CHANGE ORDER FORM

Construction Agreement

CHANGE ORDER FORM | Document Parties: Cheniere Sabine Pass Pipeline Company | Willbros Engineers, Inc You are currently viewing:
This Construction Agreement involves

Cheniere Sabine Pass Pipeline Company | Willbros Engineers, Inc

. RealDealDocs™ contains millions of easily searchable legal documents and clauses from top law firms. Search for free - click here.
Title: CHANGE ORDER FORM
Date: 8/11/2008
Industry: Oil and Gas Operations     Sector: Energy

CHANGE ORDER FORM, Parties: cheniere sabine pass pipeline company , willbros engineers  inc
50 of the Top 250 law firms use our Products every day

EXHIBIT 10.4

CHANGE ORDER FORM

PROJECT NAME: 42-inch Sabine Pass Pipeline Project

COMPANY: Cheniere Sabine Pass Pipeline Company

CONTRACTOR: Willbros Engineers, Inc.

CHANGE ORDER NUMBER: CO-017

DATE OF CHANGE ORDER: May 12, 2008

DATE OF AGREEMENT: February 1, 2006

The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)

This change order is for accounting purposes to move the charges associated with an electrical cable relocation at Duck Blind road from CO-010 to CO-017. At Cheniere’s direction, Willbros made payments directly to Jeff Davis Electric Coop in the amounts shown on the attached Willbros invoices. Jeff Davis services and the amounts paid were outside Willbros’ construction scope of work covered by CO-010. Originally, Jeff Davis invoices were handled as a provisional amount associated with engineering in CO-010.

Adjustment to price under the Agreement:

 

 

 

 

The original Guaranteed Maximum Price was

  

$

67,670,200

Net change by previously authorized Change Orders #1 - 16

  

$

2,510,650

The Guaranteed Maximum Price prior to the Change Order was

  

$


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more