Back to top

CHANGE ORDER NUMBER 123108AW TO ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES FIXED PRICE CONTRACT

Construction Agreement

CHANGE ORDER NUMBER 123108AW TO ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES FIXED PRICE CONTRACT | Document Parties: AVENTINE RENEWABLE ENERGY HOLDINGS INC You are currently viewing:
This Construction Agreement involves

AVENTINE RENEWABLE ENERGY HOLDINGS INC

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: CHANGE ORDER NUMBER 123108AW TO ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES FIXED PRICE CONTRACT
Date: 3/16/2009
Industry: Chemical Manufacturing     Sector: Basic Materials

CHANGE ORDER NUMBER 123108AW TO ENGINEERING, PROCUREMENT AND CONSTRUCTION SERVICES FIXED PRICE CONTRACT, Parties: aventine renewable energy holdings inc
50 of the Top 250 law firms use our Products every day

Exhibit 10.5.2

 

CHANGE ORDER NUMBER 123108AW

TO

ENGINEERING, PROCUREMENT AND

CONSTRUCTION SERVICES

FIXED PRICE CONTRACT

LOCATION: AURORA, NEBRASKA

 

 

THIS CHANGE ORDER (“Change Order”) is made and entered into effective as of December 31, 2008 (the “Effective Date”) by and between Aventine Renewable Energy - Aurora West, LLC (“Owner”) and Kiewit Energy Company (“Kiewit”).

 

WHEREAS, Owner and Kiewit are parties to that certain Engineering, Procurement and Construction Services Fixed Price Contract dated May 31, 2007 (the “Contract”); and

 

WHEREAS, pursuant to Article 6 of the Contract, Owner provides the following as written direction to Kiewit to make certain changes in the Work, and Kiewit by its signature below accepts such direction.

 

 

1.

Capitalized terms not defined herein shall have the meaning set forth in the Contract.

 

 

2.

Pursuant to Section 9.5 of the Contract, Owner directed Kiewit to suspend the Work on the Plant as of November 14, 2008 (the “Date of Suspension”).

 

 

3.

Pursuant to the terms of the Contract, Owner owes Kiewit $16,609,020 (subject to the Dispute Resolution procedures referenced below), which amount includes $10,528,171 not previously invoiced for the agreed progress of the Work completed as of the Date of Suspension, $3,824,929 previously invoiced as due and owing for Work performed in October 2008 for which payment was deferred, and $2,255,920 for sales and use tax.  Such amount is due and owing to Kiewit as of December 24, 2008, and may be subject to adjustment which may be mutually agreed upon by Kiewit and Owner or determined pursuant to the Dispute Resolution procedures set forth in Article 18 of the Contract.  Such amount shall be paid by Owner to Kiewit in accordance with the payment schedule set forth in Section 12 below.  Nothing contained in the Change Order shall be deemed to constitute the creation of indebtedness of Owner under any of its loan documents and the amount owing hereunder arose in the ordinary course of business of Owner.

 

 

4.

In addition to the amounts Owner owes Kiewit in Section 3, the parties agree that Owner shall pay Kiewit the following:  (i) Kiewit’s costs, with no profit or mark-up to be paid by Owner, associated with the directed suspension of the work in the lump sum amount of $2,936,600, and (ii) $2,000,000 as an allowance for the amounts invoiced by Kiewit’s subcontractors and material subcontractors (collectively the “Subcontractors”) for such Subcontractors’ suspension costs, plus a mark-up of twenty percent (20%) of such invoiced costs (“Subcontractors’ Suspension Costs”), which amounts, to the extent not disputed by Owner, shall be paid by Owner to Kiewit in accordance with the payment schedule set forth in Section 12 below.  Such amount includes payment for the

 

 


 

 

 

 

Suspension Services defined below.  Kiewit will work with Owner, and shall allow Owner to work with Kiewit’s Subcontractors (to the extent allowed under the terms of such subcontracts), in an effort to reduce the Subcontractors’ Suspension Costs.  Disputes regarding the validity or amount of the Subcontractors’ Suspension Costs claims and Kiewit invoice(s) based thereon will be resolved pursuant to Article 18 of the Contract.

 

 

5.

If the total Subcontractors’ Suspension Costs exceed the allowance provided for in Section 4 above, the additional amount of Subcontractors’ Suspension Costs in excess of the allowance shall be added to the amount owed by Owner to Kiewit pursuant to this Change Order and shall be paid as an additional payment on July 31, 2009 in accordance with the provisions of Section 12 below.  If the total Subcontractors’ Suspension Costs do not exceed the allowance provided for in Section 4 above, Kiewit will credit the difference between the allowance and the actual Subcontractors’ Suspension Costs to the last amounts payable to Kiewit in accordance with Section 12 of this Change Order.

 

 

6.

Owner and Kiewit agree that the Work may be suspended for up to 180 days from the Date of Suspension (the “Suspension Period”).  If Owner is not in default of the payment obligations specified in this Change Order, Owner may terminate the Suspension Period and direct Kiewit to resume construction of the Work following the delivery to Kiewit of (i) 10 days advance written notice to resume the Work and (ii) reasonable evidence reasonably satisfactory to Kiewit that Owner can satisfy the remaining financial obligations of this Change Order and the Contract and (iii) payment in full of all remaining amounts payable under this Change Order (without consideration of the schedule in Section 12 below); provided, however, that nothing in this Change Order shall be construed to limit or restrict Kiewit’s entitlement to an equitable adjustment to the Contract Sum arising from the suspension (including costs associated with re-mobilization and rescheduling of the Work) and the Schedule in connection with such suspension in accordance with Article 6 of the Contract.

 

 

7.

If the Suspension Period expires without the Owner’s termination of the Suspension Period in accordance with the terms of the Contract and this Change Order, the Contract shall be deemed to have been terminated for the Owner’s convenience under Section 9.4 of the Contract, and Owner shall pay Kiewit any amounts due Kiewit under Section 9.4 of the Contract and all remaining payments due under this Change Order (without consideration of the schedule in Section 12 below);  provided there shall be no duplication of payments under Section 9.4 of the Contract and this Change Order.  Notwithstanding the provision contained in the first sentence of Section 9.4, Owner may enter into a contract with another entity to complete construction of the Plant, if Owner has made all payments due Kiewit under Section 9.4 of the Contract and all remaining payments due under this Change Order; provided there shall be no duplication of payments under Section 9.4 of the Contract and this Change Order.

 

 

8.

During the Suspension Period, all Contract milestone dates and Schedule deadlines are tolled and, in the event of re-mobilization, shall be reestablished by change order pursuant to Article 6 of the Contract; provided, however, that in the event of such remobilization, Kiewit shall be excused from the notice requirements contained in Sections 6.2 and 6.3 of the Contract.  The amounts set out in Sections 3, 4 and 5 above

 

 

 

2


 

 

 

and the rental payments or demobilization costs for the Cranes as set forth in Section 15 below shall be the only amounts due to Kiewit for costs associated with the Suspension Period; provided that nothing in this sentence shall preclude Kiewit from entitlement to a change order as set forth in Section 6 above in the event the Suspension Period is terminated.

 

 

9.

For so long as Owner complies with the payment provisions of this Change Order, Kiewit will provide qualified personnel on the Plant Site to perform necessary maintenance of equipment in accordance with equipment manufacturer’s operation and maintenance manuals (collectively the “Suspension Services”) during the Suspension Period.  Other than the Suspension Services, Kiewit has no obligation during the Suspension Period to continue performance of the Work at the Plant Site.  During the Suspension Period, Kiewit shall have no obligation to comply with the requirements of 10.2 (Security), 11.1 (Kiewit Representatives), 11.3 (Project Reviews and Approvals) and 20.11 (Time is of the Essence) and, except to the extent that Kiewit has previously received payment or receives funds from the Owner in accordance with the payment schedule set out in Section 12, Kiewit shall be excused from any requirement under the Contract to keep the project lien free with respect to those liens filed by Subcontractors which represent amounts unpaid under such subcontract, or to indemnify and/or reimburse the Owner with respect to such liens.  During the performance of the Suspension Services, Owner shall have access to the Plant Site, but in no event shall Owner be entitled to modify the Work completed to the Date of Suspension nor shall Owner be entitled to operate any equipment existing on the Plant Site without Kiewit’s prior written consent.

 

 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more