Exhibit 10.38
CONSTRUCTION
AGREEMENT
Between
DENDREON CORPORATION
Owner,
- and -
THE HENDERSON CORPORATION
Contractor.
As of November 4, 2005
TABLE OF
CONTENTS
|
|
|
|
|
|
|
ARTICLE
|
|
PAGE
|
|
ARTICLE I
|
|
Contract Documents
|
|
1
|
|
ARTICLE II
|
|
Scope of the Work
|
|
3
|
|
ARTICLE III
|
|
Contract Sum and Guaranteed Maximum
Price
|
|
5
|
|
ARTICLE IV
|
|
Reimbursable Costs
|
|
8
|
|
ARTICLE V
|
|
Non-Reimbursable Costs
|
|
8
|
|
ARTICLE VI
|
|
Schedule of the Work and Early
Occupancy
|
|
10
|
|
ARTICLE VII
|
|
Contractor’s Work
|
|
12
|
|
ARTICLE VIII
|
|
Trade Contracts
|
|
21
|
|
ARTICLE IX
|
|
Discounts, Rebates and Refunds
|
|
22
|
|
ARTICLE X
|
|
Accounting Records
|
|
22
|
|
ARTICLE XI
|
|
Applications for Payment
|
|
23
|
|
ARTICLE XII
|
|
Assignment
|
|
25
|
|
ARTICLE XIII
|
|
Liens and Claims
|
|
25
|
|
ARTICLE XIV
|
|
Events of Default and Termination or Suspension
of Agreement
|
|
26
|
|
ARTICLE XV
|
|
Bonds
|
|
30
|
|
ARTICLE XVI
|
|
Management of the Work by Contractor and
Owner
|
|
30
|
|
ARTICLE XVII
|
|
Consultants
|
|
31
|
|
ARTICLE XVIII
|
|
Insurance
|
|
31
|
|
ARTICLE XIX
|
|
Hazardous Materials
|
|
31
|
|
ARTICLE XX
|
|
Materials and Equipment
|
|
32
|
|
ARTICLE XXI
|
|
Substitutions
|
|
33
|
|
ARTICLE XXII
|
|
Changes in the Work
|
|
35
|
|
ARTICLE XXIII
|
|
Inspection and Testing
|
|
37
|
|
ARTICLE XXIV
|
|
Ownership and Use of Documents;
Confidentiality
|
|
38
|
|
ARTICLE XXV
|
|
Nondisclosure
|
|
39
|
|
ARTICLE XXVI
|
|
Owner’s Right To Perform Work And to
Award Separate Contracts; and Cooperation with Separate
Contractors
|
|
40
|
|
ARTICLE XXVII
|
|
Equal Opportunity
|
|
40
|
|
ARTICLE XXIII
|
|
Claims For Damages
|
|
41
|
|
ARTICLE XXIX
|
|
Additional Provisions
|
|
41
|
THIS AGREEMENT,
made as of the 4
th
day of November, 2005,
by and between DENDREON CORPORATION, having an office at 3005 First
Avenue, Seattle, Washington, 98121 (“Owner”), and THE
HENDERSON, having an office at 575 State Hwy. 28, Raritan, New
Jersey, 08869 (“Contractor”).
W I T N E S S E T H
:
WHEREAS, Owner intends to develop a therapeutic
biotechnology processing facility at 220 Hanover Avenue, Hanover,
New Jersey (the “Project”).
WHEREAS , Contractor has been advised that, under
separate agreement, Owner has retained the services of
Perkins & Will, to provide certain architectural services
for the Project (the “Architect”); Affiliated Engineers
NW, Inc. to provide certain engineering services for the Project
(the “Engineer”); and AES Clean Technology, Inc., to
provide certain design and build services for the clean room to be
located within the Project (the “Design Builder” and
collectively the Architect, Engineer and Design Builder shall be
referred to as “Architect”) and such other required
consulting engineers, design build professionals and Architects
(the “Consultants”) as deemed necessary by Owner to
prepare preliminary and final plans, specifications, working
drawings and other construction documents for the Project (the
final versions of which are hereinafter collectively referred to as
the “Construction Documents”); and
WHEREAS , Contractor has been advised that, pursuant to
this Agreement, Owner intends to retain the services of Contractor
(a) to consult with Owner and Architect in the preparation of
the Construction Documents and (b) to perform construction
related services and to arrange for, monitor, supervise, administer
and contract for the construction (collectively the
“Work”) of all or any portion of the Project, all as
more particularly set forth in Article II hereof; and
WHEREAS , Contractor desires to be retained by Owner to
perform, or cause to be performed, the Work;
NOW, THEREFORE
, in consideration of the mutual
covenants and agreements contained herein, Contractor and Owner
hereby agree as follows.
ARTICLE I
Contract
Documents
1.01 The contract documents
(collectively, the “Contract Documents”) shall consist
of the following:
(a) This Agreement, including all
the Exhibits annexed hereto and made a part hereof;
(b) The Construction Documents
identified on Exhibit “A” hereto, and such other
Construction Documents as may hereafter be prepared by Architect or
Consultants and approved in writing by Owner;
(c) Any form of trade contractor
approval letter as Owner may use to evidence its approval of the
award of “Trade Contracts” to “Trade
Contractors” (as such terms are defined in Section 8.01
hereof) (the “Trade Contractor Approval
Letter”);
(d) Change Orders, Emergency Change
Orders and Field Orders (as such terms are defined in Article XXIII
hereof);
(e) The payment and performance
bonds required to be provided by Trade Contractors in accordance
with the provisions of Article XV hereof; and
(f) The Progress Schedule (as
defined in section 7.01(k) hereof) to be initially prepared for the
Work by Contractor and submitted to Owner for its approval in
accordance with the provisions of Section 7.01(k) for the
construction and Final Completion (as such term is defined in
Section 6.01 hereof) of the Work, as the same may be updated,
modified or extended, subject to Owner’s prior approval, in
accordance with the applicable provisions of this Agreement. A copy
of the preliminary schedule, as of the date of this Agreement, is
attached hereto as Exhibit C .
1.02 The Contract Documents form the
contract between Owner and Contractor. References in the Contract
Documents to “the contract” or “this
contract” shall be deemed to include all of the Contract
Documents. References to “this Agreement” or “the
Agreement” shall refer to this instrument, which is one of
the Contract Documents.
1.03 The intent of the Contract
Documents is to include in the Work all labor, materials and
supplies, insurance, tools, equipment, permits (excluding building
and site work permits which shall be paid for by Owner), licenses,
taxes, approvals, transportation, testing and field surveying
(customarily furnished by general contractors) and other services
and items required in connection with the satisfactory performance,
execution and Final Completion of the Work in accordance with the
Contract Documents. Matters not expressly included in the Contract
Documents but which are reasonably inferable therefrom shall be
deemed included as a part of the Work. Controlled inspections, as
required by any governmental authority, shall be provided by the
Owner.
1.04 The Contract Documents are
complementary and cumulative and what is called for by one shall be
as binding as if called for by all.
1.05 Words and abbreviations which
have well known technical or trade meanings are used in the
Contract Documents in accordance with such recognized
meanings.
1.06 If any conflicts or ambiguities
exist in or between the Construction Documents, the Construction
Documents and any of the Contract Documents, or the Construction
Documents and existing conditions at the Project Site, Contractor
shall, immediately upon discovery of such conflict or ambiguity,
bring the same to the attention of Owner for resolution. It is
expressly understood and agreed that Owner, in consultation with
Architect, shall be the interpreter of the Construction Documents
and shall resolve any such conflicts and ambiguities. Any Work
relating to any such conflict or ambiguity which is performed by
Contractor’s own forces or any Trade Contractor
after
2
discovery by Contractor but before Owner has had
a reasonable time to respond to or address such condition, as
provided herein, shall be at Contractor’s or such Trade
Contractor’s sole risk, cost and expense.
1.07 Modifications to parts of the
Contract Documents are for the purpose of varying, modifying,
rescinding or adding to the Contract Documents. All modifications
should be read together with the portions of the Contract Documents
to which they relate.
1.08 The drawings and specifications
comprising the Construction Documents are complementary. Anything
shown in any of the drawings and not mentioned in the
specifications, or mentioned in any of the specifications and not
shown in the drawings, shall have the same effect as if shown or
mentioned in both.
1.09 A typical or representative
detail indicated on the Construction Documents shall constitute the
standard for workmanship and materials throughout corresponding
parts of the Work, unless otherwise shown.
1.10 The layout of mechanical and
electrical systems, equipment, fixtures, piping, ductwork,
conduits, specialty items and accessories indicated on the
Construction Documents is diagrammatic. The actual scope of the
Work shall be carried out so as not to affect the architectural and
structural integrity and limitations of the Project and shall be
performed in such sequence and manner so as to avoid conflicts and
provide clear access to all control points, including valves,
strainers, control devices and specialty items of every nature
related to such systems and equipment in conformance with all
applicable codes; it being agreed Contractor shall not be liable or
responsible for errors, omissions, or coordination deficiencies in,
between or among the Construction Documents. Subject to the
provisions of Section 29.01 hereof, if Contractor discovers or
has knowledge of (i) conflicts in or the shop drawings, the
coordination drawings or the Construction Documents, or
(ii) any conflicts between existing conditions at the Site
(which Contractor is aware of or by testing as agreed to by Owner)
and the Construction Documents which, in Contractor’s
opinion, are of a nature that may affect the architectural or
structural integrity or limitations of the Project, Contractor
immediately shall bring the same to the attention of Owner and
Architect for resolution in the manner provided in
Section 1.06 hereof. Any Work relating to any such conflict
which is performed by Contractor or by any Trade Contractor after
discovery but prior to the resolution of the same shall be borne by
the responsible party in accordance with
Section 1.06
ARTICLE II
Scope of the
Work
2.01 Contractor shall perform all
Construction services described in this Agreement in connection
with the construction of the Work. The general scope of the Work,
as initially reflected in the Construction Documents and as set
forth in Exhibit A, will be developed into a detailed design and
construction program and further refined as the preparation of the
Construction Documents progresses so as to include, and further
define, (i) the scope, parameters and anticipated timing for
the Work, and (ii) Owner’s and Contractor’s
understanding of the quality of the materials and workmanship
required and expected. Contractor represents that (i) it has
fully acquainted itself with
3
the general design concept and scope of the
Work, as reflected in the Construction Documents, (ii) it has
visited the Project site and existing buildings, if any, including
the location of adjacent structures and utilities, and is generally
familiar with access to the Project site and with the observable
condition of any existing buildings. Owner shall be responsible for
obtaining all consents, licenses and easements required from
adjoining property owners.
2.02 In addition to the services
referred to in Section 2.01 hereof, Contractor, shall perform
and furnish, or cause to be performed and furnished all labor,
materials, plant, power, light, heat, water (to the extent that
power, light, heat and water – and the equipment associated
therewith – are not already otherwise available in the
building and are necessary to perform the Work, in which case such
utility costs shall be a Reimbursable Costs in accordance with
Article IV herein ) , telephone, tools, supplies, equipment,
services, transportation, scaffolding, permits, (excluding building
and site permits which shall be paid for by Owner) licenses,
supervision and shall provide all services, business
administration, management, coordination and supervision, necessary
for, or incidental to, the successful prosecution and Final
Completion of the Work, including, but not limited to, all
services, business administration, management, coordination and
supervision of the services provided by AES and all other Trade
Contractors in connection with the Project (the “General
Conditions Work Items”) in the most expeditious and
economical manner, consistent with best industry accepted
standards, strict and complete compliance with codes and ordinances
having jurisdiction over the Work, lawful construction practices
and the interests of Owner relating to quality, timely economical
completion of the Work, to the extent made known to the Contractor.
The Work shall be performed and executed in a customary and
workmanlike manner by qualified and efficient workers, in
conformance with the Contract Documents and best industry trade
practices.
2.03 Contractor agrees to furnish
efficient business administration with emphasis on budget control,
construction scheduling, coordination of the Work, supervision and
Construction in an expeditious and economical manner consistent
with the interests of Owner and shall assist Owner in developing
and maintaining a climate of understanding and good will with all
governmental and quasi-governmental agencies affected by the
Project, the local communities adjacent to the Project site,
proposed tenants and the public at large. Contractor shall require
all Trade Contractors (as such term is defined in Section 8.01
hereof) to comply with Contractor’s instructions related to
storage of materials and scheduling. Contractor shall generally
advise and assist the Owner on all matters concerning the
construction of the Project upon which the Owner requests advice
and assistance and also about all matters concerning which
Contractor, being familiar with the construction industry, might
normally be consulted. All recommendations to be rendered by
Contractor shall be in writing when requested, stating advantages
and disadvantages and evaluating alternatives and shall be in
sufficient detail to enable Owner to analyze such recommendations
and make informed decisions with respect thereto. Without limiting
the foregoing, Contractors’ obligations are more fully
described herein.
2.04 Contractor accepts the
relationship of trust and confidence established between it and
Owner by this Agreement and covenants to Owner to furnish its best
professional skill and judgment and to cooperate with Owner,
Architect and Consultants in furthering the interests of Owner as
made known to Contractor. Contractor understands that it is the
Owner’s intent to construct the Project at a reasonable cost
and in the most expeditious fashion given budgetary considerations.
Accordingly, Contractor will devote its best efforts (consistent
with the Project Budget and Schedule) toward (i)
4
maintaining the cost level of the Project at the
lowest possible point consistent with good construction practices,
(ii) carrying out Owner’s intent and direction of the
Architect’s and Consultants’ Construction Documents and
(iii) achieving the most rapid and efficient construction and
completion of the Project. Contractor will use its best efforts to
bring to the Owner’s attention any possibilities for savings
that may present themselves during the course of Contractor’s
performance under this Agreement and will confer with Owner
periodically in order to determine whether there are any areas
where, by design change or otherwise, costs may be reduced.
Contractor shall not knowingly accept for its own account any trade
discounts, except to the extent permitted by Article IX, or
contributions, or deal with (or recommend that the Owner deal with)
any firm in which Contractor has any financial or other interest,
or undertake any activity or employment which would or could create
a conflict of interest or compromise the Contractor’s
judgment or prevent the Contractor from serving the best interests
of the Owner. If Contractor shall become aware of any facts which
are or may be in violation of the preceding sentence or shall have
any financial or other interest in any firm with which the Owner is
dealing or proposes to deal with in connection with the Project,
Contractor shall immediately advise Owner thereof in writing. It
shall be deemed a conflict of interest and a material breach of the
terms of this Contract, for Contractor to knowingly employ at the
Project, or knowingly recommend acceptance of bids from Trade
Contractors employing, with respect to the Project, any relatives
(including in-laws) of any of the officers or directors, or
executives of the Contractor. Any breach hereunder shall entitle
the Owner to terminate this Agreement upon seven
(7) days’ prior notice.
ARTICLE III
Contract Sum and
Guaranteed Maximum
Price
3.01 As consideration for the full
and complete performance of the Work and all of Contractor’s
obligations hereunder, Owner shall pay to Contractor a sum of money
(“Contract Sum”) equal to the total of:
|
|
(i)
|
a fee
(“Contractor’s Fee”) Contractor’s Fee
includes all overhead (including home office personnel and expenses
not otherwise reimbursable under Section 3.10 hereof) and
profit;
|
|
|
(ii)
|
General
Conditions, as provided in Section 3.03 and;
|
|
|
(iii)
|
Contractor’s Reimbursable Costs as defined
in Article IV hereof.
|
provided, however, that except as
expressly provided herein, the Contract Sum shall not exceed
fifteen million dollars ($15,000,000) (the “Guaranteed
Maximum Price” or “GMP”)
3.02 The Contractor’s Fee
which includes all costs not otherwise identified in this Agreement
and profit shall be a fixed fee of five hundred forty thousand
dollars ($540,000) (“Contractor’s Fixed Fee”),
plus, subject to terms of the Agreement, an additional one hundred
twenty three thousand five hundred fifty five dollars ($123,555)
for obtaining Substantial Completion by July 31, 2006
(“Contractor’s Substantial Completion Fee”) plus
another one hundred twenty three thousand five hundred fifty five
dollars ($123, 555) for achieving Substantial Completion for a
Contract Sum not to exceed the GMP.
3.03 The Contractor’s General
Conditions Costs, as approved in advance by Owner, which are more
fully defined in Section 3.09 below are estimated at one
hundred ninety five thousand dollars ($195,000).
5
3.04 Contractor acknowledges that
the Documents identified on Exhibit “A” annexed hereto
are incomplete and are being developed by Architect. However,
Contractor represents that the documents in Exhibit “A”
contain sufficient information so as to provide Contractor with an
understanding of the scope of the Work and the level of finishes so
as to enable Contractor to prepare the Preliminary Budget which
will be provided to Owner upon completion.
3.05 Unless adjusted by Change Order
pursuant to Article XXII below, in no event shall the Contract Sum
exceed the Guaranteed Maximum Price.
3.06 In the event that the GMP is
adjusted by Change Order as defined in Article XXII below,
Contractor shall be entitled to a Contractors fee of the total of
the actual Reimbursable Costs and actual General Conditions which
are included in such Change Order with no mark-up for
fee.
3.07 Payments on account of the
Contractor’s Fee and General Conditions, shall be paid
monthly, simultaneously with each progress payment made to
Contractor under Article XI hereof. The proportion of the
Contractor’s Fee earned at the date of any Application for
Payment (as such term is defined in Section 11.01(a) hereof)
shall be calculated as defined in Section 11.01 for the Work
completed in such Application for Payment. All payments to
Contractor shall be subject to the hold-back requirements set forth
in Article 3.08 below.
3.08 Unless otherwise agreed to by
Owner and Contractor, Owner shall make progress payments to
Contractor pursuant to the provisions of Article XI hereof, subject
to a hold-back on the Trade Contract Costs (hereinafter defined)
(including payments to Trade Contractors for the performance of
General Conditions Work Items pursuant to Trade Contracts) in an
amount equal to ten percent (10%) of each such Trade
Contractor Costs.
6
3.09 The General Conditions Costs
shall include, but not be limited to, the following:
(a) Rates for the following
classifications of personnel and who provide services in connection
with the Work and for such time as is actually devoted to the Work,
Project Executive, Project Manager, Project Engineer(s), Assistant
Project Manager(s), Estimator(s), Project Superintendent(s),
Assistant Superintendent(s), On-site Safety Coordinator,
Mechanical/Electrical Project Manager(s) and Superintendent(s),
Project Accountant(s), Timekeepers, Teamsters, Master Mechanics,
Elevator Operators, Operating Engineers, laborers, personnel
engaged (e.g. at shops or on the road) in expediting the production
or transportation of materials or equipment, clerical and data
processing personnel, estimators, schedulers and
accountants;
(b) actual costs and expenses
incurred in connection with telegrams, telephones (and charges),
fax, messenger service, blueprinting, xeroxing, photographs, field
office, trailers, correspondence and other similar petty cash items
directly related to the Work; and
(c) Actual costs of all temporary
structures and their maintenance, less the reasonable salvage value
obtainable on such items which are used but not totally consumed in
the performance of the Work; provided, however, that at
Owner’s option and at its direction, Contractor either shall
(i) deliver all such temporary structures to Owner,
(ii) use reasonable efforts to sell the same for the account
of Owner, or (iii) discard the same in the manner set forth in
Section 6.06 hereof;
(d) Rental charges and maintenance
expenses for any temporary structure necessary in connection with
the performance of the Work, including the installation, erection,
removal, transportation and delivery costs thereof;
(e) Rental charges of all machinery
and equipment (exclusive of hand tools) used at the Project site
and necessary in connection with the performance of the Work,
together with costs incurred in the installation thereof, and the
dismantling, removal, transportation and delivery of the
same;
(f) Actual costs incurred by
Contractor in performing General Conditions Work Items by
Contractor’s own labor force or by Trade Contractors retained
by Contractor to perform the same, provided such costs are not
back-chargeable or deductible from any other Trade Contractor for
any reason;
(g) license fees necessary for the
performance of the Work, fines, violations or penalties
and
(h) legal and accounting fees
reasonably incurred in performance of the Work, excluding any legal
and accounting fees incurred by Contractor (i) as a result of
failure of Contractor (as opposed to Trade Contractors) to perform
in accordance with this Agreement, or arising out of the negligence
of Contractor or (ii) provided Owner has paid Contractor,
wrongful failure of Contractor to pay any Trade Contractor,
supplier or others in connection with the Project and
(iii) arising out of or related to the negotiation of this
Agreement.
7
ARTICLE IV
Reimbursable
Costs
4.01 In addition to the
Contractor’s Fee, and General Conditions payable hereunder,
and Owner shall reimburse Contractor for the actual costs
necessarily incurred by Contractor in the proper performance of the
Work (hereinafter the “Reimbursable Costs”), which
Reimbursable Costs shall be at rates not higher than those which
are competitive and prevailing in the locality for work and
services similar to the Work and shall be comprised of the costs
listed in Subsections (a) through
(f) hereunder:
(a) costs of freight, trucking and,
subject to Owner’s prior written approval, the warehousing of
materials required for the Work;
(b) payments made by Contractor for
work performed and materials, supplies and equipment furnished
pursuant to Trade Contracts and/or Purchase Orders (and Change
Orders) approved by Owner in accordance with the provisions of this
Agreement (“Trade Contract Costs”);
(c) Federal, State and local sales,
use, excise, personal property and other similar taxes, if any,
which may be required to be paid by Contractor in connection with
the Work, except taxes applicable, directly or indirectly, to the
Contractor’s Fee;
(d) actual costs reasonably and
necessarily incurred due to an emergency, not compensated by
insurance, affecting the safety of persons or property, except to
the extent caused by Contractor’s negligence or
Contractor’s intentional failure to comply with the terms of
this Agreement. As a condition precedent to payment for such costs
Contractor must give written notice to Owner within 48-hours after
incurring such costs;
(e) premiums for insurance as
required in Exhibit B.
(f) additional utility costs as per
paragraph 2.02
4.02 Contractor shall use its best
efforts to minimize the Reimbursable Costs incurred in the
performance of the Work, consistent with the intent and purposes of
this Agreement, sound business practice and the reasonable
instructions of Owner.
ARTICLE V
Non-Reimbursable
Costs
5.01 Except to the extent included
in Section 3.09 or Article IV, Owner shall not reimburse
Contractor for any of the following costs, all of which shall be
borne by Contractor at its sole cost and expense:
(a) salaries or other compensation
of any principals and branch office heads of Contractor.
8
(b) expenses of operating
Contractor’s home and branch offices, including overhead and
administrative expenses except to the extent that such expenses are
reimbursable pursuant to the provisions of Section 3.09 or
Article IV hereof;
(c) any part of Contractor’s
capital expenses, including interest on capital employed in
connection with the Work;
(d) (i) costs not reimbursed by
insurance, due (x) to the negligent acts or omissions or
willful misconduct of Contractor, or Contractor’s failure to
perform its obligations under this Agreement or (y) from the
violation by Contractor of any Federal, State or local laws,
ordinances or statutes; (ii) casualty losses and related
expenses sustained by Contractor in connection with tools,
equipment, supplies and other personal effects owned or rented by
Contractor; and (iii) any other costs which would have been
insured but for the failure of Contractor to carry the insurance
required to be carried hereunder or the failure of Contractor to
comply with the requirements of any insurance carriers providing
insurance coverage for the Project, as set forth in Exhibit
B hereof;
(e) costs of uncovering, correcting
or replacing defective Work which has arisen by reason of
Contractor’s gross negligence or intentional breach of this
Agreement or failure to properly supervise or coordinate the
Work;
(f) losses, costs, and expenses
(including attorneys’ fees and disbursements) incurred by
Contractor in connection with, or as a result of, the occurrence of
any event expressly provided for under the terms of this Agreement
wherein Contractor agrees to indemnify and hold harmless Owner
against such losses, costs and expenses (except Owner shall
reimburse Contractor for legal fees incurred in discharging or
bonding Trade Contractor mechanic’s liens as provided for in
Section 3.10(i);
(g) General Conditions Costs which
are back-charged to or are deducted from any Trade Contractor for
any reason;
(h) costs incurred by reason of
Contractor’s failure to comply with its obligations under
this Agreement, including costs in the form of penalties, fines or
other similar charges, as well as any and all costs incurred in
contravention of laws, rules and regulations attributable to
Contractor’s gross negligence;
(i) except as otherwise provided in
Subsection 4.01 hereof, premiums for other insurance carried by
Contractor;
(j) costs of any item expressly
excluded from, or not expressly included within, the items referred
to in Section 3.09 or 4.01 hereof; and
(k) costs of any item or expense
which this Agreement provides are to be paid or borne by Contractor
at its sole cost and expense.
9
ARTICLE VI
Schedule of the Work and Early
Occupancy
6.01 Contractor shall commence the
Work hereunder within ten (10) days of receipt and by
Contractor of a Notice to Proceed and shall promptly and diligently
perform its responsibilities hereunder such, so that the Work shall
be (a) Substantially Completed (as defined herein) on or
before July 31, 2006 (“Substantial Completion
Date”), and (b) completed on or before the date which is
ninety (90) days from the latest Substantial Completion Date
(“Final Completion Date”), in each case as set forth in
the Progress Schedule, subject to adjustments as hereinafter
provided, including Contemplated Delays (as defined in
Section 6.02 hereof).
The Work shall be deemed
substantially completed (“Substantial Completion”) on
the date when the Work shall be sufficiently completed and all of
the following shall have occurred: (a) Owner may use and
occupy the Project without interference for all of its intended
uses, (b) only minor Punch List items (as such term is defined
in Section 7.02(cc) hereof), if any, remain incomplete
provided they do not interfere with such use and occupancy and
(c) a temporary certificate of occupancy shall have been
issued by the appropriate local governmental authority for such
portion of the Work. The Work shall be deemed finally completed
(“Final Completion”) on the date when the Work shall
have been finally completed and Owner shall have received
satisfactory evidence, that:
(a) all Work, including all items
set forth on the Punch Lists (as defined in Section 7.02(cc)),
has been fully and satisfactorily completed in a good and
workmanlike manner, in conformance with the Contract Documents and
in full compliance with all applicable laws, rules, requirements
and regulations of all governmental authorities having jurisdiction
over the Work;
(b) all final certificates of
approval relating to the Work, including a Final Certificate of
Occupancy of the entire Work and the contemplated uses of the
Project, including, without limitation, all necessary
certifications of any entity having jurisdiction thereof or any
successor thereto, shall have been issued and delivered to the
Owner unless the failure to secure said approvals is related to the
design of the Project, and unless the inability to secure such
certificates is beyond Contractor’s reasonable control;
and
(c) all required receipts, releases
of liens, affidavits, waivers, guarantees, warranties, bonds,
as-built drawings and any other documents required under this
Agreement or the Trade Contractors shall have been issued and
delivered to Owner.
6.02 Anything contained in the
foregoing provisions of this Article VI to the contrary
notwithstanding, if and to the extent that there are hindrances to,
or delays in, the performance of the Work by reason of Contemplated
Delays (as such term is defined in this Section 6.02) and if
Contractor demonstrates that the Work is actually hindered or
delayed thereby, any Substantial Completion Date or the Final
Completion Date, as the case may be, shall be postponed by the
actual number of days attributable to each such demonstrated cause.
For purposes of this Agreement, “Contemplated Delays”
(a) shall be deemed to include delays or hindrances caused by
(i) the acts or
10
omissions of Owner and Architect (including
Change Orders providing for an extension of time and suspensions of
work pursuant to Article XXII below), as well as (ii) strikes,
(iii) fire, (iv) acts of God, (v) acts of the public
enemy, (vi) unavailability of, or inability to obtain, labor
or materials by reason of shortages which affect the supply or
availability of labor or materials, (vii) floods,
(viii) rebellions, riots, insurrections or sabotage,
(ix) labor disputes provided such disputes are beyond
Contractor’s control and provided Contractor takes all
responsible steps possible to remediate them,
(x) Manufacturer’s inability to deliver completed
product to the Project site unless such failure to deliver is
caused by the negligence of Contractor, (xi) severe weather
conditions, (xii) concealed conditions and Hazardous
Materials, and (b) shall be recognized only if Contractor has
used its best efforts to minimize the period of delay or hindrance
by means which include, without limitation, seeking alternate
sources of labor or materials or acceleration of the Work, but such
efforts shall not require Contractor to incur any additional costs.
If Contractor wishes to make a claim for an extension of the
Substantial Completion Date or the Final Completion Date by reason
of a Contemplated Delay, Contractor shall give notice (in
accordance with the provisions of Section 29.08 hereof) to
Owner of such claim within ten (10) days after knowledge of
any Contemplated Delay, which notice shall set forth in detail the
nature of each Contemplated Delay, the date or dates upon which
each cause of delay began (and ended), the number of days of delay
attributable to each such cause, and the action taken, or to be
taken, by Contractor to minimize the period of delay if possible.
Any such extension shall be deemed accepted by Owner only if
reflected in a validly issued Change Order which acceptance shall
not be unreasonably withheld or delayed.
6.03 In furtherance of the
provisions of Sections 6.01 and 6.02 hereof, Contractor shall
include in all Trade Contracts, whether for labor or materials or
both, a provision entitling Contractor to terminate or cancel such
Trade Contract in the event of a breach thereby by the Trade
Contractor or any other occurrence or omission thereunder which
would result in a delay in, or hindrance to, the timely progress of
the Work.
6.04 Contractor shall notify Owner
promptly if the Work will not be completed within the time provided
for in the Project Schedule. If Contractor so notifies Owner, or
if, in the opinion of Owner reasonably exercised, Contractor falls
behind in the Project Schedule for any reason other than a
Contemplated Delay, Contractor shall take appropriate action to
improve the progress of the Work and shall, if requested by Owner,
submit operational plans to demonstrate the manner in which the
lost time may be regained if possible.
6.05 On or before the Substantial
Completion Date, Contractor shall clear, or cause to be cleared,
the Project Site and the Project of any debris, construction
materials, rubbish, rubble, discarded equipment or spillage caused
by Contractor or its Trade Contractors of solid or liquid waste in
full compliance with all applicable environmental laws, shall
remove all tools, construction equipment, machinery and surplus
materials, and shall maintain the Project free of such items
(attributable to Contractor’s work) until Final Completion.
In addition, on or before the Substantial Completion Date,
Contractor shall clean, or cause to be cleaned in broom clean
condition the Project, as provided in the Construction Documents.
If the Project or the Project site are injured or damaged by
Contractor, in the course of Contractor’s cleaning or
removal, Contractor, without increase to the Guaranteed Maximum
Price, promptly shall repair and restore the portion thereof so
damaged or injured to its condition immediately prior to such
damage or injury in a manner satisfactory to Owner
11
and Architect. If Contractor fails to undertake
or cause the undertaking of the aforesaid cleaning, removal and
repairs, in such event, the Owner may, at Owner’s sole
option, avail itself of any of the remedies provided in this
Agreement and, subject to giving 48 hours’ prior written
notice to Contractor, Owner may also perform, or cause to be
performed, the aforesaid cleaning, removal and repairs and, in such
event, all additional expenses incurred by Owner in connection
therewith, at Owner’s option, shall be reimbursed to Owner
either (a) by Owner not paying Contractor monies then due or
next becoming due from Owner to Contractor hereunder, or
(b) by Contractor paying such amounts to Owner on demand,
after rendition of a bill or statement therefor.
6.06 Prior to Substantial Completion
of the Work, Owner or Owner’s designees shall have the right
to use or occupy all or any portion of the Project or to install or
cause the installation of furniture, furnishings and equipment
therein, or to allow other contractors to perform tenant work,
provided that such occupancy shall not materially interfere with
Contractor’s performance of its obligations hereunder
(including harmonious labor relations) and, provided further, that
Owner or Owner’s designees, as the case may be, shall be
liable for any delay, or personal injuries to, or death of, any
person and for property damage, to the extent the same is caused by
the acts or omissions of Owner or Owner’s designees, as the
case may be, in connection with their aforesaid use or occupancy of
the Project. Such use or occupancy by Owner or Owner’s
designees shall not (a) constitute acceptance by Owner of any
element of the Work or the space, systems, materials or equipment
incorporated in the Project, (b) be construed as a waiver of
any right or claim by Owner in connection with any Work, or
(c) affect the obligations of Contractor or any Trade
Contractor for any Work which is not in accordance with this
Agreement, the respective Trade Contracts or the Contract
Documents. Contractor shall continue performance of the Work in a
manner which shall not unreasonably interfere with the aforesaid
use, occupancy and operation by Owner or Owner’s designees.
Contractor agrees that it shall not unreasonably interfere with, or
object to, such use or occupancy by Owner or Owner’s
designees and that it shall cooperate with Owner and any designated
occupants to facilitate such early occupancy.
6.07 Owner and Owner’s
designees shall have the right of access to the entrances, loading
facilities and such other services as Contractor shall be using or
providing to the Project. Such right of access shall be subject to
the reasonable rules of Contractor, which rules (a) shall be
for the sole purpose of coordinating such access and for observing
all safety and precautionary measures, and (b) shall not
hinder, prohibit or interfere with such access. In addition, Owner
may require the use and operation of any completed heating,
ventilating or air conditioning equipment at the time that Owner or
Owner’s designees occupy or use any portion of the
Project.
ARTICLE VII
Contractor’s
Work
7.01 Pre-Construction Phase .
Contractor agrees that during the pre-construction phase of the
Work (the “Pre-Construction Phase”), it shall perform
the following services:
(a) consult with Owner and Architect
to ascertain Owner’s needs and goals and the requirements of
the Work;
12
(b) thoroughly review all
preliminary plans and specifications, and all revisions and
additions thereto, for the purpose of preparing and submitting to
Owner preliminary budgets (“Construction Budget”), to
be in such form and contain such detail as required by Owner and
which Construction Budget shall be revised as requested by Owner or
more frequently if Owner so requires;
(c) provide assistance to, and
cooperate with Owner and Architect in obtaining all necessary
approvals of governmental authorities having jurisdiction over the
Project;
(d) thoroughly investigate existing
conditions at the Project Site and consult with and advise Owner
and Architect concerning all materials and major design, building
systems and construction elements to be incorporated in the Work,
taking into consideration costs, availability, lead time for
ordering materials, speed of construction and
maintenance;
(e) review estimates, if any, of
Architect and Consultants with respect to the costs of the
Work;
(f) review the Construction
Documents (but without assuming Architect’s responsibility
for errors and omissions) as they are being prepared for the
purpose of making recommendations, and make recommendations to
Owner and Architect with respect to the following:
(i) the availability of labor,
materials and supplies;
(ii) elimination of possible
conflicts and/or overlapping jurisdictions among the various trades
or overlapping responsibilities among Trade Contractors;
(iii) variations from customary
construction practices and methods which, in the opinion of
Contractor, may cause difficulties or occasion delay in the
performance of the Work, it being expressly understood that by
review of the Construction Documents under this entire paragraph,
Contractor shall not thereby assume responsibility for design
errors and omissions;
(iv) discrepancies and deficiencies
in the Construction Documents, or between the Construction
Documents and existing conditions at the Project;
(v) costs of labor, supplies,
materials and equipment to be used in the performance of the
Work;
(vi) unit prices and
alternates;
(vii) required temporary and Project
support facilities; and
(viii) construction economies
through alternative methods, materials, or concepts, consistent
with Owner’s requirements and sound construction
practice;
(g) establish, implement and observe
all safety, health and environmental protection
13
measures during performance of the Work,
consistent with the requirements of all applicable Federal, State
and local laws, rules and regulations; submit to Owner, and
periodically update, as necessary, appropriate or may be required,
safety plans for the Project showing the manner in which the
aforesaid measures are implemented; and designate a responsible
person or persons of Contractor’s office organization, as
site safety coordinator. The performance of such services by
Contractor shall not relieve it or any of the Trade Contractors of
their respective responsibilities for the safety of persons and
property in compliance with this Agreement and all statutes, rules,
regulations and orders applicable to the Work;
(h) in consultation with Owner and
Architect, develop the most favorable way of bidding the Work,
including, without limitation, the size and scope of each bid
package, and dates of bidding and use of “fast-track”
methods;
(i) make a labor survey, including
an analysis of the costs, types and quality of labor required for
the Work and a forecast of the availability thereof as and when
needed, including a survey and schedule of the dates of all union
labor contracts coming up for renewal during the projected period
of construction;
(j) make recommendations regarding,
and render assistance necessary for, the development and
administration of an effective labor relations program for the Work
and the avoidance of labor disputes during the performance of the
Work and assist in negotiating any agreements with labor
unions;
(k) in consultation with Owner and
Architect and as expeditiously as is required for the orderly and
timely completion of the Project, prepare and submit to Owner for
its approval, a progress schedule for the performance of the Work,
make such modifications thereto as Owner may reasonably request
and, upon Owner’s approval of the same (which, subsequent to
such approval is hereinafter referred to as the “Progress
Schedule”), make no further modifications thereto without
first in each instance obtaining Owner’s prior approval
thereof. The Progress Schedule shall also (i) set forth a
construction time schedule which identifies all major and critical
components of the Project and the Work, including Architect’s
preparation of design documents, all major and critical design
details and all matters relating to Trade Contractors and Trade
Contract awards, and which identifies Owner’s
responsibilities, if any, with respect to the design documents, and
(ii) from and after the date that the same is available,
incorporate the information described in this Section 7.01.
Contractor agrees that the Progress Schedule shall not be amended,
modified or extended without Owner’s prior written
approval;
(1) advise and make recommendations
to Owner and Architect regarding the best order and sequence for
the development of the Construction Documents;
(m) maintain written records of all
communications with, and recommendations made to, Architect, and
Architect’s responses thereto; make the same available for
inspection by Owner at all times and promptly furnish to Owner
copies of all correspondence between Contractor and Architect
relative to the Work and the Project;
14
(n) advise and consult with Owner
and obtain Owner’s approval of, Trade Contractors qualified
to bid the various packages of the Work as well as methods of, and
the form of, Trade Contract awards, and award Trade Contracts all
in the manner set forth in Article VIII hereof;
(o) review with Trade Contractors
all methods and materials that may be used in connection with the
Work and make recommendations to Owner and Architect regarding
changes, if any, to the Construction Documents;
(p) make a materials survey,
including an analysis of all materials and equipment required for
the Work and a forecast of the availability thereof as and when
needed, including advice of any factors or potential occurrences
then known by Contractor which might affect the future availability
of such materials and equipment and coordinate all purchases of
materials and equipment; and
(q) assist Owner in connection with
the pre-purchasing of any long-lead materials and/or equipment to
be incorporated in the Work.
Contractor agrees to perform such
other and additional services similar in type and obligation to
those listed above, prepare such other reasonably requested
schedules, reports, budgets and other technical data, and attend
such meetings during the Pre-Construction Phase as Owner may
reasonably request in order to assist in the preparation of the
Construction Documents, cost estimates, updated Progress Schedules
and any other documents and instruments relative to the Work and
the Project, to the end that Final Completion of the Work may be
brought and maintained within the Guaranteed Maximum Price and
Substantial Completion Date.
7.02 Construction Phase .
Contractor agrees that during the construction phase (the
“Construction Phase”) of the Work, which Construction
Phase shall commence immediately upon Owner’s notification to
Contractor that current tenant has vacated the Hanover, NJ facility
and shall terminate on the date of Final Completion of the Work, it
shall perform the following services:
(a) establish procedures for the
orderly and expeditious performance and Final Completion of the
Work in accordance with the terms of this Agreement; perform, or
require to be performed, all Work necessary in connection
therewith; establish procedures for administration of Trade
Contracts; and maintain coordination among Trade
Contractors;
(b) prepare Project site
organization and lines of authority in order to carry out the Work
on a coordinated basis;
(c) organize staff and assign
personnel, as approved by Owner, to various areas to provide a
positive and efficient means by which the Work may be controlled,
coordinated and expedited;
(d) in consultation with Owner and
Architect, update the latest Construction Budget prepared in the
course of the Pre-Construction Phase, setting forth in such manner
and detail as Owner may require, all anticipated costs of the Work
for (i) all Trade Contractors performing labor or furnishing
materials under Trade Contracts, other than Trade Contracts awarded
solely for the
15
performance of General Conditions Work Items, on
a trade-by-trade and square foot basis, (ii) all of the
Contractor’s personnel and labor referred to in
Section 3.06(a) hereof, and (iii) all General Conditions
Work Items, broken down on an itemized, line item basis, and
segregated to reflect those portions of said General Conditions
Work Items which are to be performed by Contractor and those
portions which are to be performed by Trade Contractors; update
monthly, in consultation with Owner and Architect, and submit to
Owner for its approval, such Construction Budget, and make such
adjustments thereto, including adjustments by reason of approved
Change Orders and Emergency Change Orders, to keep Owner currently
informed as to the anticipated aggregate Costs of the Work.
Contractor agrees that if there exists any factor, event or
occurrence of any kind which in Contractor’s opinion,
inhibits or prevents the furnishing of accurate cost forecasts,
then and in such event, Contractor promptly shall so advise Owner
in writing;
(e) coordinate the scheduling of the
Work;
(f) require submission of, and
review, progress schedules of Trade Contractors and make
adjustments to such schedules as appropriate in an effort to
continue the expeditious Final Completion of the Work within the
time periods set forth in the Progress Schedule;
(g) except as otherwise provided in
Article XXIII hereof, obtain Owner’s written approval of any
changes in the Work and any approvals or other documents necessary
in connection therewith;
(h) conduct necessary job and
coordination meetings, which job meetings shall be held not less
often than weekly unless not required and which coordination
meetings shall be held as required, and attend all such
meetings;
(i) prepare agendas and detailed
written minutes of each job and coordination meeting and furnish
copies thereof to Owner and Architect;
(j) prepare and maintain Project
record keeping system, including records of all changes in the Work
necessitated by reason of Change Orders, Emergency Change Orders
and Field Orders, Work progress schedules, daily manpower
breakdown, shop drawing logs, material lists, records of all
pertinent communications with, and recommendations made to,
Architect and its responses thereto, and daily reports recording
manpower breakdowns on a trade-by-trade basis with a description of
the Work being performed each day by each trade, equipment and
material deliveries, visitors, special occurrences, weather
conditions, and other Work related information and make such
on-Project Site records available for inspection to Owner (and, if
required by Owner, to Architect and/or Consultants). In addition,
copies of all correspondence pertaining to the Work shall be
maintained by Contractor and shall be made available at all times
to Owner;
(k) submit to Owner each month a
“Job Progress Report” which shall describe the
following: (i) the financial condition of the Work, including
Trade Contract awards, Project modifications, anticipated cost
summary and Change Order summary; (ii) construction status,
including updated Progress Schedules with projected critical dates,
status of job progress to date, current Work activity, projected
Work activity for the following month and job photos;
(iii) drawing status and (iv) any issues that may impact
the above schedule and cost.
16
(1) require that Trade Contractors
submit and assemble and review, brochures, guarantees, certificates
of compliance and other agreements and instruments;
(m) obtain and review for
constructability (but not as a substitute for Architect’s
technical review) all shop drawings, samples and catalog cuts
submitted by Trade Contractors and comment to Owner and Architect
on their form and any significant inconsistencies between the shop
drawings and the Construction Documents; and after Contractor shall
so review said documents it shall promptly submit the shop drawings
to Architect for review and approval. Architect shall review and
return to Contractor all shop drawings and other submittals within
ten (10) business days. After return of the shop drawings from
Architect, review Architect’s comments to the shop drawings;
and distribute them to the submitting Trade Contractor and all
other affected parties so that the Work may be properly coordinated
and implemented into the Project. Contractor shall not be
responsible for design errors and omissions. Contractor shall use
its best efforts to discover and resolve any conflicts between shop
drawings submitted by Trade Contractors; Contractor acknowledges
and agrees that as part of its obligations under this Agreement,
Contractor and its Trade Contractors are to prepare and submit shop
drawings and other submissions, conduct coordination meetings and
prepare coordination drawings for the purpose of coordinating the
work required of Contractor and its Trade Contractors. Owner shall
require the attendance of Architect at coordination meetings, when
requested by Contractor. This process, in part, is intended to
recognize and resolve design conflicts in advance of fabrication
and installation of the various components of the Work. Contractor
agrees that it shall expeditiously and thoroughly prepare and
submit shop drawings and conduct and conclude the coordination
effort at the earliest possible time so as to facilitate the
recognition and resolution of conflicts, including errors in the
Construction Documents, such that any adverse effects on the
progress of the Work are avoided to the fullest extent reasonably
possible. Similarly, the proposal of substitutions in accordance
with Article XXIII of this Agreement shall be conducted at the
earliest possible time. Nothing herein shall relieve Contractor
from its own failure to comply with its obligations with respect to
shop drawings, samples and catalog cuts;
(n) at the Project Site, on a
current basis:
(i) maintain, and make available to
Owner, Architect and/or Consultants, copies of any records with
respect to Trade Contracts, shop drawings, samples, operating
manuals, the Construction Documents, equipment and any and all
other related documents and any revisions to any of the foregoing
which may arise out of, or be related to, this
Agreement;
(ii) maintain and provide, and make
available to Owner, Architect and/or Consultants, progress photos
taken on a monthly basis according to a plan, as previously
approved by Owner; and
(iii) upon final completion of the
Work, deliver to Owner copies of a complete set of marked
“as-built drawings”, with respect to mechanical,
electrical and plumbing showing the Work, as actually completed,
together with copies of all operating instructions and maintenance
manuals (bound and indexed); and
17
(o) establish and coordinate with
Owner a system for processing, expediting and administering all
Trade Contracts for the purchase of materials, supplies and
equipment. Manage the procurement and delivery of critical
materials to the Project Site and coordinate the deliveries with
the progress of the Work;
(p) notify Owner and Architect of
the progress of the Work, and advise Owner, in accordance with the
provisions of Article VI hereof, of any delays or serious potential
delays which may affect Substantial Completion of the Work and of
Contractor’s recommendations regarding such
delays;
(q) inspect and coordinate the work
of all Trade Contractors, enforce the terms of their respective
Trade Contracts and enforce strict discipline and good order among
all Trade Contractors in an effort to see that the Work is
performed in accordance with the terms of such Trade Contracts, the
Contract Documents, recognized trade standards and the applicable
laws, rules and regulations of governmental authorities having
jurisdiction over the Work and endeavor to guard Owner against any
delays, increased costs and defects and deficiencies in the Work.
In connection with the foregoing, Contractor shall (i) require
any Trade Contractor to stop the performance of any Work which
Contractor observes is not in compliance with the requirements of
its respective Trade Contract, the Contract Documents, recognized
trade standards or the applicable laws, rules and regulations of
any governmental authorities having jurisdiction over the Work;
(ii) reject and require to be corrected, those portions of the
Work which Contractor discovers does not conform to the
requirements of the applicable Trade Contract, the Contract
Documents, recognized trade standards or the applicable laws, rules
and regulations of any governmental authorities having jurisdiction
over the Work; (iii) inspect all materials, supplies and
equipment delivered or installed in connection with, or pursuant
to, any Trade Contract in an effort to determine that the same are
in compliance with the requirements of the applicable Trade
Contract, the Contract Documents, recognized trade standards and
the laws, rules and regulations of all governmental authorities
having jurisdiction over the Work and reject and require
replacement of all non-conforming materials, supplies and
equipment; and (iv) not employ on the Work any person or Trade
Contractor unfit for or unskilled in the assigned task and, remove
such unfit or unskilled employee or such Trade Contractor from the
Project site;
(r) arrange for all cutting, fitting
or patching that may be required to complete the Work or to make
its several parts fit together properly;
(s) use best efforts to resolve
disputes between Trade Contractors relative to the performance of
their work or the furnishing of materials, supplies or equipment in
connection with the Work;
(t) arrange for the storage of all
materials, supplies, systems and equipment provided in connection
with the performance of the Work;
(u) maintain the Project site in a
safe and orderly fashion and provide Project site clean-up of the
Work on a regular basis during the course of construction, and also
upon Substantial Completion and Final Completion, as provided in
this Agreement;
18
(v) enforce the implementation of
necessary safety, health and environmental protection measures (as
required under Subsection (g) of Section 7.01 hereof)
during the performance of the Work, which shall include, without
limitation, the erection and maintenance of all reasonable
safeguards and the posting of danger signs and other warnings
against hazards, conduct inspections and require that all Trade
Contractors comply with all Federal, State and local safety,
health, equal opportunity and environmental protection and other
requirements, laws, rules and regulations as well as all necessary
safety, health and environmental protection measures as provided
herein applicable to the Work;
(x) prepare a schedule of values and
Applications for Payment in a form reasonably approved by Owner;
determine, prior to the submission of each Application for Payment,
whether and to what extent the sums requested herein are due and
payable; and certify to the best of Contractor’s knowledge,
information and belief the same to Owner;
(y) make recommendations with
respect to any changes Contractor may consider necessary or
desirable in connection with the Work (including, but not limited
to, events of force majeure or Contemplated Delay), it being
understood and agreed that, except as otherwise provided in
Section 23.05 and 23.06 hereof, no changes to the Contract
Documents may be made in connection with the Work without the prior
written approval of Owner;
(z) issue to Trade Contractors
(i) all Change Orders approved by Owner, and (ii) all
Emergency Change Orders and Field Orders in the manner and in
accordance with the provisions set forth in Article XXIII
hereof;
(aa) with respect to portions of the
Work to be performed pursuant to a Change Order, an Emergency
Change Order, or a Field Order, on a time and material, unit-cost
or other similar basis, keep and require the keeping of records and
computations thereof and maintain accurate cost accounting records,
and provide copies thereof to Owner;
(bb) review all Trade
Contractors’ insurance documents for compliance with the
provisions of their respective Trade Contracts. Inform Owner of any
deficiencies in said coverage;
(cc) assist Owner in determining
when Substantial Completion of the Work has taken place; subsequent
to Substantial Completion of the Work, prepare (in consultation
with Architect) lists of incomplete or unsatisfactory Work
(“Punch Lists”) and perform or cause to be performed,
and supervise all work necessary to complete the items set forth on
the Punch Lists; provided, however, that the failure to include any
element of the Work on such Punch Lists shall not alter the
responsibility of Contractor and/or Trade Contractors to complete
the Work in accordance with the Contract Documents; and subsequent
to the completion of all items set forth on th