Change ” |
|
|
10 |
|
| |
|
“ Target
Completion Date ” |
|
|
11 |
|
| |
|
“ Termination of
LRC’s Work ” |
|
|
11 |
|
| |
|
“ Third Party
Contract ” |
|
|
11 |
|
| |
|
“ Third Party
Contract/Termination Fees ” |
|
|
11 |
|
| |
|
“ Timing or
Budget Shortfall ” |
|
|
11 |
|
| |
|
“ Work
” |
|
|
12 |
|
| |
|
“
Work/Suspension Event ” |
|
|
12 |
|
| |
|
“
Work/Suspension Notice ” |
|
|
12 |
|
| |
|
“
Work/Suspension Period ” |
|
|
13 |
|
| 2 |
|
Construction and Management of the
Property by LRC |
|
|
13 |
|
| |
|
(A) |
|
The
Construction Project |
|
|
13 |
|
| |
|
|
|
|
(1 |
) |
|
Construction Approvals
by BNPPLC |
|
|
13 |
|
|
|
|
|
|
|
|
|
|
(a) |
|
Preconstruction Approvals by
BNPPLC |
|
|
13 |
|
|
|
|
|
|
|
|
|
|
(b) |
|
Approval of Scope Changes |
|
|
13 |
|
| |
|
|
|
|
(2 |
) |
|
LRC’s Rights of
Access and to Control Construction |
|
|
13 |
|
|
|
|
|
|
|
|
|
|
(a) |
|
Performance of the Work |
|
|
14 |
|
|
|
|
|
|
|
|
|
|
(b) |
|
Third Party Contracts |
|
|
14 |
|
|
|
|
|
|
|
|
|
|
(c) |
|
Adequacy of Drawings,
Specifications and Budgets |
|
|
15 |
|
|
|
|
|
|
|
|
|
|
(d) |
|
Existing Condition of the Land and
Improvements |
|
|
15 |
|
|
|
|
|
|
|
|
|
|
(e) |
|
Correction of Defective
Work |
|
|
15 |
|
|
|
|
|
|
|
|
|
|
(f) |
|
Clean Up |
|
|
15 |
|
|
|
|
|
|
|
|
|
|
(g) |
|
No Damage for Delays |
|
|
15 |
|
|
|
|
|
|
|
|
|
|
(h) |
|
No Other Fees to LRC |
|
|
16 |
|
|
|
|
|
|
|
|
|
|
(i) |
|
Administration of Existing Space
Leases |
|
|
16 |
|
| |
|
|
|
|
(3 |
) |
|
Quality of
Work |
|
|
17 |
|
| |
|
(B) |
|
Completion
Notice |
|
|
17 |
|
| |
|
(C) |
|
Status of
Property Acquired With BNPPLC’s Funds |
|
|
17 |
|
| |
|
(D) |
|
Insurance |
|
|
18 |
|
| |
|
|
|
|
(1 |
) |
|
Liability
Insurance |
|
|
18 |
|
| |
|
|
|
|
(2 |
) |
|
Property
Insurance |
|
|
18 |
|
(ii)
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Page |
| |
|
|
|
|
(3 |
) |
|
Failure of LRC to
Obtain Insurance |
|
|
19 |
|
| |
|
|
|
|
(4 |
) |
|
Waiver of
Subrogation |
|
|
19 |
|
| |
|
(E) |
|
Condemnation |
|
|
19 |
|
| |
|
(F) |
|
Additional
Representations, Warranties and Covenants of LRC Concerning the
Property |
|
|
20 |
|
| |
|
|
|
|
(1 |
) |
|
Payment of Local
Impositions |
|
|
20 |
|
| |
|
|
|
|
(2 |
) |
|
Operation and
Maintenance |
|
|
20 |
|
| |
|
|
|
|
(3 |
) |
|
Debts for
Construction, Maintenance, Operation or Development |
|
|
21 |
|
| |
|
|
|
|
(4 |
) |
|
Permitted
Encumbrances |
|
|
22 |
|
| |
|
|
|
|
(5 |
) |
|
Books and Records
Concerning the Property |
|
|
22 |
|
| |
|
(G) |
|
BNPPLC’s
Right of Access |
|
|
22 |
|
| |
|
|
|
|
(1 |
) |
|
Access
Generally |
|
|
22 |
|
| |
|
|
|
|
(2 |
) |
|
Failure of LRC to
Perform |
|
|
22 |
|
| 3 |
|
Amounts to be Added to the Lease
Balance (in Addition to Construction Advances) |
|
|
23 |
|
| |
|
(A) |
|
Initial
Advance |
|
|
23 |
|
| |
|
(B) |
|
Carrying
Costs |
|
|
23 |
|
| |
|
(C) |
|
Commitment
Fees |
|
|
24 |
|
| |
|
(D) |
|
Future
Administrative Fees and Out-of-Pocket Costs |
|
|
24 |
|
| |
|
(E) |
|
Increased Cost
Charges and Capital Adequacy Charges |
|
|
25 |
|
| 4 |
|
Construction Advances |
|
|
26 |
|
| |
|
(A) |
|
Costs Subject
to Reimbursement Through Construction Advances |
|
|
26 |
|
| |
|
(B) |
|
Exclusions From
Reimbursable Construction Period Costs |
|
|
27 |
|
| |
|
(C) |
|
Conditions to
LRC’s Right to Receive Construction Advances |
|
|
28 |
|
| |
|
|
|
|
(1 |
) |
|
Construction Advance
Requests |
|
|
28 |
|
| |
|
|
|
|
(2 |
) |
|
Amount of the
Advances |
|
|
28 |
|
|
|
|
|
|
|
|
|
|
(a) |
|
The Maximum Construction
Allowance |
|
|
28 |
|
|
|
|
|
|
|
|
|
|
(b) |
|
Costs Previously Incurred by
LRC |
|
|
28 |
|
|
|
|
|
|
|
|
|
|
(c) |
|
Limits During any Work/Suspension
Period |
|
|
29 |
|
|
|
|
|
|
|
|
|
|
(d) |
|
Restrictions Imposed for
Administrative Convenience |
|
|
30 |
|
|
|
|
|
|
|
(3 |
) |
|
No Advances After
Certain Dates |
|
|
30 |
|
| |
|
(D) |
|
Breakage Costs
for Construction Advances Requested But Not Taken |
|
|
30 |
|
| |
|
(E) |
|
No Third Party
Beneficiaries |
|
|
30 |
|
| |
|
(F) |
|
No
Waiver |
|
|
30 |
|
| 5 |
|
Application of Insurance and
Condemnation Proceeds |
|
|
30 |
|
| |
|
(A) |
|
Collection and
Application Generally |
|
|
30 |
|
| |
|
(B) |
|
Advances of
Escrowed Proceeds to LRC |
|
|
31 |
|
| |
|
(C) |
|
Status of
Escrowed Proceeds After Commencement of the Term of the
Lease |
|
|
31 |
|
| |
|
(D) |
|
Special
Provisions Applicable After a 97-10/Meltdown Event or Event of
Default |
|
|
32 |
|
| |
|
(E) |
|
LRC’s
Obligation to Restore |
|
|
32 |
|
(iii)
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Page |
| |
|
(F) |
|
Special
Provisions Concerning a Complete Taking |
|
|
32 |
|
| |
|
(G) |
|
Preservation of
LRC’s Right to Receive Construction Advances |
|
|
32 |
|
| 6 |
|
Notice of Cost Overruns and Pre-lease
Force Majeure Events |
|
|
33 |
|
| |
|
(A) |
|
Notice of
Projected Cost Overruns |
|
|
33 |
|
| |
|
(B) |
|
Pre-lease Force
Majeure Event Events and Notices |
|
|
33 |
|
| 7 |
|
Suspension and Termination of
LRC’s Work |
|
|
33 |
|
| |
|
(A) |
|
Rights and
Obligations During a Work/Suspension Period |
|
|
33 |
|
| |
|
(B) |
|
LRC’s
Election to Terminate LRC’s Work |
|
|
33 |
|
| |
|
(C) |
|
BNPPLC’s
Election to Terminate LRC’s Work |
|
|
36 |
|
| |
|
(D) |
|
Surviving
Rights and Obligations |
|
|
37 |
|
| |
|
(E) |
|
Cooperation
After a Termination of LRC’s Work |
|
|
37 |
|
| 8 |
|
LRC’s Obligation for a
97-10/Prepayment |
|
|
39 |
|
| 9 |
|
Indemnity for Covered Construction
Period Losses |
|
|
39 |
|
| |
|
(A) |
|
Covenant to
Indemnify Against Covered Construction Period Losses |
|
|
39 |
|
| |
|
(B) |
|
Certain Losses
Included or Excluded |
|
|
41 |
|
| |
|
|
|
|
(1 |
) |
|
Environmental |
|
|
41 |
|
| |
|
|
|
|
(2 |
) |
|
Failure to Maintain a
Safe Work Site |
|
|
41 |
|
| |
|
|
|
|
(3 |
) |
|
Failure to Complete
Construction |
|
|
41 |
|
| |
|
|
|
|
(4 |
) |
|
Fraud |
|
|
41 |
|
| |
|
|
|
|
(5 |
) |
|
Excluded Taxes and
Other Exclusions |
|
|
42 |
|
| |
|
|
|
|
(6 |
) |
|
Action or Omission of
Tenant Under Existing Space Lease |
|
|
42 |
|
| |
|
(C) |
|
Express
Negligence Protection |
|
|
42 |
|
| |
|
(D) |
|
Survival of
Indemnity |
|
|
43 |
|
| |
|
(E) |
|
Due Date for
Indemnity Payments |
|
|
43 |
|
| |
|
(F) |
|
Order of
Application of Payments |
|
|
44 |
|
| |
|
(G) |
|
Defense of
BNPPLC |
|
|
44 |
|
| |
|
|
|
|
(1 |
) |
|
Assumption of
Defense |
|
|
44 |
|
| |
|
|
|
|
(2 |
) |
|
Indemnity Not
Contingent |
|
|
44 |
|
| |
|
(H) |
|
Notice of
Claims |
|
|
44 |
|
| |
|
(I) |
|
Settlements
Without the Prior Consent of LRC |
|
|
45 |
|
| |
|
|
|
|
(1 |
) |
|
Election to Pay
Reasonable Settlement Costs in Lieu of Actual |
|
|
45 |
|
| |
|
|
|
|
(2 |
) |
|
Conditions to
Election |
|
|
45 |
|
| |
|
|
|
|
(3 |
) |
|
Indemnity Survives
Settlement |
|
|
45 |
|
(iv)
TABLE OF CONTENTS
(Continued)
Exhibits and Schedules
|
|
|
| Exhibit A |
|
Legal Description |
| |
|
|
| Exhibit B |
|
Description of the Construction
Project and Budget |
| |
|
|
| Exhibit C |
|
Construction Advance Request
Form |
| |
|
|
| Exhibit D |
|
Pre-lease Force Majeure Event
Notice |
| |
|
|
| Exhibit E |
|
Notice of Termination by LRC’s
Work |
| |
|
|
| Exhibit F |
|
Notice of LRC’s Intent to
Terminate |
| |
|
|
| Exhibit G |
|
Notice of Increased Funding
Commitment by BNPPLC |
| |
|
|
| Exhibit H |
|
Notice of Increased Time Commitment
by BNPPLC |
| |
|
|
| Exhibit I |
|
Notice of Rescission of LRC’s
Intent to Terminate |
(v)
CONSTRUCTION AGREEMENT
(LIVERMORE/PARCEL 7)
This CONSTRUCTION AGREEMENT
(LIVERMORE/PARCEL 7) (this “ Agreement ”), dated
as of December 18, 2007 (the “ Effective Date
”), is made by and between BNP PARIBAS LEASING CORPORATION
(“ BNPPLC ”), a Delaware corporation, and LAM
RESEARCH CORPORATION(“ LRC ”), a Delaware
corporation.
RECITALS
Contemporaneously with the execution
of this Agreement, BNPPLC and LRC are executing a Common
Definitions and Provisions Agreement (Livermore/ Parcel 7) dated as
of the Effective Date (the “ Common Definitions and
Provisions Agreement ”), which by this reference is
incorporated into and made a part of this Agreement for all
purposes. As used in this Agreement, capitalized terms
defined in the Common Definitions and Provisions Agreement and not
otherwise defined in this Agreement are intended to have the
respective meanings assigned to them in the Common Definitions and
Provisions Agreement.
At the request of LRC and to
facilitate the transaction contemplated in the other Operative
Documents, contemporaneously with this Agreement BNPPLC is
acquiring the Land described in Exhibit A and other
Property.
Also contemporaneously with this
Agreement, BNPPLC and LRC are executing a Lease Agreement
(Livermore/ Parcel 7) (the “ Lease ”), pursuant
to which the parties expect that LRC will lease the Land described
in Exhibit A and other Property from BNPPLC for a lease
term that will commence on the Completion Date (as defined
below).
In anticipation of the construction
of new or additional Improvements for LRC’s use pursuant to
the Lease, BNPPLC and LRC have agreed upon the terms and conditions
upon which BNPPLC is willing to authorize LRC to arrange and manage
such construction and upon which BNPPLC is willing to provide funds
for such construction, and by this Agreement BNPPLC and LRC desire
to evidence such agreement.
ENGAGEMENT AND AUTHORIZATION
Subject to the terms and conditions
set forth in this Agreement, BNPPLC does hereby engage and
authorize LRC — and LRC does hereby accept such engagement
and authorization, as an independent contractor for BNPPLC —
to construct the Construction Project on the Land and to manage
such construction for BNPPLC as BNPPLC’s construction agent.
As more particularly provided in subparagraph 2(A)(2) below, LRC
will have full and exclusive rights of
access
to the Land and all Improvements on the Land to accomplish such
construction. However, the rights and authority granted to LRC by
this Agreement are expressly made subject and subordinate to the
terms and condition hereinafter set forth and to the Permitted
Encumbrances and to any other claims or encumbrances affecting the
Land or the Property that may be asserted by third parties other
than Liens Removable by BNPPLC.
GENERAL TERMS AND CONDITIONS
1
Additional
definitions . As used in this Agreement, capitalized
terms defined above will have the respective meanings assigned to
them above; as indicated above, capitalized terms that are defined
in the Common Definitions and Provisions Agreement and that are
used but not defined herein will have the respective meanings
assigned to them in the Common Definitions and Provisions
Agreement; and, the following terms will have the following
respective meanings:
“ 97-10/Meltdown Event
” means any of the following:
(a) LRC gives a Notice of LRC’s
Intent to Terminate and thereafter (i) fails to rescind the same as
described in subparagraph 7(B)(7) within ten days after BNPPLC
responds with any Increased Commitment, or (ii) gives a Notice
of Termination by LRC as provided in subparagraph 7(B)(1); or
(b) LRC gives a notice to terminate
the Supplemental Payment Obligation imposed by the Purchase
Agreement as described in subparagraph 6(A) of the Purchase
Agreement; or
(c) BNPPLC gives notice to LRC as
described in subparagraph 7(C) to cause a Termination of
LRC’s Work; or
(d) LRC fails for any reason
whatsoever to substantially complete the Construction Project and
give a Completion Notice to BNPPLC prior to the Target Completion
Date; or
(e) for any reason whatsoever
(including the accrual of Carrying Costs), the Funded Construction
Allowance exceeds the Maximum Construction Allowance.
“
97-10/Prepayment ” means a payment to BNPPLC required
by Paragraph 8, which will equal eighty-nine percent (89%) of
the aggregate of all 97-10/Project Costs paid or
Construction
Agreement (Livermore/ Parcel 7) — Page 2
incurred on or
prior to the date of such payment, less amounts (if any) then owed
by BNPPLC to LRC pursuant to this Agreement as reimbursements for
Reimbursable Construction Period Costs paid by LRC and not
theretofore reimbursed.
“
97-10/Project Costs ” means all of the following, but
without duplication of any item, including any of the following
paid or reimbursed from the Initial Advance:
(a) the net purchase price paid
by BNPPLC to acquire the Land and existing Improvements;
(b) costs incurred for the Work,
including not only hard costs incurred for the new Improvements
described in Exhibit B , but also the following costs
to the extent reasonably incurred in connection with the
Construction Project:
| |
• |
|
soft costs, such as architectural fees, engineering fees and
fees and costs paid in connection with obtaining project permits
and approvals required by Governmental Authorities or any Permitted
Encumbrance, |
| |
| |
• |
|
site preparation costs, and |
| |
| |
• |
|
costs of offsite and other public improvements required as
conditions of governmental approvals for the Construction Project
or required by any Permitted Encumbrances; |
(c) costs incurred to maintain
insurance required by (and consistent with the requirements of)
this Agreement prior to the Completion Date;
(d) Local Impositions that have
accrued or become due prior to the Completion Date;
(e) Accrued Construction Period
Interest Expense; and
(f) any costs in addition to those
described in clauses (a) through (e) preceding that GAAP
(as it exists on the Effective Date) would allow BNPPLC to
capitalize as part of the cost of the Property or that the
97-10/Pronouncement would allow BNPPLC to characterize as project
costs, including cancellation or termination fees or other
compensation payable by LRC or BNPPLC pursuant to any contract
concerning the Construction Project made by LRC or BNPPLC with any
general contractor, architect, engineer or other third party
because of any election by LRC or BNPPLC to cancel or terminate
such contract.
Construction
Agreement (Livermore/ Parcel 7) — Page 3
However,
notwithstanding the foregoing, 97-10/Project Costs will not include
Pre-lease Force Majeure Losses, Commitment Fees, the Arrangement
Fee, any Administrative Fee or any legal fees which are included in
Transaction Expenses. Further, 97-10 Project Costs will not include
costs incurred to satisfy any Existing Space Lease to the extent
such cost would not have been incurred but for such Existing Space
Lease. (Thus, for example, costs of providing any required
janitorial service to a tenant under an Existing Space Lease would
not be included. In contrast, a Local Imposition that must be paid
irrespective of the requirements of any Existing Space Lease may
qualify as a 97-10/Project Cost even if payment of such Local
Imposition is required by an Existing Space Lease.)
“
97-10/Pronouncement ” means the pronouncement issued
by the Emerging Issues Task Force of the Financial Accounting
Standards Board in 1998 titled “ EITF 97-10: The Effect of
Lessee Involvement in Asset Construction ”, which
provides that certain kinds of involvement by a lessee in pre-lease
commencement construction will cause the lessee to be considered as
the owner of the leased property during the construction period and
then will require application of the appropriate sale and leaseback
accounting rules.
“
Accrued Construction Period Interest Expense ” means
interest that has accrued and that BNPPLC has paid or is obligated
to pay on Funding Advances used to pay or reimburse 97-10/Project
Costs for any period prior to the Completion Date. Subject to the
limitations and qualifications set out below in this
definition:
(1) Accrued Construction Period Interest Expense will include
a percentage, equal to the aggregate Percentages of all
Participants (under and as defined in the Participation Agreement),
of Carrying Costs and Commitment Fees that are added to the
Outstanding Construction Allowance as provided in this Agreement,
it being understood that the additional amounts BNPPLC must pay to
the Participants under the Participation Agreement because of the
accrual of Carrying Costs and Commitment Fees effectively
constitute construction period interest on advances the
Participants make to BNPPLC under the Participation
Agreement.
(2) Accrued Construction Period Interest Expense will also
include any interest and other finance charges that accrue prior to
the Completion Date because of Funding Advances provided to BNPPLC
by BNPPLC’s Parent in the form of loans.
However, the
interest and other finance charges accruing on Funding Advances
provided by BNPPLC’s Parent and included in Accrued
Construction Period Interest Expense will not in any event exceed
the portion of Carrying Costs attributable to the percentage of the
Lease Balance funded or maintained by such Funding Advances,
computed as if such
Construction
Agreement (Livermore/ Parcel 7) — Page 4
Carrying Costs
accrued at a per annum rate equal to LIBOR ( i.e. , before
the addition of the Secured Spread as provided in subparagraph
3(B)). Further, Accrued Construction Period Interest Expense will
not include any Carrying Costs (or the corresponding interest or
finance charges that BNPPLC must pay to the Participants under the
Participation Agreement or to BNPPLC’s Parent) that accrue
from time to time in respect of the portion of the Lease Balance
which exceeds the outstanding 97-10/Project Costs. For example,
Accrued Construction Period Interest Expense will not include any
portion of Carrying Costs (or any corresponding interest or finance
charges that BNPPLC must pay to the Participants under the
Participation Agreement or to BNPPLC’s Parent) because of the
inclusion in the Lease Balance of the Arrangement Fee,
Administrative Fees or other amounts excluded from 97-10/Project
Costs as described in the last paragraph of the definition thereof
set out above. Without limiting the foregoing, Accrued Construction
Period Interest Expense will not include any portion of Carrying
Costs included in Pre-lease Force Majeure Losses (as set forth in
the definition thereof below) or interest or finance charges that
BNPPLC must pay to the Participants under the Participation
Agreement or to BNPPLC’s Parent because of the accrual of
such portion of Carrying Costs.
“
Administrative Fee ” has the meanings indicated in
subparagraph 3(A) and subparagraph 3(D).
“
Affiliate’s Contract ” has the meaning indicated
in subparagraph 2(A)(2)(b)2).
“
Arrangement Fee ” has the meaning indicated in
subparagraph 3(A).
“
Capital Adequacy Charges ” has the meaning indicated
in subparagraph 3(E)(1).
“
Carrying Costs ” has the meaning indicated in
subparagraph 3(B).
“
Commitment Fees ” has the meaning indicated in
subparagraph 3(C).
“
Complete Taking ” means a taking by eminent domain
prior to the Completion Date over LRC’s objection of all of
the Land or the Property, or so much thereof as to make it
impossible to complete the Construction Project for its intended
uses on the Land regardless of any Scope Changes BNPPLC may be
willing to approve or any Increased Commitment that BNPPLC may be
willing to provide.
“
Completion Date ” means the date upon which LRC gives
the notice to BNPPLC which is required by subparagraph 2(B), after
having substantially completed the Construction Project and having
obtained any certificate of occupancy or other permit (temporary or
permanent) required for the commencement of LRC’s use of the
Improvements.
Construction
Agreement (Livermore/ Parcel 7) — Page 5
“
Completion Notice ” means the notice required by
subparagraph 2(B) from LRC to BNPPLC, advising BNPPLC that LRC has
substantially completed construction of the Construction Project
and has obtained any certificate of occupancy or other permit
(temporary or permanent) required for the commencement of
LRC’s use of the Improvements.
“
Construction Advances ” means actual advances of funds
made by or on behalf of BNPPLC to or on behalf of LRC as provided
in Paragraph 4, which sets forth LRC’s rights to receive
advances for Reimbursable Construction Period Costs. The term
“Construction Advances” will not, however, include
advances of insurance proceeds, condemnation proceeds or other
Escrowed Proceeds to pay or reimburse costs of repairs or
restoration.
“
Construction Advance Request ” has the meaning
indicated in subparagraph 4(C)(1).
“
Construction Allowance ” means the allowance to be
provided by BNPPLC for the design and construction of the
Construction Project, against which and from which Carrying Costs,
Construction Advances and other amounts will be or may be charged
and paid as provided in various provisions of this Agreement
(including Paragraphs 3 and 4).
“
Construction Budget ” means the budget for the
Construction Project set forth in Exhibit B .
“
Construction Project ” means the new buildings or
other substantial Improvements to be constructed, or the alteration
of existing Improvements, as described generally in
Exhibit B .
“
Covered Construction Period Losses ” has the meaning
indicated in subparagraph 9(A).
“
Defective Work ” has the meaning indicated in
subparagraph 2(A)(2)(e).
“ FOCB
Notice ” means a notice from BNPPLC to LRC advising LRC
of any of the following events or circumstances, and also advising
LRC that because of any of the following events or circumstances
BNPPLC will be entitled to make the election described in
subparagraph 7(C), which will constitute a Termination of
LRC’s Work and a 97-10/Meltdown Event:
(1) LRC has taken action to cancel or
terminate or reduce the coverage available to BNPPLC under the
builder’s risk insurance obtained for the Construction
Construction
Agreement (Livermore/ Parcel 7) — Page 6
Project as
required by this Agreement, or LRC has otherwise failed to maintain
any insurance or to provide insurance certificates to BNPPLC as
required by this Agreement and not cured such failure within ten
days after receiving notice thereof, or
(2) LRC has given any Pre-lease Force
Majeure Event Notice to BNPPLC, or
(3) an Event of Default has occurred
and is continuing; or
(4) a Work/Suspension Event has
occurred and not been rectified by LRC.
“
Force Majeure Event ” means (A) any taking of any
part of the Property by eminent domain prior to the Completion
Date, and (B) any damage to the Improvements or disruption of
the Work that occurs prior to the Completion Date, excluding,
however, any damage or disruption that would not have occurred or
been suffered but for any act or any omission of LRC or of any
LRC’s contractors or subcontractors during the period prior
to any Termination of LRC’s Work as provided in subparagraphs
7(B) and 7(C) or during any subsequent period in which LRC does not
relinquish possession or control of the Construction Project. Force
Majeure Events will include, for example and without limitation
damage to the Improvements or disruption of the Work caused by
fire, or acts of God (such as flood, lightning, earthquake or
hurricane), war, strikes and other labor disputes, riot or similar
civil disturbance, or any act or omission (which is not requested
or authorized by LRC) of any tenant (or of a tenant’s
employees or of any other party acting under such tenant’s
control or with the approval or authorization of such tenant) under
an Existing Space Lease; but only to the extent such damage or
disruption is beyond the control of and not caused in whole or in
part by negligence, illegal acts or willful misconduct on the part
of LRC or of its employees or of any other party acting under
LRC’s control or with the approval or authorization of
LRC.
“
Funded Construction Allowance ” means on any day the
Outstanding Construction Allowance on that day, including all
Construction Advances and Carrying Costs added to the Outstanding
Construction Allowance on or prior to that day, plus the amount of
any Qualified Prepayments deducted on or prior to that day in the
calculation of such Outstanding Construction Allowance.
“
Future Work ” has the meaning indicated in
subparagraph 4(C)(2)(b).
“
Increased Cost Charges ” has the meaning indicated in
subparagraph 3(E)(1).
“
Increased Commitment ” has the meaning indicated in
subparagraph 7(B)(6).
“
Increased Funding Commitment ” has the meaning
indicated in
Construction
Agreement (Livermore/ Parcel 7) — Page 7
subparagraph
7(B)(6)(a).
“
Increased Time Commitment ” has the meaning indicated
in subparagraph 7(B)(6)(b).
“
Initial Advance ” has the meaning indicated in
subparagraph 3(A).
“
LRC’s Estimate of Force Majeure Delays ” has the
meaning indicated in subparagraph 7(B)(4).
“
LRC’s Estimate of Force Majeure Excess Costs ”
has the meaning indicated in subparagraph 7(B)(3).
“
Maximum Construction Allowance ” means an amount equal
to the difference computed by subtracting the Initial Advance from
$46,500,000, as such amount may be increased from time to time by
any Increased Funding Commitment made by BNPPLC as provided in
subparagraph 7(B)(6).
“
Notice of LRC’s Intent to Terminate ” has the
meaning indicated in subparagraph 7(B)(2).
“
Notice of LRC’s Intent to Terminate Because of a Force
Majeure Event ” has the meaning indicated in subparagraph
7(B)(5).
“
Notice of Termination by LRC ” has the meaning
indicated in subparagraph 7(B)(1).
“
Outstanding Construction Allowance ” means, as of any
date, the difference (but not less than zero) of (A) the total
Construction Advances made by or on behalf of BNPPLC on or prior to
such date in question, plus (B) all Carrying Costs, Commitment
Fees, Administrative Fees, Increased Cost Charges and Capital
Adequacy Charges added on or prior to the date as provided in
Paragraph 3, less (C) any funds received and applied as
Qualified Prepayments on or prior to such date.
“
Pre-lease Casualty ” has the meaning indicated in
subparagraph 2(A)(2)(a).
“
Pre-lease Force Majeure Delays ” means delays in the
completion of the Work to the extent (but only to the extent)
caused by a Pre-lease Force Majeure Event.
“
Pre-lease Force Majeure Event ” means a Force Majeure
Event that occurs prior to the Completion Date; provided,
however, that if LRC does not notify BNPPLC of any such Force
Majeure Event by the delivery of a Pre-lease Force Majeure Event
Notice within thirty days after the Force Majeure Event first
occurs or commences, then such Force
Construction
Agreement (Livermore/ Parcel 7) — Page 8
Majeure
Event will not qualify as a “Pre-lease Force Majeure
Event” for purposes of this Agreement or the other Operative
Documents.
“
Pre-lease Force Majeure Event Notice ” has the meaning
indicated in subparagraph 6(B).
“
Pre-lease Force Majeure Excess Costs ” means the
amount (if any) by which the increases in the costs of the Work
resulting directly and solely from a Pre-lease Force Majeure Event
(such as, for example, the costs of repairing damage to the
Improvements caused by a Pre-lease Force Majeure Event) exceed the
amounts available to pay or reimburse LRC for such increased costs.
Amounts available to pay or reimburse such increased costs will
include (a) insurance proceeds or any recovery from a third
party (including any Escrowed Proceeds held by BNPPLC), and
(b) any part of the Construction Allowance (including any
unused contingency amount in the Construction Budget) not used or
needed to cover other Reimbursable Construction Period Costs.
“
Pre-lease Force Majeure Losses ” means any of the
following Losses resulting from any taking of the Property, damage
to the Improvements or disruption of the Work which constitutes a
Pre-lease Force Majeure Event:
(a) the costs of repairing any such
damage to the extent that such costs have, as of the date of any
required determination of Pre-lease Force Majeure Losses, been paid
or reimbursed from a Construction Advance (and thus are included in
the Lease Balance as of that date), to be distinguished from costs
of repairs paid or reimbursed from insurance proceeds or from any
recovery from a third party;
(b) any diminution in the value of
the Property resulting from any such taking or resulting from any
such damage that has not, as of the date of the required
determination of Pre-lease Force Majeure Losses, been
repaired;
(c) any increase in the total amount
of Carrying Costs, Commitment Fees, Administrative Fees, Increased
Cost Charges and Capital Adequacy Charges (and any other amounts)
added to the Lease Balance as provided in Paragraph 3 solely
by reason of Pre-lease Force Majeure Delays; and
(d) to the extent not already
included in the increase described in the preceding clause, all
increases in Carrying Costs that are attributable to the amounts
included in Pre-lease Force Majeure Losses pursuant to the
preceding clause (a);
but in each
case such amounts will constitute Pre-lease Force Majeure Losses
only to the extent, if any, that they are not offset by
condemnation or insurance proceeds which are
Construction
Agreement (Livermore/ Parcel 7) — Page 9
(1) paid
by reason of such Pre-lease Force Majeure Event (including
insurance proceeds paid to compensate BNPPLC or LRC for increased
financing costs, the lost time value of BNPPLC’s investment
in the Project or business interruption) and (2) applied as a
Qualified Prepayment to reduce the Lease Balance.
It is
understood that costs of repairing damage caused by a Pre-lease
Force Majeure Event which are not covered by insurance proceeds by
reason of an insurance policy deductible permitted by the Minimum
Insurance Requirements, and thus are paid or reimbursed from a
Construction Advance instead, will constitute Pre-Lease Force
Majeure Losses.
Also, for
purposes of this definition, the diminution in the value of the
Improvements, as described in the preceding clause (b), because of
any damage that constitutes a Pre-lease Force Majeure Event will
not exceed the amount thereof estimated in good faith by any
independent appraiser or insurance adjuster engaged by BNPPLC to
determine such amount after BNPPLC has received a Pre-lease Force
Majeure Event Notice as provided in subparagraph 6(B), nor will it
exceed the cost of repairing the damage as estimated in good faith
by any such independent insurance adjuster or as indicated by any
bona fide written bid to make the repairs that BNPPLC obtains from
a reputable contractor capable of making the repairs.
“
Prior Work ” has the meaning indicated in subparagraph
4(C)(2)(b).
“
Projected Cost Overruns ” means the excess (if any),
calculated as of the date of each Construction Advance Request, of
(1) the total of projected Reimbursable Construction Period
Costs yet to be incurred or for which LRC has yet to be reimbursed
hereunder (including projected Reimbursable Construction Period
Costs for Future Work), over (2) the balance of the remaining
Construction Allowance then projected to be available to cover such
costs. The balance of the remaining Construction Allowance then
projected to be available will equal: (i) the amount (if any)
by which the Maximum Construction Allowance exceeds the Funded
Construction Allowance, plus (ii) any Escrowed Proceeds
then available or expected to be available to cover costs of
repairs and restoration that LRC will perform as part of the Work
after a casualty or condemnation, less (iii) all
projected future Carrying Costs, Commitment Fees, Administrative
Fees and other amounts to be added to the Outstanding Construction
Allowance as provided in Paragraph 3.
“
Reimbursable Construction Period Costs ” has the
meaning indicated in subparagraph 4(A).
“
Remaining Proceeds ” has the meaning indicated in
subparagraph 5(A).
Construction
Agreement (Livermore/ Parcel 7) — Page 10
“
Scope Change ” means a change to the Construction
Project that, if implemented, will make the quality, function or
capacity of the Improvements “materially different” (as
defined below in this subparagraph) than as described or inferred
by the site plan or plans and renderings referenced in
Exhibit B . The term “ Scope Change
” is not intended to include the mere refinement, correction
or detailing of the site plan, plans or renderings submitted to
BNPPLC by LRC. As used in this definition, a “material
difference” means a difference that could reasonably be
expected to (a) cause the Lease Balance to exceed the fair
market value of the Property when the Construction Project is
completed and all Construction Advances required in connection
therewith have been funded, or significantly increase any such
excess, (b) change the general character of the Improvements
from that needed to accommodate the uses to be permitted by
subparagraph 2(A) of the Lease, or (c) cause or
exacerbate Projected Cost Overruns.
“
Target Completion Date ” means the date which is the
last day of the 18 th calendar month
following the Effective Date, as such date may be extended from
time to time by any Increased Time Commitment made by BNPPLC as
provided in subparagraph 7(B)(6).
“
Termination of LRC’s Work ” means a termination
of LRC’s rights and obligations to continue the Work because
of an election to terminate made by LRC pursuant to subparagraph
7(B) or because of an election by BNPPLC made pursuant to
subparagraph 7(C).
“
Third Party Contract ” has the meaning indicated in
subparagraph 2(A)(2)(b)1).
“
Third Party Contract/Termination Fees ” means any
amounts, however denominated, for which LRC will be obligated under
a Third Party Contract as a result of any election or decision by
LRC to terminate such Third Party Contract, including
demobilization costs; provided, however, amounts payable only by
reason of Prior Work as of the date of any such termination will
not be characterized as Third Party Contract/Termination Fees. If
LRC reserves an absolute express right in a Third Party Contract to
terminate such contract at any time, without cause, for a specified
U.S. dollar amount, such amount will constitute a Third Party
Contract/Termination Fee. If no such right is reserved in a Third
Party Contract, the amount of damages that LRC is required to pay
(in addition to payments required for Prior Work) upon a
repudiation of the Third Party Contract by LRC will qualify as a
“Third Party Contract/Termination Fee” applicable to
such contract for purposes of this Agreement.
“
Timing or Budget Shortfall ” means that, as of any
time prior to the Completion Date, (i) the remaining available
Construction Allowance will not be sufficient to cover
Construction
Agreement (Livermore/ Parcel 7) — Page 11
Reimbursable
Construction Period Costs yet to be paid or reimbursed from
Construction Advances (x) because the cost of the Work exceeds
budgeted expectations (resulting in Projected Cost Overruns)
through no fault of LRC or its employees or any other party acting
under LRC’s control or with the approval or authorization of
LRC, (y) because of any Pre-lease Force Majeure Event or
(z) because LRC can no longer satisfy conditions to
BNPPLC’s obligation to provide further Construction Advances,
or (ii) the Work will not be substantially completed prior to
the Target Completion Date through no fault of LRC or its employees
or any other party acting under LRC’s control or with the
approval or authorization of LRC. As used in this definition with
respect to any party, the term “fault” will not include
inadequate estimation of time or dollars unless shown to be caused
by the negligence or willful misconduct of that party.
“
Work ” has the meaning indicated in subparagraph
2(A)(2)(a).
“
Work/Suspension Event ” means any of the
following:
(1) Projected Cost Overruns have
become more likely than not, in BNPPLC’s good faith judgment
(taking into account any notices or Construction Draw Requests from
LRC indicating that a Pre-lease Force Majeure Event may result in
Projected Cost Overruns), and BNPPLC has notified LRC of such
judgment and the reasons therefor.
(2) Delays in the Work (including any
delays resulting from damage to the Property by fire or other
casualty or from any taking of the Property by eminent domain) have
made it substantially unlikely, in BNPPLC’s good faith
judgment, that LRC will be able to complete the Construction
Project in accordance with the requirements of this Agreement prior
to the Target Completion Date using only the funds available to LRC
under this Agreement, and BNPPLC has notified LRC of such judgment
and the reasons therefor.
(3) With respect to any Construction
Advance, BNPPLC has requested, but LRC has failed to provide within
thirty days after receipt of the request: (1) invoices,
requests for payment from contractors and other evidence reasonably
establishing that the costs and expenses for which LRC has
requested or is requesting reimbursement constitute actual
Reimbursable Construction Period Costs, and (2) canceled
checks, lien waivers or other evidence reasonably establishing that
all prior Construction Advances paid to LRC have been used by LRC
to pay the Reimbursable Construction Period Costs for which the
prior advances were requested and made.
“
Work/Suspension Notice ” means a notice from BNPPLC to
LRC advising LRC of any event or circumstances that constitute a
Work/Suspension Event and advising LRC that (1) before the
Work/Suspension Event is rectified BNPPLC may limit
Construction
Construction
Agreement (Livermore/ Parcel 7) — Page 12
Advances to LRC
as permitted by this Agreement, and (2) unless LRC does
rectify the Work/Suspension Event within thirty days after
LRC’s receipt of such notice, BNPPLC may elect to send an
FOCB Notice in anticipation of a Termination of LRC’s
Work.
“
Work/Suspension Period ” means any period
(1) beginning with the date of any Work/Suspension Notice,
FOCB Notice or Notice of LRC’s Intent to Terminate, and
(2) ending on the earlier of (a) the first date upon
which (i) no Work/Suspension Events are continuing,
(ii) all previous FOCB Notices and Notices of LRC’s
Intent to Terminate (if any) have been rescinded, and (iii) no
97-10/Meltdown Events have occurred, or (b) the effective date
of any Termination of LRC’s Work as described in subparagraph
7(B) or subparagraph 7(C).
|
|
|
| 2 |
|
Construction and
Management of the Property by LRC . |
(A) The
Construction Project .
(1) Construction Approvals by
BNPPLC .
(a) Preconstruction Approvals by
BNPPLC . LRC has submitted and obtained BNPPLC’s approval
of the site plan and descriptions of the Construction Project
referenced in Exhibit B . Also set forth in
Exhibit B is a general description of the Construction
Project. The Construction Project, as constructed by LRC pursuant
to this Agreement, and all construction contracts and other
agreements executed or adopted by LRC in connection therewith, must
not be inconsistent in any material respect with the plans or other
items referenced in Exhibit B , except to the extent
otherwise provided by any Scope Change approved by BNPPLC.
(b) Approval of Scope Changes
. Before making a Scope Change, LRC must provide to BNPPLC a
reasonably detailed written description of the Scope Change, a
revised Construction Budget and a copy of any changes to the
drawings, plans and specifications for the Improvements required in
connection therewith, all of which must be approved in writing by
BNPPLC before the Scope Change is implemented. After receiving such
items, BNPPLC will endeavor in good faith to promptly respond to
any request by LRC for approval of the Scope Change. BNPPLC will
not, however, be liable for any failure to provide a prompt
response. Further, BNPPLC’s approval will not in any event
constitute a waiver of subparagraph 2(A)(3) or of any other
provision of this Agreement or other Operative Documents.
Construction
Agreement (Livermore/ Parcel 7) — Page 13
(2) LRC’s Rights of Access
and to Control Construction . Subject to the terms and
conditions set forth in this Agreement, and prior to any
Termination of LRC’s Work as provided in subparagraphs 7(B)
and 7(C), LRC will have full access to the Land and all
Improvements on the Land to the exclusion of BNPPLC or others
claiming through BNPPLC (except as provided in subparagraph 2(G))
and will have the sole right to control and the sole responsibility
for the design and construction of the Construction Project,
including the means, methods, sequences and procedures implemented
to accomplish such design and construction. Although title to all
Improvements will vest in BNPPLC (as more particularly provided in
subparagraph 2(C)), BNPPLC’s obligation with respect to the
Construction Project will be limited to the making of advances
under and subject to the conditions set forth in this Agreement.
Without limiting the foregoing, LRC acknowledges and agrees
that:
(a) Performance of the Work .
Except as provided in subparagraphs 7(A) and 7(D), LRC must, using
commercially reasonable efforts and in an expeditious and
economical manner not inconsistent with the interests of BNPPLC,
perform or cause to be performed all work required, and must
provide or cause to be provided all supplies and materials
required, to demolish and remove existing Improvements on the
Property (as appropriate to accommodate the new Improvements to be
constructed) and to design and complete construction of the
Construction Project (collectively, the “ Work
”) no later than the Target Completion Date. The Work will
include obtaining all necessary building permits and other
governmental approvals required in connection with the design and
construction of the Construction Project, or required in connection
with the use and occupancy thereof ( e.g., certificates of
occupancy). The Work will also include any repairs or restoration
required because of damage to Improvements by fire or other
casualty prior to the Completion Date (a “ Pre-lease
Casualty ”); provided, however , the cost of any
such repairs or restoration will be subject to reimbursement not
only through Construction Advances made to LRC on and subject to
the terms and conditions of this Agreement, but also through the
application of Escrowed Proceeds as provided in Paragraph 5;
and, provided further , like other Work, any such repairs
and restoration to be provided by LRC will be subject to
subparagraphs 7(A) and 7(B), which establish certain rights of LRC
to suspend or discontinue any Work. LRC will carefully schedule and
supervise all Work, will check all materials and services used in
connection with all Work and will keep full and detailed accounts
as may be necessary to document expenditures made or expenses
incurred for the Work.
(b) Third Party Contracts
.
Construction
Agreement (Livermore/ Parcel 7) — Page 14
1) LRC will not enter into any
construction contract or other agreement with a third party
concerning the Work or the Construction Project (a “ Third
Party Contract ”) in the name of BNPPLC or otherwise
purport to bind BNPPLC to any obligation to any third party.
2) In any Third Party Contract
between LRC and any of its Affiliates (an “
Affiliate’s Contract ”) LRC must reserve the
right to terminate such contract at any time, without cause, and
without subjecting LRC to liability for any Third Party
Contract/Termination Fee. Further, LRC must not enter into any
Affiliate’s Contract that obligates LRC to pay more than
would be required under an arms-length contract or that would
require LRC to pay its Affiliate any amount in excess of the sum of
actual, out-of-pocket direct costs and internal labor costs
incurred by the Affiliate to perform such contract.
(c) Adequacy of Drawings,
Specifications and Budgets . BNPPLC has not made and will not
make any representations as to the adequacy of the Construction
Budget or any other budget or any site plans, renderings, plans,
drawings or specifications for the Construction Project, and no
modification of any such budgets, site plans, renderings, plans,
drawings or specifications that may be required from time to time
will entitle LRC to any adjustment in the Construction
Allowance.
(d) Existing Condition of the Land
and Improvements . LRC is familiar with the conditions of the
Land and any existing Improvements on the Land. LRC will have no
claim for damages against BNPPLC or for an increase in the
Construction Allowance or for an extension of the deadline
specified in subparagraph 2(A)(2)(a) for completing the Work by
reason of any condition (concealed or otherwise) of or affecting
the Land or Improvements.
(e) Correction of Defective
Work . LRC will promptly correct all Work performed prior to
any Termination of LRC’s Work that does not comply with the
requirements of this Agreement for any reason other than a
Pre-lease Casualty (“ Defective Work ”). If LRC
fails to correct any Defective Work or fails to carry out Work in
accordance with this Agreement, BNPPLC may (but will not be
required to) order LRC to stop all Work until the cause for such
failure has been eliminated.
(f) Clean Up . Upon the
completion of all Work, LRC will remove all waste material and
rubbish from and about the Land, as well as all tools, construction
equipment, machinery and surplus materials. LRC will keep the Land
and the Improvements thereon in a reasonably safe and sightly
condition as
Construction
Agreement (Livermore/ Parcel 7) — Page 15
Work
progresses.
(g) No Damage for Delays . LRC
will have no claim for damages against BNPPLC or for an increase in
the Construction Allowance by reason of any delay in the
performance of any Work. Nor will LRC have any claim for an
extension of the deadline specified in subparagraph 2(A)(2)(a) for
completing the Work because of any such period of delay, except
that (i) in the case of any Pre-lease Force Majeure Delays,
LRC will have certain rights as set forth in subparagraph 7(B) and
other provisions of this Agreement, and (ii) in the event of
intentional interference with the Work by BNPPLC itself for which
LRC provides written notice to cease, LRC will be entitled to an
extension of the deadline specified in subparagraph 2(A)(2)(a) as
needed because of any delays resulting from such intentional
interference. It is also understood that any such intentional
interference by BNPPLC will constitute a Force Majeure Event. In no
event, however, will BNPPLC’s exercise of its rights and
remedies permitted under this Agreement or the other Operative
Documents be construed as intentional interference with LRC’s
performance of any Work; and thus neither BNPPLC’s exercise
of its right to withhold Construction Advances at any time when LRC
has failed to satisfy all conditions herein to such advances, nor
BNPPLC’s exercise of its right to terminate Work by LRC as
provided in subparagraph 7(C), be considered as intentional
interference with the Work or a Pre-lease Force Majeure
Event.
(h) No Other Fees to LRC .
Except as provided in the next subparagraph, LRC will have no claim
under this Agreement for any fee or other compensation or for any
reimbursement of internal administrative or overhead expenses
(other than the out-of-pocket overhead expenses properly included
in the Construction Budget, if any), it being understood that LRC
is executing this Agreement in consideration of the rights
expressly granted to it herein and in the other Operative
Documents.
(i) Administration of Existing
Space Leases . Prior to any Termination of LRC’s Work,
LRC’s rights under this Agreement will extend to and include
the right to enforce and administer Existing Space Leases and to
receive and enjoy all benefits conferred upon BNPPLC by the
Existing Space Leases, including the right to receive rents
thereunder as they become due. Without limiting the foregoing, LRC
may (on behalf of BNPPLC) exercise any right to terminate any
Existing Space Lease provided therein in the event of a default by
the tenant thereunder. LRC must apply all rents paid to it under
the Existing Space Leases prior to the Completion Date in the
following order: (A) first, to pay on behalf of BNPPLC the
management fee due to LRC as described
Construction
Agreement (Livermore/ Parcel 7) — Page 16
below in this
subparagraph; (B) second, to pay any costs incurred to provide
maintenance or repairs or services, if any, required of the
landlord by the Existing Space Leases; (C) third, to reimburse
BNPPLC for any Losses it may incur with respect to the Property or
this Agreement, other than Covered Construction Period Losses for
which BNPPLC is entitled to be indemnified by LRC pursuant to this
Agreement. LRC must also pay any such rents not otherwise applied
as provided in the preceding sentence, or needed by LRC to pay
amounts described in the preceding sentence, over to BNPPLC for
application as a Qualified Prepayment. As compensation for
administering the Existing Space Leases during each calendar month
or portion thereof after the Effective Date and prior to the
Completion Date or any Termination of LRC’s Work, LRC will be
entitled to the payment by or on behalf of BNPPLC of a management
fee of three percent (3%) of the rents payable (whether or not
collected) under the Existing Space Leases for such calendar month
or portion thereof.
(3) Quality of Work . LRC will
cause the Work undertaken and administered by it pursuant to this
Agreement to be performed (a) in a safe and good and
workmanlike manner, (b) in accordance with Applicable Laws,
and (c) in compliance with the provisions of this Agreement
and the material provisions of the Permitted Encumbrances.
(B) Completion Notice .
Within fifteen Business Days after LRC substantially completes
construction of the Construction Project and obtains any
certificate of occupancy or other permit (temporary or permanent)
required by Applicable Laws for the commencement of LRC’s use
and occupancy of the Improvements, LRC must provide a notice (a
“ Completion Notice ”) to BNPPLC, advising
BNPPLC thereof, and thereby establish the Completion Date. For
purposes of this Agreement and the other Operative Documents,
BNPPLC will be entitled to rely without investigation upon any such
notice given by LRC as evidence that LRC has, in fact,
substantially completed the Construction Project and has obtained
any certificate of occupancy or other permit (temporary or
permanent) required for the commencement of LRC’s use of the
Improvements, and after giving any such notice LRC will be estopped
from later claiming that the Completion Date has not
occurred.
(C) Status of Property
Acquired With BNPPLC’s Funds . All Improvements
constructed on the Land as provided in this Agreement will
constitute “Property” for purposes of the Lease and
other Operative Documents. Further, to the extent heretofore or
hereafter acquired (in whole or in part) with any portion of the
Initial Advance or with any Construction Advances or with other
funds for which LRC receives reimbursement from the Initial Advance
or Construction Advances, all furnishings, furniture, chattels,
permits, licenses, franchises, certificates and other personal
property of whatever nature will be considered as having been
acquired on behalf of BNPPLC by LRC and will constitute
“Property” for purposes of the Lease and other
Operative Documents, as will all renewals or replacements of or
substitutions for any
Construction
Agreement (Livermore/ Parcel 7) — Page 17
such
Property. The parties intend that title to the Improvements and to
any other such Property will vest in BNPPLC without passing through
LRC or LRC’s Affiliates before it is transferred to BNPPLC
from contractors, suppliers, vendors or other third Persons, but
with the understanding that all such Property will be accepted by
BNPPLC subject to the terms and conditions of the other Operative
Documents, including subparagraph 4(C)(1) of the Lease
(concerning the characterization of the Lease and other Operative
Documents for tax and certain other purposes). Although nothing
herein constitutes authorization of LRC by BNPPLC to bind BNPPLC to
any construction contract or other agreement with a third Person,
any construction contract or other agreement executed by LRC for
the acquisition or construction of Improvements or other components
of the Property may, as LRC deems appropriate, provide for the
direct transfer of title to BNPPLC as described in the preceding
sentence.
(D) Insurance .
(1) Liability Insurance .
Throughout the period prior to any Termination of LRC’s Work,
LRC must maintain commercial general liability insurance against
claims for bodily and personal injury, death and property damage
occurring in or upon or resulting from any occurrence in or upon
the Property under one or more insurance policies that satisfy the
Minimum Insurance Requirements, which are set forth in an exhibit
to the Common Definitions and Provisions Agreement. LRC must
deliver and maintain with BNPPLC for each liability insurance
policy required by this Agreement written confirmation of the
policy and the scope of the coverage provided thereby issued by the
applicable insurer or its authorized agent, which confirmation must
also satisfy the Minimum Insurance Requirements.
(2) Property Insurance .
Throughout the period prior to any Termination of LRC’s Work,
LRC must also keep all Improvements (including all alterations,
additions and changes made to the Improvements) insured against
fire and other casualty under one or more property insurance
policies that satisfy the Minimum Insurance Requirements. LRC must
deliver and maintain with BNPPLC for each property insurance policy
required by this Agreement written confirmation of the policy and
the scope of the coverage provided thereby issued by the applicable
insurer or its authorized agent, which confirmation must also
satisfy the Minimum Insurance Requirements. If any of the Property
is destroyed or damaged by fire, explosion, windstorm, hail or by
any other casualty against which insurance has been required
hereunder, (i) BNPPLC may, but will not be obligated to, make
proof of loss if not made promptly by LRC after notice from BNPPLC,
(ii) each insurance company concerned is hereby authorized and
directed to make payment for such loss directly to BNPPLC for
application as required by Paragraph 5, and (iii) BNPPLC
may settle, adjust or compromise any and all claims for loss,
damage or destruction under any policy or policies of insurance
(provided, that so long as no 97-10/Meltdown Event has occurred and
no Event of Default has occurred and
Construction
Agreement (Livermore/ Parcel 7) — Page 18
is continuing,
BNPPLC must provide LRC with at least forty-five days notice of
BNPPLC’s intention to settle any such claim before settling
it unless LRC has already approved of the settlement by BNPPLC).
BNPPLC will not in any event or circumstances be liable or
responsible for failure to collect, or to exercise diligence in the
collection of, any insurance proceeds. If any casualty results in
damage to or loss or destruction of the Property, LRC must give
prompt notice thereof to BNPPLC and Paragraph 5 will
apply.
(3) Failure of LRC to Obtain
Insurance . If LRC fails to obtain any insurance or to provide
confirmation of any insurance as required by this Agreement, BNPPLC
will be entitled (but not required) to obtain the insurance that
LRC has failed to obtain or for which LRC has not provided the
required confirmation and, without limiting BNPPLC’s other
remedies under the circumstances, BNPPLC may charge the cost of
such insurance against the Construction Allowance as if it were a
Construction Advance paid to LRC as hereinafter provided.
(4) Waiver of Subrogation .
LRC, for itself and for any Person claiming through it (including
any insurance company claiming by way of subrogation), waives any
and every claim which arises or may arise in its favor against
BNPPLC or any other Interested Party for any and all Losses, to the
extent that LRC is compensated by insurance or would be compensated
by the insurance policies contemplated in this Agreement, but for
any deductible or self-insured retention maintained under such
insurance or but for a failure of LRC to maintain the insurance as
required by this Agreement. LRC agrees to have such insurance
policies properly endorsed so as to make them valid notwithstanding
this waiver, if such endorsement is required to prevent a loss of
insurance.
(E) Condemnation .
Immediately upon obtaining knowledge of the institution of any
proceedings for the condemnation of the Property or any portion
thereof, or any other similar governmental or quasi-governmental
proceedings arising out of injury or damage to the Property or any
portion thereof, each party must promptly notify the other
(provided, however, BNPPLC will have no liability for its failure
to provide such notice) of the pendency of such proceedings. Prior
to any Termination of LRC’s Work, LRC must, if requested by
BNPPLC, diligently prosecute any such proceedings and consult with
BNPPLC, its attorneys and experts and cooperate with them as
reasonably requested in the carrying on or defense of any such
proceedings. All proceeds of condemnation awards or proceeds of
sale in lieu of condemnation with respect to the Property and all
judgments, decrees and awards for injury or damage to the Property
will be paid to BNPPLC as Escrowed Proceeds, and all such proceeds
will be applied as provided in Paragraph 5. BNPPLC is hereby
authorized, in its own name or in the name of LRC or in the name of
both, to settle and deliver valid acquittances for, or to challenge
and to appeal from, any such judgment, decree or award concerning
condemnation of any of the
Construction
Agreement (Livermore/ Parcel 7) — Page 19
Property
(provided, that so long as no 97-10/Meltdown Event has occurred and
no Event of Default has occurred and is continuing, BNPPLC must
provide LRC with at least forty-five days notice of BNPPLC’s
intention to settle any such claim before settling it unless LRC
has already approved of the settlement by BNPPLC). BNPPLC will not
in any event or circumstances be liable or responsible for failure
to collect, or to exercise diligence in the collection of, any such
proceeds, judgments, decrees or awards.
(F) Additional
Representations, Warranties and Covenants of LRC Concerning the
Property . Without limiting the rights granted to LRC by other
provisions of this Agreement to be reimbursed from Construction
Advances for the cost of complying with the following, LRC
represents, warrants and covenants as follows:
(1) Payment of Local
Impositions . Throughout the period prior to any Termination of
LRC’s Work, LRC must pay or cause to be paid prior to
delinquency all ad valorem taxes assessed against the Property and
other Local Impositions. If requested by BNPPLC from time to time,
LRC will furnish BNPPLC with receipts or other appropriate evidence
showing payment of all Local Impositions prior to the applicable
delinquency date therefor.
Notwithstanding
the foregoing, LRC may in good faith, by appropriate proceedings,
contest the validity, applicability or amount of any asserted Local
Imposition, and pending such contest LRC will not be deemed in
default under any of the provisions of this Agreement because of
the Local Imposition if (1) LRC diligently prosecutes such
contest to completion in a manner reasonably satisfactory to
BNPPLC, and (2) LRC promptly causes to be paid any amount
adjudged by a court of competent jurisdiction to be due, with all
costs, penalties and interest thereon, promptly after such judgment
becomes final; provided, however, in any event each such contest
must be concluded and the contested Local Impositions must be paid
by LRC prior to the earlier of (i) the date that any criminal
prosecution is instituted or overtly threatened against BNPPLC or
its directors, officers or employees because of the nonpayment
thereof, or (ii) the date any writ or order is issued under
which any property owned or leased by BNPPLC (including the
Property) may be seized or sold or any other action is taken or
overtly threatened against BNPPLC or against any property owned or
leased by BNPPLC because of the nonpayment thereof, or
(iii) any Designated Sale Date upon which, for any reason, LRC
or an Affiliate of LRC or any Applicable Purchaser does not
purchase BNPPLC’s interest in the Property pursuant to the
Purchase Agreement for a price to BNPPLC (when taken together with
any Supplemental Payment paid by LRC pursuant to the Purchase
Agreement, in the case of a purchase by an Applicable Purchaser)
equal to the Break Even Price.
(2) Operation and Maintenance
. Throughout the period prior to any
Construction
Agreement (Livermore/ Parcel 7) — Page 20
Termination of
LRC’s Work, LRC must operate and maintain the Property in a
good and workmanlike manner and in compliance with Applicable Laws
and Existing Space Leases in all material respects and pay or cause
to be paid all fees or charges of any kind in connection therewith.
(If LRC does not promptly correct any failure of the Property to
comply with Applicable Laws that is the subject of a written
complaint or demand for corrective action given by any Governmental
Authority to LRC, or to BNPPLC and forwarded by it to LRC, then for
purposes of the preceding sentence, LRC will be considered not to
have maintained the Property “in compliance with all
Applicable Laws in all material respects” whether or not the
noncompliance would be material in the absence of the complaint or
demand.) LRC must not use or occupy, or allow the use or occupancy
of, the Property in any manner which violates any Applicable Law or
which constitutes a public or private nuisance or which makes void,
voidable or cancelable any insurance then in force with respect
thereto. Without limiting the generality of the foregoing, LRC must
not conduct or permit others to conduct Hazardous Substance
Activities on the Property, except Permitted Hazardous Substance
Use and Remedial Work; and LRC must not discharge or permit the
discharge of anything (including Permitted Hazardous Substances) on
or from the Property that would require any permit under applicable
Environmental Laws, other than (1) storm water runoff,
(2) fume hood emissions, (3) waste water discharges
through a publicly owned treatment works, (4) discharges that
are a necessary part of any Remedial Work, and (5) other similar
discharges consistent with the definition of Permitted Hazardous
Substance Use which do not significantly increase the risk of
Environmental Losses to BNPPLC, in each case in compliance with
Environmental Laws. To the extent that any of the following would,
individually or in the aggregate, increase the likelihood of a
97-10/Meltdown Event or materially and adversely affect the value
of the Property or the use of the Property for purposes permitted
by this Agreement, LRC must not, without BNPPLC’s prior
consent: (i) initiate or permit any zoning reclassification of the
Property; (ii) seek any variance under existing zoning
ordinances applicable to the Property; (iii) use or permit the
use of the Property in a manner that would result in such use
becoming a nonconforming use under applicable zoning ordinances or
similar laws, rules or regulations; (iv) execute or file any
subdivision plat affecting the Property; or (v) consent to the
annexation of the Property to any municipality. LRC will not cause
or permit any drilling or exploration for, or extraction, removal
or production of, minerals from the surface or subsurface of the
Property, and LRC must not do anything that could reasonably be
expected to significantly reduce the market value of the Property.
If LRC receives a notice or claim from any federal, state or other
Governmental Authority that the Property is not in compliance with
any Applicable Law, or that any action may be taken against BNPPLC
because the Property does not comply with any Applicable Law, LRC
must promptly furnish a copy of such notice or claim to
BNPPLC.
(3) Debts for Construction,
Maintenance, Operation or Development . LRC
Construction
Agreement (Livermore/ Parcel 7) — Page 21
must promptly
pay or cause to be paid all debts and liabilities incurred by it or
its contractors or subcontractors in the construction, maintenance,
operation or development of the Property. Such debts and
liabilities will include those incurred for labor, material and
equipment and all debts and charges for utilities servicing the
Property.
(4) Permitted Encumbrances .
LRC must comply with and will cause to be performed all of the
covenants, agreements and obligations imposed upon the owner of any
interest in the Property by the Permitted Encumbrances throughout
the period prior to any Termination of LRC’s Work. LRC must
not, without the prior consent of BNPPLC, enter into, initiate,
approve or consent to any modification of any Permitted Encumbrance
that would create or expand or purport to create or expand
obligations or restrictions encumbering BNPPLC’s interest in
the Property.
(5) Books and Records Concerning
the Property . LRC must keep books and records that are
accurate and complete in all material respects for LRC’s
construction and management of the Property as contemplated in this
Agreement and must permit all such books and records (including all
contracts, statements, invoices, bills and claims for labor,
materials and services supplied for the construction and operation
of any Improvements) to be inspected and copied by BNPPLC during
reasonable business hours.
(G) BNPPLC’s Right of
Access .
(1) Access Generally . BNPPLC
and BNPPLC’s representatives may enter the Property at any
time after reasonable prior notice to LRC for the purpose of making
inspections or performing any work BNPPLC is authorized to
undertake by the next subparagraph or for the purpose of confirming
whether LRC has complied with the requirements of this Agreement or
the other Operative Documents.
(2) Failure of LRC to Perform
. If LRC fails to perform any act or to take any action required of
it by this Agreement or other Operative Documents, or to pay any
money which LRC is required by this Agreement or other Operative
Documents to pay, then in addition to any other remedies specified
herein or otherwise available, BNPPLC may, perform or cause to be
performed such act or take such action or pay such money. (To the
extent that expenses so incurred by BNPPLC, or money so paid by
BNPPLC, qualify as Covered Construction Period Losses, LRC must pay
the same to BNPPLC upon demand. If any such expenses incurred or
money paid do not qualify as Covered Construction Period Losses,
they will be included - with interest — in the Balance of
Unpaid Covered Construction Period Losses under and as defined in
the Purchase Agreement.) Further, BNPPLC, upon making such payment,
will be subrogated to all of the rights of the person, corporation
or body politic receiving such payment. But nothing herein will
imply any duty upon the part of BNPPLC to do any work which, under
any
Construction
Agreement (Livermore/ Parcel 7) — Page 22
provision of
this Agreement or otherwise, LRC may be required to perform, and
the performance thereof by BNPPLC will not constitute a waiver of
LRC’s default. BNPPLC may during the progress of any such
work permitted by BNPPLC hereunder on or in the Property keep and
store upon the Property all necessary materials, to
|