AMENDED & RESTATED
AGREEMENT
FOR CONSTRUCTION OF HOKU
ELECTRIC SUBSTATION
AND ASSOCIATED
FACILITIES
THIS AMENDED
& RESTATED AGREEMENT for the construction of Hoku electric
substation and associated facilities (the “Agreement”)
is entered into as of the __ 17th _______ day of __
September ____, 2008 by and between HOKU MATERIALS, INC.,
One Hoku Way, Pocatello, Idaho 83204 (“Hoku”) and IDAHO
POWER COMPANY, P.O. Box 70, Boise, Idaho 83707 (“Idaho
Power” or “IPCO”). Hoku and IPCO may also be
referred to hereinafter individually as “Party” or
collectively as the “Parties”.
RECITALS
A.
Hoku is developing a manufacturing
plant to produce polysilicon, a key material used in the production
of solar cells and integrated circuits. The construction of an
electric substation and associated transmission facilities is
required to allow IPCO to supply electric capacity and energy to
Hoku’s manufacturing complex located at One Hoku Way in
Pocatello, Idaho (“Hoku Facility”). Hoku has requested
that the substation and associated facilities be sized to allow
IPCO to provide electric service to the Hoku Facility in an amount
up to 82 Megawatts (“MW”) of demand.
B.
Hoku and IPCO are parties to that
certain Agreement for Construction of Hoku Electric Substation and
Associated Facilities dated December 28, 2007 (the “Prior
Agreement’). This Agreement shall amend and restate in its
entirety, the Prior Agreement.
C.
Because the Hoku Facility will be
located in an area where Idaho Power does not have existing
facilities of adequate capacity, delivery of power to the Hoku
Facility site will require the construction of (1) approximately
six (6) miles of 138,000 volt overhead transmission line to
interconnect with Idaho Power’s existing transmission system,
(2) a new 138,000-13,800 volt electric substation at the Hoku
Facility to supply up to 82 MWs with two 67 MVA transformers, and
(3) additional equipment and facilities at IPCO’s existing
substations. These facilities are sometimes hereinafter
collectively referred to as the “Requested Facilities”
and are described in greater detail in Exhibit 1 to this Agreement.
This Agreement is not subject to or governed by Rule H, Idaho
Power’s tariff governing line installations, including any
revisions to that rule, or any successor rules or
schedules.
D.
Idaho Power will construct the
Requested Facilities in accordance with the terms and provisions of
this Agreement.
E.
Pursuant to the Prior Agreement,
HOKU has paid Idaho Power the sum of $7,402,000, the receipt of
which is hereby acknowledged by Idaho Power. An outstanding balance
of $3,701,000 is presently owed under the prior Agreement and is
hereby acknowledged by Hoku. This outstanding amount is included in
the payments listed in Section 2.1 below.
NOW, THEREFORE,
in consideration of the mutual obligations and undertakings set
forth herein, and other good and valuable consideration, the
sufficiency of which is hereby acknowledged, Hoku and Idaho Power
agree as follows:
AGREEMENTS
1.
Construction of Requested
Facilities Without
duplicating any of the work performed pursuant to the Prior
Agreement, and in furtherance thereof:
1.1
Idaho Power will construct the
Requested Facilities to provide for the delivery of power
(capacity) at a point generally described as the load side
terminals of the substation transformer 13.8 kilovolt
(“kV”) disconnect switches at the Hoku Facility (the
“Delivery Point”).
1.2
Idaho Power will use commercially
reasonable efforts to provide up to 20 MW of transmission service
from the Alameda Substation by May 18, 2009. Requested facilities,
including the second transmission line from the Don Substation,
will be constructed and ready to serve up to 43 MW of demand by
July 19, 2009. Idaho Power will use commercially reasonable efforts
to complete final construction of the Requested Facilities by
August 19, 2009. However, Hoku recognizes that Idaho Power’s
ability to complete the Requested Facilities on or before that date
is subject to the receipt of the payments and performance under the
contract from Hoku as described herein, Idaho Power’s ability
to obtain required labor, materials and equipment, timely receipt
of satisfactory easements and rights of way, and timely receipt of
governmental regulatory authorizations.
1.3
If Idaho Power fails to meet the
completion deadline described above, and such failure is not
excused as provided in Section 1.2, the Parties agree that Hoku may
submit the matter to the Idaho Public Utilities Commission
(“Commission”) for appropriate relief, and pending
final resolution, Hoku’s obligation to make further payments
pursuant to the terms of this Agreement shall be
suspended.
2.1
Excluding amounts previously paid
for design and engineering expenses, and including the amounts paid
pursuant to the Prior Agreement, the total cost for the
construction of the Requested Facilities is estimated to be
$16,542,000. Hoku’s payments to IPCO
constitute a Contribution In Aid of Construction
(“CIAC”) and include a tax gross-up of thirty-one
percent (31%) to cover IPCO’s resulting income tax liability.
Hoku shall pay IPCO in the amounts and at the times specified
below:
|
September 30,
2008
|
|
|
|
|
|
October 15,
2008
|
|
|
|
|
|
November 15,
2008
|
|
|
|
|
|
December 15,
2008
|
|
|
|
|
At the
completion of the project, Idaho Power will provide a true-up of
the actual work order costs to the $16,542,000 estimate. Idaho
Power will provide Hoku a report that will reflect actual dollars
charged to the project by labor, materials, purchased services,
overheads, and other expenses. Idaho Power will refund to Hoku any
over collected amounts; any amounts under collected will be
invoiced to Hoku with the refund or payment to be made to Idaho
Power within 30 days from the true-up date. In the event of
significant scheduling changes, the payment milestones will be
delayed or accelerated accordingly. The total estimated cost of the
Requested Facilities does not include costs associated with use of
any temporary substations, transmission or distribution facilities
that may be necessary to provide Hoku with temporary demonstration
power prior to the expected August 19, 2009, completion date.
The cost of such temporary facilities will
be invoiced to and paid by Hoku separately from this Agreement and
has no impact on the performance of either party under this
Agreement.
2.2
If Hoku fails to pay an amount due
on or before the payment milestone date specified in Section 2.1,
any obligation of Idaho Power to further perform under this
Agreement will be suspended pending receipt of such payment. If,
after Idaho Power’s delivery to Hoku of notice that such
payment has not been received, Hoku fails to make such payment
within ten (10) days of Idaho Power sending such notice, Idaho
Power may, in its sole discretion, terminate this Agreement. Hoku
acknowledges that any delay in payment is likely to result in a
schedule delay pursuant to Section 1.2 of this Agreement. If this
Agreement is terminated by Idaho Power pursuant to this Section
2.2, Idaho Power shall refund to Hoku any porti
|