Exhibit 10.56
CONSTRUCTION AGREEMENT
BETWEEN
NETWORK APPLIANCE, INC.
(“NAI”)
AND
BNP PARIBAS LEASING CORPORATION
(“BNPPLC”)
July 17, 2007
TABLE OF CONTENTS
| |
|
|
|
|
| |
|
Page |
|
|
ENGAGEMENT AND
AUTHORIZATION
|
|
|
1 |
|
|
GENERAL TERMS
AND CONDITIONS
|
|
|
2 |
|
|
1
Additional
definitions
|
|
|
2 |
|
|
“97-10/Maximum Permitted Prepayment”
|
|
|
2 |
|
|
“97-10/Meltdown Event”
|
|
|
2 |
|
|
“97-10/Prepayment”
|
|
|
3 |
|
|
“97-10/Project Costs”
|
|
|
3 |
|
|
“97-10/Pronouncement”
|
|
|
4 |
|
|
“NAI’s Estimate of Force Majeure
Delays”
|
|
|
4 |
|
|
“NAI’s Estimate of Force Majeure Excess
Costs”
|
|
|
4 |
|
|
“Accrued
Construction Period Interest Expense”
|
|
|
4 |
|
|
“Administrative Fee”
|
|
|
5 |
|
|
“Affiliate’s Contract”
|
|
|
5 |
|
|
“Arrangement Fee”
|
|
|
5 |
|
|
“Capital
Adequacy Charges”
|
|
|
5 |
|
|
“Carrying
Costs”
|
|
|
5 |
|
|
“Commitment Fee Rate”
|
|
|
5 |
|
|
“Commitment Fees”
|
|
|
6 |
|
|
“Complete
Taking”
|
|
|
6 |
|
|
“Completion Date”
|
|
|
6 |
|
|
“Completion Notice”
|
|
|
6 |
|
|
“Construction Advances”
|
|
|
6 |
|
|
“Construction Advance Request”
|
|
|
6 |
|
|
“Construction Allowance”
|
|
|
7 |
|
|
“Construction Budget”
|
|
|
7 |
|
|
“Construction Project”
|
|
|
7 |
|
|
“Covered
Construction Period Losses”
|
|
|
7 |
|
|
“Defective Work”
|
|
|
7 |
|
|
“FOCB
Notice”
|
|
|
7 |
|
|
“Force
Majeure Event”
|
|
|
8 |
|
|
“Funded
Construction Allowance”
|
|
|
8 |
|
|
“Future
Work”
|
|
|
8 |
|
|
“Ground
Lease Rents”
|
|
|
8 |
|
|
“Increased Cost Charges”
|
|
|
8 |
|
|
“Increased Commitment”
|
|
|
8 |
|
|
“Increased Funding Commitment”
|
|
|
8 |
|
|
“Increased Time Commitment”
|
|
|
8 |
|
|
“Initial
Advance”
|
|
|
8 |
|
|
“Maximum
Construction Allowance”
|
|
|
8 |
|
|
“Notice
of NAI’s Intent to Terminate”
|
|
|
8 |
|
|
“Notice
of NAI’s Intent to Terminate Because of a Force Majeure
Event”
|
|
|
8 |
|
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
| |
|
Page |
|
|
“Notice
of Termination by NAI”
|
|
|
9 |
|
|
“Outstanding Construction Allowance”
|
|
|
9 |
|
|
“Owner’s Election to Continue
Construction”
|
|
|
9 |
|
|
“Pre-lease Casualty”
|
|
|
9 |
|
|
“Pre-lease Force Majeure Delays”
|
|
|
9 |
|
|
“Pre-lease Force Majeure Event”
|
|
|
9 |
|
|
“Pre-lease Force Majeure Event Notice”
|
|
|
9 |
|
|
“Pre-lease Force Majeure Excess Costs”
|
|
|
9 |
|
|
“Pre-lease Force Majeure Losses”
|
|
|
9 |
|
|
“Prior
Work”
|
|
|
10 |
|
|
“Projected Cost Overruns”
|
|
|
10 |
|
|
“Reimbursable Construction Period Costs”
|
|
|
11 |
|
|
“Remaining Proceeds”
|
|
|
11 |
|
|
“Scope
Change”
|
|
|
11 |
|
|
“Target
Completion Date”
|
|
|
11 |
|
|
“Termination of NAI’s Work”
|
|
|
11 |
|
|
“Third
Party Contract”
|
|
|
11 |
|
|
“Third
Party Contract/Termination Fees”
|
|
|
12 |
|
|
“Timing
or Budget Shortfall”
|
|
|
12 |
|
|
“Work”
|
|
|
12 |
|
|
“Work/Suspension Event”
|
|
|
12 |
|
|
“Work/Suspension Notice”
|
|
|
13 |
|
|
“Work/Suspension Period”
|
|
|
13 |
|
|
2 Construction and Management of the
Property by NAI
|
|
|
14 |
|
|
(A) The
Construction Project
|
|
|
14 |
|
|
(1) Construction Approvals by BNPPLC
|
|
|
14 |
|
|
(a)Preconstruction
Approvals by BNPPLC
|
|
|
14 |
|
|
(b)Approval of
Scope Changes
|
|
|
14 |
|
|
(2) NAI’s Right to Possession and to Control
Construction
|
|
|
14 |
|
|
(a)Performance of
the Work
|
|
|
15 |
|
|
(b)Third Party
Contracts
|
|
|
15 |
|
|
(c)Adequacy of
Drawings, Specifications and Budgets
|
|
|
16 |
|
|
(d)Existing
Condition of the Land and Improvements
|
|
|
16 |
|
|
(e)Correction of
Defective Work
|
|
|
16 |
|
|
(f)Clean Up
|
|
|
16 |
|
|
(g)No Damage for
Delays
|
|
|
16 |
|
|
(h)No Fee For
Construction Management
|
|
|
17 |
|
|
(3) Quality
of Work
|
|
|
17 |
|
|
(B) Completion Notice
|
|
|
17 |
|
|
(C) Status of
Property Acquired With BNPPLC’s Funds
|
|
|
17 |
|
(ii)
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
| |
|
Page |
|
|
(D) Insurance
|
|
|
18 |
|
|
(1) Liability
Insurance
|
|
|
18 |
|
|
(2) Property
Insurance
|
|
|
18 |
|
|
(3) Failure of NAI
to Obtain Insurance
|
|
|
19 |
|
|
(4) Waiver of
Subrogation
|
|
|
19 |
|
|
(E) Condemnation
|
|
|
19 |
|
|
(F) Additional Representations, Warranties and Covenants of
NAI Concerning the Property
|
|
|
20 |
|
|
(1) Payment
of Local Impositions
|
|
|
20 |
|
|
(2) Operation
and Maintenance
|
|
|
21 |
|
|
(3) Debts for
Construction, Maintenance, Operation or Development
|
|
|
22 |
|
|
(4) Permitted
Encumbrances and the Ground Lease
|
|
|
22 |
|
|
(5) Books and
Records Concerning the Property
|
|
|
22 |
|
|
(G) BNPPLC’s Right of Access
|
|
|
22 |
|
|
(1) Access
Generally
|
|
|
22 |
|
|
(2) Failure
of NAI to Perform
|
|
|
23 |
|
|
3 Amounts to be Added to the Lease
Balance (in Addition to Construction Advances)
|
|
|
23 |
|
|
(A) Initial
Advance
|
|
|
24 |
|
|
(B) Carrying
Costs
|
|
|
25 |
|
|
(C) Commitment Fees
|
|
|
25 |
|
|
(D) Future
Administrative Fees and Out-of-Pocket Costs
|
|
|
26 |
|
|
(E) Increased
Cost Charges and Capital Adequacy Charges
|
|
|
26 |
|
|
(F) Ground
Lease Payments
|
|
|
27 |
|
|
4 Construction
Advances
|
|
|
27 |
|
|
(A) Costs
Subject to Reimbursement Through Construction Advances
|
|
|
27 |
|
|
(B) Exclusions From Reimbursable Construction Period
Costs
|
|
|
29 |
|
|
(C) Conditions to NAI’s Right to Receive Construction
Advances
|
|
|
29 |
|
|
(1) Construction
Advance Requests
|
|
|
29 |
|
|
(2) Amount of the
Advances
|
|
|
30 |
|
|
(a) The Maximum
Construction Allowance
|
|
|
30 |
|
|
(b) Costs
Previously Incurred by NAI
|
|
|
30 |
|
|
(c) Limits During
any Work/Suspension Period
|
|
|
31 |
|
|
(d) Restrictions
Imposed for Administrative Convenience
|
|
|
31 |
|
|
(3) No Advances
After Certain Dates
|
|
|
31 |
|
|
(D) Breakage
Costs for Construction Advances Requested But Not Taken
|
|
|
31 |
|
|
(E) No Third
Party Beneficiaries
|
|
|
32 |
|
|
(F) No
Waiver
|
|
|
32 |
|
|
5 Application of Insurance and
Condemnation Proceeds
|
|
|
32 |
|
|
(A) Collection and Application Generally
|
|
|
32 |
|
(iii)
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
|
|
|
|
|
|
| |
|
(B) |
|
Advances of Escrowed
Proceeds to NAI |
|
|
33 |
|
| |
|
(C) |
|
Status of Escrowed
Proceeds After Commencement of the Term of the Lease |
|
|
33 |
|
| |
|
(D) |
|
Special Provisions
Applicable After a 97-10/Meltdown Event or Event of Default |
|
|
33 |
|
| |
|
(E) |
|
NAI’s Obligation to
Restore |
|
|
33 |
|
| |
|
(F) |
|
Special Provisions
Concerning a Complete Taking |
|
|
34 |
|
| 6 |
|
Notice of Cost Overruns and Pre-lease
Force Majeure Events |
|
|
34 |
|
| |
|
(A) |
|
Notice of Projected Cost
Overruns |
|
|
34 |
|
| |
|
(B) |
|
Pre-lease Force Majeure
Event Events and Notices |
|
|
34 |
|
| 7 |
|
Suspension and Termination of
NAI’s Work |
|
|
34 |
|
| |
|
(A) |
|
Rights and Obligations
During a Work/Suspension Period |
|
|
34 |
|
| |
|
(B) |
|
NAI’s Election to
Terminate NAI’s Work |
|
|
34 |
|
| |
|
(C) |
|
BNPPLC’s Election
to Terminate NAI’s Work |
|
|
38 |
|
| |
|
(D) |
|
Surviving Rights and
Obligations |
|
|
38 |
|
| |
|
(E) |
|
Cooperation After a
Termination of NAI’s Work |
|
|
38 |
|
| 8 |
|
Continuation of Construction by
BNPPLC |
|
|
40 |
|
| |
|
(A) |
|
Owner’s Election to
Continue Construction |
|
|
40 |
|
|
|
|
|
|
(1) |
|
Take Control of the Property |
|
|
40 |
|
|
|
|
|
|
(2) |
|
Continuation of Construction |
|
|
40 |
|
|
|
|
|
|
(3) |
|
Arrange for Turnkey Construction |
|
|
41 |
|
|
|
|
|
|
(4) |
|
Suspension or Termination of
Construction by BNPPLC |
|
|
41 |
|
| |
|
(B) |
|
Powers Coupled With an
Interest |
|
|
42 |
|
| 9 |
|
NAI’s Obligation for
97-10/Prepayments |
|
|
42 |
|
| 10 |
|
Indemnity for Covered Construction
Period Losses |
|
|
43 |
|
| |
|
(A) |
|
Covenant to Indemnify
Against Covered Construction Period Losses |
|
|
43 |
|
| |
|
(B) |
|
Certain Losses Included
or Excluded |
|
|
44 |
|
|
|
|
|
|
(1) |
|
Environmental |
|
|
44 |
|
|
|
|
|
|
(2) |
|
Failure to Maintain a Safe Work
Site |
|
|
44 |
|
|
|
|
|
|
(3) |
|
Failure to Complete
Construction |
|
|
45 |
|
|
|
|
|
|
(4) |
|
Fraud |
|
|
45 |
|
|
|
|
|
|
(5) |
|
Excluded Taxes and Established
Misconduct |
|
|
45 |
|
| |
|
(C) |
|
Express Negligence
Protection |
|
|
45 |
|
| |
|
(D) |
|
Survival of
Indemnity |
|
|
46 |
|
| |
|
(E) |
|
Due Date for Indemnity
Payments |
|
|
46 |
|
| |
|
(F) |
|
Order of Application of
Payments |
|
|
46 |
|
| |
|
(G) |
|
Defense of BNPPLC |
|
|
46 |
|
|
|
|
|
|
(1) |
|
Assumption of Defense |
|
|
46 |
|
|
|
|
|
|
(2) |
|
Indemnity Not Contingent |
|
|
46 |
|
| |
|
(H) |
|
Notice of Claims |
|
|
47 |
|
| |
|
(I) |
|
Withholding of Consent to
Settlements Proposed by NAI |
|
|
47 |
|
| |
|
(J) |
|
Settlements Without the
Prior Consent of NAI |
|
|
47 |
|
(iv)
TABLE OF CONTENTS
(Continued)
| |
|
|
|
|
| |
|
Page |
|
|
(1)
Election to Pay Reasonable Settlement Costs in Lieu of
Actual
|
|
|
47 |
|
|
(2)
Conditions to Election
|
|
|
48 |
|
|
(3)
Indemnity Survives Settlement
|
|
|
48 |
|
|
(K) No
Authority to Admit Wrongdoing on the Part of NAI
|
|
|
48 |
|
|
(L) Refunds
of Covered Construction Period Losses Paid by NAI
|
|
|
49 |
|
|
(1)
Payment by BNPPLC After Refund
|
|
|
49 |
|
|
(2)
Meaning of Refund
|
|
|
49 |
|
|
(3)
Conditions to Payment
|
|
|
50 |
|
Exhibits and Schedules
| |
|
|
|
|
|
Exhibit A
|
|
Legal Description |
|
Exhibit B
|
|
Description of the
Construction Project and Budget |
|
Exhibit C
|
|
Construction Advance
Request Form |
|
Exhibit D
|
|
Pre-lease Force Majeure
Event Notice |
|
Exhibit E
|
|
Notice of Termination by
NAI's Work |
|
Exhibit F
|
|
Notice of NAI's Intent
to Terminate |
|
Exhibit G
|
|
Notice of Increased
Funding Commitment by BNPPLC |
|
Exhibit H
|
|
Notice of Increased Time
Commitment by BNPPLC |
|
Exhibit I
|
|
Notice of Rescission of
NAI's Intent to Terminate |
(v)
CONSTRUCTION AGREEMENT
This CONSTRUCTION AGREEMENT (this
“ Agreement ”), dated as of July 17, 2007
(the “ Effective Date ”), is made by and between
BNP PARIBAS LEASING CORPORATION (“ BNPPLC ”), a
Delaware corporation, and NETWORK APPLIANCE, INC. (“
NAI ”), a Delaware corporation.
RECITALS
Contemporaneously with the execution
of this Agreement, BNPPLC and NAI are executing a Common
Definitions and Provisions Agreement dated as of the Effective Date
(the “ Common Definitions and Provisions Agreement
”), which by this reference is incorporated into and made a
part of this Agreement for all purposes. As used in this
Agreement, capitalized terms defined in the Common Definitions and
Provisions Agreement and not otherwise defined in this Agreement
are intended to have the respective meanings assigned to them in
the Common Definitions and Provisions Agreement.
At the request of NAI and to
facilitate the transaction contemplated in the other Operative
Documents, contemporaneously with this Agreement BNPPLC is
executing and accepting a Ground Lease from NAI (the “
Ground Lease ”), pursuant to which BNPPLC is acquiring
a leasehold estate in the Land described in Exhibit A
and any existing Improvements on such Land.
Also contemporaneously with this
Agreement, BNPPLC and NAI are executing a Lease Agreement (the
“ Lease ”), pursuant to which the parties expect
that NAI will lease the Improvements on the Land described in
Exhibit A from BNPPLC for a lease term that will
commence on the Completion Date (as defined below).
In anticipation of the construction
of new or additional Improvements for NAI’s use pursuant to
the Lease, BNPPLC and NAI have agreed upon the terms and conditions
upon which BNPPLC is willing to authorize NAI to arrange and manage
such construction and upon which BNPPLC is willing to provide funds
for such construction, and by this Agreement BNPPLC and NAI desire
to evidence such agreement.
ENGAGEMENT AND AUTHORIZATION
Subject to the terms and conditions
set forth in this Agreement, BNPPLC does hereby engage and
authorize NAI — and NAI does hereby accept such engagement
and authorization, as an independent contractor for BNPPLC —
to construct the Construction Project on the Land and to manage
such construction for BNPPLC. As more particularly provided in
subparagraph 2(A)(2) below, NAI will take possession and control of
the Land and all
Improvements on the Land to accomplish such construction. However,
the rights and authority granted to NAI by this Agreement are
expressly made subject and subordinate to the terms and condition
hereinafter set forth and to the Ground Lease, to the Permitted
Encumbrances and to any other claims or encumbrances affecting the
Land or the Property that may be asserted by third parties other
than Liens Removable by BNPPLC.
GENERAL TERMS AND CONDITIONS
1
Additional
definitions . As used in this Agreement, capitalized
terms defined above will have the respective meanings assigned to
them above; as indicated above, capitalized terms that are defined
in the Common Definitions and Provisions Agreement and that are
used but not defined herein will have the respective meanings
assigned to them in the Common Definitions and Provisions
Agreement; and, the following terms will have the following
respective meanings:
“
97-10/Maximum Permitted Prepayment ” as of any date
means the amount equal to eighty-nine and nine-tenths of one
percent (89.9%) of the aggregate of all 97-10/Project Costs paid or
incurred on or prior to such date.
“
97-10/Meltdown Event ” means any of the
following:
(a) NAI gives a Notice of NAI’s
Intent to Terminate and thereafter (i) fails to rescind the same as
described in subparagraph 7(B)(7) within ten days after BNPPLC
responds with any Increased Commitment, or (ii) gives a Notice
of Termination by NAI as provided in subparagraph 7(B)(1); or
(b) NAI gives a notice to terminate
its Supplemental Payment Obligation under the Purchase Agreement as
described in subparagraph 6(B) of the Purchase Agreement;
or
(c) BNPPLC gives notice to NAI as
described in subparagraph 7(C) to cause a Termination of
NAI’s Work; or
(d) NAI fails for any reason
whatsoever to substantially complete the Construction Project and
give a Completion Notice to BNPPLC prior to the Target Completion
Date; or
(e) for any reason whatsoever
(including the accrual of Carrying Costs), the Funded Construction
Allowance exceeds the Maximum Construction Allowance.
Construction Agreement - Page 2
“
97-10/Prepayment ” means any payment to BNPPLC
required by Paragraph 9, which in each case will equal
(A) the 97-10/Maximum Permitted Prepayment, computed as of the
date on which the payment becomes due, less (B) the sum of
(1) the accreted value of any prior payments actually received
by BNPPLC from NAI constituting 97-10/Prepayments, and
(2) amounts (if any) then owed by BNPPLC to NAI pursuant to
this Agreement as reimbursements for Reimbursable Construction
Period Costs paid by NAI and not theretofore reimbursed. For
purposes of the preceding sentence, “accreted value” of
a payment means the amount of the payment plus an amount equal to
the interest that would have accrued on the payment if it bore
interest at the Effective Rate plus the Spread.
“
97-10/Project Costs ” means the following:
(a) costs incurred for the Work,
including not only hard costs incurred for the new Improvements
described in Exhibit B , but also the following costs
to the extent reasonably incurred in connection with the
Construction Project:
| |
• |
|
soft costs, such as architectural fees, engineering fees and
fees and costs paid in connection with obtaining project permits
and approvals required by governmental authorities or any Permitted
Encumbrance, |
| |
| |
• |
|
site preparation costs, and |
| |
| |
• |
|
costs of offsite and other public improvements required as
conditions of governmental approvals for the Construction Project
or required by any Permitted Encumbrances; |
(b) costs incurred to maintain
insurance required by (and consistent with the requirements of)
this Agreement prior to the Completion Date;
(c) Local Impositions that have
accrued or become due prior to the Completion Date;
(d) Accrued Construction Period
Interest Expense; and
(e) any costs in addition to those
described in clauses (a) through (d) preceding that GAAP (as
it exists on the Effective Date) would allow BNPPLC to capitalize
as part of the cost of the Property or that the 97-10/Pronouncement
would allow BNPPLC to characterize as project costs, including:
(1) cancellation or termination
Construction Agreement - Page 3
fees or other
compensation payable by NAI or BNPPLC pursuant to any contract
concerning the Construction Project made by NAI or BNPPLC with any
general contractor, architect, engineer or other third party
because of any election by NAI or BNPPLC to cancel or terminate
such contract, and (2) any costs that BNPPLC incurs and is
allowed to capitalize to continue or complete the Construction
Project after any Owner’s Election to Continue Construction
as provided in subparagraph 8(A).
However,
notwithstanding the foregoing, 97-10/Project Costs will not include
Pre-lease Force Majeure Losses, Administrative Fees, the
Arrangement Fee or any legal fees which are included in Transaction
Expenses.
“
97-10/Pronouncement ” means the pronouncement issued
by the Emerging Issues Task Force of the Financial Accounting
Standards Board in 1998 titled “ EITF 97-10: The Effect of
Lessee Involvement in Asset Construction ”, which
provides that certain kinds of involvement by a lessee in pre-lease
commencement construction will cause the lessee to be considered as
the owner of the leased property during the construction period and
then will require application of the appropriate sale and leaseback
accounting rules.
“
NAI’s Estimate of Force Majeure Delays ” has the
meaning indicated in subparagraph 7(B)(4).
“
NAI’s Estimate of Force Majeure Excess Costs ”
has the meaning indicated in subparagraph 7(B)(3).
“
Accrued Construction Period Interest Expense ” means
interest that has accrued and that BNPPLC has paid or is obligated
to pay on Funding Advances for any period prior to the Completion
Date. Such interest will include a percentage, equal to the
aggregate Percentages of all Participants (under and as defined in
the Participation Agreement), of Carrying Costs and Commitment Fees
that accrue after the execution of any Participation Agreement and
that are added to the Outstanding Construction Allowance as
provided in this Agreement, it being understood that the additional
amounts BNPPLC must pay to the Participants under the Participation
Agreement because of the accrual of Carrying Costs and Commitment
Fees effectively constitute construction period interest on
advances the Participants make to BNPPLC under the Participation
Agreement. Accrued Construction Period Interest Expense will also
include any interest and other finance charges that accrue prior to
the Completion Date because of Funding Advances provided to BNPPLC
by BNPPLC’s Parent in the form of loans, regardless of
whether BNPPLC’s obligation in respect of such loans is
limited to BNPPLC’s interest in the Property. However, any
such interest and other finance charges accruing on Funding
Advances provided by BNPPLC’s Parent and included in Accrued
Construction Period Interest Expense will not exceed the Carrying
Costs attributable to the portion of the Lease Balance funded or
maintained by
Construction Agreement - Page 4
such Funding
Advances. Further, Accrued Construction Period Interest will not
include any portion of Carrying Costs included in Pre-lease Force
Majeure Losses (as set forth in the definition thereof below) or
interest or finance charges that BNPPLC must pay to the
Participants under the Participation Agreement because of the
accrual of such portion of Carrying Costs.
“
Administrative Fee ” has the meanings indicated in
subparagraph 3(A) and subparagraph 3(D).
“
Affiliate’s Contract ” has the meaning indicated
in subparagraph 2(A)(2)(b)2).
“
Arrangement Fee ” has the meaning indicated in
subparagraph 3(A).
“
Capital Adequacy Charges ” has the meaning indicated
in subparagraph 3(E)(1).
“
Carrying Costs ” has the meaning indicated in
subparagraph 3(B).
“
Commitment Fee Rate ” means, for each Construction
Period, the amount established as of the date (in this definition,
the “ CFR Test Date ”) that is two Business Days
prior to such period by reference to the pricing grid below, based
upon the ratio calculated by dividing (1) Adjusted EBITDA for
the then latest Rolling Four Quarters Period that ended prior to
(and for which NAI has reported earnings as necessary to compute
Adjusted EBITDA) into (2) the Total Debt of NAI and its
Subsidiaries (determined on a consolidated basis) as of the end of
such Rolling Four Quarters Period. In each case, the Commitment Fee
Rate will be established at the Level in the pricing grid below
which corresponds to such ratio; provided , that promptly
after earnings are reported by NAI for the latest quarter in any
Rolling Four Quarters Period, NAI must notify BNPPLC of any
resulting change in the Commitment Fee Rate under this definition,
and no reduction in the Commitment Fee Rate from one period to the
next will be effective for purposes of this Agreement unless, prior
to the CFR Test Date for the next period, NAI shall have provided
BNPPLC with a written notice setting forth and certifying the
calculation under this definition that justifies the
reduction.
| |
|
|
|
|
|
Levels |
|
Ratio of Total Debt to Adjusted EBITDA |
|
Spread |
|
Level I
|
|
less than 0.5 |
|
8.0 basis points |
|
Level II
|
|
greater than or equal to 0.5, but
less than 1.0 |
|
10.0 basis points |
Construction Agreement - Page 5
| |
|
|
|
|
|
Levels |
|
Ratio of Total Debt to Adjusted EBITDA |
|
Spread |
|
Level III
|
|
greater than or equal to 1.0, but
less than 1.5 |
|
12.5 basis points |
|
Level IV
|
|
greater than or equal to 1.5 |
|
15.0 basis points |
All
determinations of the Spread by BNPPLC will, in the absence of
clear and demonstrable error, be binding and conclusive for
purposes of the Operative Documents. Further BNPPLC may, but will
not be required, to rely on the determination of the Spread set
forth in any notice delivered by NAI as described above in clause
(a) of this definition..
“
Commitment Fees ” has the meaning indicated in
subparagraph 3(C).
“
Complete Taking ” means a taking by eminent domain
prior to the Completion Date over NAI’s objection of all of
the Land or the Property, or so much thereof as to make it
impossible to complete the Construction Project for its intended
uses on the Land regardless of any Scope Changes BNPPLC may be
willing to approve or any Increased Commitment that BNPPLC may be
willing to provide.
“
Completion Date ” means the date upon which NAI gives
the notice to BNPPLC which is required by subparagraph 2(B), after
having substantially completed the Construction Project and having
obtained any certificate of occupancy or other permit (temporary or
permanent) required for the commencement of NAI’s use of the
Improvements.
“
Completion Notice ” means the notice required by
subparagraph 2(B) from NAI to BNPPLC, advising BNPPLC that NAI has
substantially completed construction of the Construction Project
and has obtained any certificate of occupancy or other permit
(temporary or permanent) required for the commencement of
NAI’s use of the Improvements.
“
Construction Advances ” means (1) actual advances
of funds made by or on behalf of BNPPLC to or on behalf of NAI as
provided in Paragraph 4, which sets forth NAI’s rights
to receive advances for Reimbursable Construction Period Costs, and
(2) other amounts paid or incurred by BNPPLC that subparagraph
8(A) or other provisions of this Agreement allow BNPPLC to
characterize as Construction Advances. The term “Construction
Advances” will not, however, include advances of insurance
proceeds, condemnation proceeds or other Escrowed Proceeds to pay
or reimburse costs of repairs or restoration.
“
Construction Advance Request ” has the meaning
indicated in subparagraph 4(C)(1).
Construction Agreement - Page 6
“
Construction Allowance ” means the allowance to be
provided by BNPPLC for the design and construction of the
Construction Project, against which and from which Carrying Costs,
Construction Advances and other amounts will be or may be charged
and paid as provided in various provisions of this Agreement
(including Paragraphs 3, 4 and 8).
“
Construction Budget ” means the budget for the
Construction Project set forth in Exhibit B .
“
Construction Project ” means the new buildings or
other substantial Improvements to be constructed, or the alteration
of existing Improvements, as described generally in
Exhibit B .
“
Covered Construction Period Losses ” has the meaning
indicated in subparagraph 10(A).
“
Defective Work ” has the meaning indicated in
subparagraph 2(A)(2)(e).
“ FOCB
Notice ” means a notice from BNPPLC to NAI advising NAI
of any of the following events or circumstances, and also advising
NAI that because of any of the following events or circumstances
BNPPLC will be entitled to make the election described in
subparagraph 7(C), which will constitute a Termination of
NAI’s Work and a 97-10/Meltdown Event:
(1) NAI has taken action to cancel or
terminate or reduce the coverage available to BNPPLC under the
builder’s risk insurance obtained for the Construction
Project as required by this Agreement, or NAI has otherwise failed
to maintain any insurance or to provide insurance certificates to
BNPPLC as required by this Agreement and not cured such failure
within ten days after receiving notice thereof, or
(2) NAI has given any Pre-lease Force
Majeure Event Notice to BNPPLC, or
(3) an Event of Default has
occurred and is continuing; or
(4) a Work/Suspension Event has
occurred and continued for more than thirty consecutive days after
NAI’s receipt of a Work/Suspension Notice advising NAI of
such Work/Suspension Event, and subsequent to such thirty day
period the Work/Suspension Event has not been rectified by
NAI.
“
Force Majeure Event ” means (A) any taking of any
part of the Property by eminent domain prior to the Completion
Date, and (B) any damage to the Improvements or
Construction Agreement - Page 7
disruption of
the Work that occurs prior to the Completion Date and that is
caused by fire or acts of God (such as flood, lightning, earthquake
or hurricane), war, strikes and other labor disputes, or riot or
similar civil disturbance, but only to the extent such damage or
disruption (i) is beyond the control of and not caused in
whole or in part by negligence, illegal acts or willful misconduct
on the part of NAI or of its employees or of any other party acting
under NAI’s control or with the approval or authorization of
NAI, and (ii) could not have been avoided or overcome by the
exercise of due diligence or reasonable foresight on the part of
NAI or of any other such party.
“
Funded Construction Allowance ” means on any day the
Outstanding Construction Allowance on that day, including all
Construction Advances and Carrying Costs added to the Outstanding
Construction Allowance on or prior to that day, plus the amount of
any Qualified Prepayments deducted on or prior to that day in the
calculation of such Outstanding Construction Allowance.
“
Future Work ” has the meaning indicated in
subparagraph 4(C)(2)(b).
“
Ground Lease Rents ” has the meaning indicated in
subparagraph 3(F).
“
Increased Cost Charges ” has the meaning indicated in
subparagraph 3(E)(1).
“
Increased Commitment ” has the meaning indicated in
subparagraph 7(B)(6).
“
Increased Funding Commitment ” has the meaning
indicated in subparagraph 7(B)(6)(a).
“
Increased Time Commitment ” has the meaning indicated
in subparagraph 7(B)(6)(b).
“
Initial Advance ” has the meaning indicated in
subparagraph 3(A).
“
Maximum Construction Allowance ” means an amount equal
to the difference computed by subtracting the Initial Advance from
$61,000,000, as such amount may be increased from time to time by
any Increased Funding Commitment made by BNPPLC as provided in
subparagraph 7(B)(6).
“
Notice of NAI’s Intent to Terminate ” has the
meaning indicated in subparagraph 7(B)(2).
“
Notice of NAI’s Intent to Terminate Because of a Force
Majeure Event ” has the meaning indicated in subparagraph
7(B)(5).
Construction Agreement - Page 8
“
Notice of Termination by NAI ” has the meaning
indicated in subparagraph 7(B)(1).
“
Outstanding Construction Allowance ” means, as of any
date, the difference (but not less than zero) of (A) the total
Construction Advances made by or on behalf of BNPPLC on or prior to
such date in question, plus (B) all Carrying Costs, Commitment
Fees, Administrative Fees, Increased Cost Charges and Capital
Adequacy Charges added on or prior to the date as provided in
Paragraph 3, less (C) any funds received and applied as
Qualified Prepayments on or prior to such date.
“
Owner’s Election to Continue Construction ” has
the meaning indicated in subparagraph 8(A).
“
Pre-lease Casualty ” has the meaning indicated in
subparagraph 2(A)(2)(a).
“
Pre-lease Force Majeure Delays ” means delays in the
completion of the Work to the extent (but only to the extent)
caused solely by a Pre-lease Force Majeure Event.
“
Pre-lease Force Majeure Event ” means a Force Majeure
Event that occurs prior to the Completion Date; provided,
however, that if NAI does not notify BNPPLC of any such Force
Majeure Event by the delivery of a Pre-lease Force Majeure Event
Notice within thirty days after the Force Majeure Event first
occurs or commences, then such Force Majeure Event will not qualify
as a “Pre-lease Force Majeure Event” for purposes of
this Agreement or the other Operative Documents.
“
Pre-lease Force Majeure Event Notice ” has the meaning
indicated in subparagraph 6(B).
“
Pre-lease Force Majeure Excess Costs ” means the
amount (if any) by which the increases in the costs of the Work
resulting directly and solely from a Pre-lease Force Majeure Event
(such as, for example, the costs of repairing damage to the
Improvements caused by a Pre-lease Force Majeure Event) exceed the
amounts available to pay or reimburse NAI for such increased costs.
Amounts available to pay or reimburse such increased costs will
include (a) insurance proceeds or any recovery from a third
party (including any Escrowed Proceeds held by BNPPLC), and
(b) any part of the Construction Allowance (including any
unused contingency amount in the Construction Budget) not used or
needed to cover other Reimbursable Construction Period Costs.
“
Pre-lease Force Majeure Losses ” means any of the
following Losses that BNPPLC suffers by reason of any taking or
damage to the Improvements which constitutes a Pre-lease Force
Majeure Event:
Construction Agreement - Page 9
(a) the costs of repairing any such
damage to the extent that such costs have, as of the date of any
required determination of Pre-lease Force Majeure Losses, been paid
or reimbursed from a Construction Advance (and thus are included in
the Lease Balance as of that date), to be distinguished from costs
of repairs paid or reimbursed from insurance proceeds or from any
recovery from a third party;
(b) any diminution in the value of
the Improvements resulting from any such taking or resulting from
any such damage that has not, as of the date of the required
determination of Pre-lease Force Majeure Losses, been
repaired;
(c) any increase in the total amount
of Carrying Costs, Commitment Fees, Administrative Fees, Increased
Cost Charges, Capital Adequacy Charges and Ground Lease Rents (and
any other amounts) added to the Lease Balance as provided in
Paragraph 3 solely by reason of Pre-lease Force Majeure
Delays; and
(d) to the extent not already
included in the increase described in the preceding clause, all
increases in Carrying Costs that are attributable to the amounts
included in Pre-lease Force Majeure Losses pursuant to the
preceding clause (a);
but in each
case such amounts will constitute Pre-lease Force Majeure Losses
only to the extent, if any, that they are not offset by
condemnation or insurance proceeds which are (1) paid by reason of
such Pre-lease Force Majeure Event (including insurance proceeds
paid to compensate BNPPLC or NAI for increased financing costs, the
lost time value of BNPPLC’s investment in the Project or
business interruption) and (2) applied as a Qualified
Prepayment to reduce the Lease Balance.
Also, for
purposes of this definition, the diminution in the value of the
Improvements, as described in the preceding clause (b), because of
any damage that constitutes a Pre-lease Force Majeure Event will
not exceed the amount thereof estimated in good faith by any
independent appraiser or insurance adjuster engaged by BNPPLC to
determine such amount after BNPPLC has received a Pre-lease Force
Majeure Event Notice as provided in subparagraph 6(B), nor will it
exceed the cost of repairing the damage as estimated in good faith
by any such independent insurance adjuster or as indicated by any
bona fide written bid to make the repairs that BNPPLC obtains from
a reputable contractor capable of making the repairs.
“
Prior Work ” has the meaning indicated in subparagraph
4(C)(2)(b).
“
Projected Cost Overruns ” means the excess (if any),
calculated as of the date of each Construction Advance Request, of
(1) the total of projected Reimbursable Construction
Construction Agreement - Page 10
Period Costs
yet to be incurred or for which NAI has yet to be reimbursed
hereunder (including projected Reimbursable Construction Period
Costs for Future Work), over (2) the balance of the remaining
Construction Allowance then projected to be available to cover such
costs. The balance of the remaining Construction Allowance then
projected to be available will equal: (i) the amount (if any)
by which the Maximum Construction Allowance exceeds the Funded
Construction Allowance, plus (ii) any Escrowed Proceeds
then available or expected to be available to cover costs of
repairs and restoration that NAI will perform as part of the Work
after a casualty or condemnation, less (iii) all
projected future Carrying Costs, Commitment Fees, Administrative
Fees and other amounts to be added to the Outstanding Construction
Allowance as provided in Paragraph 3.
“
Reimbursable Construction Period Costs ” has the
meaning indicated in subparagraph 4(A).
“
Remaining Proceeds ” has the meaning indicated in
subparagraph 5(A).
“
Scope Change ” means a change to the Construction
Project that, if implemented, will make the quality, function or
capacity of the Improvements “materially different” (as
defined below in this subparagraph) than as described or inferred
by the site plan or plans and renderings referenced in
Exhibit B . The term “ Scope Change
” is not intended to include the mere refinement, correction
or detailing of the site plan, plans or renderings submitted to
BNPPLC by NAI. As used in this definition, a “material
difference” means a difference that could reasonably be
expected to (a) cause the Lease Balance to exceed the fair
market value of the Property when the Construction Project is
completed and all Construction Advances required in connection
therewith have been funded, or significantly increase any such
excess, (b) change the general character of the Improvements
from that needed to accommodate the uses to be permitted by
subparagraph 2(A) of the Lease, or (c) cause or
exacerbate Projected Cost Overruns.
“
Target Completion Date ” means the date which is last
day of the 18th calendar month following the Effective Date, as
such date may be extended from time to time by any Increased Time
Commitment made by BNPPLC as provided in subparagraph
7(B)(6).
“
Termination of NAI’s Work ” means a termination
of NAI’s rights and obligations to continue the Work because
of an election to terminate made by NAI pursuant to subparagraph
7(B) or because of an election by BNPPLC made pursuant to
subparagraph 7(C).
“
Third Party Contract ” has the meaning indicated in
subparagraph 2(A)(2)(b)1).
Construction Agreement - Page 11
“
Third Party Contract/Termination Fees ” means any
amounts, however denominated, for which NAI will be obligated under
a Third Party Contract as a result of any election or decision by
NAI to terminate such Third Party Contract, including
demobilization costs; provided, however, amounts payable only by
reason of Prior Work as of the date of any such termination will
not be characterized as Third Party Contract/Termination Fees. If
NAI reserves an absolute express right in a Third Party Contract to
terminate such contract at any time, without cause, for a specified
U.S. dollar amount, such amount will constitute a Third Party
Contract/Termination Fee. If no such right is reserved in a Third
Party Contract, the amount of damages that NAI is required to pay
(in addition to payments required for Prior Work) upon a
repudiation of the Third Party Contract by NAI will qualify as a
“Third Party Contract/Termination Fee” applicable to
such contract for purposes of this Agreement.
“
Timing or Budget Shortfall ” means that, as of any
time prior to the Completion Date, (i) the remaining available
Construction Allowance will not be sufficient to cover Reimbursable
Construction Period Costs yet to be paid or reimbursed from
Construction Advances (x) because the cost of the Work exceeds
budgeted expectations (resulting in Projected Cost Overruns)
through no fault of NAI or its employees or any other party acting
under NAI’s control or with the approval or authorization of
NAI, (y) because of any Pre-lease Force Majeure Event or
(z) because NAI can no longer satisfy conditions to
BNPPLC’s obligation to provide further Construction Advances,
or (ii) the Work will not be substantially completed prior to
the Target Completion Date through no fault of NAI or its employees
or any other party acting under NAI’s control or with the
approval or authorization of NAI. As used in this definition with
respect to any party, the term “fault” will not include
inadequate estimation of time or dollars unless shown to be caused
by the negligence or wilful misconduct of that party.
“
Work ” has the meaning indicated in subparagraph
2(A)(2)(a).
“
Work/Suspension Event ” means any of the
following:
(1) Projected Cost Overruns have
become more likely than not, in BNPPLC’s good faith judgment
(taking into account any notices or Construction Draw Requests from
NAI indicating that a Pre-lease Force Majeure Event may result in
Projected Cost Overruns), and BNPPLC has notified NAI of such
judgement and the reasons therefor.
(2) Delays in the Work (including any
delays resulting from damage to the Property by fire or other
casualty or from any taking of any part of the Property by
condemnation) have made it substantially unlikely, in
BNPPLC’s good faith judgment, that NAI will be able to
complete the Construction Project in accordance with the
requirements of this Agreement prior to the Target Completion Date
using only the funds
Construction Agreement - Page 12
available to
NAI under this Agreement, and BNPPLC has notified NAI of such
judgement and the reasons therefor.
(3) BNPPLC has requested with respect
to any Construction Advance, but NAI has failed to provide within
thirty days after receipt of the request: (1) invoices,
requests for payment from contractors and other evidence reasonably
establishing that the costs and expenses for which NAI has
requested or is requesting reimbursement constitute actual
Reimbursable Construction Period Costs, and (2) canceled
checks, lien waivers or other evidence reasonably establishing that
all prior Construction Advances paid to NAI have been used by NAI
to pay the Reimbursable Construction Period Costs for which the
prior advances were requested and made.
“
Work/Suspension Notice ” means a notice from BNPPLC to
NAI advising NAI of any event or circumstances that constitute a
Work/Suspension Event and advising NAI that (1) before the
Work/Suspension Event is rectified BNPPLC may limit Construction
Advances to NAI as permitted by this Agreement, and (2) unless
NAI does rectify the Work/Suspension Event within thirty days after
NAI’s receipt of such notice, BNPPLC may elect to send an
FOCB Notice in anticipation of a Termination of NAI’s
Work.
“
Work/Suspension Period ” means any period
(1) beginning with the date of any Work/Suspension Notice,
FOCB Notice or Notice of NAI’s Intent to Terminate, and
(2) ending on the earlier of (a) the first date upon
which (i) no Work/Suspension Events are continuing,
(ii) all previous FOCB Notices and Notices of NAI’s
Intent to Terminate (if any) have been rescinded, and (iii) no
97-10/Meltdown Events have occurred, or (b) the effective date
of any Termination of NAI’s Work as described in subparagraph
7(B) or subparagraph 7(C).
Construction Agreement - Page 13
2
Construction and
Management of the Property by NAI .
(A) The Construction
Project .
(1) Construction Approvals by
BNPPLC .
(a) Preconstruction Approvals by
BNPPLC . NAI has submitted and obtained BNPPLC’s approval
of the site plan and descriptions of the Construction Project
referenced in Exhibit B . Also set forth in
Exhibit B is a general description of the Construction
Project. The Construction Project, as constructed by NAI pursuant
to this Agreement, and all construction contracts and other
agreements executed or adopted by NAI in connection therewith, must
not be inconsistent in any material respect with the plans or other
items referenced in Exhibit B , except to the extent
otherwise provided by any Scope Change approved by BNPPLC and
except as otherwise provided in subparagraph 8(A) if BNPPLC should
make an Owner’s Election to Continue Construction after any
Termination of NAI’s Work.
(b) Approval of Scope Changes
. Before making a Scope Change, NAI must provide to BNPPLC a
reasonably detailed written description of the Scope Change, a
revised Construction Budget and a copy of any changes to the
drawings, plans and specifications for the Improvements required in
connection therewith, all of which must be approved in writing by
BNPPLC before the Scope Change is implemented. After receiving such
items, BNPPLC will endeavor in good faith to respond promptly (and
in any event no later than thirty days after such receipt) to any
request by NAI for approval of the Scope Change. BNPPLC will not,
however, be liable for any failure to provide a prompt response.
Further, BNPPLC’s approval will not in any event constitute a
waiver of subparagraph 2(A)(3) or of any other provision of this
Agreement or other Operative Documents.
(2) NAI’s Right to
Possession and to Control Construction . Subject to the terms
and conditions set forth in this Agreement, and prior to any
Termination of NAI’s Work as provided in subparagraphs 7(B)
and 7(C), NAI will have possession of the Land and all Improvements
on the Land to the exclusion of BNPPLC and will have the sole right
to control and the sole responsibility for the design and
construction of the Construction Project, including the means,
methods, sequences and procedures implemented to accomplish such
design and construction. Although title to all Improvements will
vest in BNPPLC (as more particularly provided in subparagraph
2(C)), BNPPLC’s obligation with respect to the Construction
Project will be limited to the making of advances under and subject
to the conditions set forth in this
Construction Agreement - Page 14
Agreement.
Without limiting the foregoing, NAI acknowledges and agrees
that:
(a) Performance of the Work .
Except as provided in subparagraphs 7(A) and 7(D), NAI must, using
its best skill and judgment and in an expeditious and economical
manner not inconsistent with the interests of BNPPLC, perform or
cause to be performed all work required, and must provide or cause
to be provided all supplies and materials required, to design and
complete construction of the Construction Project (collectively,
the “ Work ”) no later than the Target
Completion Date. The Work will include obtaining all necessary
building permits and other governmental approvals required in
connection with the design and construction of the Construction
Project, or required in connection with the use and occupancy
thereof ( e.g., certificates of occupancy). The Work will
also include any repairs or restoration required because of damage
to Improvements by fire or other casualty prior to the Completion
Date (a “ Pre-lease Casualty ”); provided,
however , the cost of any such repairs or restoration will be
subject to reimbursement not only through Construction Advances
made to NAI on and subject to the terms and conditions of this
Agreement, but also through the application of Escrowed Proceeds as
provided in Paragraph 5; and, provided further , like
other Work, any such repairs and restoration to be provided by NAI
will be subject to subparagraphs 7(A) and 7(B), which establish
certain rights of NAI to suspend or discontinue any Work. NAI will
carefully schedule and supervise all Work, will check all materials
and services used in connection with all Work and will keep full
and detailed accounts as may be necessary to document expenditures
made or expenses incurred for the Work.
(b) Third Party Contracts
.
1) NAI will not enter into any
construction contract or other agreement with a third party
concerning the Work or the Construction Project (a “ Third
Party Contract ”) in the name of BNPPLC or otherwise
purport to bind BNPPLC to any obligation to any third party.
2) In any Third Party Contract
between NAI and any of its Affiliates (an “
Affiliate’s Contract ”) NAI must reserve the
right to terminate such contract at any time, without cause, and
without subjecting NAI to liability for any Third Party
Contract/Termination Fee. Further, NAI must not enter into any
Affiliate’s Contract that obligates NAI to pay more than
would be required under an arms-length contract or that would
require NAI to pay its Affiliate any amount in excess of the sum of
actual, out-of-pocket direct costs and internal labor costs
incurred by the Affiliate to perform such contract.
Construction Agreement - Page 15
(c) Adequacy of Drawings,
Specifications and Budgets . BNPPLC has not made and will not
make any representations as to the adequacy of the Construction
Budget or any other budget or any site plans, renderings, plans,
drawings or specifications for the Construction Project, and no
modification of any such budgets, site plans, renderings, plans,
drawings or specifications that may be required from time to time
will entitle NAI to any adjustment in the Construction
Allowance.
(d) Existing Condition of the Land
and Improvements . NAI is familiar with the conditions of the
Land and any existing Improvements on the Land. NAI will have no
claim for damages against BNPPLC or for an increase in the
Construction Allowance or for an extension of the deadline
specified in subparagraph 2(A)(2)(a) for completing the Work by
reason of any condition (concealed or otherwise) of or affecting
the Land or Improvements.
(e) Correction of Defective
Work . NAI will promptly correct all Work performed prior to
any Termination of NAI’s Work that does not comply with the
requirements of this Agreement for any reason other than a
Pre-lease Casualty (“ Defective Work ”). If NAI
fails to correct any Defective Work or fails to carry out Work in
accordance with this Agreement, BNPPLC may (but will not be
required to) order NAI to stop all Work until the cause for such
failure has been eliminated.
(f) Clean Up . Upon the
completion of all Work, NAI will remove all waste material and
rubbish from and about the Land, as well as all tools, construction
equipment, machinery and surplus materials. NAI will keep the Land
and the Improvements thereon in a reasonably safe and sightly
condition as Work progresses.
(g) No Damage for Delays . NAI
will have no claim for damages against BNPPLC or for an increase in
the Construction Allowance by reason of any delay in the
performance of any Work. Nor will NAI have any claim for an
extension of the deadline specified in subparagraph 2(A)(2)(a) for
completing the Work because of any such period of delay, except
that (i) in the case of any Pre-lease Force Majeure Delays,
NAI will have certain rights as set forth in subparagraph 7(B) and
other provisions of this Agreement, and (ii) in the event of
intentional interference with the Work by BNPPLC itself for which
NAI provides written notice to cease, NAI will be entitled to an
extension of the deadline specified in subparagraph 2(A)(2)(a) as
needed because of any delays resulting from such intentional
interference. It is also understood that any such intentional
Construction Agreement - Page 16
interference by
BNPPLC will constitute a Force Majeure Event. In no event, however,
will BNPPLC’s exercise of its rights and remedies permitted
under this Agreement or the other Operative Documents be construed
as intentional interference with NAI’s performance of any
Work; and thus neither BNPPLC’s exercise of its right to
withhold Construction Advances at any time when NAI has failed to
satisfy all conditions herein to such advances, nor BNPPLC’s
exercise of its right to terminate Work by NAI as provided in
subparagraph 7(C), be considered as intentional interference with
the Work or a Pre-lease Force Majeure Event.
(h) No Fee For Construction
Management . NAI will have no claim under this Agreement for
any fee or other compensation or for any reimbursement of internal
administrative or overhead expenses (other than the out-of-pocket
overhead expenses properly included in the Construction Budget, if
any), it being understood that NAI is executing this Agreement in
consideration of the rights expressly granted to it herein and in
the other Operative Documents.
(3) Quality of Work . NAI will
cause the Work undertaken and administered by it pursuant to this
Agreement to be performed (a) in a safe and good and
workmanlike manner, (b) in accordance with Applicable Laws,
and (c) in compliance with the provisions of this Agreement
and the material provisions of the Permitted Encumbrances.
(B) Completion Notice .
Within fifteen Business Days after NAI substantially completes
construction of the Construction Project and obtains any
certificate of occupancy or other permit (temporary or permanent)
required by Applicable Laws for the commencement of NAI’s use
and occupancy of the Improvements, NAI must provide a notice (a
“ Completion Notice ”) to BNPPLC, advising
BNPPLC thereof, and thereby establish the Completion Date. For
purposes of this Agreement and the other Operative Documents,
BNPPLC will be entitled to rely without investigation upon any such
notice given by NAI as evidence that NAI has, in fact,
substantially completed the Construction Project and has obtained
any certificate of occupancy or other permit (temporary or
permanent) required for the commencement of NAI’s use of the
Improvements, and after giving any such notice NAI will be estopped
from later claiming that the Completion Date has not
occurred.
(C) Status of Property
Acquired With BNPPLC’s Funds . All Improvements
constructed on the Land as provided in this Agreement will
constitute “Property” for purposes of the Lease and
other Operative Documents. Further, to the extent heretofore or
hereafter acquired (in whole or in part) with any portion of the
Initial Advance or with any Construction Advances or with other
funds for which NAI receives reimbursement from the Initial Advance
or Construction Advances, all furnishings, furniture, chattels,
permits, licenses, franchises, certificates and other personal
property of whatever nature will be considered as having been
Construction Agreement - Page 17
acquired
on behalf of BNPPLC by NAI and will constitute
“Property” for purposes of the Lease and other
Operative Documents, as will all renewals or replacements of or
substitutions for any such Property. The parties intend that title
to the Improvements and to any other such Property will vest in
BNPPLC without passing through NAI or NAI’s Affiliates before
it is transferred to BNPPLC from contractors, suppliers, vendors or
other third Persons, but with the understanding that all such
Property will be accepted by BNPPLC subject to the terms and
conditions of the other Operative Documents, including
subparagraph 4(C)(1) of the Lease (concerning the
characterization of the Lease and other Operative Documents for tax
and certain other purposes). Although nothing herein constitutes
authorization of NAI by BNPPLC to bind BNPPLC to any construction
contract or other agreement with a third Person, any construction
contract or other agreement executed by NAI for the acquisition or
construction of Improvements or other components of the Property
may, as NAI deems appropriate, provide for the direct transfer of
title to BNPPLC as described in the preceding sentence.
(D) Insurance .
(1) Liability Insurance .
Throughout the period prior to any Termination of NAI’s Work,
NAI must maintain commercial general liability insurance against
claims for bodily and personal injury, death and property damage
occurring in or upon or resulting from any occurrence in or upon
the Property under one or more insurance policies that satisfy the
Minimum Insurance Requirements, which are set forth in an exhibit
to the Common Definitions and Provisions Agreement. NAI must
deliver and maintain with BNPPLC for each liability insurance
policy required by this Agreement written confirmation of the
policy and the scope of the coverage provided thereby issued by the
applicable insurer or its authorized agent, which confirmation must
also satisfy the Minimum Insurance Requirements.
(2) Property Insurance .
Throughout the period prior to any Termination of NAI’s Work,
NAI must also keep all Improvements (including all alterations,
additions and changes made to the Improvements) insured against
fire and other casualty under one or more property insurance
policies that satisfy the Minimum Insurance Requirements. NAI must
deliver and maintain with BNPPLC for each property insurance policy
required by this Agreement written confirmation of the policy and
the scope of the coverage provided thereby issued by the applicable
insurer or its authorized agent, which confirmation must also
satisfy the Minimum Insurance Requirements. If any of the Property
is destroyed or damaged by fire, explosion, windstorm, hail or by
any other casualty against which insurance has been required
hereunder, (i) BNPPLC may, but will not be obligated to, make
proof of loss if not made promptly by NAI after notice from BNPPLC,
(ii) each insurance company concerned is hereby authorized and
directed to make payment for such loss directly to BNPPLC for
application as required by Paragraph 5, and (iii) BNPPLC
may settle, adjust or compromise any and all claims for
Construction Agreement - Page 18
loss, damage or
destruction under any policy or policies of insurance (provided,
that so long as no 97-10/Meltdown Event has occurred and no Event
of Default has occurred and is continuing, BNPPLC must provide NAI
with at least forty-five days notice of BNPPLC’s intention to
settle any such claim before settling it unless NAI has already
approved of the settlement by BNPPLC). BNPPLC will not in any event
or circumstances be liable or responsible for failure to collect,
or to exercise diligence in the collection of, any insurance
proceeds. If any casualty results in damage to or loss or
destruction of the Property, NAI must give prompt notice thereof to
BNPPLC and Paragraph 5 will apply.
(3) Failure of NAI to Obtain
Insurance . If NAI fails to obtain any insurance or to provide
confirmation of any insurance as required by this Agreement, BNPPLC
will be entitled (but not required) to obtain the insurance that
NAI has failed to obtain or for which NAI has not provided the
required confirmation and, without limiting BNPPLC’s other
remedies under the circumstances, BNPPLC may charge the cost of
such insurance against the Construction Allowance as if it were a
Construction Advance paid to NAI as hereinafter provided.
(4) Waiver of Subrogation .
NAI, for itself and for any Person claiming through it (including
any insurance company claiming by way of subrogation), waives any
and every claim which arises or may arise in its favor against
BNPPLC or any other Interested Party for any and all Losses, to the
extent that NAI is compensated by insurance or would be compensated
by the insurance policies contemplated in this Agreement, but for
any deductible or self-insured retention maintained under such
insurance or but for a failure of NAI to maintain the insurance as
required by this Agreement. NAI agrees to have such insurance
policies properly endorsed so as to make them valid notwithstanding
this waiver, if such endorsement is required to prevent a loss of
insurance.
(E) Condemnation .
Immediately upon obtaining knowledge of the institution of any
proceedings for the condemnation of the Property or any portion
thereof, or any other similar governmental or quasi-governmental
proceedings arising out of injury or damage to the Property or any
portion thereof, each party must promptly notify the other
(provided, however, BNPPLC will have no liability for its failure
to provide such notice) of the pendency of such proceedings. Prior
to any Termination of NAI’s Work, NAI must, if requested by
BNPPLC, diligently prosecute any such proceedings and consult with
BNPPLC, its attorneys and experts and cooperate with them as
reasonably requested in the carrying on or defense of any such
proceedings. All proceeds of condemnation awards or proceeds of
sale in lieu of condemnation with respect to the Property and all
judgments, decrees and awards for injury or damage to the Property
will be paid to BNPPLC as Escrowed Proceeds, and all such proceeds
will be applied as provided in Paragraph 5. BNPPLC is hereby
authorized, in its own name or in the name of
Construction Agreement - Page 19
NAI or
in the name of both, to settle and deliver valid acquittances for,
or to challenge and to appeal from, any such judgment, decree or
award concerning condemnation of any of the Property (provided,
that so long as no 97-10/Meltdown Event has occurred and no Event
of Default has occurred and is continuing, BNPPLC must provide NAI
with at least forty-five days notice of BNPPLC’s intention to
settle any such claim before settling it unless NAI has already
approved of the settlement by BNPPLC). BNPPLC will not in any event
or circumstances be liable or responsible for failure to collect,
or to exercise diligence in the collection of, any such proceeds,
judgments, decrees or awards.
(F) Additional
Representations, Warranties and Covenants of NAI Concerning the
Property . Without limiting the rights granted to NAI by other
provisions of this Agreement to be reimbursed from Construction
Advances for the cost of complying with the following, NAI
represents, warrants and covenants as follows:
(1) Payment of Local
Impositions . Throughout the period prior to any Termination of
NAI’s Work, NAI must pay or cause to be paid prior to
delinquency all ad valorem taxes assessed against the Property and
other Local Impositions. If requested by BNPPLC from time to time,
NAI will furnish BNPPLC with receipts or other appropriate evidence
showing payment of all Local Impositions prior to the applicable
delinquency date therefor.
Notwithstanding
the foregoing, NAI may in good faith, by appropriate proceedings,
contest the validity, applicability or amount of any asserted Local
Imposition, and pending such contest NAI will not be deemed in
default under any of the provisions of this Agreement because of
the Local Imposition if (1) NAI diligently prosecutes such
contest to completion in a manner reasonably satisfactory to
BNPPLC, and (2) NAI promptly causes to be paid any amount
adjudged by a court of competent jurisdiction to be due, with all
costs, penalties and interest thereon, promptly after such judgment
becomes final; provided, however, in any event each such contest
must be concluded and the contested Local Impositions must be paid
by NAI prior to the earlier of (i) the date that any criminal
prosecution is instituted or overtly threatened against BNPPLC or
its directors, officers or employees because of the nonpayment
thereof, or (ii) the date any writ or order is issued under
which any property owned or leased by BNPPLC (including the
Property) may be seized or sold or any other action is taken or
overtly threatened against BNPPLC or against any property owned or
leased by BNPPLC because of the nonpayment thereof, or
(iii) any Designated Sale Date upon which, for any reason, NAI
or an Affiliate of NAI or any Applicable Purchaser does not
purchase BNPPLC’s interest in the Property pursuant to the
Purchase Agreement for a price to BNPPLC (when taken together with
any Supplemental Payment paid by NAI pursuant to the Purchase
Agreement, in the case of a purchase by an Applicable Purchaser)
equal to the Break Even Price.
Construction Agreement - Page 20
(2) Operation and Maintenance
. Throughout the period prior to any Termination of NAI’s
Work, NAI must operate and maintain the Property in a good and
workmanlike manner and in compliance with Applicable Laws in all
material respects and pay or cause to be paid all fees or charges
of any kind in connection therewith. (If NAI does not promptly
correct any failure of the Property to comply with Applicable Laws
that is the subject of a written complaint or demand for corrective
action given by any Governmental Authority to NAI, or to BNPPLC and
forwarded by it to NAI, then for purposes of the preceding
sentence, NAI will be considered not to have maintained the
Property “in compliance with all Applicable Laws in all
material respects” whether or not the noncompliance would be
material in the absence of the complaint or demand.) NAI must not
use or occupy, or allow the use or occupancy of, the Property in
any manner which violates any Applicable Law or which constitutes a
public or private nuisance or which makes void, voidable or
cancelable any insurance then in force with respect thereto.
Without limiting the generality of the foregoing, NAI must not
conduct or permit others to conduct Hazardous Substance Activities
on the Property, except Permitted Hazardous Substance Use and
Remedial Work; and NAI must not discharge or permit the discharge
of anything (including Permitted Hazardous Substances) on or from
the Property that would require any permit under applicable
Environmental Laws, other than (1) storm water runoff,
(2) fume hood emissions, (3) waste water discharges
through a publicly owned treatment works, (4) discharges that
are a necessary part of any Remedial Work, and (5) other
similar discharges consistent with the definition of Permitted
Hazardous Substance Use which do not significantly increase the
risk of Environmental Losses to BNPPLC, in each case in strict
compliance with Environmental Laws. To the extent that any of the
following would, individually or in the aggregate, increase the
likelihood of a 97-10/Meltdown Event or materially and adversely
affect the value of the Property or the use of the Property for
purposes permitted by this Agreement, NAI must not, without
BNPPLC’s prior consent: (i) initiate or permit any
zoning reclassification of the Property; (ii) seek any
variance under existing zoning ordinances applicable to the
Property; (iii) use or permit the use of the Property in a
manner that would result in such use becoming a nonconforming use
under applicable zoning ordinances or similar laws, rules or
regulations; (iv) execute or file any subdivision plat
affecting the Property; or (v) consent to the annexation of
the Property to any municipality. NAI will not cause or permit any
drilling or exploration for, or extraction, removal or production
of, minerals from the surface or subsurface of the Property, and
NAI must not do anything that could reasonably be expected to
significantly reduce the market value of the Property. If NAI
receives a notice or claim from any federal, state or other
governmental authority that the Property is not in compliance with
any Applicable Law, or that any action may be taken against BNPPLC
because the Property does not comply with any Applicable Law, NAI
must promptly furnish a copy of such notice or claim to
BNPPLC.
Construction Agreement - Page 21
(3) Debts for Construction,
Maintenance, Operation or Development . NAI must promptly pay
or cause to be paid all debts and liabilities incurred by it or its
contractors or subcontractors in the construction, maintenance,
operation or development of the Property. Such debts and
liabilities will include those incurred for labor, material and
equipment and all debts and charges for utilities servicing the
Property.
(4) Permitted Encumbrances and the
Ground Lease . NAI must comply with and will cause to be
performed all of the covenants, agreements and obligations imposed
upon the owner of any interest in the Property by the Permitted
Encumbrances or the Ground Lease throughout the period prior to any
Termination of NAI’s Work. NAI must not, without the prior
consent of BNPPLC, create any new Permitted Encumbrance or enter
into, initiate, approve or consent to any modification of any
Permitted Encumbrance that would create or expand or purport to
create or expand obligations or restrictions encumbering
BNPPLC’s interest in the Property. (Whether BNPPLC must give
any such consent requested by NAI prior to the Completion Date will
be governed by subparagraph 4(C) of the Closing
Certificate.)
(5) Books and Records Concerning
the Property . NAI must keep books and records that are
accurate and complete in all material respects for NAI’s
construction and management of the Property as contemplated in this
Agreement and must permit all such books and records (including all
contracts, statements, invoices, bills and claims for labor,
materials and services supplied for the construction and operation
of any Improvements) to be inspected and copied by BNPPLC.
(G) BNPPLC’s Right of
Access .
(1) Access Generally . BNPPLC
and BNPPLC’s representatives may enter the Property at any
time for the purpose of making inspections or performing any work
BNPPLC is authorized to undertake by the next subparagraph or for
the purpose confirming whether NAI has complied with the
requirements of this Agreement or the other Operative Documents.
However, prior to any Termination of NAI’s Work, BNPPLC or
BNPPLC’s representative will, before making any entry upon
the Property or performing any work on the Property authorized by
this Agreement, do the following
(a) BNPPLC will give NAI at least 24
hours notice, unless BNPPLC believes in good faith that an
emergency may exist or a Default has occurred and is continuing,
because of which significant damage to the Property or other
significant Losses may be sustained if BNPPLC delays entry to the
Property; and
(b) if then requested to do so by NAI
in order to maintain NAI’s
Construction Agreement - Page 22
security,
BNPPLC or its representative will: (i) sign in at NAI’s
security or information desk if NAI has such a desk on the
premises, (ii) wear a visitor’s badge or other
reasonable identification, (iii) permit an employee of NAI to
observe such inspection or work, and (iv) comply with other
similar reasonable nondiscriminatory security requirements of NAI
that do not, individually or in the aggregate, significantly
interfere with inspections or work of BNPPLC authorized by this
Agreement.
(2) Failure of NAI to Perform
. If NAI fails to perform any act or to take any action required of
it by this Agreement or other Operative Documents, or to pay any
money which NAI is required by this Agreement or other Operative
Documents to pay, and if such failure or action constitutes an
Event of Default or renders BNPPLC or any director, officer,
employee or Affiliate of BNPPLC at risk of criminal prosecution or
renders BNPPLC’s interest in the Property or any part thereof
at risk of forfeiture by forced sale or otherwise, then in addition
to any other remedies specified herein or otherwise available,
BNPPLC may, perform or cause to be performed such act or take such
action or pay such money. (To the extent that expenses so incurred
by BNPPLC, or money so paid by BNPPLC, qualify as a Covered
Construction Period Losses, NAI must pay the same to BNPPLC upon
demand. If any such expenses incurred or money paid do not qualify
as Covered Construction Period Losses, but do constitute
97-10/Project Costs, BNPPLC may treat them as Construction Advances
hereunder. To the extent that any such expenses incurred or money
paid do not qualify as Covered Construction Period Losses and do
constitute 97-10/Project Costs, they will be included — with
interest — in the Balance of Unpaid Covered Construction
Period Losses under and as defined in the Purchase Agreement.)
Further, BNPPLC, upon making such payment, will be subrogated to
all of the rights of the person, corporation or body politic
receiving such payment. But nothing herein will imply any duty upon
the part of BNPPLC to do any work which, under any provision of
this Agreement or otherwise, NAI m
|