Title: PROFESSIONAL SERVICES AGREEMENT
Date: 5/10/2007

PROFESSIONAL SERVICES AGREEMENT, Parties: cassco amaizing energy  llc , engineerg snyder & associates  inc
50 of the Top 250 law firms use our Products every day
 

Exhibit 10.18

PROFESSIONAL SERVICES AGREEMENT
NORTHWEST WATER AND SEWER EXTENSION, 2007
ATLANTIC, IOWA

I.

 

NAME OF PARTIES OF THE AGREEMENT

This Agreement, made and entered into this 28 TH day of December, 2006, by and between the CASSCO Amaizing Energy, LLC, hereinafter called “OWNER” and Snyder Associates, Inc., 1800 West 22nd Street, Suite 200, Atlantic, Iowa, a corporation, hereinafter called “ENGINEER” as follows:

II.

 

NAME OF PROFFESSIONAL SERVICE

The OWNER shall retain the ENGINEER to complete Professional Services for the preparation of preliminary concepts and design, final design of construction plans and specifications, contract documents, right-of-way and easement acquisitions, bid letting and construction services to include staking, observation and administration, for work described as the Northwest Sewer and Water Extension, including installation of water mains, sanitary sewer mains, and necessary appurtenances thereto from an industrial development site located in northwest Atlantic to the existing municipal system, hereinafter called the “PROJECT.”

III.

 

SCOPE OF WORK

 

A.

 

GENERAL

The ENGINEER shall provide Professional Services as required to complete the preparation and assembly of the PROJECT as named in Article II and as described hereinafter as follows:

 

1.

 

The PROJECT will be divided into Right-of-Way (ROW) Services, Basic (design) Services, Bid Services and Construction Services:

 

 

 

 

 

2.

 

The ENGINEER will assist the OWNER in obtaining geotechnical information and will complete acquisition plats, design, plans and specifications, construction documents, bid letting, construction staking, administration and observation, and final project acceptance for the proposed PROJECT.

 

B.

 

RIGHT-OF-WAY SERVICES

Upon award of this contract, the ENGINEER will provide Right-of-Way Services as follows:

 

1.

 

Determine ROW needs for the project route.

 

 

 

 

 

2.

 

Prepare plats.

 


 

 

 

C.

 

BASIC ENGINEERING SERVICES

The ENGINEER will provide the Basic Engineering Services as follows. Payment shall be made as specified in Article VI of this Agreement.

 

1.

 

PROJECT ADMINISTRATION

The ENGINEER shall perform the following administrative services during the design of the PROJECT:

 

a.

 

Progress reports as requested to the OWNER.

 

 

 

 

 

b.

 

Monthly billing reports.

 

 

 

 

 

c.

 

Project coordination for engineering and coordination with the OWNER, land owners, and utility companies.

 

 

 

 

 

d.

 

Project design review.

 

 

 

 

 

e.

 

Miscellaneous meetings to review progress, and attend informal meetings, Board meetings and Public Hearings.

 

2.

 

TOPOGRAPHY SURVEY

The ENGINEER will perform field surveys as necessary to provide sufficient information for the design of the proposed improvements.

 

3.

 

PRELIMINARY DESIGN PHASE

The ENGINEER will prepare preliminary design drawings and review said drawings with the OWNER for the following improvements:

 

a.

 

Provide preliminary water and sewer layout,

 

 

 

 

 

b.

 

Provide quantities for selected alternative.

 

4.

 

FINAL DESIGN PHASE

 

 

a.

 

The ENGINEER shall prepare construction documents for the PROJECT. The plans shall include, but not be limited to, the following information:

 

 

Extension of existing water main

 

 

 

Connection to existing system

 

 

 

 

 

 

8” PVC water main, valves, fittings, bends, etc

 

 

 

 

 

 

Fire hydrants

 

 

 

 

 

 

Bore and encasement beneath roadways and railroads

 

 

 

 

 

 

Service Connections, curb stop, etc.

 

 

Extension of existing sanitary sewer main:

 

 

 

Connection to existing system

 

 

 

 

 

 

10” PVC sewer main, fittings, etc.

 

 

 

 

 

 

Manholes

 

 

 

 

 

 

Bore and encasement beneath roadways and railroads

 

 

 

 

 

 

Service Connections

 

 

 

 

 

 

Profile of sewer main and existing ground

 

 

Surface restoration

The design shall be the responsibility of the ENGINEER. During this

 


 

process, the ENGINEER shall prepare and apply for any necessary permits that might be required for the construction of the PROJECT.

 

b.

 

Soils Investigation and Materials Testing — Should it be determined necessary, the ENGINEER shall utilize the services of private testing laboratories for soils investigation for the PROJECT. The proposal for these services shall be approved by the OWNER prior to authorization to proceed. The OWNER shall be responsible for payment for those services directly to the testing laboratory.

 

 

 

 

 

c.

 

Probable Costs — The ENGINEER shall prepare a statement of the total probable cost for the PROJECT based upon the design developed. Statements of probable construction costs prepared by the ENGINEER represent the best judgment as a design professional familiar with the construction industry. It is recognized, however, that the ENGINEER has no control over the cost of labor, materials or equipment, over the Contractor’s methods of determining bid prices, or over competitive bidding or market conditions. Accordingly, the ENGINEER does not guarantee that any actual cost will not vary from any cost estimate prepared by the ENGINEER.

 

D.

 

BID SERVICES

Upon receipt of OWNER authorization under the Final Design Phase as described herein, the ENGINEER shall perform the following services:

 

a.

 

Construction Contract Documents — The PROJECT will be let by the OWNER and the ENGINEER shall supply the necessary documents for this process.

 

 

 

 

 

b.

 

Advertising — The ENGINEER shall answer questions from potential contractors, subcontractor and suppliers, and coordinate with OWNER staff during this phase of services.

 

 

 

 

 

c.

 

Bidding — The ENGINEER shall attend the meeting at which bids are received, tabulate the bids and make recommendations to the OWNER regarding the awarding of the construction contract to the lowest qualified bidder.

 

E.

 

CONSTRUCTION SERVICES

 

 

1.

 

CONSTRUCTION ADMINISTRATION PHASE

Upon award of the construction contracts, the ENGINEER shall perform the following administrative services during construction of the PROJECT:

 

a.

 

During the construction phases, the ENGINEER shall specify the testing of materials and administrative procedures to be as directed by the ENGINEER.

 

 

 

 

 

b.

 

Preconstruction Conference — The ENGINEER shall arrange and conduct a preconstruction conference with the Contractor and OWNER to review the contract requirements, details of construction, utility conflicts and work schedule prior to construction.

 

 

 

 

 

c.

 

Site Observation — The ENGINEER shall visit the construction site, at such times and with such frequency deemed necessary by the ENGINEER, to (a)

 


 

 

 

 

observe the progress and (b) determine if the results of the construction work substantially conforms to the drawings and specifications in the Construction Documents. Site Observation does not include observation or administration of the Storm Water Pollution Prevent Plan (SWPPP) which is the sole responsibility of OWNER (See Article III. G. 2., herein).

 

d.

 

Contractor Payment Requests — The ENGINEER shall review the requests of the contractor for progress payments and shall approve a request, based upon site observations, which authorizes payments and is a declaration that the contractor’s work has progressed to the point indicated.

 

 

 

 

 

e.

 

Notification of Nonconformance — The ENGINEER shall notify the OWNER of any observed work, which does not conform to the construction contract, make recommendations to the OWNER for the correction of nonconforming work and, at the request of the OWNER, see that these recommendations are implemented by the contractor.

 

 

 

 

 

f.

 

Shop Drawings — The ENGINEER shall review shop drawings and other submissions of the Contractor for general compliance with the construction contract.

 

 

 

 

 

g.

 

Change Orders — The ENGINEER shall prepare change orders for approval of the OWNER.

 

 

 

 

 

h.

 

Substantially Complete and Final Site Observation — The ENGINEER shall perform a site observation to determine if the PROJECT is substantially complete according to the plans and specifications and make recommendation on final payment for each construction phase.

 

 

 

 

 

i.

 

During the Construction Services Phase, the ENGINEER shall confer with the OWNER’S Project Officer to report PROJECT status.

 

 

 

 

 

j.

 

If the Contractor exceeds the estimated working and/or calendar days in completing construction of the PROJECT, or if change orders or PROJECT additions require additional working days, the ENGINEER will be compensated for administration, inspecting and staking services based on established hourly rates and fixed expenses outlined in the Engineer’s Standard Fee Schedule (Attachment A).

 

 

 

 

 

k.

 

Final Acceptance — It is understood that the OWNER will accept any portion of the PROJECT only after recommendation by the ENGINEER. Final acceptance of the PROJECT by the OWNER shall not be deemed to release the Contractor from responsibility for insuring that the work is done in a good and workmanlike manner, free of defects in materials and workmanship nor the ENGINEER for his liability of design.

 

 

2.

 

CONSTRUCTION STAKING

The ENGINEER shall be responsible for providing all construction stakes for the PROJECT. The construction documents will contain a provision that the ENGINEER will provide one set of stakes for each construction operation. Any staking that is destroyed due to construction that has to be replaced, will be at the Contractor’s expense.

 


 

 

3.

 

CONSTRUCTION OBSERVATION

The ENGINEER will provide one or more Resident Engineer or Resident Construction Observer for the PROJECT as required during the Construction Phases. If the Contractor requests a waiver of any provisions of the plans and specifications, the ENGINEER will make a recommendation on the request to the OWNER for their determination. No waiver shall be granted if such waiver would serve to reduce the quality of the final product. The OWNER shall never be deemed to have authorized the ENGINEER to consent to the use of defective workmanship or materials. The Resident Engineer or Construction Observer will give guidance to the PROJECT during the construction periods, including the following:

 

a.

 

Setting and/or checking of lines and grades required during construction.

 

 

 

 

 

b.

 

Observation of the work for general compliance with plans and specifications. Observation does not include observation or administration of the Storm Water Pollution Prevent Plan (SWPPP), if any is required for the site, which is the sole responsibility


 
SITE SEARCH

AGREEMENTS / CONTRACTS

Document Title:

Entire Document: (optional)

Governing Law:(optional)


Try our advanced search >>
 

CLAUSES

Search Contract Clauses >>

Browse Contract Clause Library>>

Get Email Updates
Email:
This is only a partial view of this document. We have millions of legal documents and clauses drafted by top law firms. learn more search for free browse for free learn more