Exhibit 10.9
AGREEMENT FOR GUARANTEED MAXIMUM
PRICE
CONSTRUCTION
SERVICES
CHANGE ORDER
30 December 2004
|
|
|
|
|
Project: Wynn Las Vegas
|
|
Change Order
No.: 7
|
|
|
|
|
“Contractor”:
MARNELL CORRAO ASSOCIATES,
INC.
222 Via Marnell Way
Las Vegas, Nevada 89119
|
|
“Owner”:
WYNN LAS VEGAS, LLC
3131 Las Vegas Boulevard
So.
Las Vegas, Nevada 89109
|
That certain Agreement for
Guaranteed Maximum Price Construction Services between Owner and
Contractor for Wynn Las Vegas (“Project”) dated as
of June 4, 2002 (“Contract”) is hereby modified as
follows:
The Scope of Work associated with
Change Order No. 7 is detailed in the following Change Order
narrative by project area. It should be noted that the Owner
generally agrees with the Scope of the Work but reserves the right
to perform a detailed audit of the Change Order documentation
pursuant to the terms of this Agreement. Subsequent adjustments, if
any, will be credited to the Cost of the Work:
|
|
1.
|
Revised
Machine Roof Steel
|
Provide added and modified steel at
the machine room roof at the tower roof level. All work shall be
completed in accordance with Butler Ashworth Architect’s
Highrise drawing revisions dated 12 April 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-43 dated 15 October 2004,
$33,970 .
|
|
2.
|
Added
Platform for Window Washing Stage Access
|
Provide structural detailing,
fabrication and erection of added platform for rooftop window
washing stage access. All work shall be completed in accordance
with Butler Ashworth Architects’ structural drawings dated 15
July 2004, 21 July 2004 and item No. 346 of the Project Meeting
Minutes.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-44 dated 6 October 2004,
$262,000 .
Provide five (5) added roof ladders
for access to high roof areas and perimeter catwalk for window
washing stages. All work shall be completed in accordance with
Lochsa Engineering sketches LESK54 thru LESK66 dated 10 September
2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-45 dated 15 November 2004, as
modified and agreed upon 21 December 2004, $108,618
.
|
|
5.
|
Catwalk
Level Added Staging Rooms
|
Provide framing, drywall, doors,
frames and hardware for catwalk level staging rooms at stair Nos. 1
– 3. All work shall be completed in accordance with Butler
Ashworth Architects’ NOC HR037 dated 30 June 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-55 dated 15 October 2004,
$7,927 .
|
|
6.
|
Sorting
Golden Beach Marble
|
Provide labor to related to the
sorting, re-packaging and stocking of Tower guestroom marble due to
color shade variation and edge chipping on floors 25, 26, 27 and
28. All work is in accordance with WDD Field Directive of 3 March
2004 and 3 May 2004 letter to MCA.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-35 dated 23 June 2004 as
modified and agreed upon, $67,136 .
- 2 -
|
|
7.
|
Repair
Damaged/Broken Marble Material
|
Reimbursement to T. Nickolas for
repairs to damaged and broken marble materials as itemized on T.
Nickolas broken material logs from 14 November 2003 through 17 June
2004. All work in accordance with WDD field direction in support of
the project schedule.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-37 dated 22 September 2004,
$88,652 .
|
|
8.
|
Repairing
Damaged/Broken Marble Material
|
Reimbursement to T. Nickolas for
repairs to damaged and broken marble materials as itemized on T.
Nickolas broken material logs from 22 June 2004 through 10 November
2004. All work in accordance with WDD field direction in support of
the project schedule.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 70102-38 dated 23 November 2004,
$55,519 .
|
|
1.
|
Control
Valves for Gas Meters
|
Provide 16” control valves for
the gas meters for the central plant boilers. All work shall be
completed in accordance with WDD direction.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71102-02 dated 22 October 2004,
$32,660 .
|
|
2.
|
Electrical
Revisions per 6/28/04 Drawings
|
Provide door wiring revisions and
related electrical changes and power to trash compactors provided
by Owner’s vendor. All work shall be completed in accordance
with Butler Ashworth Architects’ revised electrical drawings
dated 28 June 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71102-10 dated 8 November 2004,
$61,846 .
- 3 -
|
|
3.
|
Employee
Entrance Canopy
|
Provide foundations, concrete
walkway, 260 lf of awning structure, wall panel system, fire
sprinkler and electrical/lighting work. All work shall be completed
in accordance with Butler Ashworth Architects design criteria as
issued 10/20/04 including subsequent clarification sketches issued
in support of Arup report dated 12/10/04.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71102-16 dated 17 December 2004 as
modified and agreed upon to reflect reduced lighting scope 22
December 2004, $186,233 .
|
|
4.
|
Removable
Patio Railing
|
Provide removable aluminum railing,
in lieu of steel railing, along the Grand Patio due to weight
concern. All work shall be completed per WDD field
direction.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71102-13 dated 30 November 2004,
$6,524 .
|
|
5.
|
Mail Room
Mechanical Emergency Shunt
|
Provide electrical work for the
installation of an emergency mechanical system shut-off switch in
the Mail Room. All work shall be completed in accordance with
Butler Ashworth Architects’ revised sketches dated 10
December 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71102-15 dated 17 December 2004,
$3,868 .
|
|
1.
|
Relocate
Mechanical Piping
|
Relocate existing mechanical piping
from the mezzanine level to the Casino Level due to equipment
conflicts. All work shall be completed in accordance with Butler
Ashworth Architects NOC LR-2-107 dated 27 August 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. LR-2-107 dated 12 September 2004,
$32,429 .
- 4 -
|
|
2.
|
Relocate
Mechanical Mains
|
Relocation of the existing piping
mains to accommodate the reorientation of PCH coils. All work shall
be completed in accordance with Butler Ashworth Architects’
revised mechanical drawings LR-S-2-MPZ.05 dated 1 June
2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71202-7/1/04 dated 1 July 2004,
$72,598 .
|
|
3.
|
Casino
Linear Diffuser Modifications
|
Change 8’ linear diffusers to
44” due to curvature of adjacent millwork. Provide
non-functional linear diffuser infill between the 44”
diffusers for aesthetic purposes. All work shall be completed in
accordance with verbal direction provided during a field review
meeting by WDD.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71202-05 Rev. 1 dated 9 July 2004,
$89,968 .
|
|
4.
|
Performance
Lounge Redesign
|
Provide all additional work related
to the modification of the existing Performance Lounge design into
an Ultra Lounge concept. All work shall be completed in accordance
with revised Butler Ashworth Architects’ and WDD Interior
Design drawings dated 1 June and 28 June 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Revised Change Proposal Request No. 71202-12 dated 30 December
2004, $1,004,987 .
|
|
5.
|
Revisions
per 28 June 2004 Drawings
|
Provide framing, drywall, plumbing,
mechanical piping, fan coil units, sheet metal, electrical and
lighting work in the Performance lounge raised floor area and
patio, Mezzanine Level, Casino Level, Spa Level. All work shall be
completed in accordance with Butler Ashworth Architects’ and
WDD Interiors drawing revisions dated 28 June 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71202-15 dated 15 November 2004,
$477,199 .
- 5 -
|
|
6.
|
Spa and W.
Ink Pen / Sunglasses Store Mechanical, Plumbing and Electrical
Revisions
|
Provide all work related to base
building modifications associated with revised operational program
including but not necessarily limited to added fire sprinklers and
piping for the Spa Tanning Room; install piping and connections to
fan coil unit serving the pen and sunglasses store; install fan
coil unit and associated ductwork in pen and sunglasses store;
miscellaneous mechanical and ductwork changes at the Spa Level and
restrooms. All work shall be in accordance with Butler Ashworth
architects’ revised mechanical, plumbing and electrical
drawings dated 26 August 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71202-17 dated 15 November 2004,
$127,778 .
Provide lighting revisions in the
Race & Sports Book, added dryers in the Spa and re-circuiting
of Spa exhaust fans. All work shall be completed in accordance with
Butler Ashworth Architects’ revised electrical drawings dated
20 September 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No.71202-18 as revised and agreed upon
per MCA letter of 23 December 2004, $10,000 .
Provide framing, drywall, taping and
sealing work. All work shall be completed in accordance with Butler
Ashworth Architects’ NOC’s, Design Change Directives,
Clark County Building Department Notifications and Architectural
Directives issued between 28 June and 16 October 2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No.71202-24 dated 21 December 2004,
$615,082 .
|
|
9.
|
Cancellation
of Sound Attenuated Ceilings at Mechanical Rooms
|
De-mobilization and materials cost
for the cancelled sound attenuated ceiling added per Butler
Ashworth Architects’ drawing LR-M2A3.03. The ceilings were
canceled on 1 June 2004 pursuant to a conversation between Perry
Eiman of MCA and Todd Nisbet of WDD. Approved cost for portion of
Work that was completed and associated re-stocking fees for
isolation hangers.
- 6 -
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No. 71202-25 dated 21 December 2004,
$17,185 .
|
|
10.
|
Bombard
Electrical Extra Work Ticket Revisions
|
Provide miscellaneous extra
electrical work. All work shall be completed in accordance with
Butler Ashworth Architects’ NOC’s, Design Change
Directives, Clark County Building Department Notifications and
Architectural Directives issued between 28 June and 26 September
2004.
Increase to Guaranteed Maximum
Price. Total increase per
MCA Change Proposal Request No.71202-26 dated 27 December 2004,
$492,800 .
|
|
1.
|
Nightclub
Budget Validation
|
Reconcile C