Exhibit 10.27
ADDENDUM
TO THE AGREEMENT FOR THE ENGINEERING, PROCUREMENT AND CONSTRUCTION
OF A WAVE ENERGY POWER PLANT SIGNED ON JULY 27, 2006 BETWEEN
IBERDROLA ENERGIAS MARINAS DE CANTABRIA, S.A. AND OCEAN POWER
TECHNOLOGIES LIMITED.
Made
and entered into in Madrid on February 18, 2008.
B
E T W E E N
Of the
one part,
IBERDROLA ENERGIAS MARINAS DE CANTABRIA, S.A., with
registered offices in Santander, Cantabria, Calle Amos de
Escalante, number 6, 2B, represented by Mr. Javier Garcia
Perez, with Spanish Identification Document number 30.604.192-R and
Mr. Rafael de Icaza de La Sota, with Spanish Identification
Document number 16.035.858-M, in his capacity as attorneys, as
accredited by means of the deed of incorporation of the company
signed on September 25, 2006 before the Notary of Madrid
Mr. Miguel Raiz-Gallardon Garcia de la Rasilla under number
7.567 of his protocol (the “ CLIENT ”).
And,
of the other part,
OCEAN
POWER TECHOLOGIES LIMITED , a company incorporated in England
and Wales Company No. 5225532) with its registered
office at Warwick Innovation Centre, Gallows Hill, Warwick CV334
6UW, United Kingdom, represented by Mr. Mark Draper, with UK
Passaport number 80061626, in his capacity as Director of Company
(the “ CONTRACTOR ”).
The
CLIENT and the CONTRACTOR shall hereinafter be referred to
collectively as the “ Parties ”, and
individually as “ Party ”.
W
H E R E A S
| I. |
|
Whereas, in July 27, 2006, the Parties have signed an
Agreement for the Engineering, Procurement and Construction of a
Wave Energy Power Plant (hereinafter, the “ EPC
Agreement ”). |
| |
| II. |
|
Whereas, the Parties have agreed to modify the milestones and
the regulation of the PAC and the DAC and other terms of the EPC
Agreement, so it suits better with the development of the Works,
namely to accommodate a separate completion of the installation,
commissioning, PAC and DAC for the PowerBuoy PB40ES and associated
mooring system, on the one hand, and the Subsca cable and
Underwater Substation ‘Pod’ on the other. |
| III. |
|
In virtue of the aforesaid, the Parties, hereby execute this
Addendum to the EPC Agreement (the “ Addendum
”), which will be governed by the following clauses: |
CLAUSE 1
CHANGES TO CLAUSE 1 OF THE EPC AGREEMENT; REFERENCES TO DEFINED
TERMS AND CLAUSES.
| 1. |
|
The Parties agree to change Clause 1 of the EPC Agreement that
will read as follows: |
“1. DEFINITIONS
1.1
For the purposes of this Agreement, the following terms shall have
the meaning set forth beside each of them (such meanings to be
equally applicable to both the singular and plural forms of the
terms defined).
| |
|
|
|
Agreement
|
|
Means this agreement together with
all of its Annexes. |
|
|
|
|
|
Agreed
Price
|
|
Means the compensation due by the
CLIENT to the CONTRACTOR for the entire and satisfactory execution
of the Works determined pursuant to Clause is of this Agreement
that shall be paid to the CONTRACTOR according to the Schedule of
Milestones. |
|
|
|
|
|
Business
Day
|
|
Means any day that is not a
Saturday, Sunday or holiday (whether a national, regional or local
holiday) in Madrid and Cantabria. |
|
|
|
|
|
Calendar
|
|
Means the timeline for execution
of the Works contained in Annex II. |
|
|
|
|
|
Certificate of
Completion of Commissioning of the PB40ES PowerBuoy and mooring
system
|
|
Means the certificate issued by
the Contractor’s Representative which accredits that the
Commissioning Period of the PB40ES PowerBuoy and mooring system is
finalized and the PB40ES PowerBuoy and mooring system is ready for
Provisional Acceptance pursuant to Clause 9 of this
Agreement. |
|
|
|
|
|
Certificate of
Completion of Commissioning of the Subsea cable and Underwater
Substation ‘pod’
|
|
Means the certificate issued by
the Contractor’s Representative which accredits that the
Commissioning Period of the Subsea cable and Underwater Substation
‘pod’ is finalized and the Subsea cable and Underwater
Substation ‘Pod’ is ready for Provisional Acceptance
pursuant ot Clause 9 of this Agreement. |
|
|
|
|
|
Certificate of
Completion of Installation of the PB40ES
|
|
Means the certificate issued by
the Contractor’s Representative which accredits that the
PB40ES PowerBuoy |
| |
|
|
|
PowerBuoy and
mooring system
|
|
and mooring system is ready for
commissioning. |
|
|
|
|
|
Certificate of
Completion of Installation of Subsea cable and
Underwater
|
|
Means the certificate issued by
the Contractor’s Representative which accredits that the
Subsea cable and Underwater Substation ‘Pod’ is ready
for commissioning. |
|
|
|
|
|
Substation
‘Pod’ Client’s Representative
|
|
Means the representative of the
Client as designated in Clause 26 of this Agreement. |
|
|
|
|
|
Commissioning
Period of the PB40ES PowerBuoy and mooring system
|
|
Period commencing upon issue of
the Certificate of Completion of Installation of the PB40ES
PowerBuoy and mooring system and finishes at the signature of the
Provisional Acceptance Certificate of the PB40ES PowerBuoy and
mooring system. |
|
|
|
|
|
Commissioning
Period of the Subsea cable and Underwater Substation
‘Pod’
|
|
Period commencing upon issue of
the Certificate of Completion of Installation of the Subsea cable
and Underwater Substation ‘Pod’ and finishes at the
signature of the Provisional Acceptance Certificate of the Subsea
cable and Underwater Substation ‘Pod’. |
|
|
|
|
|
Commissioning
Protocol of the PB40ES PowerBuoy and mooring system
|
|
The preliminary Commissioning
Protocol for the PB40ES PowerBuoy and mooring system is attached to
the Agreement as Annex X. The final Commissioning Protocol for the
PB40ES PowerBuoy and mooring system shall be delivered by the
CONTRACTOR to the CLIENT at least one month prior to the Scheduled
date for commencement of the commissioning of the PB40ES PowerBuoy
and mooring system. |
|
|
|
|
|
Commissioning
Protocol of the Subsea cable and Underwater Substation
‘Pod’
|
|
The Preliminary Commissioning
Protocol for the Subsea cable and Underwater Substation
‘Pod’ connected to the PB40ES PowerBuoy is attached to
the Agreement as Annex X. The final commissioning Protocol for the
Subsea cable and Underwater Substation ‘Pod’ shall be
delivered by the CONTRACTOR to the CLIENT at least one month prior
to the scheduled date for commencement of the commissioning of the
Subsea cable and Underwater Substation ‘Pod’. |
|
|
|
|
|
Contractor’s Representative
|
|
Means the person appointed by the
CONTRACTOR in this Agreement under Clause 27.1, who acts on behalf
of the CONTRACTOR. |
|
|
|
|
|
Day
|
|
Means a calendar day. |
|
|
|
|
|
Definitive
Acceptance Certificate of the PB40ES PowerBuoy and mooring
system
|
|
Document to the signed by the
Client and the Contractor after conclusion of Testing Period of the
PB40ES PowerBuoy and mooring system in accordance with Clause 10. A
draft of this document is included in Annex VII. |
| |
|
|
|
Definitive
Acceptance Certificate of the Subsea cable and Underwater
Substation ‘Pod’
|
|
Document to be signed by the
Client and the contractor after conclusion of Testing Period of the
Subsea cable and Underwater Substation ‘Pod’ in
accordance with Clause 10. A draft of this document is included in
Annex VII. |
|
|
|
|
|
Equipment
|
|
Means the equipment and/or
materials supplied by the CONTRACTOR and falling within the scope
of this Agreement, as defined in Clause 3 and the related
Annexes. |
|
|
|
|
|
EURIBOR
|
|
Means the interest rate applicable
among the banks published in Brussels for the three months deposits
in Euros as it is defined daily in the Telerate screen, page 248,
11:00 morning time (central Europe time), the second banking day
previous to the beginning of every period in which the Automatic
Paying System is operative in Trans European Real Time TARGET. This
rate shall be increased, as the case may be, with any cost,
surcharges, taxes, etc, as duly supported by documents, which are
referred to in the EURIBOR definition. |
|
|
|
|
|
Final
Commissioning Protocol of the PB40ES PowerBuoy and mooring
system
|
|
Means the Commissioning Protocol
delivered by the CONTRACTOR to the CLIENT at least one month prior
to the scheduled date for commencement of the commissioning of the
PB40ES PowerBuoy and Mooring system. |
|
|
|
|
|
Final
Commissioning Protocol of the Subsea cable and Underwater
Substation ‘Pod’
|
|
Means the Commissioning Protocol
delivered by the CONTRACTOR to the CLIENT at least one month prior
to the scheduled date for commencement of the commissioning of the
Subsea cable and Underwater Substation ‘Pod’. |
|
|
|
|
|
Force
Majenre
|
|
Means any event or fact as
described in Clause 24 of this Agreement. |
|
|
|
|
|
IBERENOVA
|
|
Means Iberdrola Energias
Renovables II S.A., Sociedad Unipersonal, a company incorporated
and validly existent under the laws of Spain: registered with the
Madrid Commercial Registry, of Section 8, page 285710, Tax
Identification Number (C.I.F.) A-83028035, with registered office
at Madrid, Calle Tomas Redando, number 1. |
|
|
|
|
|
IDAE
|
|
Means Instituto para la
Diversificacion Y Ahorro de la Energia, S.A., public entity
ascribed to the Ministry of Industry, Tourism and Commerce through
the General Secretary of Energy, with domicile in Madrid, at Calle
Madera number 8 and CIF number Q 2820009 E. |
|
|
|
|
|
Independent
Expert
|
|
Means the qualified specialist
appointed by the School of Industrial Engineers of Madrid or the
Institute of Mechanical Engineers or Electrical Engineers in
London, |
| |
|
|
| |
|
U.K. upon request by either Party. |
| |
|
|
| Insurance Schedule |
|
Means the required policies that the CONTRACTOR
must take out and maintain under this Agreement. |
| |
|
|
| Intellectual and Industrial
Property |
|
Means all (i) trademarks, trade names,
Internet domain names, logos, symbols, all applications and
registrations for the foregoing and all goodwill associated
therewith and symbolized thereby; (ii) patents, utility models,
registrations, invention disclosures and applications therefore,
including divisions, continuations, continuations-in-part and
including renewals, extensions and reissues and all inventions and
discoveries whether patentable or not; (iii) published and
unpublished works of authorship, whether copyrightable or not
(including databases and other compilations of information),
Copyrights therein and thereto, and registrations and applications
therefore, and all renewals, extensions, restorations and reversion
thereof; and (iv) other industrial and intellectual property or
proprietary rights; concerning the Plant and the PowerBuoy
TM
system. |
| |
|
|
| Know How |
|
Means all the information, trade secrets,
documents, technical data, technical knowledge, including
processes, schematics, business methods, formulae, drawings,
prototypes, models, designs, quality control systems, quality
standards and specifications developed or acquired by the
CONTRACTOR, presently or in the future, concerning the Plant and
the PowerBuoy TM system, or
its design, constructions, commissioning, use, exploitation and
assembling. |
| |
|
|
| Major Defects |
|
Means such defects that could affect the
production and/or transmission of energy by the PB40ES PowerBuoy
and mooring system or Subsea cable and Underwater Substation
‘Pod’ and/or the safety of the PB40ES PowerBuoy and
mooring system and/or the Subsea cable and Underwater Substation
‘Pod’ and/or of the people working therein. |
| |
|
|
| Milestone |
|
Means the relevant stages of progress of the
Works as described under the Schedule of Milestones and
Calendar. |
| |
|
|
| Minor Defects |
|
Means such material defects that are not Major
Defects. |
| |
|
|
| Notice of Approval |
|
Means the document issued by the Client under
Clause 19.2 (i) of this Agreement. |
| |
|
|
| Notice of Completion |
|
Means the communication sent by the Contractor
to the |
| |
|
|
| |
|
Client under clause 19.2 (i) which accredits
the completion of a Milestone. |
| |
|
|
| Notice of Pending Works |
|
Means the document issued by the Client under
Clause 19.2 (ii) of this Agreement. |
| |
|
|
| OPT |
|
Means Ocean Power Technologies, Inc., a company
incorporated and validly existent under the laws of New Jersey,
USA; with registered office at 1590 Reed Road, Pennington, NJ,
USA. |
| |
|
|
| Order for Change |
|
Means the document signed by both the Client
and the Contractor for a given modification of the Works under
clauses 11.1 or 11.2 of this Agreement. |
| |
|
|
| Parties |
|
Means the Client and the Contractor
jointly. |
| |
|
|
| Party |
|
Means the Client or the Contractor, as the
context may require. |
| |
|
|
| PB40ES PowerBuoy and mooring
system |
|
Means the PowerBuoy ® 1
x 40kW PB40ES, its mooring system, and all other ancillary
equipment and services required to provide a complete installation
of the PowerBuoy 1 x 40kW PB40ES. As described in Annex 1. |
| |
|
|
| Phase 1 |
|
Means Phase 1 of the Santona Wave Energy
Project as defined in Recital 1 of this Agreement in which the
parties to the Project have studied and decided about the viability
of the Project at the Site. |
| |
|
|
| Phase 2A |
|
Means Phase 2A of the Santona Wave Energy
Project as defined in Recital IV of this Agreement, consisting of
the design, manufacture, factory tests, dispatch and unloading, ex
works delivery, assembly and commissioning of the PowerBuoy
TM 1 x
40kW PB40ES, its mooring system, the underwater substation and
submarine cable both with capacity for energy evacuation of this
PowerBuoy TM and
other nine (9) 150kW PB150 PowerBuoys TM and
all other ancillary equipment and services required to provide a
complete installation of the PowerBuoy TM 1 x
40kW PB40ES. All as described in Annex 1. |
| |
|
|
| Phase 2B |
|
Means Phase 2B of the Santona Wave Energy
Project consisting of the design, manufacture, factory tests,
dispatch and unloading, ex-works delivery, assembly and
commissioning of the nine PoweBuoys TM 9 x
150kW PB150, their mooring systems, submarine cables and all other
ancillary equipment and services required to provide a complete
installation of the PowerBuoys TM
. |
| |
|
|
|
PowerBuoy
TM
|
|
Means the Technology owned by the
Contractor. |
|
|
|
|
|
Preliminary
Commissioning Protocol
|
|
Means the Commission Protocol
attached to the Agreement as Annex X. |
|
|
|
|
|
Provisional
Acceptance Certificate or PAC of the PB40ES PowerBuoy and mooring
system
|
|
Document to be signed by the
Client and the Contractor to put on record the satisfactory
completion of the Commissioning Protocol of the PB40ES PowerBuoy
and mooring system, including all Minor Defects that the Contractor
must remedy prior to the signature of DAC of the PB40ES PowerBuoy
and mooring system. A draft of this Document is included in Annex
VI. |
|
|
|
|
|
Provisional
Acceptance Certificate or PAC of the Subsea cable and Underwater
Substation ‘Pod’
|
|
Document to be signed by the
Client and the Contractor to put on record the satisfactory
completion of the Commissioning Protocol of the Subsea cable and
Underwater Substation ‘Pod’, including all Minor
Defects that the Contractor must remedy prior to signature of DAC
of the Subsea cable and Underwater Substation ‘Pod’. A
draft of this Document is included in Annex VI. |
|
|
|
|
|
Santoňa Wave
Energy Agreement
|
|
Means the agreement signed on
July 2, 2004 by OPT, IBERENOVA, SODERCAN, and IDAE, and
modified on June 17, 2005 to included TOTAL as a
party. |
|
|
|
|
|
Santoňa Wave
Energy Project or SWEP
|
|
Means the pilot project consisting
of a power plant harnessing wave energy with an initial installed
capacity of 1.39 MW on the north coast of Spain based on the
Technology. |
|
|
|
|
|
Schedule of
Milestones
|
|
Means the schedule describing the
progress of the Works and the timeline for payment of the Agreed
Price contained in Annex V. |
|
|
|
|
|
Site
|
|
Means the place where the PB40ES
PowerBuoy and mooring system and the Subsea cable and Underwater
Substation ‘Pod’ will be installed located at the coast
opposite the “Punta del Pescador” Lighthouse in
Santoňa; in the Cantabrian region in Spain as specified in
Annex XIII. |
|
|
|
|
|
SODERCAN
|
|
Means Sociedad para el Desarrallo
Regional de Cantabria, S.A., a company incorporated and validly
existent under the laws of Spain by virtue of its incorporation
deed granted on December 15, 1984 before the Notary of
Santander, Mr. Jose Antonia Olascoega, with number 1271 of his
public protocol; registered with the Cantabria Commercial Registry,
at Volume 296, Book 101, Sheet 60 and Page S-1751; Tax
Identification Number (C.I.F.) A-3904457, with |
| |
|
|
|
|
|
registered office at Santander,
Avenida de Los Infantes 32, “Quinta Labal”. |
|
|
|
|
|
SPV
|
|
Means the public limited company
created by IBERENOVA, IDAE, OPT, SODERCAN and TOTAL for the
construction and operation of the Santona Wave Project as agreed
under the Santona Wave Energy Agreement. |
|
|
|
|
|
Subcontractors
|
|
All firms or individuals
contracted by the CONTRACTOR to do part of the Works contemplated
in this Agreement. |
|
|
|
|
|
Subsea cable and
Underwater Substation ‘Pod’
|
|
Means the underwater substation
and submarine cable, as described in Annex I, with capacity
for energy evacuation of the PB40ES PowerBuoy and other nine
(9) 150kW PB150 PowerBuoys. |
|
|
|
|
|
Taxes
|
|
Means any taxes, rates, special
levies (“contribuciones especiales”), charges
(“exacciones parafiscales”) or any other encumbrance of
tax nature, required by any administrative authority, including
surcharges, interests and penalties. |
|
|
|
|
|
Technical
Documentation
|
|
Means the documents, workshop
plans, calculations and sketches listed in Annex IX of this
Agreement. |
|
|
|
|
|
Technology
|
|
Means the technology for
electricity generation harnessing the energy produced by the waves
called PowerBuoy TM system owned by
the CONTRACTOR. In particular, it means all the Know How and
Intellectual and Industrial Property related to the PowerBuoy
TM
system, including the moorings and the underwater
substation. |
|
|
|
|
|
Testing Period of
the PB40ES PowerBuoy and mooring system
|
|
Means six months including three
months between October and March (inclusive); plus any extensions
made hereunder. Period commencing upon signature of the Provisional
Acceptance of the PB40ES PowerBuoy and mooring system and finishing
at the signature of the Definitive Acceptance Certificate of the
PB40ES PowerBuoy and mooring system. |
|
|
|
|
|
Testing Period of
the Subsea cable and Underwater Substation
‘Pod’
|
|
Means six months commencing upon
signature of the Provisional Acceptance Certificate of the Subsea
cable and Underwater Substation ‘Pod’ and finishing at
the signature of the Definitive Acceptance Certificate of the
Subsea cable and Underwater Substation ‘Pod’. |
| |
|
|
|
Time for
Completion
|
|
Means the period of time for the
Contractors completing the assembly, installation and commissioning
of the PB40ES PowerBuoy and mooring system and Subsea cable and
Underwater Substation ‘Pod’ according to this
Agreement. |
| |
|
TOTAL
|
|
Means Total Eolica S.A., a company
incorporated and validly existent under the laws of Spain
registered with the La Coruna Commercial Registry, at
Section S, Page 25547; Tax Identification Number (C.I.F)
A-15745706, with registered office at Avenida Fernando de Casas
Novoa, number 37, planta B,3°A,. |
| |
|
Works
|
|
Means all actions work and
services for the supply, construction and commissioning of the
PB40ES PowerBuoy and mooring system and the Subsea cable and
Underwater Substation ‘Pod’ described in Clause 3 of
this Agreement. |
| 1.2 |
|
Other terms may be defined in other clauses of this
Agreement.” |
CLAUSE 2
CHANGES TO DEFINITION OF PLANT.
The
Parties agree that, unless otherwise agreed under this Addendum,
each and every reference to “Plant” throughout the EPC
Agreement is replaced by — “PB40ES PowerBuoy and
mooring system and/or the Subsea cable and Underwater Substation
‘Pod’” – both as defined in Clause 1 of the
EPC Agreement as amended by this Addendum.
CLAUSE 3
CHANGES TO CLAUSE 3.1 OF THE EPC AGREEMENT.
The
Parties agree to change Clause 3.1 of the EPC Agreement that will
read as follows:
| “3.7 |
|
The CONTRACTOR shall perform the Works and shall deliver the
Equipment according to the Technical Documentation according to
Annex IX.” |
CLAUSE 4
CHANGES TO CLAUSE 4 OF THE EPC AGREEMENT
The
Parties agree that Clause 4.2 of the EPC Agreement shall be amended
as follows:
| “4.2 |
|
Upon signing the Provisional Acceptance Certificate of the
PB40ES PowerBuoy and mooring |
| |
|
system, the CONTRACTOR shall hand over the “as
built” documents of the Equipment included in the PB40ES
PowerBuoy and mooring system in accordance with Annex IX, and any
other documentation as may be agreed between the Parties, all the
documents generated during commissioning of the PB40ES PowerBuoy
and mooring system, including any modifications based on reasonable
written comments made by the CLIENT and agreed by the CONTRACTOR on
the Provisional Acceptance of the PB40ES PowerBuoy and mooring
system. |
| |
| |
|
Upon signing the Provisional Acceptance Certificate of the
Subsea cable and Underwater Substation ‘Pod’, the
CONTRACTOR shall hand over the “as built” documents of
the Subsea cable and Underwater Substation ‘Pod’ in
accordance with Annex IX, and any other documentation as may be
agreed between the Parties, all the documents generated during
commissioning of the Subsea cable and Underwater Substation
‘Pod’, including any modifications based on reasonable
written comments made by the CLIENT and agreed by the CONTRACTOR on
the Provisional of the Subsea cable and Underwater Substation
‘Pod’.” |
CLAUSE 5
CHANGES TO CLAUSE 6.6 OF THE EPC AGREEMENT
The
Parties agree to change Clause 6.6 of the EPC Agreement that will
read as follows:
| “6.6 |
|
If any fault or defect is discovered during testing and/or
inspection as contemplated in Clause 6.4, the CONTRACTOR shall be
responsible for correcting the fault or defect prior to the
relevant PAC.” |
CLAUSE 6
CHANGES TO CLAUSE 7 OF THE EPC AGREEMENT
The
Parties agree to change Clauses 7.2, 7.4 and 7.5 of the EPC
Agreement that will read as follows:
| 7.2 |
|
The PB40ES PowerBuoy and mooring system and the Subsea cable
and Underwater Substation ‘Pod’ shall be installed at
the Site once the CLIENT has given its written confirmation that
the required permits and consents for installation have been
obtained. |
| (...) |
|
|
| |
| 7.4 |
|
Inspections by the CLIENT shall not release the CONTRACTOR
from any of its obligations and liabilities hereunder nor shall
they imply acceptance of the PB40ES PowerBuoy and mooring system,
or the Subsea cable and Underwater Substation
‘Pod’. |
(...)
| 7.5 |
|
As soon as the CONTRACTOR considers the assembly and
installation of the PB40ES PowerBuoy and mooring system is
complete, according to the terms of this Agreement, it shall issue
a Certificate of Completion of Installation of the PB40ES PowerBuoy
and mooring system indicating that the PB40ES PowerBuoy and mooring
system is ready for Commissioning. |
| |
| |
|
As soon as the CONTRACTOR considers the assembly and
installation of the Subsea cable and Underwater Substation
‘Pod’ connected to the PB40ES PowerBuoy is complete,
according to the terms of this Agreement, it shall issue a
Certificate of Completion of Installation of the Subsea cable and
Underwater Substation ‘Pod’ indicating that the Subsea
cable and Underwater Substation ‘Pod’ is ready for
Commissioning.” |
CLAUSE 7
CHANGES TO CLAUSE 8 OF THE EPC AGREEMENT
The
Parties agree to change Clause 8 of the EPC Agreement that will
read
|