Exhibit 10.21
STANDARD LARGE GENERATOR
INTERCONNECTION AGREEMENT (LGIA)
BETWEEN
ARIZONA PUBLIC SERVICE COMPANY
AND, TOGETHER,
ABITIBI CONSOLIDATED SALES CORPORATION
AND
SNOWFLAKE WHITE MOUNTAIN POWER, LLC
APS CONTRACT NO. 52023
TABLE OF CONTENTS
| |
|
|
|
|
| |
|
Page |
|
|
RECITALS
|
|
|
1 |
|
|
|
|
|
|
|
|
ARTICLE 1.
DEFINITIONS
|
|
|
2 |
|
|
|
|
|
|
|
|
ARTICLE 2.
EFFECTIVE DATE, TERM,, AND TERMINATION
|
|
|
11 |
|
|
|
|
|
|
|
|
2.1
Effective
Date
|
|
|
11 |
|
|
2.2
Term Of
Agreement
|
|
|
11 |
|
|
2.3
Termination
Procedures
|
|
|
11 |
|
|
2.3.1
Written Notice
|
|
|
11 |
|
|
2.3.2
Default
|
|
|
11 |
|
|
2.4
Termination
Costs
|
|
|
11 |
|
|
2.5
Disconnection
|
|
|
12 |
|
|
2.6
Survival
|
|
|
12 |
|
|
|
|
|
|
|
|
ARTICLE 3.
REGULATORY FILINGS
|
|
|
13 |
|
|
|
|
|
|
|
|
3.1 F
iling
|
|
|
13 |
|
|
|
|
|
|
|
|
ARTICLE 4. SCOPE
OF SERVICE
|
|
|
13 |
|
|
|
|
|
|
|
|
4.1 I
nterconnection Product
Options
|
|
|
13 |
|
|
4.1.1 Energy
Resource Interconnection Service
|
|
|
13 |
|
|
4.1.1.1 The
Product
|
|
|
13 |
|
|
4.1.1.2
Transmission Delivery Service Implications
|
|
|
13 |
|
|
4.1.2
Network Resource Interconnection Service
|
|
|
14 |
|
|
4.1.2.1 The
Product
|
|
|
14 |
|
|
4.1.2.2
Transmission Delivery Service Implications
|
|
|
14 |
|
|
4.2
Provision Of
Service
|
|
|
16 |
|
|
4.3
Performance
Standards
|
|
|
16 |
|
|
4.4
No Transmission Delivery
Service
|
|
|
16 |
|
|
4.5
Interconnection Customer
Provided Services
|
|
|
16 |
|
|
|
|
|
|
|
|
ARTICLE 5.
INTERCONNECTION FACILITIES ENGINEERING, PROCUREMENT, &
CONSTRUCTION
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
|
|
5.1
Options
|
|
|
16 |
|
|
5.1.1
Standard Option
|
|
|
16 |
|
|
5.1.2
Alternate Option
|
|
|
16 |
|
|
5.1.3 Option
to Build
|
|
|
17 |
|
|
5.1.4
Negotiated Option
|
|
|
17 |
|
|
5.2
General Conditions
Applicable to Option
to
Build
|
|
|
17 |
|
|
5.3
Liquidated
Damages
|
|
|
19 |
|
|
5.4
Power System
Stabilizers
|
|
|
20 |
|
|
5.5
Equipment
Procurement
|
|
|
20 |
|
|
5.6
Construction
Commencement
|
|
|
20 |
|
|
5.7 W
ork P rogress
|
|
|
21 |
|
|
5.8
Information
Exchange
|
|
|
21 |
|
- i -
| |
|
|
|
|
| |
|
Page |
|
|
5.9
Limited
Operation
|
|
|
21 |
|
|
5.10
Interconnection
Customer’s Interconnection Facilities
(‘icif’)
|
|
|
21 |
|
|
5.10.1
Interconnection Customer’s Interconnection Facility
Specifications
|
|
|
21 |
|
|
5.10.2
Transmission Provider’s Review
|
|
|
22 |
|
|
5.10.3 ICIF
Construction
|
|
|
22 |
|
|
5.11
Transmission
Provider’s Interconnection Facilities
Construction
|
|
|
22 |
|
|
5.12
Access
Rights
|
|
|
22 |
|
|
5.13
Lands Of Other Property
Owners
|
|
|
23 |
|
|
5.14
Permits
|
|
|
23 |
|
|
5.15
Early Construction
of Base Case
Facilities
|
|
|
23 |
|
|
5.16
suspension
|
|
|
23 |
|
|
5.17
Taxes
|
|
|
24 |
|
|
5.17.1
Interconnection Customer Payments Not Taxable
|
|
|
24 |
|
|
5.17.2
Representations and Covenants
|
|
|
24 |
|
|
5.17.3
Indemnification for the Cost Consequences of Current Tax Liability
Imposed Upon the Transmission Provider
|
|
|
25 |
|
|
5.17.4 Tax
Gross-Up Amount
|
|
|
25 |
|
|
5.17.5
Private Letter Ruling or Change or Clarification of
Law
|
|
|
26 |
|
|
5.17.6
Subsequent Taxable Events
|
|
|
27 |
|
|
5.17.7
Contests
|
|
|
27 |
|
|
5.17.8
Refund
|
|
|
28 |
|
|
5.17.9 Taxes
Other Than Income Taxes
|
|
|
29 |
|
|
5.17.10
Transmission Owners Who Are Not Transmission
Providers
|
|
|
29 |
|
|
5.18
Tax Status
|
|
|
29 |
|
|
5.19
Modification
|
|
|
29 |
|
|
5.19.1
General
|
|
|
29 |
|
|
5.19.2
Standards
|
|
|
30 |
|
|
5.19.3
Modification Costs
|
|
|
30 |
|
|
|
|
|
|
|
|
ARTICLE 6. TESTING
AND INSPECTION
|
|
|
30 |
|
|
|
|
|
|
|
|
6.1
Pre-Commercial Operation
Date Testing And Modifications
|
|
|
30 |
|
|
6.2
Post-Commercial Operation
Date Testing And Modifications
|
|
|
30 |
|
|
6.3
Right To Observe
Testing
|
|
|
31 |
|
|
6.4
Right To
Inspect
|
|
|
31 |
|
|
|
|
|
|
|
|
ARTICLE 7.
METERING
|
|
|
31 |
|
|
|
|
|
|
|
|
7.1
General
|
|
|
31 |
|
|
7.2
Check
Meters
|
|
|
31 |
|
|
7.3
Standards
|
|
|
31 |
|
|
7.4
Testing Of Metering
Equipment
|
|
|
32 |
|
|
7.5
Metering
Data
|
|
|
32 |
|
|
|
|
|
|
|
|
ARTICLE 8.
COMMUNICATIONS
|
|
|
32 |
|
|
|
|
|
|
|
|
8.1
Interconnection Customer
Obligations
|
|
|
32 |
|
|
8.2
Remote Terminal
Unit
|
|
|
32 |
|
|
8.3
No
Annexation
|
|
|
33 |
|
- ii -
| |
|
|
|
|
| |
|
Page |
|
|
ARTICLE 9.
OPERATIONS
|
|
|
33 |
|
|
|
|
|
|
|
|
9.1
General
|
|
|
33 |
|
|
9.2
Control Area
Notification
|
|
|
33 |
|
|
9.3
Transmission Provider
Obligations
|
|
|
33 |
|
|
9.4
Interconnection Customer
Obligations
|
|
|
33 |
|
|
9.5
Start-Up And
Synchronization
|
|
|
34 |
|
|
9.6
Reactive
Power
|
|
|
34 |
|
|
9.6.1 Power
Factor Design Criteria
|
|
|
34 |
|
|
9.6.2
Voltage Schedules
|
|
|
34 |
|
|
9.6.2.1
Governors and Regulators
|
|
|
34 |
|
|
9.6.3
Payment for Reactive Power
|
|
|
35 |
|
|
9.7
Outages And
Interruptions
|
|
|
35 |
|
|
9.7.1
Outages
|
|
|
35 |
|
|
9.7.1.1 Outage
Authority and Coordination
|
|
|
35 |
|
|
9.7.1.2 Outage
Schedules
|
|
|
35 |
|
|
9.7.1.3 Outage
Restoration
|
|
|
36 |
|
|
9.7.2
Interruption of Service
|
|
|
36 |
|
|
9.7.3
Under-Frequency and Over Frequency Conditions
|
|
|
37 |
|
|
9.7.4 System
Protection and Other Control Requirements
|
|
|
37 |
|
|
9.7.4.1 System
Protection Facilities
|
|
|
37 |
|
|
9.7.5
Requirements for Protection
|
|
|
38 |
|
|
9.7.6 Power
Quality
|
|
|
38 |
|
|
9.8
Switching And Tagging
Rules
|
|
|
39 |
|
|
9.9
Use Of Interconnection
Facilities By Third Parties
|
|
|
39 |
|
|
9.9.1
Purpose of Interconnection Facilities
|
|
|
39 |
|
|
9.9.2 Third
Party Users
|
|
|
39 |
|
|
9.10
Disturbance Analysis Data
Exchange
|
|
|
39 |
|
|
|
|
|
|
|
|
ARTICLE 10.
MAINTENANCE
|
|
|
40 |
|
|
|
|
|
|
|
|
10.1
Transmission Provider
Obligations
|
|
|
40 |
|
|
10.2
Interconnection Customer
Obligations
|
|
|
40 |
|
|
10.3
Coordination
|
|
|
40 |
|
|
10.4
Secondary
Systems
|
|
|
40 |
|
|
10.5
Operating And Maintenance
Expenses
|
|
|
40 |
|
|
|
|
|
|
|
|
ARTICLE 11.
PERFORMANCE OBLIGATION
|
|
|
40 |
|
|
|
|
|
|
|
|
11.1
Interconnection Customer
Interconnection Facilities
|
|
|
40 |
|
|
11.2
Transmission
Provider’s Interconnection Facilities
|
|
|
40 |
|
|
11.3
Network Upgrades And
Distribution Upgrades
|
|
|
41 |
|
|
11.4
Transmission
Credits
|
|
|
41 |
|
|
11.4.1
Repayment of Amounts Advanced for Network Upgrades
|
|
|
41 |
|
|
11.5
Provision Of
Security
|
|
|
42 |
|
|
11.6
Interconnection Customer
Compensation
|
|
|
43 |
|
|
11.6.1
Interconnection Customer Compensation for Actions During Emergency
Condition 43
|
|
|
|
|
|
|
|
|
|
|
|
ARTICLE 12.
INVOICE
|
|
|
43 |
|
- iii -
| |
|
|
|
|
| |
|
Page |
|
|
12.1
General
|
|
|
43 |
|
|
12.2
Final
Invoice
|
|
|
43 |
|
|
12.3
Payment
|
|
|
44 |
|
|
12.4
Disputes
|
|
|
44 |
|
|
|
|
|
|
|
|
ARTICLE 13.
EMERGENCIES
|
|
|
44 |
|
|
|
|
|
|
|
|
13.1
Definition
|
|
|
44 |
|
|
13.2
Obligations
|
|
|
44 |
|
|
13.3
Notice
|
|
|
44 |
|
|
13.4
Immediate
Action
|
|
|
45 |
|
|
13.5
Transmission Provider
Authority
|
|
|
45 |
|
|
13.5.1
General
|
|
|
45 |
|
|
13.5.2
Reduction and Disconnection
|
|
|
45 |
|
|
13.6
Interconnection Customer
Authority
|
|
|
46 |
|
|
13.7
Limited
Liability
|
|
|
46 |
|
|
|
|
|
|
|
|
ARTICLE 14.
REGULATORY REQUIREMENTS AND GOVERNING LAW
|
|
|
46 |
|
|
|
|
|
|
|
|
14.1
Regulatory
Requirements
|
|
|
46 |
|
|
14.2
Governing
Law
|
|
|
47 |
|
|
|
|
|
|
|
|
ARTICLE 15.
NOTICES
|
|
|
47 |
|
|
|
|
|
|
|
|
15.1
General
|
|
|
47 |
|
|
15.2 B
illings and P ayments
|
|
|
47 |
|
|
15.3
Alternative Forms of
Notice
|
|
|
47 |
|
|
15.4
Operations and Maintenance
Notice
|
|
|
47 |
|
|
|
|
|
|
|
|
ARTICLE 16. FORCE
MAJEURE
|
|
|
47 |
|
|
|
|
|
|
|
|
ARTICLE 17.
DEFAULT
|
|
|
48 |
|
|
|
|
|
|
|
|
17.1
Default
|
|
|
48 |
|
|
17.1.1
General
|
|
|
48 |
|
|
17.1.2 Right
to Terminate
|
|
|
48 |
|
|
|
|
|
|
|
|
ARTICLE 18.
INDEMNITY, CONSEQUENTIAL DAMAGES AND INSURANCE
|
|
|
48 |
|
|
|
|
|
|
|
|
18.1
Indemnity
|
|
|
48 |
|
|
18.1.1
Indemnified Person
|
|
|
49 |
|
|
18.1.2
Indemnifying Party
|
|
|
49 |
|
|
18.1.3
Indemnity Procedures
|
|
|
49 |
|
|
18.2
Consequential
Damages
|
|
|
50 |
|
|
18.3
Insurance
|
|
|
50 |
|
|
|
|
|
|
|
|
ARTICLE 19.
ASSIGNMENT
|
|
|
52 |
|
|
|
|
|
|
|
|
ARTICLE 20.
SEVERABILITY
|
|
|
52 |
|
|
|
|
|
|
|
|
ARTICLE 21.
COMPARABILITY
|
|
|
52 |
|
|
|
|
|
|
|
|
ARTICLE 22.
CONFIDENTIALITY
|
|
|
53 |
|
|
|
|
|
|
|
|
22.1
Confidentiality
|
|
|
53 |
|
|
22.1.1
Term
|
|
|
53 |
|
- iv -
| |
|
|
|
|
| |
|
Page |
|
|
22.1.2
Scope
|
|
|
53 |
|
|
22.1.3
Release of Confidential Information
|
|
|
53 |
|
|
22.1.4
Rights
|
|
|
54 |
|
|
22.1.5 No
Warranties
|
|
|
54 |
|
|
22.1.6
Standard of Care
|
|
|
54 |
|
|
22.1.7 Order
of Disclosure
|
|
|
54 |
|
|
22.1.8
Termination of Agreement
|
|
|
54 |
|
|
22.1.9
Remedies
|
|
|
55 |
|
|
22.1.10
Disclosure to FERC, its Staff, or a State
|
|
|
55 |
|
|
|
|
|
|
|
|
ARTICLE 23.
ENVIRONMENTAL RELEASES
|
|
|
56 |
|
|
|
|
|
|
|
|
ARTICLE 24.
INFORMATION REQUIREMENTS
|
|
|
56 |
|
|
|
|
|
|
|
|
24.1
Information
Acquisition
|
|
|
56 |
|
|
24.2
Information Submission by
Transmission Provider
|
|
|
56 |
|
|
24.3
Updated Information
Submission by Interconnection Customer
|
|
|
56 |
|
|
24.4
Information
Supplementation
|
|
|
57 |
|
|
|
|
|
|
|
|
ARTICLE 25.
INFORMATION ACCESS AND AUDIT RIGHTS
|
|
|
58 |
|
|
|
|
|
|
|
|
25.1
Information
Access
|
|
|
58 |
|
|
25.2
Reporting of Non-Force
Majeure Events
|
|
|
58 |
|
|
25.3
Audit
Rights
|
|
|
58 |
|
|
25.4
Audit Rights
Periods
|
|
|
58 |
|
|
25.4.1 Audit
Rights Period for Construction-Related Accounts and
Records
|
|
|
58 |
|
|
25.4.2 Audit
Rights Period for All Other Accounts and Records
|
|
|
58 |
|
|
25.5
Audit
Results
|
|
|
59 |
|
|
|
|
|
|
|
|
ARTICLE 26.
SUBCONTRACTORS
|
|
|
59 |
|
|
|
|
|
|
|
|
26.1
General
|
|
|
59 |
|
|
26.2
Responsibility of
Principal
|
|
|
59 |
|
|
26.3
No Limitation by
Insurance
|
|
|
59 |
|
|
|
|
|
|
|
|
ARTICLE 27.
DISPUTES
|
|
|
59 |
|
|
|
|
|
|
|
|
27.1
Submission
|
|
|
59 |
|
|
27.2
External Arbitration
Procedures
|
|
|
60 |
|
|
27.3
Arbitration
Decisions
|
|
|
60 |
|
|
27.4
Costs
|
|
|
60 |
|
|
|
|
|
|
|
|
ARTICLE 28.
REPRESENTATIONS, WARRANTIES, AND COVENANTS
|
|
|
60 |
|
|
|
|
|
|
|
|
28.1
General
|
|
|
60 |
|
|
28.1.1 Good
Standing
|
|
|
60 |
|
|
28.1.2
Authority
|
|
|
61 |
|
|
28.1.3 No
Conflict
|
|
|
61 |
|
|
28.1.4
Consent and Approval
|
|
|
61 |
|
|
|
|
|
|
|
|
ARTICLE 29. JOINT
OPERATING COMMITTEE
|
|
|
61 |
|
|
|
|
|
|
|
|
ARTICLE 30.
MISCELLANEOUS
|
|
|
62 |
|
|
|
|
|
|
|
|
30.1
Binding
Effect
|
|
|
62 |
|
- v -
| |
|
|
|
|
| |
|
Page |
|
|
30.2
Conflicts
|
|
|
62 |
|
|
30.3
Rules of
Interpretation
|
|
|
62 |
|
|
30.4
Entire
Agreement
|
|
|
63 |
|
|
30.5
No Third Party
Beneficiaries
|
|
|
63 |
|
|
30.6
Waiver
|
|
|
63 |
|
|
30.7
Headings
|
|
|
63 |
|
|
30.8
Multiple
Counterparts
|
|
|
63 |
|
|
30.9
Amendment
|
|
|
63 |
|
|
30.10
Modification by the
Parties
|
|
|
63 |
|
|
30.11
Reservation of
Rights
|
|
|
64 |
|
|
30.12
No
Partnership
|
|
|
64 |
|
| |
|
Appendix A
– Interconnection Facilities, Network Upgrades, and
Distribution Upgrades
|
|
|
|
Appendix B
– Milestones
|
|
|
|
Appendix C
– Interconnection Details
|
|
|
|
Appendix D
– Security Arrangements Details
|
|
|
|
Appendix E
– Commercial Operation Date
|
|
|
|
Appendix F
– Addresses for Delivery of Notices and Billings
|
|
|
|
Appendix G
– Requirements of a Wind Generating Plant
|
|
|
|
Appendix H
– Reliability Management System Agreement
|
- vi -
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT
THIS STANDARD LARGE GENERATOR
INTERCONNECTION AGREEMENT (“Agreement”) is made and
entered into this 1st day of November 2006, by and between Abitibi
Consolidated Sales Corporation (“Abitibi”), a
corporation organized and existing under the laws of the State of
Delaware, and Snowflake White Mountain Power, LLC
(“Snowflake”), a corporation organized and existing
under the laws of the State of Arizona (collectively, the
“Interconnection Customer” with a Large Generating
Facility), and Arizona Public Service Company (“APS”),
a corporation organized and existing under the laws of the State of
Arizona (“Transmission Provider and/or Transmission
Owner”). Abitibi and Snowflake hereby agree to be jointly and
severally responsible for all rights and obligations attributed to
the Interconnection Customer as such are set forth in this
Agreement. Interconnection Customer and Transmission Provider each
may be referred to as a “Party” or collectively as the
“Parties.”
Recitals
WHEREAS, APS, as Transmission
Provider operates the Transmission System; and
WHEREAS, Abitibi and APS are
parties to a grandfathered Interconnection and Operating Agreement
(“IOA”) that provides Interconnection Service to
Abitibi Unit #1 and Unit #2;
WHEREAS, such preexisting IOA
was filed with FERC on October 8, 2002, in Docket No.
ER03-22-000, was accepted by FERC as effective on September 9,
2002, via letter order issued on December 6, 2002, and
is designated as APS Contract No. 51637;
WHEREAS, Abitibi and APS
intend for this Agreement to fully replace and supersede the IOA
upon its Effective Date;
WHEREAS, Snowflake intends to
construct and own a 22 MW Generating Facility on Abitibi’s
property and shall utilize the pre-existing Point of
Interconnection with the Transmission System to provide
Interconnection Service to such new Generating Facility;
WHEREAS, Abitibi and
Snowflake have entered into a Lease Agreement dated
September 14, 2005 that grants Snowflake access and use rights
over Abitibi’s Interconnection Facilities in order for
Snowflake to obtain Interconnection Service with the Transmission
System;
WHEREAS, pursuant to the
Operations Provisions that are included as Addendum 1 to the Lease
Agreement dated September 14, 2005, Abitibi shall be
responsible for the operations of the three Generating Facilities
to be interconnected to the Transmission System at a singular Point
of Interconnection pursuant to this Agreement;
1
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
WHEREAS, this Agreement shall
be considered a “Facility Agreement,” as such term is
defined in the Operations Provisions addendum to the Lease
Agreement dated September 14, 2005;
WHEREAS, Interconnection
Customer intends to own, lease and/or control and operate the
Generating Facility identified as a Large Generating Facility in
Appendix C to this Agreement; and,
WHEREAS, Interconnection
Customer and Transmission Provider have agreed to enter into this
Agreement for the purpose of interconnecting the Large Generating
Facility with the Transmission System;
NOW, THEREFORE, in
consideration of and subject to the mutual covenants contained
herein, it is agreed:
When used in this Standard Large
Generator Interconnection Agreement, terms with initial
capitalization that are not defined in Article 1 shall have
the meanings specified in the Article in which they are used or the
Open Access Transmission Tariff (Tariff).
Article 1. Definitions
Adverse System Impact shall
mean the negative effects due to technical or operational limits on
conductors or equipment being exceeded that may compromise the
safety and reliability of the electric system.
Affected System shall mean an
electric system other than the Transmission Provider’s
Transmission System that may be affected by the proposed
interconnection.
Affected System Operator
shall mean the entity that operates an Affected System.
Affiliate shall mean, with
respect to a corporation, partnership or other entity, each such
other corporation, partnership or other entity that directly or
indirectly, through one or more intermediaries, controls, is
controlled by, or is under common control with, such corporation,
partnership or other entity.
Ancillary Services shall mean
those services that are necessary to support the transmission of
capacity and energy from resources to loads while maintaining
reliable operation of the Transmission Provider’s
Transmission System in accordance with Good Utility Practice.
Applicable Laws and
Regulations shall mean all duly promulgated applicable federal,
state and local laws, regulations, rules, ordinances, codes,
decrees, judgments, directives, or judicial or administrative
orders, permits and other duly authorized actions of any
Governmental Authority.
2
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Applicable Reliability
Council shall mean the reliability council applicable to the
Transmission System to which the Generating Facility is directly
interconnected.
Applicable Reliability
Standards shall mean the requirements and guidelines of NERC,
the Applicable Reliability Council, and the Control Area of the
Transmission System to which the Generating Facility is directly
interconnected.
Base Case shall mean the base
case power flow, short circuit, and stability data bases used for
the Interconnection Studies by the Transmission Provider or
Interconnection Customer.
Breach shall mean the failure
of a Party to perform or observe any material term or condition of
the Standard Large Generator Interconnection Agreement.
Breaching Party shall mean a
Party that is in Breach of the Standard Large Generator
Interconnection Agreement.
Business Day shall mean
Monday through Friday, excluding Federal Holidays.
Calendar Day shall mean any
day including Saturday, Sunday or a Federal Holiday.
Clustering shall mean the
process whereby a group of Interconnection Requests is studied
together, instead of serially, for the purpose of conducting the
Interconnection System Impact Study.
Commercial Operation shall
mean the status of a Generating Facility that has commenced
generating electricity for sale, excluding electricity generated
during Trial Operation.
Commercial Operation Date of
a unit shall mean the date on which the Generating Facility
commences Commercial Operation as agreed to by the Parties pursuant
to Appendix E to the Standard Large Generator Interconnection
Agreement.
Confidential Information
shall mean any confidential, proprietary or trade secret
information of a plan, specification, pattern, procedure, design,
device, list, concept, policy or compilation relating to the
present or planned business of a Party, which is designated as
confidential by the Party supplying the information, whether
conveyed orally, electronically, in writing, through inspection, or
otherwise.
Control Area shall mean an
electrical system or systems bounded by interconnection metering
and telemetry, capable of controlling generation to maintain its
interchange schedule with other Control Areas and contributing to
frequency regulation of the interconnection. A Control Area must be
certified by the Applicable Reliability Council.
Default shall mean the
failure of a Breaching Party to cure its Breach in accordance with
Article 17 of the Standard Large Generator Interconnection
Agreement.
3
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Dispute Resolution shall mean
the procedure for resolution of a dispute between the Parties in
which they will first attempt to resolve the dispute on an informal
basis.
Distribution System shall
mean the Transmission Provider’s facilities and equipment
used to transmit electricity to ultimate usage points such as homes
and industries directly from nearby generators or from interchanges
with higher voltage transmission networks which transport bulk
power over longer distances. The voltage levels at which
distribution systems operate differ among areas.
Distribution Upgrades shall
mean the additions, modifications, and upgrades to the Transmission
Provider’s Distribution System at or beyond the Point of
Interconnection to facilitate interconnection of the Generating
Facility and render the transmission service necessary to effect
Interconnection Customer’s wholesale sale of electricity in
interstate commerce. Distribution Upgrades do not include
Interconnection Facilities.
Effective Date shall mean the
date on which the Standard Large Generator Interconnection
Agreement becomes effective upon execution by the Parties subject
to acceptance by FERC, or if filed unexecuted, upon the date
specified by FERC.
Emergency Condition shall
mean a condition or situation: (1) that in the judgment of the
Party making the claim is imminently likely to endanger life or
property; or (2) that, in the case of a Transmission Provider,
is imminently likely (as determined in a non-discriminatory manner)
to cause a material adverse effect on the security of, or damage to
Transmission Provider’s Transmission System, Transmission
Provider’s Interconnection Facilities or the electric systems
of others to which the Transmission Provider’s Transmission
System is directly connected; or (3) that, in the case of
Interconnection Customer, is imminently likely (as determined in a
non-discriminatory manner) to cause a material adverse effect on
the security of, or damage to, the Generating Facility or
Interconnection Customer’s Interconnection Facilities. System
restoration and black start shall be considered Emergency
Conditions; provided, that Interconnection Customer is not
obligated by the Standard Large Generator Interconnection Agreement
to possess black start capability.
Energy Resource Interconnection
Service shall mean an Interconnection Service that allows the
Interconnection Customer to connect its Generating Facility to the
Transmission Provider’s Transmission System to be eligible to
deliver the Generating Facility’s electric output using the
existing firm or nonfirm capacity of the Transmission
Provider’s Transmission System on an as available basis.
Energy Resource Interconnection Service in and of itself does not
convey transmission service.
Engineering & Procurement
(E&P) Agreement shall mean an agreement that authorizes the
Transmission Provider to begin engineering and procurement of long
lead-time items necessary for the establishment of the
interconnection in order to advance the implementation of the
Interconnection Request.
Environmental Law shall mean
Applicable Laws or Regulations relating to pollution or protection
of the environment or natural resources.
4
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Federal Power Act shall mean
the Federal Power Act, as amended, 16 U.S.C. §§ 791a
et seq.
FERC shall mean the Federal
Energy Regulatory Commission (Commission) or its successor.
Force Majeure shall mean any
act of God, labor disturbance, act of the public enemy, war,
insurrection, riot, fire, storm or flood, explosion, breakage or
accident to machinery or equipment, any order, regulation or
restriction imposed by governmental, military or lawfully
established civilian authorities, or any other cause beyond a
Party’s control. A Force Majeure event does not include acts
of negligence or intentional wrongdoing by the Party claiming Force
Majeure.
Generating Facility shall
mean Interconnection Customer’s device for the production of
electricity identified in the Interconnection Request, but shall
not include the Interconnection Customer’s Interconnection
Facilities.
Generating Facility Capacity
shall mean the net capacity of the Generating Facility and the
aggregate net capacity of the Generating Facility where it includes
multiple energy production devices.
Good Utility Practice shall
mean any of the practices, methods and acts engaged in or approved
by a significant portion of the electric industry during the
relevant time period, or any of the practices, methods and acts
which, in the exercise of reasonable judgment in light of the facts
known at the time the decision was made, could have been expected
to accomplish the desired result at a reasonable cost consistent
with good business practices, reliability, safety and expedition.
Good Utility Practice is not intended to be limited to the optimum
practice, method, or act to the exclusion of all others, but rather
to be acceptable practices, methods, or acts generally accepted in
the region.
Governmental Authority shall
mean any federal, state, local or other governmental regulatory or
administrative agency, court, commission, department, board, or
other governmental subdivision, legislature, rulemaking board,
tribunal, or other governmental authority having jurisdiction over
the Parties, their respective facilities, or the respective
services they provide, and exercising or entitled to exercise any
administrative, executive, police, or taxing authority or power;
provided, however, that such term does not include Interconnection
Customer, Transmission Provider, or any Affiliate thereof.
Hazardous Substances shall
mean any chemicals, materials or substances defined as or included
in the definition of “hazardous substances,”
“hazardous wastes,” “hazardous materials,”
“hazardous constituents,” “restricted hazardous
materials,” “extremely hazardous substances,”
“toxic substances,” “radioactive
substances,” “contaminants,”
“pollutants,” “toxic pollutants” or words
of similar meaning and regulatory effect under any applicable
Environmental Law, or any other chemical, material or substance,
exposure to which is prohibited, limited or regulated by any
applicable Environmental Law.
Initial Synchronization Date
shall mean the date upon which the Generating Facility is initially
synchronized and upon which Trial Operation begins.
5
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
In-Service Date shall mean
the date upon which the Interconnection Customer reasonably expects
it will be ready to begin use of the Transmission Provider’s
Interconnection Facilities to obtain back feed power.
Interconnection Customer
shall mean any entity, including the Transmission Provider,
Transmission Owner or any of the Affiliates or subsidiaries of
either, that proposes to interconnect its Generating Facility with
the Transmission Provider’s Transmission System.
Interconnection Customer’s
Interconnection Facilities shall mean all facilities and
equipment, as identified in Appendix A of the Standard Large
Generator Interconnection Agreement, that are located between the
Generating Facility and the Point of Change of Ownership, including
any modification, addition, or upgrades to such facilities and
equipment necessary to physically and electrically interconnect the
Generating Facility to the Transmission Provider’s
Transmission System. Interconnection Customer’s
Interconnection Facilities are sole use facilities.
Interconnection Facilities
shall mean the Transmission Provider’s Interconnection
Facilities and the Interconnection Customer’s Interconnection
Facilities. Collectively, Interconnection Facilities include all
facilities and equipment between the Generating Facility and the
Point of Interconnection, including any modification, additions or
upgrades that are necessary to physically and electrically
interconnect the Generating Facility to the Transmission
Provider’s Transmission System. Interconnection Facilities
are sole use facilities and shall not include Distribution
Upgrades, Stand Alone Network Upgrades or Network Upgrades.
Interconnection Facilities
Study shall mean a study conducted by the Transmission Provider
or a third party consultant for the Interconnection Customer to
determine a list of facilities (including Transmission
Provider’s Interconnection Facilities and Network Upgrades as
identified in the Interconnection System Impact Study), the cost of
those facilities, and the time required to interconnect the
Generating Facility with the Transmission Provider’s
Transmission System. The scope of the study is defined in
Section 8 of the Standard Large Generator Interconnection
Procedures.
Interconnection Facilities Study
Agreement shall mean the form of agreement contained in
Appendix 4 of the Standard Large Generator Interconnection
Procedures for conducting the Interconnection Facilities
Study.
Interconnection Feasibility
Study shall mean a preliminary evaluation of the system impact
and cost of interconnecting the Generating Facility to the
Transmission Provider’s Transmission System, the scope of
which is described in Section 6 of the Standard Large
Generator Interconnection Procedures.
Interconnection Feasibility Study
Agreement shall mean the form of agreement contained in
Appendix 2 of the Standard Large Generator Interconnection
Procedures for conducting the Interconnection Feasibility
Study.
6
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Interconnection Request shall
mean an Interconnection Customer’s request, in the form of
Appendix 1 to the Standard Large Generator Interconnection
Procedures, in accordance with the Tariff, to interconnect a new
Generating Facility, or to increase the capacity of, or make a
Material Modification to the operating characteristics of, an
existing Generating Facility that is interconnected with the
Transmission Provider’s Transmission System.
Interconnection Service shall
mean the service provided by the Transmission Provider associated
with interconnecting the Interconnection Customer’s
Generating Facility to the Transmission Provider’s
Transmission System and enabling it to receive electric energy and
capacity from the Generating Facility at the Point of
Interconnection, pursuant to the terms of the Standard Large
Generator Interconnection Agreement and, if applicable, the
Transmission Provider’s Tariff.
Interconnection Study shall
mean any of the following studies: the Interconnection Feasibility
Study, the Interconnection System Impact Study, and the
Interconnection Facilities Study described in the Standard Large
Generator Interconnection Procedures.
Interconnection System Impact
Study shall mean an engineering study that evaluates the impact
of the proposed interconnection on the safety and reliability of
Transmission Provider’s Transmission System and, if
applicable, an Affected System. The study shall identify and detail
the system impacts that would result if the Generating Facility
were interconnected without project modifications or system
modifications, focusing on the Adverse System Impacts identified in
the Interconnection Feasibility Study, or to study potential
impacts, including but not limited to those identified in the
Scoping Meeting as described in the Standard Large Generator
Interconnection Procedures.
Interconnection System Impact
Study Agreement shall mean the form of agreement contained in
Appendix 3 of the Standard Large Generator Interconnection
Procedures for conducting the Interconnection System Impact
Study.
IRS shall mean the Internal
Revenue Service.
Joint Operating Committee
shall be a group made up of representatives from Interconnection
Customers and the Transmission Provider to coordinate operating and
technical considerations of Interconnection Service.
Large Generating Facility
shall mean a Generating Facility having a Generating Facility
Capacity of more than 20 MW.
Loss shall mean any and all
losses relating to injury to or death of any person or damage to
property, demand, suits, recoveries, costs and expenses, court
costs, attorney fees, and all other obligations by or to third
parties, arising out of or resulting from the other Party’s
performance, or non-performance of its obligations under the
Standard Large Generator Interconnection Agreement on behalf
7
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
of the indemnifying Party, except in cases of gross negligence or
intentional wrongdoing by the indemnifying Party.
Material Modification shall
mean those modifications that have a material impact on the cost or
timing of any Interconnection Request with a later queue priority
date.
Metering Equipment shall mean
all metering equipment installed or to be installed at the
Generating Facility pursuant to the Standard Large Generator
Interconnection Agreement at the metering points, including but not
limited to instrument transformers, MWh-meters, data acquisition
equipment, transducers, remote terminal unit, communications
equipment, phone lines, and fiber optics.
NERC shall mean the North
American Electric Reliability Council or its successor
organization.
Network Resource shall mean
any designated generating resource owned, purchased, or leased by a
Network Customer under the Network Integration Transmission Service
Tariff. Network Resources do not include any resource, or any
portion thereof, that is committed for sale to third parties or
otherwise cannot be called upon to meet the Network
Customer’s Network Load on a non-interruptible basis.
Network Resource Interconnection
Service shall mean an Interconnection Service that allows the
Interconnection Customer to integrate its Large Generating Facility
with the Transmission Provider’s Transmission System
(1) in a manner comparable to that in which the Transmission
Provider integrates its generating facilities to serve native load
customers; or (2) in an RTO or ISO with market based
congestion management, in the same manner as Network Resources.
Network Resource Interconnection Service in and of itself does not
convey transmission service.
Network Upgrades shall mean
the additions, modifications, and upgrades to the Transmission
Provider’s Transmission System required at or beyond the
point at which the Interconnection Facilities connect to the
Transmission Provider’s Transmission System to accommodate
the interconnection of the Large Generating Facility to the
Transmission Provider’s Transmission System.
Notice of Dispute shall mean
a written notice of a dispute or claim that arises out of or in
connection with the Standard Large Generator Interconnection
Agreement or its performance.
Optional Interconnection
Study shall mean a sensitivity analysis based on assumptions
specified by the Interconnection Customer in the Optional
Interconnection Study Agreement.
Optional Interconnection Study
Agreement shall mean the form of agreement contained in
Appendix 5 of the Standard Large Generator Interconnection
Procedures for conducting the Optional Interconnection Study.
Party or Parties shall mean
Transmission Provider, Transmission Owner, Interconnection Customer
or any combination of the above.
8
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Point of Change of Ownership
shall mean the point, as set forth in Appendix A to the
Standard Large Generator Interconnection Agreement, where the
Interconnection Customer’s Interconnection Facilities connect
to the Transmission Provider’s Interconnection
Facilities.
Point of Interconnection
shall mean the point, as set forth in Appendix A to the
Standard Large Generator Interconnection Agreement, where the
Interconnection Facilities connect to the Transmission
Provider’s Transmission System.
Queue Position shall mean the
order of a valid Interconnection Request, relative to all other
pending valid Interconnection Requests, that is established based
upon the date and time of receipt of the valid Interconnection
Request by the Transmission Provider.
Reasonable Efforts shall
mean, with respect to an action required to be attempted or taken
by a Party under the Standard Large Generator Interconnection
Agreement, efforts that are timely and consistent with Good Utility
Practice and are otherwise substantially equivalent to those a
Party would use to protect its own interests.
Scoping Meeting shall mean
the meeting between representatives of the Interconnection Customer
and Transmission Provider conducted for the purpose of discussing
alternative interconnection options, to exchange information
including any transmission data and earlier study evaluations that
would be reasonably expected to impact such interconnection
options, to analyze such information, and to determine the
potential feasible Points of Interconnection.
Site Control shall mean
documentation reasonably demonstrating: (1) ownership of, a
leasehold interest in, or a right to develop a site for the purpose
of constructing the Generating Facility; (2) an option to
purchase or acquire a leasehold site for such purpose; or
(3) an exclusivity or other business relationship between
Interconnection Customer and the entity having the right to sell,
lease or grant Interconnection Customer the right to possess or
occupy a site for such purpose.
Small Generating Facility
shall mean a Generating Facility that has a Generating Facility
Capacity of no more than 20 MW.
Stand Alone Network Upgrades
shall mean Network Upgrades that an Interconnection Customer may
construct without affecting day-to-day operations of the
Transmission System during their construction. Both the
Transmission Provider and the Interconnection Customer must agree
as to what constitutes Stand Alone Network Upgrades and identify
them in Appendix A to the Standard Large Generator
Interconnection Agreement.
Standard Large Generator
Interconnection Agreement (LGIA) shall mean the form of
interconnection agreement applicable to an Interconnection Request
pertaining to a Large Generating Facility that is included in the
Transmission Provider’s Tariff.
9
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Standard Large Generator
Interconnection Procedures (LGIP) shall mean the
interconnection procedures applicable to an Interconnection Request
pertaining to a Large Generating Facility that are included in the
Transmission Provider’s Tariff.
System Protection Facilities
shall mean the equipment, including necessary protection signal
communications equipment, required to protect (1) the
Transmission Provider’s Transmission System from faults or
other electrical disturbances occurring at the Generating Facility
and (2) the Generating Facility from faults or other
electrical system disturbances occurring on the Transmission
Provider’s Transmission System or on other delivery systems
or other generating systems to which the Transmission
Provider’s Transmission System is directly connected.
Tariff shall mean the
Transmission Provider’s Tariff through which open access
transmission service and Interconnection Service are offered, as
filed with FERC, and as amended or supplemented from time to time,
or any successor tariff.
Transmission Owner shall mean
an entity that owns, leases or otherwise possesses an interest in
the portion of the Transmission System at the Point of
Interconnection and may be a Party to the Standard Large Generator
Interconnection Agreement to the extent necessary.
Transmission Provider shall
mean the public utility (or its designated agent) that owns,
controls, or operates transmission or distribution facilities used
for the transmission of electricity in interstate commerce and
provides transmission service under the Tariff. The term
Transmission Provider should be read to include the Transmission
Owner when the Transmission Owner is separate from the Transmission
Provider.
Transmission Provider’s
Interconnection Facilities shall mean all facilities and
equipment owned, controlled or operated by the Transmission
Provider from the Point of Change of Ownership to the Point of
Interconnection as identified in Appendix A to the Standard
Large Generator Interconnection Agreement, including any
modifications, additions or upgrades to such facilities and
equipment. Transmission Provider’s Interconnection Facilities
are sole use facilities and shall not include Distribution
Upgrades, Stand Alone Network Upgrades or Network Upgrades.
Transmission System shall
mean the facilities owned, controlled or operated by the
Transmission Provider or Transmission Owner that are used to
provide transmission service under the Tariff.
Trial Operation shall mean
the period during which Interconnection Customer is engaged in
on-site test operations and commissioning of the Generating
Facility prior to Commercial Operation.
10
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Article 2. Effective Date, Term, and Termination
| 2.1 |
|
Effective Date. This LGIA shall become effective upon
execution by the Parties subject to acceptance by FERC (if
applicable), or if filed unexecuted, upon the date specified by
FERC. Transmission Provider shall promptly file this LGIA with FERC
upon execution in accordance with Article 3.1, if
required. |
| |
| 2.2 |
|
Term of Agreement. Subject to the provisions of
Article 2.3, this LGIA shall remain in effect for a period of
ten (10) years from the Effective Date or such other longer
period as Interconnection Customer may request and shall be
automatically renewed for each successive one-year period
thereafter. Provided, however, that if the Interconnection
Customer’s Lease Agreement dated September 14, 2005 or
the Operations Provisions, thereto, are set to terminate or
otherwise cease to be effective, Interconnection Customer shall
process such termination consistent with Article 2.3.1 unless
Transmission Provider and Interconnection Customer can mutually
agree upon the amendments and/or modifications necessary to retain
this Agreement as effective given such change in
circumstances. |
| |
| 2.3 |
|
Termination Procedures. |
| |
2.3.1 |
|
Written Notice . This LGIA may be terminated by
Interconnection Customer after giving Transmission Provider ninety
(90) Calendar Days advance written notice, or by Transmission
Provider notifying FERC after the Generating Facility permanently
ceases Commercial Operation. |
| |
| |
2.3.2 |
|
Default . Either Party may terminate this LGIA in
accordance with Article 17. |
| |
| |
2.3.3 |
|
Notwithstanding Articles 2.3.1 and 2.3.2, no termination shall
become effective until the Parties have complied with all
Applicable Laws and Regulations applicable to such termination,
including the filing with FERC of a notice of termination of this
LGIA, which notice has been accepted for filing by FERC. |
| 2.4 |
|
Termination Costs. If a Party elects to terminate this
Agreement pursuant to Article 2.3 above, each Party shall pay
all costs incurred (including any cancellation costs relating to
orders or contracts for Interconnection Facilities and equipment)
or charges assessed by the other Party, as of the date of the other
Party’s receipt of such notice of termination, that are the
responsibility of the Terminating Party under this LGIA. In the
event of termination by a Party, the Parties shall use commercially
Reasonable Efforts to mitigate the costs, damages and charges
arising as a consequence of termination. Upon termination of this
LGIA, unless otherwise ordered or approved by FERC: |
| |
2.4.1 |
|
With respect to any portion of Transmission Provider’s
Interconnection Facilities that have not yet been constructed or
installed, Transmission Provider shall to the extent possible and
with Interconnection Customer’s authorization cancel any
pending orders of, |
11
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
or return, any materials or equipment for, or contracts for
construction of, such facilities; provided that in the event
Interconnection Customer elects not to authorize such cancellation,
Interconnection Customer shall assume all payment obligations with
respect to such materials, equipment, and contracts, and
Transmission Provider shall deliver such material and equipment,
and, if necessary, assign such contracts, to Interconnection
Customer as soon as practicable, at Interconnection
Customer’s expense. To the extent that Interconnection
Customer has already paid Transmission Provider for any or all such
costs of materials or equipment not taken by Interconnection
Customer, Transmission Provider shall promptly refund such amounts
to Interconnection Customer, less any costs, including penalties
incurred by Transmission Provider to cancel any pending orders of
or return such materials, equipment, or contracts. |
| |
| |
|
|
If an Interconnection Customer terminates this LGIA, it shall
be responsible for all costs incurred in association with that
Interconnection Customer’s interconnection, including any
cancellation costs relating to orders or contracts for
Interconnection Facilities and equipment, and other expenses
including any Network Upgrades for which Transmission Provider has
incurred expenses and has not been reimbursed by Interconnection
Customer. |
| |
| |
2.4.2 |
|
Transmission Provider may, at its option, retain any portion of
such materials, equipment, or facilities that Interconnection
Customer chooses not to accept delivery of, in which case
Transmission Provider shall be responsible for all costs associated
with procuring such materials, equipment, or facilities. |
| |
| |
2.4.3 |
|
With respect to any portion of the Interconnection Facilities,
and any other facilities already installed or constructed pursuant
to the terms of this LGIA, Interconnection Customer shall be
responsible for all costs associated with the removal, relocation
or other disposition or retirement of such materials, equipment, or
facilities. |
| 2.5 |
|
Disconnection . Upon termination of this LGIA, the
Parties will take all appropriate steps to disconnect the Large
Generating Facility from the Transmission System. All costs
required to effectuate such disconnection shall be borne by the
terminating Party, unless such termination resulted from the
non-terminating Party’s Default of this LGIA or such
non-terminating Party otherwise is responsible for these costs
under this LGIA. |
| |
| 2.6 |
|
Survival . This LGIA shall continue in effect after
termination to the extent necessary to provide for final billings
and payments and for costs incurred hereunder, including billings
and payments pursuant to this LGIA; to permit the determination and
enforcement of liability and indemnification obligations arising
from acts or events that occurred while this LGIA was in effect;
and to permit each Party to have access to the lands of the other
Party pursuant to this LGIA or other applicable agreements, to
disconnect, remove or salvage its own facilities and
equipment. |
12
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
Article 3. Regulatory Filings
| 3.1 |
|
Filing . Transmission Provider shall file this LGIA (and
any amendment hereto) with the appropriate Governmental Authority,
if required. Interconnection Customer may request that any
information so provided be subject to the confidentiality
provisions of Article 22. If Interconnection Customer has
executed this LGIA, or any amendment thereto, Interconnection
Customer shall reasonably cooperate with Transmission Provider with
respect to such filing and to provide any information reasonably
requested by Transmission Provider needed to comply with applicable
regulatory requirements. |
Article 4. Scope of Service
| 4.1 |
|
Interconnection Product Options . Interconnection
Customer has selected the following (checked) type of
Interconnection Service: |
| |
4.1.1 |
|
Energy Resource Interconnection Service. |
| |
4.1.1.1 |
|
The Product . Energy Resource Interconnection Service
allows Interconnection Customer to connect the Large Generating
Facility to the Transmission System and be eligible to deliver the
Large Generating Facility’s output using the existing firm or
non-firm capacity of the Transmission System on an “as
available” basis. To the extent Interconnection Customer
wants to receive Energy Resource Interconnection Service,
Transmission Provider shall construct facilities identified in
Attachment A. |
| |
| |
4.1.1.2 |
|
Transmission Delivery Service Implications . Under
Energy Resource Interconnection Service, Interconnection Customer
will be eligible to inject power from the Large Generating Facility
into and deliver power across the interconnecting Transmission
Provider’s Transmission System on an “as
available” basis up to the amount of MWs identified in the
applicable stability and steady state studies to the extent the
upgrades initially required to qualify for Energy Resource
Interconnection Service have been constructed. Where eligible to do
so ( e.g., PJM, ISO-NE, NYISO), Interconnection Customer may
place a bid to sell into the market up to the maximum identified
Large Generating Facility output, subject to any conditions
specified in the interconnection service approval, and the Large
Generating Facility will be dispatched to the extent
Interconnection Customer’s bid clears. In all other
instances, no transmission delivery service from the Large
Generating Facility is assured, but Interconnection Customer may
obtain Point-to-Point Transmission Service, Network Integration
Transmission Service, or be used for secondary network transmission
service, pursuant to Transmission Provider’s Tariff, up to
the maximum output identified in the stability and steady state
studies. In those instances, in order for Interconnection Customer
to obtain the right to deliver or |
13
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
inject energy beyond the Large Generating Facility Point of
Interconnection or to improve its ability to do so, transmission
delivery service must be obtained pursuant to the provisions of
Transmission Provider’s Tariff. The Interconnection
Customer’s ability to inject its Large Generating Facility
output beyond the Point of Interconnection, therefore, will depend
on the existing capacity of Transmission Provider’s
Transmission System at such time as a transmission service request
is made that would accommodate such delivery. The provision of firm
Point-to-Point Transmission Service or Network Integration
Transmission Service may require the construction of additional
Network Upgrades. |
| |
4.1.2 |
|
Network Resource Interconnection Service. |
| |
4.1.2.1 |
|
The Product . Transmission Provider must conduct the
necessary studies and construct the Network Upgrades needed to
integrate the Large Generating Facility (1) in a manner
comparable to that in which Transmission Provider integrates its
generating facilities to serve native load customers; or
(2) in an ISO or RTO with market based congestion management,
in the same manner as all Network Resources. To the extent
Interconnection Customer wants to receive Network Resource
Interconnection Service, Transmission Provider shall construct the
facilities identified in Attachment A to this LGIA. |
| |
| |
4.1.2.2 |
|
Transmission Delivery Service Implications . Network
Resource Interconnection Service allows Interconnection
Customer’s Large Generating Facility to be designated by any
Network Customer under the Tariff on Transmission Provider’s
Transmission System as a Network Resource, up to the Large
Generating Facility’s full output, on the same basis as
existing Network Resources interconnected to Transmission
Provider’s Transmission System, and to be studied as a
Network Resource on the assumption that such a designation will
occur. Although Network Resource Interconnection Service does not
convey a reservation of transmission service, any Network Customer
under the Tariff can utilize its network service under the Tariff
to obtain delivery of energy from the interconnected
Interconnection Customer’s Large Generating Facility in the
same manner as it accesses Network Resources. A Large Generating
Facility receiving Network Resource Interconnection Service may
also be used to provide Ancillary Services after technical studies
and/or periodic analyses are performed with respect to the Large
Generating Facility’s ability to provide any applicable
Ancillary Services, provided that such studies and analyses have
been or would be required in connection with the provision of such
Ancillary Services by any existing Network Resource. However, if an
Interconnection Customer’s Large Generating Facility has not
been designated as a Network Resource by any load, it cannot be
required to provide Ancillary Services except to the extent such
requirements extend to all generating facilities that are similarly
situated. The |
14
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
provision of Network Integration Transmission Service or firm
Point-to-Point Transmission Service may require additional studies
and the construction of additional upgrades. Because such studies
and upgrades would be associated with a request for delivery
service under the Tariff, cost responsibility for the studies and
upgrades would be in accordance with FERC’s policy for
pricing transmission delivery services. |
| |
| |
|
|
Network Resource Interconnection Service does not necessarily
provide Interconnection Customer with the capability to physically
deliver the output of its Large Generating Facility to any
particular load on Transmission Provider’s Transmission
System without incurring congestion costs. In the event of
transmission constraints on Transmission Provider’s
Transmission System, Interconnection Customer’s Large
Generating Facility shall be subject to the applicable congestion
management procedures in Transmission Provider’s Transmission
System in the same manner as Network Resources. |
| |
| |
|
|
There is no requirement either at the time of study or
interconnection, or at any point in the future, that
Interconnection Customer’s Large Generating Facility be
designated as a Network Resource by a Network Service Customer
under the Tariff or that Interconnection Customer identify a
specific buyer (or sink). To the extent a Network Customer does
designate the Large Generating Facility as a Network Resource, it
must do so pursuant to Transmission Provider’s Tariff. |
| |
| |
|
|
Once an Interconnection Customer satisfies the requirements for
obtaining Network Resource Interconnection Service, any future
transmission service request for delivery from the Large Generating
Facility within Transmission Provider’s Transmission System
of any amount of capacity and/or energy, up to the amount initially
studied, will not require that any additional studies be performed
or that any further upgrades associated with such Large Generating
Facility be undertaken, regardless of whether or not such Large
Generating Facility is ever designated by a Network Customer as a
Network Resource and regardless of changes in ownership of the
Large Generating Facility. However, the reduction or elimination of
congestion or redispatch costs may require additional studies and
the construction of additional upgrades. |
| |
| |
|
|
To the extent Interconnection Customer enters into an
arrangement for long term transmission service for deliveries from
the Large Generating Facility outside Transmission Provider’s
Transmission System, such request may require additional studies
and upgrades in order for Transmission Provider to grant such
request. |
15
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| 4.2 |
|
Provision of Service . Transmission Provider shall
provide Interconnection Service for the Large Generating Facility
at the Point of Interconnection. |
| |
| 4.3 |
|
Performance Standards . Each Party shall perform all of
its obligations under this LGIA in accordance with Applicable Laws
and Regulations, Applicable Reliability Standards, and Good Utility
Practice, and to the extent a Party is required or prevented or
limited in taking any action by such regulations and standards,
such Party shall not be deemed to be in Breach of this LGIA for its
compliance therewith. If such Party is a Transmission Provider or
Transmission Owner, then that Party shall amend the LGIA and submit
the amendment to FERC for approval. |
| |
| 4.4 |
|
No Transmission Delivery Service . The execution of this
LGIA does not constitute a request for, nor the provision of, any
transmission delivery service under Transmission Provider’s
Tariff, and does not convey any right to deliver electricity to any
specific customer or Point of Delivery. |
| |
| 4.5 |
|
Interconnection Customer Provided Services . The
services provided by Interconnection Customer under this LGIA are
set forth in Article 9.6 and Article 13.5.1.
Interconnection Customer shall be paid for such services in
accordance with Article 11.6. |
Article 5. Interconnection Facilities Engineering,
Procurement, and Construction
| 5.1 |
|
Options . Unless otherwise mutually agreed to between
the Parties, Interconnection Customer shall select the In-Service
Date, Initial Synchronization Date, and Commercial Operation Date;
and either Standard Option or Alternate Option set forth below for
completion of Transmission Provider’s Interconnection
Facilities and Network Upgrades as set forth in Appendix A,
Interconnection Facilities and Network Upgrades, and such dates and
selected option shall be set forth in Appendix B,
Milestones. |
| |
5.1.1 |
|
Standard Option . Transmission Provider shall design,
procure, and construct Transmission Provider’s
Interconnection Facilities and Network Upgrades, using Reasonable
Efforts to complete Transmission Provider’s Interconnection
Facilities and Network Upgrades by the dates set forth in
Appendix B, Milestones. Transmission Provider shall not be
required to undertake any action which is inconsistent with its
standard safety practices, its material and equipment
specifications, its design criteria and construction procedures,
its labor agreements, and Applicable Laws and Regulations. In the
event Transmission Provider reasonably expects that it will not be
able to complete Transmission Provider’s Interconnection
Facilities and Network Upgrades by the specified dates,
Transmission Provider shall promptly provide written notice to
Interconnection Customer and shall undertake Reasonable Efforts to
meet the earliest dates thereafter. |
| |
| |
5.1.2 |
|
Alternate Option . If the dates designated by
Interconnection Customer are acceptable to Transmission Provider,
Transmission Provider shall so notify Interconnection Customer
within thirty (30) Calendar Days, and shall assume
responsibility for the design, |
16
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
procurement and construction of Transmission Provider’s
Interconnection Facilities by the designated dates. |
| |
| |
|
|
If Transmission Provider subsequently fails to complete
Transmission Provider’s Interconnection Facilities by the
In-Service Date, to the extent necessary to provide back feed
power; or fails to complete Network Upgrades by the Initial
Synchronization Date to the extent necessary to allow for Trial
Operation at full power output, unless other arrangements are made
by the Parties for such Trial Operation; or fails to complete the
Network Upgrades by the Commercial Operation Date, as such dates
are reflected in Appendix B, Milestones; Transmission Provider
shall pay Interconnection Customer liquidated damages in accordance
with Article 5.3, Liquidated Damages, provided, however, the
dates designated by Interconnection Customer shall be extended day
for day for each day that the applicable RTO or ISO refuses to
grant clearances to install equipment. |
| |
| |
5.1.3 |
|
Option to Build . If the dates designated by
Interconnection Customer are not acceptable to Transmission
Provider, Transmission Provider shall so notify Interconnection
Customer within thirty (30) Calendar Days, and unless the
Parties agree otherwise, Interconnection Customer shall have the
option to assume responsibility for the design, procurement and
construction of Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades on the dates specified
in Article 5.1.2. Transmission Provider and Interconnection
Customer must agree as to what constitutes Stand Alone Network
Upgrades and identify such Stand Alone Network Upgrades in
Appendix A. Except for Stand Alone Network Upgrades,
Interconnection Customer shall have no right to construct Network
Upgrades under this option. |
| |
| |
5.1.4 |
|
Negotiated Option . If Interconnection Customer elects
not to exercise its option under Article 5.1.3, Option to
Build, Interconnection Customer shall so notify Transmission
Provider within thirty (30) Calendar Days, and the Parties
shall in good faith attempt to negotiate terms and conditions
(including revision of the specified dates and liquidated damages,
the provision of incentives or the procurement and construction of
a portion of Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades by Interconnection
Customer) pursuant to which Transmission Provider is responsible
for the design, procurement and construction of Transmission
Provider’s Interconnection Facilities and Network Upgrades.
If the Parties are unable to reach agreement on such terms and
conditions, Transmission Provider shall assume responsibility for
the design, procurement and construction of Transmission
Provider’s Interconnection Facilities and Network Upgrades
pursuant to 5.1.1, Standard Option. |
| 5.2 |
|
General Conditions Applicable to Option to Build. If
Interconnection Customer assumes responsibility for the design,
procurement and construction of Transmission Provider’s
Interconnection Facilities and Stand Alone Network Upgrades, |
17
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
(1) Interconnection Customer shall engineer, procure equipment,
and construct Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades (or portions thereof)
using Good Utility Practice and using standards and specifications
provided in advance by Transmission Provider; |
| |
| |
|
|
(2) Interconnection Customer’s engineering, procurement
and construction of Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades shall comply with all
requirements of law and Applicable Reliability Standards to which
Transmission Provider would be subject in the engineering,
procurement or construction of Transmission Provider’s
Interconnection Facilities and Stand Alone Network Upgrades; |
| |
| |
|
|
(3) Transmission Provider shall review and approve the
engineering design, equipment acceptance tests, and the
construction of Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades; |
| |
| |
|
|
(4) prior to commencement of construction, Interconnection
Customer shall provide to Transmission Provider a schedule for
construction of Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades, and shall promptly
respond to requests for information from Transmission
Provider; |
| |
| |
|
|
(5) at any time during construction, Transmission Provider
shall have the right to gain unrestricted access to Transmission
Provider’s Interconnection Facilities and Stand Alone Network
Upgrades and to conduct inspections of the same; |
| |
| |
|
|
(6) at any time during construction, should any phase of the
engineering, equipment procurement, or construction of Transmission
Provider’s Interconnection Facilities and Stand Alone Network
Upgrades not meet the standards and specifications provided by
Transmission Provider, Interconnection Customer shall be obligated
to remedy deficiencies in that portion of Transmission
Provider’s Interconnection Facilities and Stand Alone Network
Upgrades; |
| |
| |
|
|
(7) Interconnection Customer shall indemnify Transmission
Provider for claims arising from Interconnection Customer’s
construction of Transmission Provider’s Interconnection
Facilities and Stand Alone Network Upgrades under the terms and
procedures applicable to Article 18.1 Indemnity; |
| |
| |
|
|
(8) Interconnection Customer shall transfer control of
Transmission Provider’s Interconnection Facilities and Stand
Alone Network Upgrades to Transmission Provider; |
| |
| |
|
|
(9) Unless Parties otherwise agree, Interconnection Customer
shall transfer ownership of Transmission Provider’s
Interconnection Facilities and Stand-Alone Network Upgrades to
Transmission Provider; |
18
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
(10) Transmission Provider shall approve and accept for
operation and maintenance Transmission Provider’s
Interconnection Facilities and Stand Alone Network Upgrades to the
extent engineered, procured, and constructed in accordance with
this Article 5.2; and |
| |
| |
|
|
(11) Interconnection Customer shall deliver to Transmission
Provider “as-built” drawings, information, and any
other documents that are reasonably required by Transmission
Provider to assure that the Interconnection Facilities and
Stand-Alone Network Upgrades are built to the standards and
specifications required by Transmission Provider. |
| 5.3. |
|
Liquidated Damages . The actual damages to
Interconnection Customer, in the event Transmission
Provider’s Interconnection Facilities or Network Upgrades are
not completed by the dates designated by Interconnection Customer
and accepted by Transmission Provider pursuant to subparagraphs
5.1.2 or 5.1.4, above, may include Interconnection Customer’s
fixed operation and maintenance costs and lost opportunity costs.
Such actual damages are uncertain and impossible to determine at
this time. Because of such uncertainty, any liquidated damages paid
by Transmission Provider to Interconnection Customer in the event
that Transmission Provider does not complete any portion of
Transmission Provider’s Interconnection Facilities or Network
Upgrades by the applicable dates, shall be an amount equal to
1 / 2 of 1 percent per day of the actual
cost of Transmission Provider’s Interconnection Facilities
and Network Upgrades, in the aggregate, for which Transmission
Provider has assumed responsibility to design, procure and
construct. |
| |
| |
|
However, in no event shall the total liquidated damages exceed
20 percent of the actual cost of Transmission Provider’s
Interconnection Facilities and Network Upgrades for which
Transmission Provider has assumed responsibility to design,
procure, and construct. The foregoing payments will be made by
Transmission Provider to Interconnection Customer as just
compensation for the damages caused to Interconnection Customer,
which actual damages are uncertain and impossible to determine at
this time, and as reasonable liquidated damages, but not as a
penalty or a method to secure performance of this LGIA. Liquidated
damages, when the Parties agree to them, are the exclusive remedy
for the Transmission Provider’s failure to meet its
schedule. |
| |
| |
|
No liquidated damages shall be paid to Interconnection Customer
if: (1) Interconnection Customer is not ready to commence use
of Transmission Provider’s Interconnection Facilities or
Network Upgrades to take the delivery of power for the Large
Generating Facility’s Trial Operation or to export power from
the Large Generating Facility on the specified dates, unless
Interconnection Customer would have been able to commence use of
Transmission Provider’s Interconnection Facilities or Network
Upgrades to take the delivery of power for Large Generating
Facility’s Trial Operation or to export power from the Large
Generating Facility, but for Transmission Provider’s delay;
(2) Transmission Provider’s failure to meet the
specified dates is the result of the action or inaction of
Interconnection Customer or any other Interconnection |
19
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
Customer who has entered into an LGIA with Transmission
Provider or any cause beyond Transmission Provider’s
reasonable control or reasonable ability to cure; (3) the
Interconnection Customer has assumed responsibility for the design,
procurement and construction of Transmission Provider’s
Interconnection Facilities and Stand Alone Network Upgrades; or
(4) the Parties have otherwise agreed. |
| |
| 5.4 |
|
Power System Stabilizers . The Interconnection Customer
shall procure, install, maintain and operate Power System
Stabilizers in accordance with the guidelines and procedures
established by the Applicable Reliability Council. Transmission
Provider reserves the right to reasonably establish minimum
acceptable settings for any installed Power System Stabilizers,
subject to the design and operating limitations of the Large
Generating Facility. If the Large Generating Facility’s Power
System Stabilizers are removed from service or not capable of
automatic operation, Interconnection Customer shall immediately
notify Transmission Provider’s system operator, or its
designated representative. The requirements of this paragraph shall
not apply to wind generators. |
| |
| 5.5 |
|
Equipment Procurement . If responsibility for
construction of Transmission Provider’s Interconnection
Facilities or Network Upgrades is to be borne by Transmission
Provider, then Transmission Provider shall commence design of
Transmission Provider’s Interconnection Facilities or Network
Upgrades and procure necessary equipment as soon as practicable
after all of the following conditions are satisfied, unless the
Parties otherwise agree in writing: |
| |
5.5.1 |
|
Transmission Provider has completed the Facilities Study
pursuant to the Facilities Study Agreement; |
| |
| |
5.5.2 |
|
Transmission Provider has received written authorization to
proceed with design and procurement from Interconnection Customer
by the date specified in Appendix B, Milestones; and |
| |
| |
5.5.3 |
|
Interconnection Customer has provided security to Transmission
Provider in accordance with Article 11.5 by the dates
specified in Appendix B, Milestones. |
| 5.6 |
|
Construction Commencement . Transmission Provider shall
commence construction of Transmission Provider’s
Interconnection Facilities and Network Upgrades for which it is
responsible as soon as practicable after the following additional
conditions are satisfied: |
| |
5.6.1 |
|
Approval of the appropriate Governmental Authority has been
obtained for any facilities requiring regulatory approval; |
| |
| |
5.6.2 |
|
Necessary real property rights and rights-of-way have been
obtained, to the extent required for the construction of a discrete
aspect of Transmission Provider’s Interconnection Facilities
and Network Upgrades; |
20
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
5.6.3 |
|
Transmission Provider has received written authorization to
proceed with construction from Interconnection Customer by the date
specified in Appendix B, Milestones; and |
| |
| |
5.6.4 |
|
Interconnection Customer has provided security to Transmission
Provider in accordance with Article 11.5 by the dates
specified in Appendix B, Milestones. |
| 5.7 |
|
Work Progress . The Parties will keep each other advised
periodically as to the progress of their respective design,
procurement and construction efforts. Either Party may, at any
time, request a progress report from the other Party. If, at any
time, Interconnection Customer determines that the completion of
Transmission Provider’s Interconnection Facilities will not
be required until after the specified In-Service Date,
Interconnection Customer will provide written notice to
Transmission Provider of such later date upon which the completion
of Transmission Provider’s Interconnection Facilities will be
required. |
| |
| 5.8 |
|
Information Exchange . As soon as reasonably practicable
after the Effective Date, the Parties shall exchange information
regarding the design and compatibility of the Parties’
Interconnection Facilities and compatibility of the Interconnection
Facilities with Transmission Provider’s Transmission System,
and shall work diligently and in good faith to make any necessary
design changes. |
| |
| 5.9 |
|
Limited Operation . If any of Transmission
Provider’s Interconnection Facilities or Network Upgrades are
not reasonably expected to be completed prior to the Commercial
Operation Date of the Large Generating Facility, Transmission
Provider shall, upon the request and at the expense of
Interconnection Customer, perform operating studies on a timely
basis to determine the extent to which the Large Generating
Facility and Interconnection Customer’s Interconnection
Facilities may operate prior to the completion of Transmission
Provider’s Interconnection Facilities or Network Upgrades
consistent with Applicable Laws and Regulations, Applicable
Reliability Standards, Good Utility Practice, and this LGIA.
Transmission Provider shall permit Interconnection Customer to
operate the Large Generating Facility and Interconnection
Customer’s Interconnection Facilities in accordance with the
results of such studies. |
| |
| 5.10 |
|
Interconnection Customer’s Interconnection Facilities
(‘ICIF’) . Interconnection Customer shall, at its
expense, design, procure, construct, own and install the ICIF, as
set forth in Appendix A, Interconnection Facilities, Network
Upgrades and Distribution Upgrades. |
| |
5.10.1 |
|
Interconnection Customer’s Interconnection Facility
Specifications . Interconnection Customer shall submit initial
specifications for the ICIF, including System Protection
Facilities, to Transmission Provider at least one hundred eighty
(180) Calendar Days prior to the Initial Synchronization Date;
and final specifications for review and comment at least ninety
(90) Calendar Days prior to the Initial Synchronization Date.
Transmission Provider shall review such specifications to ensure
that the ICIF are compatible with the technical specifications,
operational control, and safety requirements of Transmission
Provider and comment on such specifications within thirty
(30) Calendar |
21
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
Days of Interconnection Customer’s submission. All
specifications provided hereunder shall be deemed
confidential. |
| |
| |
5.10.2 |
|
Transmission Provider’s Review . Transmission
Provider’s review of Interconnection Customer’s final
specifications shall not be construed as confirming, endorsing, or
providing a warranty as to the design, fitness, safety, durability
or reliability of the Large Generating Facility, or the ICIF.
Interconnection Customer shall make such changes to the ICIF as may
reasonably be required by Transmission Provider, in accordance with
Good Utility Practice, to ensure that the ICIF are compatible with
the technical specifications, operational control, and safety
requirements of Transmission Provider. |
| |
| |
5.10.3 |
|
ICIF Construction . The ICIF shall be designed and
constructed in accordance with Good Utility Practice. Within one
hundred twenty (120) Calendar Days after the Commercial
Operation Date, unless the Parties agree on another mutually
acceptable deadline, Interconnection Customer shall deliver to
Transmission Provider “as-built” drawings, information
and documents for the ICIF, such as: a one-line diagram, a site
plan showing the Large Generating Facility and the ICIF, plan and
elevation drawings showing the layout of the ICIF, a relay
functional diagram, relaying AC and DC schematic wiring diagrams
and relay settings for all facilities associated with
Interconnection Customer’s step-up transformers, the
facilities connecting the Large Generating Facility to the step-up
transformers and the ICIF, and the impedances (determined by
factory tests) for the associated step-up transformers and the
Large Generating Facility. The Interconnection Customer shall
provide Transmission Provider specifications for the excitation
system, automatic voltage regulator, Large Generating Facility
control and protection settings, transformer tap settings, and
communications, if applicable. |
| 5.11 |
|
Transmission Provider’s Interconnection Facilities
Construction . Transmission Provider’s Interconnection
Facilities shall be designed and constructed in accordance with
Good Utility Practice. Upon request, within one hundred twenty
(120) Calendar Days after the Commercial Operation Date,
unless the Parties agree on another mutually acceptable deadline,
Transmission Provider shall deliver to Interconnection Customer the
following “as-built” drawings, information and
documents for Transmission Provider’s Interconnection
Facilities [include appropriate drawings and relay diagrams]. |
| |
| |
|
Transmission Provider will obtain control of Transmission
Provider’s Interconnection Facilities and Stand Alone Network
Upgrades upon completion of such facilities. |
| |
| 5.12 |
|
Access Rights . Upon reasonable notice and supervision
by a Party, and subject to any required or necessary regulatory
approvals, a Party (“Granting Party”) shall furnish
at no cost to the other Party (“Access Party”)
any rights of use, licenses, rights of way and easements with
respect to lands owned or controlled by the Granting Party, its
agents (if allowed under the applicable agency agreement), or any
Affiliate, that are necessary to enable the Access Party to
obtain |
22
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
ingress and egress to construct, operate, maintain, repair,
test (or witness testing), inspect, replace or remove facilities
and equipment to: (i) interconnect the Large Generating
Facility with the Transmission System; (ii) operate and
maintain the Large Generating Facility, the Interconnection
Facilities and the Transmission System; and (iii) disconnect
or remove the Access Party’s facilities and equipment upon
termination of this LGIA. In exercising such licenses, rights of
way and easements, the Access Party shall not unreasonably disrupt
or interfere with normal operation of the Granting Party’s
business and shall adhere to the safety rules and procedures
established in advance, as may be changed from time to time, by the
Granting Party and provided to the Access Party. |
| |
| 5.13 |
|
Lands of Other Property Owners . If any part of
Transmission Provider or Transmission Owner’s Interconnection
Facilities and/or Network Upgrades is to be installed on property
owned by persons other than Interconnection Customer or
Transmission Provider or Transmission Owner, Transmission Provider
or Transmission Owner shall at Interconnection Customer’s
expense use efforts, similar in nature and extent to those that it
typically undertakes on its own behalf or on behalf of its
Affiliates, including use of its eminent domain authority, and to
the extent consistent with state law, to procure from such persons
any rights of use, licenses, rights of way and easements that are
necessary to construct, operate, maintain, test, inspect, replace
or remove Transmission Provider or Transmission Owner’s
Interconnection Facilities and/or Network Upgrades upon such
property. |
| |
| 5.14 |
|
Permits. Transmission Provider or Transmission Owner and
Interconnection Customer shall cooperate with each other in good
faith in obtaining all permits, licenses, and authorizations that
are necessary to accomplish the interconnection in compliance with
Applicable Laws and Regulations. With respect to this paragraph,
Transmission Provider or Transmission Owner shall provide
permitting assistance to Interconnection Customer comparable to
that provided to Transmission Provider’s own, or an
Affiliate’s generation. |
| |
| 5.15 |
|
Early Construction of Base Case Facilities.
Interconnection Customer may request Transmission Provider to
construct, and Transmission Provider shall construct, using
Reasonable Efforts to accommodate Interconnection Customer’s
In-Service Date, all or any portion of any Network Upgrades
required for Interconnection Customer to be interconnected to the
Transmission System which are included in the Base Case of the
Facilities Study for Interconnection Customer, and which also are
required to be constructed for another Interconnection Customer,
but where such construction is not scheduled to be completed in
time to achieve Interconnection Customer’s In-Service
Date. |
| |
| 5.16 |
|
Suspension. Interconnection Customer reserves the right,
upon written notice to Transmission Provider, to suspend at any
time all work by Transmission Provider associated with the
construction and installation of Transmission Provider’s
Interconnection Facilities and/or Network Upgrades required under
this LGIA with the condition that Transmission System shall be left
in a safe and reliable condition in accordance with Good Utility
Practice and Transmission Provider’s safety and reliability
criteria. In such event, Interconnection Customer shall be |
23
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
responsible for all reasonable and necessary costs which
Transmission Provider (i) has incurred pursuant to this LGIA
prior to the suspension and (ii) incurs in suspending such
work, including any costs incurred to perform such work as may be
necessary to ensure the safety of persons and property and the
integrity of the Transmission System during such suspension and, if
applicable, any costs incurred in connection with the cancellation
or suspension of material, equipment and labor contracts which
Transmission Provider cannot reasonably avoid; provided, however,
that prior to canceling or suspending any such material, equipment
or labor contract, Transmission Provider shall obtain
Interconnection Customer’s authorization to do so. |
| |
| |
|
Transmission Provider shall invoice Interconnection Customer
for such costs pursuant to Article 12 and shall use due
diligence to minimize its costs. In the event Interconnection
Customer suspends work by Transmission Provider required under this
LGIA pursuant to this Article 5.16, and has not requested
Transmission Provider to recommence the work required under this
LGIA on or before the expiration of three (3) years following
commencement of such suspension, this LGIA shall be deemed
terminated. The three-year period shall begin on the date the
suspension is requested, or the date of the written notice to
Transmission Provider, if no effective date is specified. |
| |
| 5.17 |
|
Taxes. |
| |
5.17.1 |
|
Interconnection Customer Payments Not Taxable. The
Parties intend that all payments or property transfers made by
Interconnection Customer to Transmission Provider for the
installation of Transmission Provider’s Interconnection
Facilities and the Network Upgrades shall be non-taxable, either as
contributions to capital, or as an advance, in accordance with the
Internal Revenue Code and any applicable state income tax laws and
shall not be taxable as contributions in aid of construction or
otherwise under the Internal Revenue Code and any applicable state
income tax laws. |
| |
| |
5.17.2 |
|
Representations and Covenants. In accordance with IRS
Notice 2001-82 and IRS Notice 88-129, Interconnection Customer
represents and covenants that (i) ownership of the electricity
generated at the Large Generating Facility will pass to another
party prior to the transmission of the electricity on the
Transmission System, (ii) for income tax purposes, the amount of
any payments and the cost of any property transferred to
Transmission Provider for Transmission Provider’s
Interconnection Facilities will be capitalized by Interconnection
Customer as an intangible asset and recovered using the
straight-line method over a useful life of twenty (20) years, and
(iii) any portion of Transmission Provider’s
Interconnection Facilities that is a “dual-use
intertie,” within the meaning of IRS Notice 88-129, is
reasonably expected to carry only a de minimis amount of
electricity in the direction of the Large Generating Facility. For
this purpose, “de minimis amount” means no more than
5 percent of the total power flows in both directions,
calculated in accordance with the “5 percent test”
set forth in IRS Notice 88-129. This is not intended to be an
exclusive list of the relevant conditions that must be met to
conform to IRS requirements for non-taxable treatment. |
24
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
At Transmission Provider’s request, Interconnection
Customer shall provide Transmission Provider with a report from an
independent engineer confirming its representation in clause (iii),
above. Transmission Provider represents and covenants that the cost
of Transmission Provider’s Interconnection Facilities paid
for by Interconnection Customer will have no net effect on the base
upon which rates are determined. |
| |
| |
5.17.3 |
|
Indemnification for the Cost Consequences of Current Tax
Liability Imposed Upon the Transmission Provider.
Notwithstanding Article 5.17.1, Interconnection Customer shall
protect, indemnify and hold harmless Transmission Provider from the
cost consequences of any current tax liability imposed against
Transmission Provider as the result of payments or property
transfers made by Interconnection Customer to Transmission Provider
under this LGIA for Interconnection Facilities, as well as any
interest and penalties, other than interest and penalties
attributable to any delay caused by Transmission Provider. |
| |
| |
|
|
Transmission Provider shall not include a gross-up for the cost
consequences of any current tax liability in the amounts it charges
Interconnection Customer under this LGIA unless
(i) Transmission Provider has determined, in good faith, that
the payments or property transfers made by Interconnection Customer
to Transmission Provider should be reported as income subject to
taxation or (ii) any Governmental Authority directs
Transmission Provider to report payments or property as income
subject to taxation; provided, however , that Transmission
Provider may require Interconnection Customer to provide security
for Interconnection Facilities, in a form reasonably acceptable to
Transmission Provider (such as a parental guarantee or a letter of
credit), in an amount equal to the cost consequences of any current
tax liability under this Article 5.17. Interconnection
Customer shall reimburse Transmission Provider for such costs on a
fully grossed-up basis, in accordance with Article 5.17.4,
within thirty (30) Calendar Days of receiving written
notification from Transmission Provider of the amount due,
including detail about how the amount was calculated. |
| |
| |
|
|
The indemnification obligation shall terminate at the earlier
of (1) the expiration of the ten year testing period and the
applicable statute of limitation, as it may be extended by
Transmission Provider upon request of the IRS, to keep these years
open for audit or adjustment, or (2) the occurrence of a
subsequent taxable event and the payment of any related
indemnification obligations as contemplated by this
Article 5.17. |
| |
| |
5.17.4 |
|
Tax Gross-Up Amount. Interconnection Customer’s
liability for the cost consequences of any current tax liability
under this Article 5.17 shall be calculated on a fully
grossed-up basis. Except as may otherwise be agreed to by the
parties, this means that Interconnection Customer will pay
Transmission Provider, in addition to the amount paid for the
Interconnection Facilities and Network Upgrades, an amount equal to
(1) the current taxes imposed on Transmission Provider
(“Current Taxes”) on the excess of (a) |
25
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
|
|
the gross income realized by Transmission Provider as a result
of payments or property transfers made by Interconnection Customer
to Transmission Provider under this LGIA (without regard to any
payments under this Article 5.17) (the “Gross Income
Amount”) over (b) the present value of future tax
deductions for depreciation that will be available as a result of
such payments or property transfers (the “Present Value
Depreciation Amount”), plus (2) an additional amount
sufficient to permit Transmission Provider to receive and retain,
after the payment of all Current Taxes, an amount equal to the net
amount described in clause (1). |
| |
| |
|
|
For this purpose, (i) Current Taxes shall be computed
based on Transmission Provider’s composite federal and state
tax rates at the time the payments or property transfers are
received and Transmission Provider will be treated as being subject
to tax at the highest marginal rates in effect at that time (the
“Current Tax Rate”), and (ii) the Present Value
Depreciation Amount shall be computed by discounting Transmission
Provider’s anticipated tax depreciation deductions as a
result of such payments or property transfers by Transmission
Provider’s current weighted average cost of capital. Thus,
the formula for calculating Interconnection Customer’s
liability to Transmission Owner pursuant to this
Article 5.17.4 can be expressed as follows: (Current Tax Rate
x (Gross Income Amount - Present Value of Tax
Depreciation))/(1-Current Tax Rate). Interconnection
Customer’s estimated tax liability in the event taxes are
imposed shall be stated in Appendix A, Interconnection
Facilities, Network Upgrades and Distribution Upgrades. |
| |
| |
5.17.5 |
|
Private Letter Ruling or Change or Clarification of Law
. At Interconnection Customer’s request and expense,
Transmission Provider shall file with the IRS a request for a
private letter ruling as to whether any property transferred or
sums paid, or to be paid, by Interconnection Customer to
Transmission Provider under this LGIA are subject to federal income
taxation. Interconnection Customer will prepare the initial draft
of the request for a private letter ruling, and will certify under
penalties of perjury that all facts represented in such request are
true and accurate to the best of Interconnection Customer’s
knowledge. Transmission Provider and Interconnection Customer shall
cooperate in good faith with respect to the submission of such
request. |
| |
| |
|
|
Transmission Provider shall keep Interconnection Customer fully
informed of the status of such request for a private letter ruling
and shall execute either a privacy act waiver or a limited power of
attorney, in a form acceptable to the IRS, that authorizes
Interconnection Customer to participate in all discussions with the
IRS regarding such request for a private letter ruling.
Transmission Provider shall allow Interconnection Customer to
attend all meetings with IRS officials about the request and shall
permit Interconnection Customer to prepare the initial drafts of
any follow-up letters in connection with the request. |
26
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
5.17.6 |
|
Subsequent Taxable Events . If, within 10 years
from the date on which the relevant Transmission Provider’s
Interconnection Facilities are placed in service, (i)
Interconnection Customer Breaches the covenants contained in
Article 5.17.2, (ii) a “disqualification
event” occurs within the meaning of IRS Notice 88-129, or
(iii) this LGIA terminates and Transmission Provider retains
ownership of the Interconnection Facilities and Network Upgrades,
Interconnection Customer shall pay a tax gross-up for the cost
consequences of any current tax liability imposed on Transmission
Provider, calculated using the methodology described in
Article 5.17.4 and in accordance with IRS Notice 90-60. |
| |
| |
5.17.7 |
|
Contests . In the event any Governmental Authority
determines that Transmission Provider’s receipt of payments
or property constitutes income that is subject to taxation,
Transmission Provider shall notify Interconnection Customer, in
writing, within thirty (30) Calendar Days of receiving
notification of such determination by a Governmental Authority.
Upon the timely written request by Interconnection Customer and at
Interconnection Customer’s sole expense, Transmission
Provider may appeal, protest, seek abatement of, or otherwise
oppose such determination. Upon Interconnection Customer’s
written request and sole expense, Transmission Provider may file a
claim for refund with respect to any taxes paid under this
Article 5.17, whether or not it has received such a
determination. Transmission Provider reserves the right to make all
decisions with regard to the prosecution of such appeal, protest,
abatement or other contest, including the selection of counsel and
compromise or settlement of the claim, but Transmission Provider
shall keep Interconnection Customer informed, shall consider in
good faith suggestions from Interconnection Customer about the
conduct of the contest, and shall reasonably permit Interconnection
Customer or an Interconnection Customer representative to attend
contest proceedings. |
| |
| |
|
|
Interconnection Customer shall pay to Transmission Provider on
a periodic basis, as invoiced by Transmission Provider,
Transmission Provider’s documented reasonable costs of
prosecuting such appeal, protest, abatement or other contest. At
any time during the contest, Transmission Provider may agree to a
settlement either with Interconnection Customer’s consent or
after obtaining written advice from nationally-recognized tax
counsel, selected by Transmission Provider, but reasonably
acceptable to Interconnection Customer, that the proposed
settlement represents a reasonable settlement given the hazards of
litigation. Interconnection Customer’s obligation shall be
based on the amount of the settlement agreed to by Interconnection
Customer, or if a higher amount, so much of the settlement that is
supported by the written advice from nationally-recognized tax
counsel selected under the terms of the preceding sentence. The
settlement amount shall be calculated on a fully grossed-up basis
to cover any related cost consequences of the current tax
liability. Any settlement without Interconnection Customer’s
consent or such written advice will relieve Interconnection
Customer from any obligation to indemnify Transmission Provider for
the tax at issue in the contest. |
27
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
5.17.8 |
|
Refund. In the event that (a) a private letter
ruling is issued to Transmission Provider which holds that any
amount paid or the value of any property transferred by
Interconnection Customer to Transmission Provider under the terms
of this LGIA is not subject to federal income taxation,
(b) any legislative change or administrative announcement,
notice, ruling or other determination makes it reasonably clear to
Transmission Provider in good faith that any amount paid or the
value of any property transferred by Interconnection Customer to
Transmission Provider under the terms of this LGIA is not taxable
to Transmission Provider, (c) any abatement, appeal, protest,
or other contest results in a determination that any payments or
transfers made by Interconnection Customer to Transmission Provider
are not subject to federal income tax, or (d) if Transmission
Provider receives a refund from any taxing authority for any
overpayment of tax attributable to any payment or property transfer
made by Interconnection Customer to Transmission Provider pursuant
to this LGIA, Transmission Provider shall promptly refund to
Interconnection Customer the following: |
(i) any payment made by Interconnection Customer under this
Article 5.17 for taxes that is attributable to the amount
determined to be non-taxable, together with interest thereon,
(ii) interest on any amount paid by Interconnection Customer
to Transmission Provider for such taxes which Transmission Provider
did not submit to the taxing authority, calculated in accordance
with the methodology set forth in FERC’s regulations at 18
CFR §35.19a(a)(2)(iii) from the date payment was made by
Interconnection Customer to the date Transmission Provider refunds
such payment to Interconnection Customer, and
(iii) with respect to any such taxes paid by Transmission
Provider, any refund or credit Transmission Provider receives or to
which it may be entitled from any Governmental Authority, interest
(or that portion thereof attributable to the payment described in
clause (i), above) owed to Transmission Provider for such
overpayment of taxes (including any reduction in interest otherwise
payable by Transmission Provider to any Governmental Authority
resulting from an offset or credit); as provided, however,
that Transmission Provider will remit such amount promptly to
Interconnection Customer only after and to the extent that
Transmission Provider has received a tax refund, credit or offset
from any Governmental Authority for any applicable overpayment of
income tax related to Transmission Provider’s Interconnection
Facilities.
| |
|
|
The intent of this provision is to leave the Parties, to the
extent practicable, in the event that no taxes are due with respect
to any payment for Interconnection Facilities and Network Upgrades
hereunder, in the same position they would have been in had no such
tax payments been made. |
28
|
|
|
| |
|
|
| Arizona Public Service Company |
|
APS Contract No. 52023 |
| LGIA (Large Generator Interconnection
Agreement) |
|
|
| |
|
|
| |
5.17.9 |
|
Taxes Other Than Income Taxes . Upon the timely request
by Interconnection Customer, and at Interconnection
Customer’s sole expense, Transmission Provider may appeal,
protest, seek abatement of, or otherwise contest any tax (other
than federal or state income tax) asserted or assessed against
Transmission Provider for which Interconnection Customer may be
required to reimburse Transmission Provider under the terms of this
LGIA. Interconnection Customer shall pay to Transmission Provider
on a periodic basis, as invoiced by Transmission Provider,
Transmission Provider’s documented reasonable costs of
prosecuting such appeal, protest, abatement, or other contest.
Interconnection Customer and Transmission Provider shall cooperate
in good faith with respect to any such contest. Unless the payment
of such taxes is a prerequisite to an appeal or abatement or cannot
be deferred, no amount shall be payable by Interconnection Customer
to Transmission Provider for such taxes until they are assessed by
a final, non-appealable order by any court or agency of competent
jurisdiction. In the event that a tax payment is withheld and
ultimately due and payable after appeal, Interconnection Customer
will be responsible for all taxes, interest and penalties, other
than penalties attributable to any delay caused by Transmission
Provider. |
| |
| |
5.17.10 |
|
Transmission Owners Who Are Not Transmission Providers.
If Transmission Provider is not the same entity as the Transmission
Owner, then (i) all references in this Article 5.17 to
Transmission Provider shall be deemed also to refer to and to
include the Transmission Owner, as appropriate, and (ii) this
LGIA shall not become effective until such Transmission Owner shall
have agreed in writing to assume all of the duties and obligations
of Transmission Provider under this Article 5.17 of this
LGIA. |
| 5.18 |
|
Tax Status . Each Party shall cooperate with the other
to maintain the other Party’s tax status. Nothing in this
LGIA is intended to adversely affect any Transmission
Provider’s tax exempt status with respect to the issuance of
bonds including, but not limited to, Local Furnishing Bonds. |
| |
| 5.19 |
|
Modification. |
| |
5.19.1 |
|
General. Either Party may undertake modifications to its
facilities. If a Party plans to undertake a modification that
reasonably may be expected to affect the other Party’s
facilities, that Party shall provide to the other Party sufficient
information regarding such modification so that the other Party may
evaluate the potential impact of such modification prior to
commencement of the work. Such information shall be deemed to be
confidential hereunder and shall include information concerning the
timing of such modifications and whether such modifications are
expected to interrupt the flow of electricity from the Large
Generating Facility. The Party desiring to perform such work shall
provide the relevant drawings, plans, and specifications to the
other Party at least ninety (90) Calendar Days in advance of
the commencement of the work or such shorter period upon which the
Parties may agree, which agreement shall not unreasonably be
withheld, conditioned or delayed. |
|